Lid ProjectsUrban Systems
Work from the Metropolitan Design Center and Department of Architecture Studios at the University of Minnesota
Minnesota Department of Transportation TAP
Metropolitan Design CenterUniversity of Minnesota
May 25, 2016
![Page 2: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/2.jpg)
Minneapolis 35W Lid Project
![Page 3: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/3.jpg)
35W Site, Context and History
![Page 4: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/4.jpg)
35 W Today
Lid Zone
![Page 5: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/5.jpg)
35W SITE DATA
Existing Land Use 35W SITE DATA
![Page 6: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/6.jpg)
$1.5 - $2 MILLION
35W SITE DATAEstimated Land Value
GENERAL EMV (BALLPARK GUESS)
![Page 7: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/7.jpg)
MEDIAN HOUSEHOLD INCOME: $25,307
HOUSEHOLDS WITH INCOME <$35K: 64% HOUSEHOLDS WITH INCOME $50K-$75K: 12.7%HOUSEHOLDS WITH INCOME BELOW POVERTY LINE: 33%
MEDIAN RENT: $622BURDENED RENTER HOUSEHOLD: 55.5% BURDENED OWNER HOUSEHOLD: 10.8%
TRANSPORTATION TO WORK (CAR, TRUCK, VAN...): 49.2% TRANSPORTATION TO WORK/PUBLIC TRANSIT: 17.2% WALK/BIKE/WORK FROM HOME: 33.6%
TRAVEL TIME TO WORK 10- 19 MINUTES: 40.4%TRAVEL TIME TO WORK 20-29 MINUTES: 21.1%TRAVEL TIME TO WORK 30+ MINUTES: 24.1%
1600’POLLUTION ZONE* DATA SOURCE: THE AMERICAN COMMUNITY SURVEY 2008-2012
Elliot Park 35W SITE DATA
![Page 8: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/8.jpg)
MEDIAN HOUSEHOLD INCOME: $13, 511
HOUSEHOLDS WITH INCOME <$35K: 79.6%HOUSEHOLDS WITH INCOME $50K-$75K: 4.5%HOUSEHOLDS WITH INCOME BELOW POVERTY LINE: 55.3%
MEDIAN RENT: $578BURDENED RENTER HOUSEHOLD: 71.4%BURDENED OWNER HOUSEHOLD: 27.1%
TRANSPORTATION TO WORK (CAR, TRUCK, VAN...): 42.8% TRANSPORTATION TO WORK/PUBLIC TRANSIT: 25.20% WALK/BIKE/WORK FROM HOME: 32%
TRAVEL TIME TO WORK 10- 19 MINUTES: 29.3%TRAVEL TIME TO WORK 20-29 MINUTES: 22.9%TRAVEL TIME TO WORK 30+ MINUTES: 28.7%
1600’POLLUTION ZONE* DATA SOURCE: THE AMERICAN COMMUNITY SURVEY 2008-2012
Cedar Riverside 35W SITE DATA
![Page 9: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/9.jpg)
MEDIAN HOUSEHOLD INCOME: $21,595
HOUSEHOLDS WITH INCOME <$35K: 65.5% HOUSEHOLDS WITH INCOME $50K-$75K: 13.6%HOUSEHOLDS WITH INCOME BELOW POVERTY LINE: 47.4%
MEDIAN RENT: $559BURDENED RENTER HOUSEHOLD: 13.6% BURDENED OWNER HOUSEHOLD: 50.1%
TRANSPORTATION TO WORK (CAR, TRUCK, VAN...): 50.3% TRANSPORTATION TO WORK/PUBLIC TRANSIT: 31.8%WALK/BIKE/WORK FROM HOME: 17.9%
TRAVEL TIME TO WORK 10- 19 MINUTES: 27.7%TRAVEL TIME TO WORK 20-29 MINUTES: 23.1%TRAVEL TIME TO WORK 30+ MINUTES: 22.5%
1600’POLLUTION ZONE* DATA SOURCE: THE AMERICAN COMMUNITY SURVEY 2008-2012
Ventura Village 35W SITE DATA
![Page 10: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/10.jpg)
Land Ownership
![Page 11: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/11.jpg)
Concept
4th Street3rd Street
11th Street
15th Street
35W
![Page 12: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/12.jpg)
Neighborhood Program
![Page 13: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/13.jpg)
Fall 2013 35W Lid Development Outcomes
4.74 million sf Total Development
![Page 14: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/14.jpg)
Potential Land and Development Program
![Page 15: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/15.jpg)
Potential Development Benefits
*Data provide by JLL (Jones Lang LaSalle)
Tax Status of Parcels in 35W Lid Project 10 Year Incremental Property Tax Revenue: $288 Million
![Page 16: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/16.jpg)
South Nicollet Mall
Re-assembling the City District Goals:
AccessibilityCommunityContextDensityEconomic DiversityEquityFull-LifeHealthInterconnectivityLiving Public RealmDistrict Identity Rebranding
Design Guidelines:
Form-Based CodesDesign QualityPedestrian OrientedDistrict CharacterEnvironmental DesignZero Carbon
![Page 17: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/17.jpg)
35W Lid Parking
![Page 18: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/18.jpg)
LRT and the 35W Lid Parking
750 Cars
![Page 19: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/19.jpg)
![Page 20: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/20.jpg)
