World Bank Document...As of February 2, 2012, out of the signed amount of SDR 20.2m (equivalent to...
Transcript of World Bank Document...As of February 2, 2012, out of the signed amount of SDR 20.2m (equivalent to...
1
Document of
The World Bank
Report No: 68508 v1
RESTRUCTURING PAPER
ON A
PROPOSED PROJECT RESTRUCTURING
OF
REGIONAL COMMUNICATION INFRASTRUCTURE PROGRAM (APL1)
MADAGASCAR COMMUNICATIONS INFRASTRUCTURE PROJECT (CIP 3)
CREDIT
March 29, 2007
TO THE
REPUBLIC OF MADAGASCAR
April 26, 2012
This document has a restricted distribution and may be used by recipients only in the
performance of their official duties. Its contents may not otherwise be disclosed without
World Bank authorization.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
2
ABBREVIATIONS AND ACRONYMS
APL Adaptable Program Loan
ARTEC
Autorité de Régulation des Technologies de Communications (ICT Regulatory
Authority)
BP Bank Procedures
CIP3 Madagascar Communications Infrastructure Project
CP Steering Committee (Comité de Pilotage)
CTBN Technical Committee for the national backbone (Comité Technique pour le Backbone
National)
DO Development Objective
EASSy Eastern Africa Submarine System
ESMF Environmental and Social Management Framework
FM Financial Management
FMR Financial Monitoring Report
FMS Financial Management System
GP General Policies
GDP Gross Domestic Product
GNI Gross National Income
ICT Information and Communications Technology
IDA International Development Association
IFC International Finance Corporation
IP Implementation Progress
IRR Internal Rate of Return
ISP Internet Service Provider
IXP Internet Exchange Points
LION Lower Indian Ocean Network
MW Microwave
MTPC
Ministère des Télécommunications, des Postes et de la Communication (Ministry for
Telecommunications, Post and Communication)
M&E Monitoring and Evaluation
OMERT
Office Malgache d’Etudes et de Régulation des Télécommunications (Malagasy Office
for Research and Telecommunication Regulation)
OD Operational Directives
OP Operational Manual
PAD Project Appraisal Document
PC Personal Computer
PPP Public Private Partnership
RCIP Regional Communications Infrastructure Program
RAP Resettlement Action Plan
RPF Resettlement Policy Framework
SBD Standard Bidding Documents
3
SDH Synchronous Digital Hierarchy
SE Executive Secretariat (Secrétariat Exécutif)
SME Small and Medium Entreprise
TELMA Telecom Malagasy
US$ United States Dollars
US United States of America
WBG World Bank Group
Vice President: Obiageli Ezekwesili
Acting Regional Integration Director: Elizabeth Lule
Country Director: Haleh Bridi
Sector Director José Luis Irigoyen
Acting Sector Manager: Doyle Gallegos
Task Team Leader: Isabel Neto
4
AFRICA REGIONAL COMMUNICATIONS INFRASTRUCTURE PROJECT
MADAGASCAR
P094103
CONTENTS
Page
A. SUMMARY ........................................................................................................................... 5 B. PROJECT STATUS .............................................................................................................. 6
C. PROPOSED CHANGES ...................................................................................................... 7
ANNEX 1: RESULTS FRAMEWORK AND MONITORING .............................................. 14
5
REGIONAL COMMUNICATIONS INFRASTRUCTURE PROJECT
RESTRUCTURING PAPER
A. SUMMARY
1. The Madagascar Communications Infrastructure Project, Credit No. 4285-
MAG, P094103 was first approved in March 2007. The current closing date is April 30,
2012. The Project Development Objective for Phase I (APL1) is to (i) to contribute to
lower prices for international capacity and extend the geographic reach of broadband
networks (the “connectivity development objective") and ( ii) contribute to improved
Government efficiency and transparency through e-government applications (the
"transparency development objective"). The PDO for Madagascar is a subset of the APL
PDO, with only the connectivity development objective applying. When the 2009 crisis
in Madagascar erupted, the project was at very early implementation stages, with only a
few initial consultancies having started. Given that the activities as had originally been
envisaged involved key policy decisions, all project activities (except for the project
management unit) had been put on hold due to the Bank's application of OP7.30 to the
country. Following MD’s decision on May 11, 2011 to resume disbursements on the
entire Madagascar portfolio, the country team set out on the preparation of a
comprehensive portfolio restructuring package (guided by the ISN under preparation at
the time) to adapt to the current operating environment. The Interim Strategy Note (ISN)
was presented to the Board in February 2012.
