Workgroup on the Assessment and Funding of School Facilities
Delegate Maggie McIntosh, Chair
Agenda
September 22, 2021
3:00 pm
Virtual Meeting
I. Call to Order and Opening Remarks
II. Gross Area Baselines in Public School Construction
Michael Rubenstein, Principal Analyst, DLS
III. Facilities Assessment and Educational Facilities Sufficiency
Standards
Bob Gorrell, Executive Director, IAC
Alex Donahue, Deputy Director of Field Operations, IAC
Tom Bart, Bureau Veritas
Bill Champion, Bureau Veritas
IV. Closing Remarks and Adjournment
September 22, 2021
Gross Area Baseline in Public School Construction
Presentation to theWorkgroup on the Assessment and Funding of
School Facilities
• “Consider and make recommendationsregarding the methods used to establish aGross Area Baseline and the MaximumState Construction Allocation for eachpublic school construction projectapproved for State funding.”
– SB 551 (Chapter 698 of 2021, also knownas Built to Learn 2.0)
Workgroup Charge
1
• Major factor in determining how much theState will pay for a new or renovated publicschool building
• Formula-based calculation that establishesthe square footage of a new or renovatedbuilding that is eligible for State funding
• Any square footage that exceeds the GrossArea Baseline (GAB) is entirely theresponsibility of the local government
What Is Gross Area Baseline?
2
• 21st Century School Facilities Act of 2018(Knott Commission bill) required a review ofthe per student square foot allocations used bythe Interagency Commission on SchoolConstruction (IAC)
• IAC approved the new GABs in May 2019based on recommendations by the Workgroupon Educational Development Specifications
• GABs replaced maximum Gross AreaAllowance
Origin of GABs
3
• For a Capital Improvement Program project, localeducation agencies (LEAs) submit a seven-yearenrollment projection for the school, including therationale and basis for the projection– State does not do enrollment projections for individual
schools
• LEAs also submit enrollment projections for adjacentschools– Allows IAC to assess if there is excess capacity in nearby
facilities
• IAC reviews LEA’s enrollment projection and makesa final determination regarding projected enrollment
Enrollment Projections
5
• Regular Education Students– 105 sq. ft. to 160 sq. ft.– Varies by level and size of school
• Special Education Students (Categories C/S/W)– 180 sq. ft. (elementary and middle schools)– 200 sq. ft. (high school)
• Career and Technical Education Students– 210 sq. ft. (high school only)
What Are Allowable Square Feet?
6
Middle School Square Feet
MIDDLE SCHOOLSGSF/Stu Total GSF
Projected Capacity
of Students*
Max. Gross Area
Allow.Gross Area Baselines
≤600 145 145
650 135 144 93,600
700 135 142 99,400
750 135 141 105,750
800 135 140 112,000
850 130 138 117,300
900 130 136 122,400
950 130 135 128,250
1000 130 134 134,000
1050 130 133 139,650
1100 130 132 145,200
1150 130 131 150,650
1200 130 130 156,000
1250 130 129 161,250 ≥1300 130 128
125
130
135
140
145
150
Previous Max. Gross Area Allowance Gross Area Baselines
8
High School Square Feet
HIGH SCHOOLS
GSF/Stu. Total GSF
Projected Capacity of Students* **
Existing Max. Gross
Area Allowance
Proposed Gross Area Baselines
≤ 800 160 160850 160 160 136,000 900 160 159 143,100 950 160 159 151,050
1,000 160 158 158,000 1,050 160 158 165,900 1,100 160 157 172,700 1,150 160 157 180,550 1,200 156 157 188,400 1,250 150 156 195,000 1,300 150 156 202,800 1,350 150 156 210,600 1,400 150 155 217,000 1,450 150 155 224,750 1,500 150 154 231,000 1,550 150 154 238,700 1,600 150 154 246,400 1,650 147 154 254,100 1,700 145 153 260,100 1,750 145 153 267,750 1,800 145 153 275,400 1,850 145 153 283,050 1,900 145 152 288,800 1,950 145 152 296,400 2,000 145 152 304,000 2,050 145 151 309,550 2,100 145 151 317,100 2,150 145 151 324,650 2,200 145 150 330,000 2,250 145 150 337,500 2,300 145 150 345,000 2,350 145 149 350,150 ≥2400 145 149
140
145
150
155
160
165
≤ 80
085
090
095
01,
000
1,05
01,
100
1,15
01,
200
1,25
01,
300
1,35
01,
400
1,45
01,
500
1,55
01,
600
1,65
01,
700
1,75
01,
800
1,85
01,
900
1,95
02,
000
2,05
02,
100
2,15
02,
200
2,25
02,
300
2,35
0≥2
400
Previous Max. Gross Area Allowance Gross Area Baselines
9
• Better alignment between educational specificationsand funding– State funding supports more square feet
• Enrollment projections are the foundation of GABcalculations– School-level enrollment projections are only available
from the LEAs
• New variance process allows IAC to approve largerdesigns based on demonstrated programmatic needs– On a case-by-case basis
Take Aways about GABs
11
September 22, 2021
IAC Staff and Bureau Veritas (SFA Vendor)
Presentation to the Workgroup on the
Assessment and Funding of School
Facilities
1
The Data Set
2
● Huge and very complex
○ >250,000 asset records with millions of data points
○ Data on spaces, building-system components, and student enrollments
● Sources
○ Provided by LEA
○ Collected by BV’s assessors on site
○ Calculated by BV based upon starting assumptions fitting most schools
● Living data set, not fixed
○ Starts with the 2020-2021 assessment data as the baseline
○ To be updated annually through
■ On-site assessments of 25% of schools statewide and
■ Mathematical aging of data of other 75% of schools by one year
The Initial Data Process
3
State LEA Review/Input
1) IAC provides starter school inventory
and enrollment data from MSDE records
1) LEA confirms inventory and provides
starting data set to the extent possible
a) List of assets with attributes (install
date, size, condition data, etc.)
b) List of spaces and their use
assignments, floor plans
2) BV assessors visit sites
a) Measure/confirm spaces
b) Confirm or log attributes of spaces
c) Assess condition of each building-
system component
2) QA/QC phase
a) LEA reviews collected data live
onscreen and can request changes
and offer corrections on
● Condition
● Space sufficiency
The Initial Data Process, cont’d.
4
State LEA Review/Input
3) BV reviews LEA suggestions and agree
or disagree with explanation to LEA
3) LEA can request QA/QC meetings as
desired to discuss any concerns or data
questions
4) IAC shares FCI data with LEAs 4) LEA can request further meetings with BV
and/or IAC staff at any time
Future Annual Reviews of Data● Process to take approximately six to nine months during which
○ IAC updates data on 25% via on-site assessments and 75% mathematically
○ LEAs provide updates resulting from locally funded/implemented changes
○ IAC presents draft data
○ LEAs review and comment/question/request changes
Physical Condition
Physical Condition
Facility Condition Index (FCI)
Educational Sufficiency
The usability of the space for supporting delivery of education
Combined Facility Score
Complete score
5
Calculating a Facility
Condition Index
Building-System Level
FCI 75%Amount Depleted
Lower is Better
=
Facility Level
FCI % =HVAC (FCI %) + Roof (FCI %) + Foundation (FCI %) + etc.
