World Bank Documentdocuments.worldbank.org/curated/en/... · 2 -providing a detailed explanation on...

12
MINISTRY OF PLANNING AND INTERNATIONAL COOPERATION 5/9/1/2466 Ref.No 13/03/2016 Date The World Bank Lebanon Country Office Bourie House 119, A.Bayhum Str. Marffaa - Solidere - Down Town P.O.Box 11-8577 - Beirut - Lebanon Subject: (Technical Support for Statistical Capacity Building) Trust Fund Grant No. (013568) Dear Rima, In reference to the subject Grant, kindly find attached Financial Statement and Auditors Report For the Period From Jan 01,2015 to Feb 29,2016. Thank you for your continues cooperation. Sincerely, Imad Najib Fakhoury Minister of Planning and V International Cooperation Mahmoud Maher cc. Financial and Administrative Affairs Department Dieco f ail Director of Finandial & Administrative Affairs Dept. THE HASHEMTTE KINoOm op JoRDAN - AMmAN TEL +962 6 4644466/70- FAX + 962 6 4649341 PO.BOX: 555 AMMAN 11118 JORDAN E-MAL:[email protected] Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Transcript of World Bank Documentdocuments.worldbank.org/curated/en/... · 2 -providing a detailed explanation on...

Page 1: World Bank Documentdocuments.worldbank.org/curated/en/... · 2 -providing a detailed explanation on the data set ofthe table franework 3-carry out alernative development scenarios

MINISTRY OF PLANNING AND INTERNATIONAL COOPERATION

5/9/1/2466Ref.No 13/03/2016Date

The World BankLebanon Country OfficeBourie House 119, A.Bayhum Str.Marffaa - Solidere - Down TownP.O.Box 11-8577 - Beirut - Lebanon

Subject: (Technical Support for Statistical Capacity Building)

Trust Fund Grant No. (013568)

Dear Rima,

In reference to the subject Grant, kindly find attached Financial Statement

and Auditors Report For the Period From Jan 01,2015 to Feb 29,2016.

Thank you for your continues cooperation.

Sincerely,

Imad Najib FakhouryMinister of Planning and

V International Cooperation

Mahmoud Mahercc. Financial and Administrative Affairs Department Dieco f ailDirector of Finandial &

Administrative Affairs Dept.

THE HASHEMTTE KINoOm op JoRDAN - AMmANTEL +962 6 4644466/70- FAX + 962 6 4649341 PO.BOX: 555 AMMAN 11118 JORDAN E-MAL:[email protected]

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: World Bank Documentdocuments.worldbank.org/curated/en/... · 2 -providing a detailed explanation on the data set ofthe table franework 3-carry out alernative development scenarios

Certified Public Accountant .4b A...N

Audit Business Advisor Training Tax - -b -

METHODOLOGYh'jj114.JI .jgojl 91039 %O:L.:JIa 0%For Auditing & Human Resources Development

Ministry of planning International Co-operation

Technical Support for statistical Capacity Building

GEF Trust Fund Grant No.TF013568

Amman, Jordan

Report on Accounting Procedures and

Internal Control Structure 2015

11941 J >* jl 2560 ye 404 w 4 A - ji. lSjlS . Ajvi . t4& ."AV

00962 79 9051570 - 00962 79 9059637: 41i 00962 6 5348020 :.S1Wh' 00962 6 5338020: .16E-mail: [email protected] [email protected]

www.methodology-jo.com

Page 3: World Bank Documentdocuments.worldbank.org/curated/en/... · 2 -providing a detailed explanation on the data set ofthe table franework 3-carry out alernative development scenarios

. S *

Certified Public Accountant 0 q 19 S4i .Audit Business Advisor Training Tax * A "AN

METHODOLOGYEQIijL" AhjI9 401 j4Jhj9 %:jLitii -JI &A -j.9For Auditing & Human Resources Development

Ministry of planning International Co-operation

Technical Support for statistical Capacity Building

GEF Trust Fund Grant No.TF013568 Program

Amman, Jordan

We have made the final audit for Technical Support for Statistical Capacity Building

Program Grant No.(TF013568) For the period Ended Feb 28, 2016.

The management of Ministry of planning and International Co-operation is responsiblefor establishing and maintaining an internal control. In fulfilling this responsibility,estimate and judgments by management are required to assess the expected benefitsand related costs of internal control policies and procedures. The objective of internalcontrol are to provide management with reasonable assurance that the assets aresafeguards against loss from authorized use or disposition and that transaction areexecuted in accordance with management's authorization and recorded properly topermit the preparation of the financial statement in accordance with international

financial reporting standard.