2. The original project development objective continues to be relevant and
achievable, but changes in the approach and selected components and indicators are
required. The extension of closing date would allow for completion of activities under the
project, which suffered from serious delays following the political crisis in Madagascar.
3. In the context of the ISN and following government’s request dated April 25,
2012, the project is now being restructured, and the main proposed changes are to (i)
cancel activities for which policy decisions are needed (and that the government is not
likely to be able to take for the foreseeable future) or that are no longer relevant in a total
amount of SDR 10,100,000 (US $ 15 m. equivalent) with the corresponding national IDA
of these resources (one third, i.e., $5m) being freed up for use in other operations in the
Madagascar portfolio; (ii) change the approach for the backbone component; (iii) extend
the credit closing date by an additional 20-months to allow for completion of the
activities, from April 30, 2012 to December 31, 2013, with the corresponding changes in
implementation and disbursement projections; (iv) reallocate funds across disbursement
categories; and (v) revise the indicators to exclude the indicators on which the project
will no longer have an impact, and adjusting the end values for proposed indicators to
reflect the extension and the reality on the ground.
4. This is the second restructuring of the project. The first restructuring was
approved in July 26, 2011, and consisted of the extension of the project closing date by 9
months, from July 31, 2011 to April 30, 2012.
6
5. The proposed changes and their consistency with the original principles and
arrangements. Changes and reallocations are consistent with the original PDO and
generally with the Regional Program principles and the Project description as originally
approved. The proposed changes are also consistent with the breakdown in
regional/national IDA allocation – ie activities are still all eligible for regional funds, as
they have not changed in their nature.
B. PROJECT STATUS
6. Project Status. As of February 2, 2012, out of the signed amount of SDR
20.2m (equivalent to $30m USD), SDR 1.34m (equivalent to $2.09m USD) has been
disbursed representing 6.67% of the signed amount. The amount undisbursed is SDR
18.85m (equivalent to $29.21m USD) and the amount committed is SDR 1.2m
(equivalent to $1.8m) representing 5.8% of the signed amount. This compares with
figures for the overall RCIP APL1 of 32% disbursements and 54% of the funds having
been committed.
7. Progress so far. The Madagascar Communications Infrastructure Project,
Credit No. 4285-MAG, P094103 was first approved in March 2007. When the 2009 crisis
in Madagascar erupted the project was at very early implementation stages, with only a
few initial consultancies having started. Given that the activities as had originally been
envisaged involved key policy decisions, all project activities (except for the project
management unit) had been put on hold due to the Bank's application of OP7.30 to the
country, which means that apart from some initial consultancies, no other project
activities have been implemented. Despite the crisis the sector has continued to grow,
although at reduced rates, and since project approval two submarine cables (EASSy and
LION) have landed in Madagascar. Ratings on progress towards the PDO and
implementation progress are currently moderately satisfactory, but these ratings also
reflect operations in Kenya and Burundi, in addition to Madagascar, which are all
participating in RCIP Phase I (APL1). In Kenya, project activities are progressing well,
after some initial delays, as well as the project indicators, as can be consulted in the latest
ISR, and an additional financing has just been approved for the project in March 2012. In
Burundi, the main project component is the development of a backbone network through
a Public Private Partnership (PPP); negotiations of the PPP took over a year and a half,
required an extension of the project, and have only recently been concluded. However,
the supply contract for the network has now been signed, and works are expected to start
during the second quarter of 2012, allowing implementation and disbursement to
accelerate. Fiduciary ratings – including financial Management and procurement are
satisfactory. The implementing entities are compliant with the Bank's financial
management requirements; and there are no overdue audit reports and interim financial
reports from these entities.