HVAC + Roof + Foundation + etc.
Depleted Value
Replacement Value6
Amount Depleted
Remaining Life
Remaining
Life
Facility Condition Index | FCI
7
HIGHER FCI● means less remaining useful lifespan (RUL)
LOWER FCI● means more remaining useful lifespan (RUL)
LOWER FCI = BETTER RELATIVE CONDITION
Lo
we
r is
be
tte
r
10
Average Depletion Level of Each Major Building SystemL
ow
er
is B
ett
er
Low
er
is B
ett
er
Educational Sufficiency
Physical Condition
Facility Condition Index (FCI)
Educational Sufficiency
The usability of the space for supporting delivery of education
Combined Facility Score
Complete score
11
Lo
we
r is
be
tte
r
12
Educational Facilities Sufficiency Standards
https://iac.mdschoolconstruction.org/?page_id=908
● Bare-minimum standards
● For existing PK-12
facilities
● For doing triage and for
comparability
● Not for use in designing
facilities
● Remediation not
mandatory
Lo
we
r is
be
tte
r
13
Sufficiency Deficiencies
The most significant deficiencies can be grouped into two categories:
Deficiency Type Method of Accounting
1) SPACE: Insufficient square
footage within a space type
Multiply missing square footage by the replacement
value of square footage ($400/SF).
2) SPACE ATTRIBUTES
a) Lighting
b) Temperature and relative
humidity
c) Acoustics
d) Air quality
● Where the deficiency is substantial and
widespread throughout the facility, adjust the
Remaining Useful Lifespan (RUL) of the
relevant building system to reflect its
insufficiency.
● Deficiencies posing a threat to facility usability
are placed into a special category for extra
emphasis.
Lo
we
r is
be
tte
r
14
Spaces Measured for Sufficiency
Educational Facilities Sufficiency Standards
1) Administrative
2) Auditorium
3) Cafeteria
4) Career Development
5) Custodial & Maintenance
6) Dining
7) Fine Arts
8) General Classroom
9) Gymnasium
10) Health Services
11) Kitchen
12) Library/Media Center
13) Locker Room
14) Pupil Services
15) Science
16) Special Education
17) Storage (non-classroom)
18) Technology & Computer Science
19) Teacher Workspace/Lounge
Items Checked for Presence
and/or Number as Appropriate
1) Play Field
2) Unpaved Recreation Area
3) Hard-Surface Court
4) Parking Spaces
Lo
we
r is
be
tte
r
15
Square-Footage-Related Space Standards
Educational Facilities Sufficiency Standards
● Multiply Projected Enrollment by
minimum square feet per student in
the Standards
Example:
General-Use Classrooms
Projected Enrollment of 1,500
X
25 NSF per student
=
37,500 NSF for 1,500 students
Step 1: Calculate Minimum Required space.
● Project fifth-year future enrollment using straight-line projection from current and
previous four years’ enrollments.
16
Calculating Space Deficiencies
Example:
Declining enrollment trends receive a growth factor of 1.0 (= flat).
17
Calculating Space Deficiencies
Step 2: Subtract actual square footage from the minimum required space to determine
the space deficiency.
● Deduct 20% of the actual space for those general classrooms that are open-plan-type
spaces
Step 3: Add up all the space deficiencies into a total space deficiency figure for the
facility.
● NOTE: Space deficiencies are only “netted” against any extra space found in that space
type, not against any extra space found in other types of space in the facility.
Step 1 (cont’d): Calculate minimum required space for the selected space type.
● Multiply projected enrollment by minimum square feet per student in the Standards.
19
Relocatables and Modulars
● Relocatables: Free-standing structure that can be
relatively easily moved to another site. Expected
Useful Life Remaining = 15.
● Modulars: More than 24 feet wide and installed
upon a foundation or not easily moved to another
site. Expected Useful Life Remaining = 20.
● BOTH: Each one is assessed as a building system
and assigned a remaining useful life span
(Remaining Useful Life) figure and an FCI figure.
● When RUL = zero, the square footage also gets
counted as a space deficiency in the general-
classroom category.
○ 116,077 SF (11%) of relocatables have an RUL
of zero.
○ 199,189 SF (10%) of modulars have an RUL
of zero.
Lo
we
r is
be
tte
r
20
Space Deficiencies by Type -- Statewide L
ow
er
is B
ett
er
*Data for these categories is small enough that it is not visible at current chart scale
Main Building(s)
Additional Space Required to Meet Minimum Standard
Combined Facility Score
Physical Condition
Facility Condition Index (FCI)
Educational Sufficiency
The usability of the space for supporting delivery of education
Combined Facility Score
Complete score
21
Lo
we
r is
be
tte
r
22
Proposed Categories in the Combined Facility Score
# Category Title Description1 Threat to Life/Safety/Health or Facility
Usability
Issues that pose immediate or potential threats to the life, health, or
safety of persons within the facility or to the usability of the facility
(i.e., results in the facility having to be closed to educational uses).
2 Space Deficiency Space(s) insufficient as measured against the Standard(s) for that
space type.
3 Damaging Other Systems Systems or deficiencies that require repairs to in order to prevent or
mitigate damage occurring to other building systems.
4 Degraded w/ Potential Mission Impact Systems that are mission critical and are beyond expected lifespan
OR systems that are at 200% or more of expected lifespan.
5 Beyond Expected Lifespan Systems that are at 100% to 200% of expected lifespan but show no
signs of required repairs.
6 Grandfathered Deficiencies Deficiencies that are “grandfathered” violations of State or locally
adopted codes, regulations, or standards.
7 Sufficiency Deficiencies—Facility Deficiencies related to sufficiency standards for fixed equipment
and inherent parts of the facility.
8 Sufficiency Deficiencies—Equipment Deficiencies related to sufficiency standards for non-fixed
equipment.
9 Functioning & Within Expected Lifespan Systems that are within their expected lifespan and do not require
replacement.