In planning and performing our audit of the project, we considered its internal

accounting controls structure in order to determine our auditing procedure, adequate

controls and proper supporting documentation have been maintained. We didn't

identify any deficiencies in internal control that we consider to be material weaknesses.

Date: Febr 29,2016Certi itorALI JA HEH

(881)

11941 AJMeI2560 y.j 404 A 4 la-J" t$jSj tkf4-a-00962 79 9051570 - 00962 79 9059637 : 00962 6 5348020: jJ1W 00962 6 5338020:

E-mail: [email protected] [email protected]

Page 4: World Bank Documentdocuments.worldbank.org/curated/en/... · 2 -providing a detailed explanation on the data set ofthe table franework 3-carry out alernative development scenarios

Ministry of Planning & International Co-operationTechnical Support for Statistical Capacity Building

GEl Trust Fund Grant No.TF013568Amman - Jordan

Financial statements, auditor's reportFor the period from Jan 01,2015 to Feb 28,20 16

Page 5: World Bank Documentdocuments.worldbank.org/curated/en/... · 2 -providing a detailed explanation on the data set ofthe table franework 3-carry out alernative development scenarios

Technical Support For Staistical Capacity buildingTF(013568-JO)

Ministry Planning & International CooperationAMMAN- JORDAN

INDEX

PAGE

Auditor's Report

Statement OfSources And Uses OfFunds A

Statement OfExpenditures B

Statement OfSpecial Bank Account C

List OfContracts D

Notes To The Financial Staements 1-2

Page 6: World Bank Documentdocuments.worldbank.org/curated/en/... · 2 -providing a detailed explanation on the data set ofthe table franework 3-carry out alernative development scenarios

Certified Public Accountant

Audit Business Advisor Training Tax -. .y.METHODOLOGY

pjLlAl ajIg.oJI W9.b.59 cbluta.Jt .

For Auditing & Human Resources Development

Independent Auditor Report

GEF Number TF (013568) Grant for

(Technical Support for Statistical Capacity Building)

Ministry of planning and Internal Cooperation-Amman - Jordan

We have audited the accompanying financial statements of trust fund Grant No. (TF013568), Technical Support

for Statistical Capacity building, which comprises the statement of Sources and Uses for the period from Jan 1,2015

to Feb28,2016 and the statement of expenditure for the period then ended, and summary of significant accountingpolicies and other explanatory notes.

Managements Responsibility:

Management is responsible for the preparation and fair presentation of these financial statements in accordance withinternational financial reporting standards. This responsibility includes: designing, implementing and maintaininginternal control relevant to the preparation and fair presentation of financial statements that are free from materialmisstatement, whether due the fraud or error, selecting and applying appropriate accounting policies and makingaccounting estimates that are reasonable in the circumstances.

Auditor's Responsibility:

Our responsibility is to express an opinion on these financial statements based on our audit. We conducted our auditin accordance with international standards on auditing. Those standards require that we comply with ethicalrequirements and plan and perform the audit to obtain reasonable assurance whether the financial statements arefree from material misstatement.

An audit involves performing procedures to obtain audit evidence about the amounts and disclosures in the financial

statements.

pinion:

a) The financial statement presents fairly, in all material respect, the Sources and Uses of Funds of the

Technical Support for Statistical Capacity building, Trust Fund Grant No. (TF013568) for the period

Jan 1,2015 to Feb 28,2016 in accordance with the international Public Sector AccountingStandards, under

the cash basis of Accounting.b) Internal control over financial reporting involved in the preparation of direct payments, and reimbursement

i.e. expenditures reimbursed on the basis of statement of cash receipts and payments can be relied upon to

support the related withdrawals as Feb 28, 2016 .c) The projectis. In all materials respect, in compliance with the laws,regulations, guidelines and provision

governed by the grant agreement.Date: Februajy2 2016Certifie or

ALl J H

11941 44YI9 1f 2560 y 404 6Z 4 1* .