8. Following MD’s decision on May 11, 2011 to resume disbursements on the
entire Madagascar portfolio, the credit closing date was extended by 9 months from July
31, 2011 until April 30, 2012 to allow for sufficient time to prepare a more
comprehensive restructuring package and to align it with the overall portfolio actions
within the framework of the Interim Strategy Note (ISN).
7
9. The original project development objective continues to be relevant and
achievable, but changes in the approach and selected activities and indicators are
required.
C. PROPOSED CHANGES
1. Results/indicators. The indicators are being revised to exclude the indicators on
which the project will no longer have an impact (only intermediate), align with
core sector indicators, and adjust the end values to reflect the proposed extended
project closing date of December 31, 2013 and the reality on the ground. The
revised targets are presented in Annex 1. Several of the original targets have been
surpassed, even with most of the project activities on hold. This can be explained
because other unforeseen events took place during this period; for example, not
only one (as expected at time of project approval), but two submarine cables
landed in Madagascar during this period, thereby accelerating sector growth.
Also, despite the lack of liberalization of the data segment in Madagascar, several
operators have in practice started providing those services, increasing competition
and reducing prices. Through this restructuring, selected indicators have been
removed where there was no longer an attribution to project activities (e.g.,
number of ISPs or number of university PCs connected to broadband) and one
additional indicator was added (‘number of towers constructed’) where there will
be a full attribution. The target values have been calculated by trying to estimate
what would be the cumulative/aggregate contribution of the project, together with
other factors, to sector growth (see Annex 1 for revised targets for volume of
international traffic, teledensity, internet subscribers, among others).
2. Components. The proposed changes in project components are as follows:
o Cancel activities for which policy decisions are needed (and that the
government is not likely to be able to take for the foreseeable future) or
that are no longer relevant: these include the technical assistance for
policy reform, capacity purchase, and setting up of a virtual landing
station. These changes will result in a cancellation of SDR 10,100,000
(US $ 15 m. equivalent) with the corresponding national IDA of these
resources (one third, i.e., $5m) being freed up for use in other operations
in the Madagascar portfolio;
o Slightly increase the costs needed for project management, to reflect the
extension of the project;
o Restructure the backbone component to focus on “passive” infrastructure
and extend backbone networks and mobile services to rural remote areas.
Originally the project had foreseen the liberalization of capacity resale in
Madagascar1, and the subsequent build out of a national backbone network
to be used by all the operators. In the absence of liberalization of capacity
resale, however, building out a full backbone network would mean that a
single operator (TELMA) would be allowed to operate it. Through this
1 Currently in Madagscar only TELMA is allowed to resell capacity, which means that any other operator
who builds a backbone network can only use it for its own use and cannot resell to others.
8
restructuring, a new approach is being proposed in which the common
rollout of infrastructure will focus on passive elements only (i.e., towers
and energy solutions rather than active equipment such as antennas and
switches) that all operators will be allowed to use and share to set up their
active elements (i.e., antennas) for backbone deployment and/or base
station installation (i.e., to increase transmission capacity and improve
coverage of the network. This would mean that the benefits of
infrastructure sharing would still be realized, even in a non-liberalized
environment, therefore still guaranteeing the principles of open access on
which the RCIP program is based. These towers would be set up in
partnership with the private sector. Where relevant, a set of sub-projects
will be implemented to provide marginal energy services to the rural
communities where these towers are located. It is expected that the
tower+energy extension sub-projects will be executed in two rounds (see
implementation schedule below).
o The table below describes the changes in project components being
proposed (as described in the Financing Agreement).