FCI
Space Data
Facility Data
Maryland Educational
Facilities Sufficiency Standards
Facility Data
Combined Facility Score
23
Categorizing the Issues Found
# Proposed Category
1Threat to Life/Safety/Health or
Facility Usability
2 Space Deficiency
3 Damaging Other Systems
4Degraded w/ Potential Mission
Impact
5 Beyond Expected Lifespan
6 Grandfathered Deficiencies
7 Sufficiency Deficiencies—Facility
8Sufficiency Deficiencies—
Equipment
9Functioning & Within Expected
Lifespan
Value to Replace
Effective Age of System
System Expected Life
Percent Degraded
FCI
Population Year 1
Population Year 2
Population Year 4
Population Year 5
Population Year 3Growth Factor
Space Data
Facility Data
Maryland Educational
Facilities Sufficiency Standards
24
Categorizing the Issues Found
Combined Facility Score
# Proposed Category
1Threat to Life/Safety/Health or Facility
Usability
2 Space Deficiency
3 Damaging Other Systems
4 Degraded w/ Potential Mission Impact
5 Beyond Expected Lifespan
6 Grandfathered Deficiencies
7 Sufficiency Deficiencies—Facility
8 Sufficiency Deficiencies—Equipment
9 Functioning & Within Expected Lifespan
Space Data
Building System
Lifespan Data
> 200% EUL?
Beyond EUL?
No
Yes
No
YesCritical?Yes
No
25
Categorizing the Issues Found
Combined Facility Score
# Proposed Category
1Threat to Life/Safety/Health or
Facility Usability
2 Space Deficiency
3 Damaging Other Systems
4Degraded w/ Potential Mission
Impact
5 Beyond Expected Lifespan
6 Grandfathered Deficiencies
7Sufficiency Deficiencies—
Facility
8Sufficiency Deficiencies—
Equipment
9Functioning & Within
Expected Lifespan
Yes
Space Data
Building System
CriticalCode IssuePrevent Damage
Critical Safety/ Threat
?
Yes
3-Prevent DamageNo
Deficiencies
6-Grandfathered
7-Facility Sufficiency
8-Equipment Sufficiency
26
Categorizing the Issues Found
Combined Facility Score
# Proposed Category
1Threat to Life/Safety/Health or
Facility Usability
2 Space Deficiency
3 Damaging Other Systems
4Degraded w/ Potential Mission
Impact
5 Beyond Expected Lifespan
6 Grandfathered Deficiencies
7Sufficiency Deficiencies—
Facility
8Sufficiency Deficiencies—
Equipment
9Functioning & Within Expected
Lifespan
Issues by Category
Category Share
1 - Threat to Life/Safety/Health or Facility
Usability 0.14%
2 - Space Deficiency 6.20%
3 - Damaging Other Systems 0.08%
4 - Degraded w/ Potential Mission Impact 0.52%
5 - Beyond Expected Lifespan 18.40%
6 - Grandfathered Deficiencies 1.00%
7 - Sufficiency Deficiencies - Facility 0.11%
9 - Functioning & Within Expected
Lifespan 73.54%
Total 100.00%
27
28
Issues that pose immediate or
potential threats to
● The life, safety, or health of
persons within the facility;
OR
● The usability of the facility
(i.e., results in the facility
having to be closed to
educational uses)
Category 1: Threats to Life, Safety,
Health, or Facility Usability (71)
● Air Conditioning Absent in 20%-plus of Classrooms (32)● Asphalt Pavement - Pedestrian (2)● Asphalt Pavement - Vehicular (3)● Athletic Surface - Lawn Area (2)● Brick (1)● Concrete Pavement - Pedestrian (1)● Fire Alarm System (14)● Gypsum Board/Plaster Ceiling● Modular Building - Classroom/Office - Standard (1)● Quarry Tile (2)● Relocatable Building - Classroom/Office - Standard (2)● Sports Courts (1)● Sprinkler System (2)● Switchgear/board w/Sub Panels - Medium Density (1)● Vinyl Composition Tile (VCT) (4)● Window (1)● Wood Sports Floor (1)
Lo
we
r is
be
tte
r
29
Proposed Categories in the Combined Facility Score
# Category Title Description1 Threat to Life/Safety/Health or Facility
Usability
Issues that pose immediate or potential threats to the life, health, or
safety of persons within the facility or to the usability of the facility
(i.e., results in the facility having to be closed to educational uses).
2 Space Deficiency Space(s) insufficient as measured against the Standard(s) for that
space type.
3 Damaging Other Systems Systems or deficiencies that require repairs to in order to prevent or
mitigate damage occurring to other building systems.
4 Degraded w/ Potential Mission Impact Systems that are mission critical and are beyond expected lifespan
OR systems that are at 200% or more of expected lifespan.
5 Beyond Expected Lifespan Systems that are at 100% to 200% of expected lifespan but show no
signs of required repairs.
6 Grandfathered Deficiencies Deficiencies that are “grandfathered” violations of State or locally
adopted codes, regulations, or standards.
7 Sufficiency Deficiencies—Facility Deficiencies related to sufficiency standards for fixed equipment
and inherent parts of the facility.
8 Sufficiency Deficiencies—Equipment Deficiencies related to sufficiency standards for non-fixed
equipment.
9 Functioning & Within Expected Lifespan Systems that are within their expected lifespan and do not require
replacement.
Workgroup on the Assessment and Funding of School Facilities
Delegate Maggie McIntosh, Chair
Wednesday, October 20 at 3:00 p.m.
Wednesday, November 3rd at 3:00 p.m.
Wednesday, November 17th at 3:00 p.m.
Wednesday, December 1st at 3:00 p.m.
Wednesday, December 15th at 3:00 p.m.