00962 79 9051570 - 00962 79 9059637: 4L 00962 6 5348020: wSQZ 00962 6 5338020: jiE-mail: [email protected] [email protected]

www.methodology-jo.com

Page 7: World Bank Documentdocuments.worldbank.org/curated/en/... · 2 -providing a detailed explanation on the data set ofthe table franework 3-carry out alernative development scenarios

Ministry Plannhg &ln teiwatiokaI Coperation

TF(013568-JOJf

Technical Support For Statistical Capacity Building,Amman - Jordan

Exibit A

Statement ofSources and Uses Of Fund as Feb 2016

( U.S. dollar)

From For the period For The Period

inception to from_ From Marchunti cloure JanO1,2015 to 14,2013 To

Notes Feb 28,2016 Dec 31,2014

Financing

Transfer From World Bank to SpecialAccount (initial amount) 3 126,267 61,267 65,000

Direct Payment 4 105,398 48,364 57,034

Total Financing 231,666 109,631 122,034

Payment

Category (1) Constants 231,358 113,056 118,301and training services

bank charges 107 107

RefundAmount 201 201Total Payments 231,666 113,364 118,301

Surplus (0) (3,733) 3,733

The notes form an integral part of this data

Page 8: World Bank Documentdocuments.worldbank.org/curated/en/... · 2 -providing a detailed explanation on the data set ofthe table franework 3-carry out alernative development scenarios

MInistry Planning & Internationa CooperationTF (013568-O)

TeclnicalSupport For Statisteial CapacityBuiding

Amman - Jordan

Exhibit B

Statement ofcExpenditures as Feb 2016

(U.S. dolar)

Allocated For the periodfrom For the period RemainingNote ammount fot the March 14,2013 to Dec from Jan01,2015 Realaning

fife of project 31,2014 to Feb 28,2016

Categora (1)

Constants and training Services 5 231,750 118,301 113,056bank charges 107refund amount 201

Total Expenditures 231,750 118,301 113,364 84

The notes form an integralpart of tis data

Page 9: World Bank Documentdocuments.worldbank.org/curated/en/... · 2 -providing a detailed explanation on the data set ofthe table franework 3-carry out alernative development scenarios

Ministry Planning& ilnternational CooperationTY (01368JO)

Tecnical Support For Statistical Capacity BuidingJ Amman - Jordan

Exhzhbit cStatemrnt ofSpecialAccount for the following vears Ended

(U.S. dollar)For theperiodfrom For the period from MarchJan 01,2015 to Feb 14,2013 to Dec 31,2014Description 28,2016

Opening Balance 3,733 -AddInitial Deposit 61,267 65,000Direct Payments 48,364 57,034Total Available 113,364 122,034Deduct:

Constants and training Services (113,056) (118,301)RefundAmounts (201)Bank Charges (107)Balance atyear end (0) 3,733

The notes form an integral part of tis data

Page 10: World Bank Documentdocuments.worldbank.org/curated/en/... · 2 -providing a detailed explanation on the data set ofthe table franework 3-carry out alernative development scenarios

AllnlsfrPlannng& nteadona ICooperatdonTF (013568-JO)

wichic irisaPpor i tntct'apacio, '-nAnunan - Jordan

ExitjItll DIlAt of Conrraer For The Period frmn 14,2013 To Feb 2820l6

- _______......._..__ .L'.S._dollar) _ _______

Allocated Category Activites Estimated con&act .4clual Contract Cur"tl RemainingAmount amount Signed amount disbursementTmining couce .first training (31 week)on basic adrnced/poweydata analysis using thestate softwae . Prepamtion for tir ngs (econd and 42,315 15/0712014 42.315 42,315third training) preperepresentaton notesDevelop exercises sessions :Ms.Celine Ferre

PAeparing the materials, Worh3hop on Dynamic GEModelingI - Erplaining the methodologies and policy Issues under the CGE2 -Pioviding a detailed explanation on the data set ofthe model3 - carry out altenative development scenarios and policy simulations 55,000 18/09/2014 55,000 55,0004 - Tabulation and interpretation ofthe results as well asfrre updates5 -data andfile management .nah as opening, nrodfing and simulationon the GE M PACK software: DrRoledAzubiFproviding the training matteials,1 - Erplaining the methodologies issues under the life table2 -providing a detailed explanation on the data set ofthe table franework3-carry out alernative development scenarios andpolicy simulations 42,000 21/12/2014 42,000 42,0004. Tabulation and interpretation of the results as well asuure updates

CS, 5 -data andfile management suh as opening. mading and analyze software231,750 Training modifying and analyze sofjware : Dr.AhmnadMobaok