Original component Revised component Part 1. Enabling Environment
Provision of technical assistance to:
a. Promote liberalization of and legal
and regulatory reforms related to
national and international
telecommunications infrastructure
and other relevant infrastructure,
including regulatory and legal reform
in the field of telecommunications
(including competition law and
policy).
b. Support capacity-building of
Ministry of Telecommunications,
Posts and Communication and
ARCT for the implementation of the
sector policy and sector reforms,
including training.
c. Finance additional studies for the
development of the national
backbone.
d. Develop the legal and regulatory
framework with respect to, inter alia,
e-transactions security, privacy and
data protection, access to
information, network security,
Provision of technical assistance to:
a. Promote liberalization of national
and international telecommunications
infrastructure.
b. Finance additional studies for the
development of the national
backbone.
c. Develop the legal and regulatory
framework of the public private
partnerships..
d. Formulate arrangements,
disbursement and governance
mechanisms to enable the building of
the national backbone and the
establishment of joint regional
infrastructure.
e. Increase capacity of the Recipient to
monitor and evaluate the results of
the Program, to meet environmental
and social safeguards and to
communicate about the Project.
9
intellectual property rights, cyber
crime, public private partnerships
and standards.
e. Formulate arrangements,
disbursement and governance
mechanisms to enable the building of
the national backbone, the
establishment of a joint regional
infrastructure access point and
internet exchange point, capacity
purchase schemes and the
establishment of a capacity pool
related to the national backbone.
f. Increase capacity of the Recipient to
monitor and evaluate the results of
the Program, to meet environmental
and social safeguards and
communicate about the Project.
Part 2. Connectivity
a. Finance capacity purchase schemes
for targeted users, in particular
universities and the Recipient;
b. Support for the establishment of joint
regional infrastructure access point
and a joint internet exchange point;
and
c. Support the building of a national
backbone through the
implementation of Sub-Projects
(with a contingency to address
environmental, social and
resettlement issues, including
resettlement compensation).
Part 2. Connectivity
a. Support for the establishment of joint
regional infrastructure through financing
telecommunication infrastructure, namely
elements of the national backbone and its
extension to rural remote areas, through the
implementation of sub-projects (with a
contingency to address environmental, social
and resettlement issues, including
resettlement compensation).
Part 3. Project Management
a. Support the Executive Secretariat
with respect to activities pertaining
to the management of the Project.
Part 3. Project Management
a. Support the Executive Secretariat
with respect to activities pertaining
to the management of the Project.
10
3. Safeguards. The project’s management of environmental and social safeguards
is satisfactory overall. The restricting of the backbone component to focus on
“passive” infrastructure has the same scope and activities as the original project.
Therefore, the safeguards category “B” remains unchanged, and it is expected that
these amendments will not trigger any new safeguard measures. safeguard
policies that applied to the parent project remain unchanged: OP 4.01
Environmental Assessment, and OP 4.12 Involuntary Resettlement. The parent
project safeguard instruments - Environmental and social Management
Framework (ESMF), and Resettlement Policy Framework (RPF) - remain
applicable. These documents do not require any modification.
4. Institutional arrangements. The institutional arrangements for the project will
be left unchanged.
5. Procurement. Procurement arrangement under the project remains unchanged
except the introduction of new procurement method "Procurement under Public
Private Partnership (PPP) arrangements" to take into account the selection of a
private operator to construct and maintain a tower network and rent access to
private operators. Applicable Guidelines are those published by the Bank in
January 2011. The client’s procurement officer is still in place.
6. Financing
o Project Costs and cancellation., the restructuring would result in the
removal of certain project activities, which would result in a cancellation
of $15 m. in the amount of the credit (10.1 SDR). Distribution of the
amount to be cancelled with regards to the different project components
would be as follows:
Project Cost By Component and/or Activity
Total
US$ m.