Low
er is
bet
ter
Statewide Facility Condition Distribution by Band•Facility Population of 1,383•Arithmetic Mean of 48.4%•Std Deviation of 14.9%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 2 0%
Band2 (0.70-0.79) 12 1%
Band3 (0.60-0.69) 237 17%
Band4 (0.50-0.59) 551 40%
Band5 (0.40-0.49) 308 22%
Band6 (0.30-0.39) 117 8%
Band7 (0.20-0.29) 53 4%
Band8 (0.10-0.19) 47 3%
Band9 (0.00-0.09) 54 4%
Total 1,383 100%
2 12
238
551
308
117
53 47 55
0
100
200
300
400
500
600
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
1
Low
er is
bet
ter
Statewide Average FCI by Major Building System
57%54%
50%53% 54%
47%51% 51%
63%
54% 57%
69%
50%45%
50%
37%
51%
0%
10%
20%
30%
40%
50%
60%
70%
80%
Average FCI by Major Building System
2
Low
er is
bet
ter
Low
er is
Bet
ter
*Data for these categories is small enough that it is not visible at current chart scale
0 500,000 1,000,000 1,500,000 2,000,000 2,500,000
Workspace/LoungePupil ServicesAdministrative
Career DevelopmentKitchen
Special EducationStorage (Non-Classroom)
Health ServicesMaintenance / Janitorial Space
Library/Media CenterScience
DiningFine Arts
Technology and Computer ScienceGymnasium / Cafeteria / Auditorium
General Classroom
Main Building(s) Relocatable Modular
Space Deficiencies by Type – StatewideAdditional Space Required to Meet Minimum Standard
**
3
square feet
Low
er is
bet
ter
Allegany Facility Condition Distribution by Band•Facility Population of 22•Arithmetic Mean of 60.6%•Std Deviation of 13.4%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 2 9%
Band3 (0.60-0.69) 17 77%
Band4 (0.50-0.59) 1 5%
Band5 (0.40-0.49) 0 0%
Band6 (0.30-0.39) 1 5%
Band7 (0.20-0.29) 0 0%
Band8 (0.10-0.19) 0 0%
Band9 (0.00-0.09) 1 5%
Total 22 100%
0
2
17
10
10 0
1
0
2
4
6
8
10
12
14
16
18
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
4
Low
er is
bet
ter
Allegany Average FCI by Major Building System
69% 69%
59%65% 65%
49%
67%63% 65% 65%
50% 52%
60%
49%
62%
0%
10%
20%
30%
40%
50%
60%
70%
80%
Average FCI by Major Building System
5
Space Deficiencies by Type – Allegany
0 2,000 2,500 3,000 3,500
Dining
Pupil Services
Maintenance / Janitorial Space
Storage (Non-Classroom)
Special Education
Library/Media Center
Health Services
Fine Arts
Technology and Computer Science
500 1,000 1,500
Relocatable Modular
Additional Space Required to Meet Minimum Standard
Main Building(s)
6
square feet
Low
er is
bet
ter
Anne Arundel Facility Condition Distribution by Band•Facility Population of 121•Arithmetic Mean of 42.7%•Std Deviation of 14.1%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 0 0%
Band3 (0.60-0.69) 5 4%
Band4 (0.50-0.59) 38 31%
Band5 (0.40-0.49) 38 31%
Band6 (0.30-0.39) 21 17%
Band7 (0.20-0.29) 8 7%
Band8 (0.10-0.19) 6 35%
Band9 (0.00-0.09) 5 4%
Total 121 100%
0 0
5
38 38
21
86 5
0
5
10
15
20
25
30
35
40
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
8
Low
er is
bet
ter
Anne Arundel Average FCI by Major Building System
50%
44% 46%
59%
47%43%
37%
48%
28%
53% 52%
40%
50%
38%
45%
30%
40%
0%
10%
20%
30%
40%
50%
60%
70%
Average FCI by Major Building System
7
Space Deficiencies by Type – Anne Arundel
- 50,000 60,000 70,000 80,000 90,000 100,000
Pupil Services
Administrative
Kitchen
Career Development
Special Education
Library/Media Center
Storage (Non-Classroom)
Health Services
Maintenance / Janitorial Space
Science
Dining
Fine Arts
Gymnasium / Cafeteria / Auditorium
Technology and Computer Science
General Classroom
10,000 20,000 30,000 40,000
Relocatable Modular
Additional Space Required to Meet Minimum Standard
Main Building(s)
*
*Data for these categories is small enough that it is not visible at current chart scale 9
square feet
Low
er is
bet
ter
Balitmore City Facility Condition Distribution by Band•Facility Population of 149•Arithmetic Mean of 47.9%•Std Deviation of 21.0%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 2 1%
Band2 (0.70-0.79) 4 3%
Band3 (0.60-0.69) 44 30%
Band4 (0.50-0.59) 43 29%
Band5 (0.40-0.49) 24 16%
Band6 (0.30-0.39) 3 2%
Band7 (0.20-0.29) 1 1%
Band8 (0.10-0.19) 12 8%
Band9 (0.00-0.09) 16 11%
Total 149 100%2
4
44 43
24
31
12
16
0
5
10
15
20
25
30
35
40
45
50
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
10
Low
er is
bet
ter
Balitmore City Average FCI by Major Building System
52%46% 46%
64%
46%49%
54%
38%
47%53% 53%
72%
46%42%
50%
43%46%
0%
10%
20%
30%
40%
50%
60%
70%
80%
Average FCI by Major Building System
11
Space Deficiencies by Type – Baltimore City
0 150,000 200,000 250,000
Pupil Services
Administrative
Special Education
Career Development
Kitchen
Storage (Non-Classroom)
Maintenance / Janitorial Space
Health Services
Library/Media Center
Technology and Computer Science
Science
Fine Arts
Dining
Gymnasium / Cafeteria / Auditorium
General Classroom
50,000 100,000
Relocatable Modular
Additional Space Required to Meet Minimum Standard
Main Building(s)
**
*Data for these categories is small enough that it is not visible at current chart scale12
square feet
Low
er is
bet
ter
Balitimore County Facility Condition Distribution by Band•Facility Population of 165•Arithmetic Mean of 45.9%•Std Deviation of 12.9%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 0 0%
Band3 (0.60-0.69) 7 4%
Band4 (0.50-0.59) 62 38%
Band5 (0.40-0.49) 68 41%
Band6 (0.30-0.39) 13 8%
Band7 (0.20-0.29) 3 2%
Band8 (0.10-0.19) 5 3%
Band9 (0.00-0.09) 7 4%
Total 165 100%
0 0
7
62
68
13
35
7
0
10
20
30
40
50
60
70
80
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
13
Low
er is
bet
ter
Balitimore County Average FCI by Major Building System
55%
45%39%
64%
47% 49%52%
47%
33%
56% 58%
38%
46%
55%51%
33%
60%
0%
10%
20%
30%
40%
50%
60%
70%
Average FCI by Major Building System
14
Space Deficiencies by Type – Baltimore County
0 150,000 200,000 250,000 300,000
Pupil Services
Kitchen
Career Development
Administrative
Special Education
Storage (Non-Classroom)
Health Services
Maintenance / Janitorial Space
Science
Library/Media Center