I - the consultant shall perform the services specified in 7erms ofreference andscope ofservices"2 - the constilant shall provide Ohe persotnel listed in Eansultant'spersonnel"to perform the services. 15,975 03/02/2015 15,975 15,9753 - the consultant shall submit to de chient the reparts in the fonin and withinthe time periods specified in * consultans Reporting Obligation"HIE Contract Signed by: Juan Munor1 - the consultant shall perform the services speciied in terms of reference andscope ofservices"2 - the consultant shall povide the personnel listedin Eansufrants personne" 36,040 30/0612015 36,040 36,0403 - the consultant shall submit to the chient the reports in the form and withinthe time periods specifed in "consthant's Reporting Obligation"THE Contract Signedby :Norma AlperinI - the consultant shallperforn the services specified in lerms ofreference andscope ofseries"2-the consultantshallprrvide thepersonnel listed in eansuliam's personnel" 40,000 23/04/2015 40,000 40,0003- the consultant shall submit to the chient the ieparrs in the form and withinthe time periods speciied in "consutant's Reporting Obligation'771E Contact Signed by:Abdel Basset A- thamna

The notes form an integral part of this data

0 0

Page 11: World Bank Documentdocuments.worldbank.org/curated/en/... · 2 -providing a detailed explanation on the data set ofthe table franework 3-carry out alernative development scenarios

Mfini&ry Planning & Inrtnhdionat CooperatintiTF (013568-JO)

Technical Support for Statistical Capacity building- Amman - Jordan

1. General;According to the agreement signed between the Hashemite Kingdom ofJordan represented byMinistry ofplanning International Cooperation (MOPIC) and the international bank forReconstruction and Development (World Bank) Approved date 1 Jan, 2013 and effectivedate 14 Mar. 2013, the world bank provided a grant from the world Bank's InstitutionalDevelopment Fund (IFD) Grant NO. (TFOI3568)/Technical Support for Statistical Capacitybuilding in amount not exceed Two hundred and thirty on thousand and seven hundred andfiy dollars US$(231,750).The grant was provided to fulfill the "Technical Supprt for Statistical Capacity buliding GrandNo. (TF013568)'the duration ofproject from 31 Jan, 2013 to 31 Oct, 2015

2. Summary of significant accounting polices2.1 Basis of PreparationThe project followed and maintained the Grant accounts under cash Basis ofAccounting in recordingthe transactions ; according the project recognizes funds when received and expenditures when paid

2.2 Recognition of eligible expenditureEligible expenditures are recognized in respect of the realizable cost ofservice required for activityand to befinanced out of the proceeds of thw grant, while the amount of grant shall be credited to anaccount opened by the bank on its books in the name of the Recipient (the Grant Amount) by virtueof the existing agreement.Payments out of the special account shall be made exclusively for eligible expenditures in accordancewith the provisions of the agreement. The special account represents the Bank Account opened by therecipient at the Central Bank

2.3 Translation Currencies:Foreign currency transactions are translated in to US Dollar at exchange rate prevailing at the dateof transaction.

3 - cash Receipts

For the period from For the period fromDate of transfer March 14,2013 to Dec Jan 1,2015 to Feb

31,2014 28,20162 April, 2014 65,00028 Jan, 2015 61,267

Total 65,000 61,267

I

Page 12: World Bank Documentdocuments.worldbank.org/curated/en/... · 2 -providing a detailed explanation on the data set ofthe table franework 3-carry out alernative development scenarios

4 - Direct payment

For the period from For the period fromDate of transfer March 14,2013 to Dec Janl,2015 to Feb Beneficiary

31,2014 28,2016

20 Oct, 2014 29,576 Celine Ferre29 Dec, 2014 27,459 KhalidAlzubi8 Sep, 2015 12,200 Norma A/perin28 Jul, 2015 16,194 NormaAlperin16 Jun, 2015 19,970 Abdel BassetAL-A thamna

Total 57,034 48,364

5- Categories

For the period from For the period from Janl,2015 to Feb1 - category (1) March 14,2013 to Dec 28,2016constants and training services 31,2014KhaledAlzubi 54,959 41Celine Ferre 42,343

AhmadMobarak 21,000 21,000Nirma Alperin 36,040

Abdel Basset AL-Athamna 40,000Juan Munoz 15,975

Total 118,301 113,056

6. Note:

Numbers have been rounded to the nearest financial statements USD correctly.

20