Current
allocation
Total
US$ m.
Disbursed
Total
US$ m.
For future
activities
Total
US$ m.
Proposed
revised
allocation
Total
$amount
to be
cancelled
COMPONENT 1 - Technical assistance to
MTPC, ARTEC, capacity building, M&E
2.94 0.35 0.88 1.23 1.71
(a) Regulatory TA 0.3 0.11 0.07 0.18
(b) Policy and Regulatory Capacity Building 0.35 0.02 0.06 0.08
(c) Complementary studies for the development
of backbone elements
0.5 0.02 0.39 0.41
(d) e-legislation and regulatory framework 0.1
(e) PPP framework development 0.3 0.19 0.12 0.31
(f) M&E Capacity Building 0.18 0.01 0.04 0.05
(g) Design of Purchase of capacity 0.17
(h) Assistance in formation of the capacity pool 0.2
(i) Environmental studies 0.1
(j) Project Communications 0.2 0.20 0.20
(k) Additional Technical Assistance 0.54
COMPONENT 2 – Connectivity 24 12.01 12.01 11.99
(a) Virtual landing station and IXP 1.5
(b) Rollout of national backbone elements. 18.5
(c) Purchase of capacity for targeted users 4
(d) Primary links – Zone 1 5.2 5.2
(e) Primary links – Zone 2 4.64 4.64
(f) Primary links – Zone 3 2.17 2.17
11
COMPONENT 3 - PROJECT
MANAGEMENT
1.36 0.91 0.85 1.76 -0.40
(a) Executive Secretary 0.32 0.23 0.13 0.36
(b) Technical Manager 0.3 0.09 0.05 0.14
(c) Procurement Specialist 0.11 0.09 0.05 0.14
(d) Financial Management Specialist 0.11 0.10 0.07 0.17
(e) M&E Specialist 0.10 0.10 0.07 0.17
(f) Communications Specialist 0.10 0.02 0.04 0.06
(g) Office Equipment 0.03 0.03 0.03
(h) Incremental Operating Cost 0.18 0.19 0.34 0.53
(i) Audit 0.08 0.02 0.03 0.05
(j) Environmental 0.03 0.01 0.03 0.04
(k) Chief account 0.03 0.04 0.07
Total Baseline Cost 28.3 1.26 13.74 15 13.30
Contingencies for resettlement 1 1.00
Price Contingencies 0.7 0.70
Unallocated 15
Total Project Costs1 30 1.26 13.74 15 15
Interest during construction
Front-end Fee
Total Financing Required 30 1.26 13.74 15 15
o Financing Plan: The disbursement projections were revised as follows:
FY Projected
(USD)
Projected
(SDR)
Cumulative
(USD)
Cumulative
FY
%
of original
credit
%
of revised credit
Before
Q3 FY12
2.89m
(actual)
1.35m
(actual)
2.08m
(actual)
1.35m
(actual) 6.67%
13.34%
Q4 FY12 0.65 0.44 2.73 1.79 8.86% 17.72%
Q1 FY13 2.17 1.47 4.90 3.25 16.08% 32.16%
Q2 FY13 0.57 0.38 5.47 3.63 17.98% 35.96%
Q3 FY13 3.82 2.59 9.29 6.22 30.81% 61.63%
Q4 FY13 2.43 1.65 11.72 7.88 38.99% 77.97%
Q1 FY14 2.75 1.87 14.48 9.74 48.24% 96.47%
Q2 FY14 0.53 0.36 15.00 10.10 50.00% 100.00%
Total 15.00m 10.10m
o Reallocations: The following reallocations are being proposed. Most
values per disbursement categories are being lowered because of the
cancellation of project activities. The operating costs are going up to
reflect the extension of the credit closing date and the increased costs for
the project which reflect the reality in the country after the political crisis.