Dining
Gymnasium / Cafeteria / Auditorium
Technology and Computer Science
Fine Arts
General Classroom
50,000 100,000
Relocatable Modular
Additional Space Required to Meet Minimum Standard
Main Building(s)
**
*Data for these categories is small enough that it is not visible at current chart scale15
square feet
Low
er is
bet
ter
Calvert Facility Condition Distribution by Band•Facility Population of 68•Arithmetic Mean of 47.3%•Std Deviation of 16.0%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 0 0%
Band3 (0.60-0.69) 5 9%
Band4 (0.50-0.59) 13 53%
Band5 (0.40-0.49) 3 19%
Band6 (0.30-0.39) 1 6%
Band7 (0.20-0.29) 2 4%
Band8 (0.10-0.19) 0 1%
Band9 (0.00-0.09) 1 7%
Total 25 100%
0 0
6
36
13
43
1
5
0
5
10
15
20
25
30
35
40
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
16
Low
er is
bet
ter
Calvert Average FCI by Major Building System
55%61%
54%
43%
57%
41%48% 52%
95%
52%46%
66%58%
41%49%
26%
40%
0%
20%
40%
60%
80%
100%
120%
Average FCI by Major Building System
17
Space Deficiencies by Type – Calvert
0 5,000 10,000 15,000 20,000 25,000 30,000
Kitchen
Career Development
Storage (Non-Classroom)
Library/Media Center
Maintenance / Janitorial Space
Health Services
General Classroom
Fine Arts
Technology and Computer Science
Dining
Gymnasium / Cafeteria / Auditorium
Main Building(s) Relocatable Modular
Additional Space Required to Meet Minimum Standard
18
square feet
Low
er is
bet
ter
Caroline Facility Condition Distribution by Band•Facility Population of 10•Arithmetic Mean of 45.5%•Std Deviation of 17.9%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 0 0%
Band3 (0.60-0.69) 1 10%
Band4 (0.50-0.59) 6 60%
Band5 (0.40-0.49) 0 0%
Band6 (0.30-0.39) 1 10%
Band7 (0.20-0.29) 1 10%
Band8 (0.10-0.19) 0 0%
Band9 (0.00-0.09) 1 10%
Total 10 100%
0 0
1
6
0
1 1
0
1
0
1
2
3
4
5
6
7
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
19
Low
er is
bet
ter
Caroline Average FCI by Major Building System
51%
41% 41% 42%
53%46%
40% 38%
85%
39%45%
60%
43%39%
49%
39%
56%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
Average FCI by Major Building System
20
Space Deficiencies by Type – Caroline
0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 9,000
Library/Media Center
Health Services
Special Education
Kitchen
Dining
Science
Storage (Non-Classroom)
Maintenance / Janitorial Space
Fine Arts
General Classroom
Technology and Computer Science
Main Building(s) Relocatable Modular
Additional Space Required to Meet Minimum Standard
21
square feet
Low
er is
bet
ter
Carroll Facility Condition Distribution by Band•Facility Population of 40•Arithmetic Mean of 51.2%•Std Deviation of 9.2%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 1 3%
Band3 (0.60-0.69) 3 8%
Band4 (0.50-0.59) 21 53%
Band5 (0.40-0.49) 11 28%
Band6 (0.30-0.39) 3 8%
Band7 (0.20-0.29) 1 3%
Band8 (0.10-0.19) 0 0%
Band9 (0.00-0.09) 0 0%
Total 40 100%
01
3
21
11
3
10 0
0
5
10
15
20
25
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
22
Low
er is
bet
ter
Carroll Average FCI by Major Building System
61%
69%
55% 56%62%
50%
59% 62%
81%
56%
64%
85%
41%45%
54%
36%
64%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
Average FCI by Major Building System
23
Space Deficiencies by Type – Carroll
0 60,000 80,000 100,000 120,000
Administrative
Pupil Services
Kitchen
Special Education
Dining
Maintenance / Janitorial Space
Storage (Non-Classroom)
Health Services
Science
Fine Arts
Technology and Computer Science
Gymnasium / Cafeteria / Auditorium
General Classroom
20,000 40,000
Relocatable Modular
Additional Space Required to Meet Minimum Standard
Main Building(s)
**
*Data for these categories is small enough that it is not visible at current chart scale24
square feet
Low
er is
bet
ter
Cecil Facility Condition Distribution by Band•Facility Population of 29•Arithmetic Mean of 50.2%•Std Deviation of 11.8%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 0 0%
Band3 (0.60-0.69) 6 21%
Band4 (0.50-0.59) 11 38%
Band5 (0.40-0.49) 8 28%
Band6 (0.30-0.39) 3 10%
Band7 (0.20-0.29) 0 0%
Band8 (0.10-0.19) 0 0%
Band9 (0.00-0.09) 1 3%
Total 29 100%
0 0
6
11
8
3
0 0
1
0
2
4
6
8
10
12
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
25
Low
er is
bet
ter
Cecil Average FCI by Major Building System
67% 66%
53%
62% 61%
51%
60%55%
37%
58%63%
55%48% 51%
34%
57%
0%
10%
20%
30%
40%
50%
60%
70%
80%
Average FCI by Major Building System
26
Space Deficiencies by Type – Cecil
15,000 20,000 25,000
Pupil Services
Administrative
Science
Special Education
Storage (Non-Classroom)
General Classroom
Maintenance / Janitorial Space
Health Services
Dining
Fine Arts
Technology and Computer Science
Gymnasium / Cafeteria / Auditorium
0 5,000 10,000
Relocatable Modular
Additional Space Required to Meet Minimum Standard
Main Building(s)
*
*Data for these categories is small enough that it is not visible at current chart scale27
square feet
Low
er is
bet
ter
Charles Facility Condition Distribution by Band•Facility Population of 39•Arithmetic Mean of 49.8%•Std Deviation of 15.7%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 0 0%
Band3 (0.60-0.69) 8 21%
Band4 (0.50-0.59) 22 56%
Band5 (0.40-0.49) 2 5%
Band6 (0.30-0.39) 2 5%
Band7 (0.20-0.29) 1 3%
Band8 (0.10-0.19) 3 8%
Band9 (0.00-0.09) 1 3%
Total 39 100%
0 0
8
22
2 21
3
1
0
5
10
15
20
25
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
28
Low
er is
bet
ter
Charles Average FCI by Major Building System
54%
44%
53%47%
54%47% 49%
54%
80%
56% 53%
91%
60%
45% 46%
30%
43%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Average FCI by Major Building System
29
Space Deficiencies by Type – Charles
60,000 80,000 100,000 120,000
Special Education
Storage (Non-Classroom)
Library/Media Center
Health Services
Maintenance / Janitorial Space
Science
Fine Arts
Dining
Technology and Computer Science
Gymnasium / Cafeteria / Auditorium
General Classroom
0 20,000 40,000
Relocatable Modular