Category of Expenditure Allocation
(SDR)
% of Financing
Current Revised Current Revised Current Revised
(1) Goods - 3,550,000 20,000 100% 100%
(2) Works - 170,000 100% 100%
(3) Consultants’ - 2,450,000 1,500,000 100% 100%
12
services,
including audits
(4) Training - 240,000 120,000 100% 100%
(5) Operating
Costs
- 120,000 370,000 100% 100%
(6) Subprojects
under Part 2(c) of
the Project
- 12,450,000 8,090,000 100% 100%
(7) Unallocated - 1,220,000
TOTAL
AMOUNT
20,200,000 10,100,000
7. Closing date: The closing date for the credit is being extended by additional 20
months from April 30, 2012 until December 31, 2013. This extension meets the
OP/BP 13.30 criteria. Project objectives continue to achievable provided that the
closing date is extended, although there will be changes in the project indicators.
A number of changes and revisions proposed in this Restructuring Paper also help
achieve the PDO. The proposed extension is necessary to allow for completion of
activities under the project, which suffered delays in initial years of project
implementation due mainly to the political crisis that has erupted in Madagascar
in early 2009. The Recipient has in place an action plan to complete the project
(see table below). According to that plan, implementation of all contracts should
be completed by December 31, 2013. An extension of 20 months would allow for
completion of those contracts. This will be the second extension of the project,
with the first one having been for 9months from July 31, 2011 to April 30, 2012,
which was approved in July 26, 2011 as a bridge period to prepare the in-depth
restructuring.
8. Implementation schedule: The proposed implementation plan is as follows:
Timeline Priority activities
Q3 FY12
Prepare 1st round of tower+energy project (ie develop technical
specs, draft business model, procurement and disbursement
arrangements for the subprojects)
Q4 FY12 Finalize arrangements and launch the 1
st round of the tower+energy
project
Q1 FY13 Evaluate the tender for the 1st round of the tower+energy project
Q2 FY13
Implementation of 1st round starts
Prepare and launch 2nd round of tower+energy project (ie adaptation
to arrangements used for the first round and launching of the tender
process for the 2nd
round)
Q3 FY13 Evaluate the tender for the 2nd
round of tower+energy project
Q4 FY13 Implementation of 2nd
round starts
Q1 FY14 Conclusion of 1st round’s implementation
Q2 FY14 Conclusion of 2nd
round’s implementation
13
9. Legal covenants: There are no changes in the legal covenants of the project, and
a disbursement condition will still be maintained regarding disbursements towards
the backbone support under Part 2 of the project (i.e., connectivity/ support to
tower plus energy projects).
14
ANNEX 1:
Results Framework and Monitoring
AFRICA: REGIONAL COMMUNICATIONS INFRASTRUCTURE PROJECT
Results Framework
Revisions to the Results Framework Comments/
Rationale for Change
PDO
Current Proposed
To contribute to lower prices
for international capacity and
extend the geographic reach of
broadband networks
No change The original PDO will remain the
same.
PDO indicators
Current Proposed change*
Volume of International traffic
(Mbit/s simplex)
Continued with revised target value
(11,870Mbit/s) at the end of the project
(current value of 1,240Mbit/s already
exceeded the initial target value of
1,000Mbit/s).
Access to Internet Services
(number of subscribers per 100
people)
Continued with revised target value of
2.97% at the end of the project (current
value of 1.66% already exceeded the
initial target value 1.15%).
Teledensity (Access to
Telephone Services (fixed
mainlines plus cellular phones
per 100 people))
Continued with revised target value of
56.12% at the end of the project (current
value of 43.8% already exceeded the initial
target value of 10%).
Price of wholesale
international E1 capacity link
Continued with revised target value of
US$1,464 at the end of the project (current
value of US$1,776 is still above the initial
target value of US$1,500).
Direct Project Beneficiaries
(number), of which female (%)
New
Intermediate Results indicators
Current Proposed change*
Increased protection of
intellectual property & of
electronic transactions
Drop Unclear attribution to the project.