Additional Space Required to Meet Minimum Standard
Main Building(s)
30
square feet
Low
er is
bet
ter
Dorchester Facility Condition Distribution by Band•Facility Population of 14•Arithmetic Mean of 47.2%•Std Deviation of 15.9%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 0 0%
Band3 (0.60-0.69) 3 21%
Band4 (0.50-0.59) 5 36%
Band5 (0.40-0.49) 3 21%
Band6 (0.30-0.39) 1 7%
Band7 (0.20-0.29) 1 7%
Band8 (0.10-0.19) 0 0%
Band9 (0.00-0.09) 1 7%
Total 14 100%
0 0
3
5
3
1 1
0
1
0
1
2
3
4
5
6
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
31
Low
er is
bet
ter
Dorchester Average FCI by Major Building System
56%
42% 44%49%
57%
28%
48%53%
79%
56% 54%
86%
32%
44%38%
30%
61%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
Average FCI by Major Building System
32
0 2,000 4,000 6,000 8,000 10,000 12,000 14,000
Storage (Non-Classroom)
Special Education
Kitchen
Maintenance / Janitorial Space
Health Services
Fine Arts
Dining
Technology and Computer Science
General Classroom
Gymnasium / Cafeteria / Auditorium
Main Building(s) Relocatable Modular
Space Deficiencies by Type – DorchesterAdditional Space Required to Meet Minimum Standard
33
square feet
Low
er is
bet
ter
Frederick Facility Condition Distribution by Band•Facility Population of 68•Arithmetic Mean of 47.3%•Std Deviation of 16.0%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 0 0%
Band3 (0.60-0.69) 6 9%
Band4 (0.50-0.59) 36 53%
Band5 (0.40-0.49) 13 19%
Band6 (0.30-0.39) 4 6%
Band7 (0.20-0.29) 3 4%
Band8 (0.10-0.19) 1 1%
Band9 (0.00-0.09) 5 7%
Total 68 100%
0 0
6
36
13
43
1
5
0
5
10
15
20
25
30
35
40
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
34
Low
er is
bet
ter
Frederick Average FCI by Major Building System
57%
49% 47%51%
54%
46%
54%48%
58%
46%
54%
67%
57%
43%47%
32%
43%
0%
10%
20%
30%
40%
50%
60%
70%
80%
Average FCI by Major Building System
35
Space Deficiencies by Type – Frederick
150,000 200,000 250,000
Pupil Services
Kitchen
Administrative
Storage (Non-Classroom)
Special Education
Library/Media Center
Science
Health Services
Maintenance / Janitorial Space
Dining
Fine Arts
Technology and Computer Science
Gymnasium / Cafeteria / Auditorium
General Classroom
0 50,000 100,000
Relocatable Modular
Additional Space Required to Meet Minimum Standard
Main Building(s)
*
*Data for these categories is small enough that it is not visible at current chart scale36
square feet
Low
er is
bet
ter
Garrett Facility Condition Distribution by Band•Facility Population of 13•Arithmetic Mean of 54.0•Std Deviation of 6.7%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 0 0%
Band3 (0.60-0.69) 3 23%
Band4 (0.50-0.59) 6 46%
Band5 (0.40-0.49) 4 31%
Band6 (0.30-0.39) 0 0%
Band7 (0.20-0.29) 0 0%
Band8 (0.10-0.19) 0 0%
Band9 (0.00-0.09) 0 0%
Total 13 100%
0 0
3
6
4
0 0 0 00
1
2
3
4
5
6
7
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
37
Low
er is
bet
ter
Garrett Average FCI by Major Building System
65%58%
64%
50%56% 58%
64%56%
90%
69%
54%
40%
60%
41%
51%44% 43%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Average FCI by Major Building System
38
Space Deficiencies by Type – Garrett
0 4,000 5,000 6,000 7,000 8,000
Library/Media Center
Pupil Services
Storage (Non-Classroom)
Kitchen
General Classroom
Maintenance / Janitorial Space
Special Education
Health Services
Fine Arts
Gymnasium / Cafeteria / Auditorium
1,000 2,000 3,000
Relocatable Modular
Additional Space Required to Meet Minimum Standard
Main Building(s)
39
square feet
Low
er is
bet
ter
Harford Facility Condition Distribution by Band•Facility Population of 52•Arithmetic Mean of 49.4%•Std Deviation of 14.4%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 0 0%
Band3 (0.60-0.69) 11 21%
Band4 (0.50-0.59) 21 40%
Band5 (0.40-0.49) 9 17%
Band6 (0.30-0.39) 5 10%
Band7 (0.20-0.29) 3 6%
Band8 (0.10-0.19) 2 4%
Band9 (0.00-0.09) 1 2%
Total 52 100%
0 0
11
21
9
5
32
1
0
5
10
15
20
25
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
40
Low
er is
bet
ter
Harford Average FCI by Major Building System
48%
55%
43%
60%
52%47%
55% 55%
35%
59% 60% 62%
54%
44%47%
34%
63%
0%
10%
20%
30%
40%
50%
60%
70%
Average FCI by Major Building System
41
- 10,000 20,000 30,000 40,000 50,000 60,000 70,000 80,000 90,000 100,000
Pupil Services
Career Development
Kitchen
Special Education
Library/Media Center
Storage (Non-Classroom)
Health Services
Maintenance / Janitorial Space
Dining
Fine Arts
Technology and Computer Science
Gymnasium / Cafeteria / Auditorium
General Classroom
Main Building(s) Relocatable Modular
Space Deficiencies by Type – HarfordAdditional Space Required to Meet Minimum Standard
*Data for these categories is small enough that it is not visible at current chart scale
*
42
square feet
Low
er is
bet
ter
Howard Facility Condition Distribution by Band•Facility Population of 76•Arithmetic Mean of 44.9%•Std Deviation of 10.6%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 0 1%
Band3 (0.60-0.69) 4 5%
Band4 (0.50-0.59) 23 30%
Band5 (0.40-0.49) 31 41%
Band6 (0.30-0.39) 10 13%
Band7 (0.20-0.29) 6 8%
Band8 (0.10-0.19) 1 1%
Band9 (0.00-0.09) 1 1%
Total 76 100%
0 0
4
23
31
10
6
1 1
0
5
10
15
20
25
30
35
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
43
Low
er is
bet
ter
Howard Average FCI by Major Building System
50%53%
40%
48%
54%
47% 46% 45%
18%
49%
56%
65%
51%46%
49%
34%
44%
0%
10%
20%
30%
40%
50%
60%
70%
Average FCI by Major Building System
44
Space Deficiencies by Type – Howard
150,000 200,000 250,000 300,000
Workspace/Lounge
Kitchen
Special Education
Career Development
Science
Administrative
Health Services
Storage (Non-Classroom)
Library/Media Center
Maintenance / Janitorial Space
Dining
Fine Arts
Gymnasium / Cafeteria / Auditorium
Technology and Computer Science
General Classroom
0 50,000 100,000
Relocatable Modular
Additional Space Required to Meet Minimum Standard
Main Building(s)
**
*Data for these categories is small enough that it is not visible at current chart scale45