Number of ISPs Drop Cancellation of related activities.
Number of market players
buying capacity at the landing
station
Drop Cancellation of the virtual landing
station activity.
Price of Internet Access
[monthly price for 256kb
connection]
Continued with revised target value of
US$40 at the end of the project (current
value of $46 already exceeded the initial
target value of $80).
Retail price of internet services
(per Mbit/s per Month, in
New This is core indicator, and
suggested to monitor in addition to
15
Revisions to the Results Framework Comments/
Rationale for Change
US$)” the current 256 kbit/s connection
price indicator.
Number of localities
(communes) with broadband
access
Continued with revised target value of 131
at the end of the project (current value of
51 already exceeded the initial target value
of 40).
Number of university PCs
connected to broadband
Drop Cancellation of capacity purchase
activities.
Number of towers constructed New This indicator was added to
measure the progress of the
expansion of backbone networks
and mobile services to rural remote
areas supported through the projet.
16
REVISED PROJECT RESULTS FRAMEWORK
Project Development Objective (PDO):
To contribute to lower prices for international capacity and extend the geographic reach of broadband networks —No Change
PDO Level Results Indicators
Co
re
UOM2
Baseline
Original
Project
Start
(2007)
Progress
To Date
(2011)
Cumulative
Target Values Frequenc
y
Data Source/
Methodolog
y
Responsibility
for Data
Collection
Comments
2012 2013
1. Volume of International traffic (Mbit/s
simplex)
Mbit/s
200
Mbits
1240
Mbit/s
(as of Dec
2011)
8570 11870 Yearly OMERT/Ope
rators OMERT
2. Access to Internet Services (number of
subscribers per 100 people) Number 0.23
1.66 (as of
Dec 2011) 2.43 2.97 Yearly OMERT
OMERT/PIC
OM
3. Teledensity (Access to Telephone
Services (fixed mainlines plus cellular
phones per 100 people))
Number 6.00
43.80
(as of Dec
2011)
51.27 56.26 Yearly PICOM OMERT/PIC
OM
4. Price of wholesale international E1
capacity link
US$/M
onth
US$
10,000/M
onth
US$
1,776/
Month
(as of dec
2011)
US$1,
464
US$1,
464
Yearly OMERT/OP
ERATORS
OMERT/PIC
OM
Average of
the prices
used by
operators
5.. Beneficiaries
Direct Project Beneficiaries (number), of
which female (%)
Number
s
0 0 280,66
9
24506
60 Yearly
socio-
economic
survey
PICOM
People in the
communities
directly
benefiting
from the
connection
2 UOM = Unit of Measurement.
17
Of which female (%)
Percent
age (%)
0 0 51%
51% Yearly
socio-
economic
survey report
PICOM
Intermediate Results and Indicators
Intermediate Results Indicators
Co
re
Unit of
Measur
ement
Baseline
Original
Project
Start
(2007)
Progress
To Date
(2011)
Target Values
Frequenc
y
Data
Source/
Methodolog
y
Responsibility
for Data
Collection
Comments
2012 2013
Intermediate Result 1: (Component One): Enabling Environment- Dropped
Intermediate Result 2: (Component Two): Connectivity—No Change
1. Price of Internet Access
256
kbit/s
per
Month,
in US$
US$ 100
US$46.4
7 (as of
dec 2011)
US$45 US$40 Yearly OMERT/
ARTEC
OMERT/PICO
M
2. Retail price of internet services
Per
Mbits/
per
month,
in US$
US$1208.
61
$186(as
of dec
2011)
$ 180 $ 160 Yearly OMERT/
ARTEC OMERT
3. Number of localities (communes) with
broadband access
Number
s 20
51
(as of
Dec
2011)
91 131 Yearly OMERT/
ARTEC OMERT
4. Number of towers constructed
Number
s 0 0 13 93 Yearly PICOM PICOM
18