square feet
Low
er is
bet
ter
Kent Facility Condition Distribution by Band•Facility Population of 5•Arithmetic Mean of 53.9%•Std Deviation of 8.9%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 0 0%
Band3 (0.60-0.69) 1 20%
Band4 (0.50-0.59) 3 60%
Band5 (0.40-0.49) 0 0%
Band6 (0.30-0.39) 1 20%
Band7 (0.20-0.29) 0 0%
Band8 (0.10-0.19) 0 0%
Band9 (0.00-0.09) 0 0%
Total 5 100%
0 0
1
3
0
1
0 0 00
0.5
1
1.5
2
2.5
3
3.5
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
46
Low
er is
bet
ter
Kent Average FCI by Major Building System
66%
80%
48%
59%51%
60%54% 54%
66% 66% 64%
45%
61%55%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
Average FCI by Major Building System
47
Space Deficiencies by Type – Kent
8,000 10,000 12,000 14,000 16,000
Science
Health Services
Special Education
Library/Media Center
Technology and Computer Science
Dining
Fine Arts
General Classroom
0 2,000 4,000 6,000
Relocatable Modular
Additional Space Required to Meet Minimum Standard
Main Building(s)
48
square feet
Low
er is
bet
ter
Montgomery Facility Condition Distribution by Band•Facility Population of 213•Arithmetic Mean of 47.5%•Std Deviation of 15.1%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 2 1%
Band3 (0.60-0.69) 33 15%
Band4 (0.50-0.59) 92 43%
Band5 (0.40-0.49) 38 18%
Band6 (0.30-0.39) 20 9%
Band7 (0.20-0.29) 11 45%
Band8 (0.10-0.19) 9 4%
Band9 (0.00-0.09) 8 4%
Total 213 100%
0 2
33
92
38
20
11 9 8
0
10
20
30
40
50
60
70
80
90
100
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
49
Low
er is
bet
ter
Montgomery Average FCI by Major Building System
60%54% 52%
63%
50%44%
51% 48%
26%
49%
59%
36%
44% 46% 49%
30%
55%
0%
10%
20%
30%
40%
50%
60%
70%
Average FCI by Major Building System
50
Space Deficiencies by Type – Montgomery
200,000 250,000 300,000 350,000
Pupil Services
Administrative
Career Development
Special Education
Kitchen
Storage (Non-Classroom)
Health Services
Science
Maintenance / Janitorial Space
Library/Media Center
Dining
Fine Arts
Technology and Computer Science
Gymnasium / Cafeteria / Auditorium
General Classroom
0 50,000 100,000 150,000
Relocatable Modular
Additional Space Required to Meet Minimum Standard
Main Building(s)
**
*Data for these categories is small enough that it is not visible at current chart scale51
square feet
Low
er is
bet
ter
Prince George’s Facility Condition Distribution by Band•Facility Population of 198•Arithmetic Mean of 52.1%•Std Deviation of 10.8%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 2 1%
Band3 (0.60-0.69) 40 20%
Band4 (0.50-0.59) 93 47%
Band5 (0.40-0.49) 37 19%
Band6 (0.30-0.39) 15 8%
Band7 (0.20-0.29) 7 4%
Band8 (0.10-0.19) 4 2%
Band9 (0.00-0.09) 0 0%
Total 198 100%
0 2
40
93
37
15
74
00
10
20
30
40
50
60
70
80
90
100
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
52
Low
er is
bet
ter
Prince George’s Average FCI by Major Building System
61%
50%
57% 58%
51% 52%
62%59%
35%
60% 60%57% 56%
50%54%
37%
45%
0%
10%
20%
30%
40%
50%
60%
70%
Average FCI by Major Building System
53
Space Deficiencies by Type – Prince George’s
200,000 250,000 300,000 350,000
Workspace/LoungePupil Services
KitchenCareer Development
AdministrativeSpecial Education
Storage (Non-Classroom)Health Services
Maintenance / Janitorial SpaceScience
Library/Media CenterDining
Technology and Computer ScienceFine Arts
Gymnasium / Cafeteria / AuditoriumGeneral Classroom
0 50,000 100,000 150,000
Relocatable Modular
Additional Space Required to Meet Minimum Standard
Main Building(s)
**
*Data for these categories is small enough that it is not visible at current chart scale54
square feet
Low
er is
bet
ter
Queen Anne’s Facility Condition Distribution by Band•Facility Population of 14•Arithmetic Mean of 46.8%•Std Deviation of 9.3%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 0 0%
Band3 (0.60-0.69) 0 0%
Band4 (0.50-0.59) 7 50%
Band5 (0.40-0.49) 4 29%
Band6 (0.30-0.39) 2 14%
Band7 (0.20-0.29) 1 7%
Band8 (0.10-0.19) 0 0%
Band9 (0.00-0.09) 0 0%
Total 14 100%
0 0 0
7
4
2
1
0 00
1
2
3
4
5
6
7
8
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
55
Low
er is
bet
ter
Queen Anne’s Average FCI by Major Building System
61%57%
45% 49%
59%
44% 45%49%
95%
46%53%
78%
60%
46%52%
35%
55%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Average FCI by Major Building System
56
Space Deficiencies by Type – Queen Anne’s
0 4,000 5,000 6,000 7,000 8,000
Special Education
Maintenance / Janitorial Space
Health Services
General Classroom
Fine Arts
Technology and Computer Science
Gymnasium / Cafeteria / Auditorium
1,000 2,000 3,000
Relocatable Modular
Additional Space Required to Meet Minimum Standard
Main Building(s)
57
square feet
Low
er is
bet
ter
Somerset Facility Condition Distribution by Band•Facility Population of 11•Arithmetic Mean of 49.2%•Std Deviation of 16.3%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 0 0%
Band3 (0.60-0.69) 1 9%
Band4 (0.50-0.59) 7 64%
Band5 (0.40-0.49) 1 9%
Band6 (0.30-0.39) 1 9%
Band7 (0.20-0.29) 0 0%
Band8 (0.10-0.19) 0 0%
Band9 (0.00-0.09) 1 9%
Total 11 100%0 0
1
7
1 1
0 0
1
0
1
2
3
4
5
6
7
8
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
58
Low
er is
bet
ter
Somerset Average FCI by Major Building System
45%40%
46% 45%40%
47%40% 39%
100%
42%50%
75%
31%
49% 48%
34%
51%
0%
20%
40%
60%
80%
100%
120%
Average FCI by Major Building System
59
Space Deficiencies by Type – Somerset
0 6,000 8,000 10,000 12,000
Pupil Services
Administrative
Workspace/Lounge
Science
Dining
Kitchen
Career Development
Maintenance / Janitorial Space
Health Services
Library/Media Center
Fine Arts
Technology and Computer Science
General Classroom
Gymnasium / Cafeteria / Auditorium
2,000 4,000
Relocatable Modular
Additional Space Required to Meet Minimum Standard
Main Building(s)
60
square feet
Low
er is
bet
ter
St. Mary’s Facility Condition Distribution by Band•Facility Population of 26•Arithmetic Mean of 51.4%•Std Deviation of 10.8%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 0 0%
Band3 (0.60-0.69) 4 15%
Band4 (0.50-0.59) 15 58%
Band5 (0.40-0.49) 3 12%
Band6 (0.30-0.39) 3 12%
Band7 (0.20-0.29) 0 0%
Band8 (0.10-0.19) 1 4%
Band9 (0.00-0.09) 0 0%
Total 26 100%
0 0
4
15
3 3
0
1
00
2
4
6
8
10
12
14
16
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
61
Low
er is
bet
ter
St. Mary’s Average FCI by Major Building System
55%59% 57%
35%
62%
47% 50% 49%
59% 59%54%
81%
46% 45%
56%
42%48%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
Average FCI by Major Building System
62
Space Deficiencies by Type – St. Mary’s
0 40,000 50,000 60,000 70,000
Pupil Services
Special Education
Storage (Non-Classroom)
Administrative
Gymnasium / Cafeteria / Auditorium
Dining
Library/Media Center
Health Services
Maintenance / Janitorial Space
Science
Fine Arts
Technology and Computer Science
General Classroom
10,000 20,000 30,000
Relocatable Modular
Additional Space Required to Meet Minimum Standard
Main Building(s)
*
*Data for these categories is small enough that it is not visible at current chart scale63
square feet
Low
er is
bet
ter
Talbot Facility Condition Distribution by Band•Facility Population of 8•Arithmetic Mean of 46.0%•Std Deviation of 17.7%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 0 0%
Band3 (0.60-0.69) 1 13%
Band4 (0.50-0.59) 4 50%
Band5 (0.40-0.49) 2 25%
Band6 (0.30-0.39) 0 0%
Band7 (0.20-0.29) 0 0%
Band8 (0.10-0.19) 0 0%
Band9 (0.00-0.09) 1 13%
Total 8 100%
0 0
1
4
2
0 0 0
1
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
64
Low
er is
bet
ter
Talbot Average FCI by Major Building System
59% 58%
42%35%
50% 47%39%
46%
100%
37%
49%
37%46%
52%43%
23%
0%
20%
40%
60%
80%
100%
120%
Average FCI by Major Building System
65
Space Deficiencies by Type – Talbot
0 500 1,000 1,500 2,000 2,500
General Classroom *
Kitchen
Storage (Non-Classroom)
Maintenance / Janitorial Space
Gymnasium / Cafeteria / Auditorium
Health Services
Special Education
Technology and Computer Science
Main Building(s) Relocatable Modular
Additional Space Required to Meet Minimum Standard
*Data for main buildings and relocatables is small enough that it is not visible at current chart scale 66
square feet
Low
er is
bet
ter
Washington Facility Condition Distribution by Band•Facility Population of 46•Arithmetic Mean of 52.4%•Std Deviation of 16.0%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 0 0%
Band3 (0.60-0.69) 18 39%
Band4 (0.50-0.59) 16 35%
Band5 (0.40-0.49) 3 7%
Band6 (0.30-0.39) 3 7%
Band7 (0.20-0.29) 2 4%
Band8 (0.10-0.19) 3 7%
Band9 (0.00-0.09) 1 2%
Total 45 100%
0 0
18
16
3 32
3
1
0
2
4
6
8
10
12
14
16
18
20
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
67
Low
er is
bet
ter
Washington Average FCI by Major Building System
63%
49%
57% 55%62%
50%
63% 66%58%
67% 68%
93%
48% 48% 50%45%
41%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Average FCI by Major Building System
68
Space Deficiencies by Type – Washington
60,000 80,000 100,000 120,000
Administrative
Kitchen
Special Education
Storage (Non-Classroom)
Library/Media Center
Science
Health Services
Maintenance / Janitorial Space
Dining
Gymnasium / Cafeteria / Auditorium
Fine Arts
Technology and Computer Science
General Classroom
0 20,000 40,000
Relocatable Modular
Additional Space Required to Meet Minimum Standard
Main Building(s)69
square feet
Low
er is
bet
ter
Wicomico Facility Condition Distribution by Band•Facility Population of 25•Arithmetic Mean of 50.3%•Std Deviation of 18.0%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 1 4%
Band3 (0.60-0.69) 10 40%
Band4 (0.50-0.59) 4 16%
Band5 (0.40-0.49) 5 20%
Band6 (0.30-0.39) 2 8%
Band7 (0.20-0.29) 1 4%
Band8 (0.10-0.19) 0 0%
Band9 (0.00-0.09) 2 8%
Total 24 100%
0
1
10
4
5
2
1
0
2
0
2
4
6
8
10
12
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
70
Low
er is
bet
ter
Wicomico Average FCI by Major Building System
54%
40%
52%56% 54%
38%
48% 49%
61%56%
68%
88%
41% 41%
52%
39%
81%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Average FCI by Major Building System
71
0 10,000 20,000 30,000 40,000 50,000 60,000 70,000 80,000 90,000
Library/Media Center
Pupil Services
Special Education
Storage (Non-Classroom)
Science
Health Services
Maintenance / Janitorial Space
Dining
Gymnasium / Cafeteria / Auditorium
Fine Arts
Technology and Computer Science
General Classroom
Main Building(s) Relocatable Modular
Space Deficiencies by Type – WicomicoAdditional Space Required to Meet Minimum Standard
**
*Data for these categories is small enough that it is not visible at current chart scale72
square feet
Low
er is
bet
ter
Worcester Facility Condition Distribution by Band•Facility Population of 14•Arithmetic Mean of 50.1%•Std Deviation of 18.7%
Low
er is
Bet
ter
FCI # Buildings Percentage of Buildings
Band1 (0.80-0.89) 0 0%
Band2 (0.70-0.79) 0 0%
Band3 (0.60-0.69) 7 50%
Band4 (0.50-0.59) 2 14%
Band5 (0.40-0.49) 1 7%
Band6 (0.30-0.39) 2 14%
Band7 (0.20-0.29) 1 7%
Band8 (0.10-0.19) 0 0%
Band9 (0.00-0.09) 1 7%
Total 14 100%
0 0
7
2
1
2
1
0
1
0
1
2
3
4
5
6
7
8
Band1(0.80-0.89)
Band2(0.70-0.79)
Band3(0.60-0.69)
Band4(0.50-0.59)
Band5(0.40-0.49)
Band6(0.30-0.39)
Band7(0.20-0.29)
Band8(0.10-0.19)
Band9(0.00-0.09)
73
Low
er is
bet
ter
Worcester Average FCI by Major Building System
57% 55%49% 47%
56%
42%
52% 54%
88%
57% 59%
94%
61%
43%50%
36%
60%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Average FCI by Major Building System
74
Space Deficiencies by Type – Worcester
4,000 5,000 6,000 7,000 8,000
General Classroom *
Pupil Services
Kitchen
Special Education
Dining
Storage (Non-Classroom)
Maintenance / Janitorial Space
Health Services
Fine Arts
Science
Gymnasium / Cafeteria / Auditorium
Technology and Computer Science
0 1,000 2,000 3,000
Relocatable Modular
Additional Space Required to Meet Minimum Standard
Main Building(s)
*Data for main buildings is small enough that it is not visible at current chart scale 75
square feet