This project: Lidding 35W and developing 17.75 acres of new development
It bridges I-35W between the University of Minnesota and downtown Minneapolis, returning 11 blocks of taxable real estate to the city’s coffers
It utilizes air rights above the highway to generate revenue for the state, while reducing weather-related impacts on the highway itself
It generates revenue to pay back the initial infrastructure investment and leverages private capital for public good, like a new light-rail transfer station
It creates public parks and district parking for a whole new family friendly community for roughly 5,000 residents and the support services they need
It stitches back together the city, divided by the interstate highways so long ago and turns undesirable land into some of the most desirable in the city
It provides space for office and research space for businesses that benefit from proximity to the University It offers a strategy of creating more open space and accommodating more density without interfering with existing neighborhoods
It reduces the noise and pollution affecting other major public and private investments like the Vikings StadiumIt extends the open space of the Yard and that around the stadium and makes it easier to walk between the University and East Downtown
![Page 21: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/21.jpg)
This project: Lidding 35W and developing 17.75 acres of new development.
Total Development Square Feet 5,053,800Residential Square Feet 3,133,263Commercial Square Feet 1,604,727Institutional Square Feet 315,810
New Tax Base17.75 Acres of new development $350,000,000 over 10 years (JLL)
Parking Structure over 35W750 carsCost: approx. 25,000 per car excluding the Green Roof
![Page 22: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/22.jpg)
St Paul 94/35E Lid Project
![Page 23: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/23.jpg)
St. Paul Capital Lid
Project SitePotential Development
![Page 24: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/24.jpg)
St. Paul Capital Lid
![Page 25: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/25.jpg)
>CATHEDRAL
I94>STATE CAPITOL
>MISSISSIPPI RIVER>DOWNTOWN ST. PAUL
>XCEL ENERGY CENTER
>MINNESOTAHISTORY CENTER
35E
St. Paul Capital Lid
![Page 26: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/26.jpg)
>CATHEDRAL
I94>STATE CAPITOL
>MISSISSIPPI RIVER>DOWNTOWN
ST. PAUL
>XCEL ENERGY CENTER
>MINNESOTAHISTORY CENTER
35E
• 1/4-mile of green street that links district assets and places, emphasizing pedestrian activity over vehicles
• 2.5 acres of public space at the district center• 16 acres of underutilized land unlocked for development• 1.6 million sf of development, representing a
community of 1,500 new residents and all of the services, spaces, and activities needed for a fully-functional neighborhood
• $320 million construction cost
St. Paul Capital Lid
![Page 27: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/27.jpg)
Edina Highway 100 Lid Project
![Page 28: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/28.jpg)
Edina Grandview LidProject SitePotential Redevelopment
![Page 29: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/29.jpg)
New Parcels
0.8acre
0.75acre
1 acre
1.25acre 1 acre
0.4acre
0.4acre0.4
acre
1.4 acre
0.5 acre
7.9 Total Acres
![Page 30: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/30.jpg)
Example of Build-out Potential
176,750 sqft
129,250
111,250
126,750
88,000
Development Potentialwith 8 floors avg/bldg:1,701,250 sqft
106,500
162,500 sq ft
103,500 sqft
68,000
96,750
100,500 sq ft
93,500
106,000
129,250
102,750
![Page 31: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/31.jpg)
District Parking
90
105
145 cars
48
165 cars
200 cars
315
48
200 cars
Lid and Adjacent Parking:606 spacesTotal District Parking:1,316 spaces
![Page 32: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/32.jpg)
Lid Section
Existing
Proposed Section along Pedestrian Mall
![Page 33: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/33.jpg)
![Page 34: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/34.jpg)
• 8 acres of underutilized land unlocked for development• 1.8 acres of public space at the heart of the district• 1.7 million sf of potential development, representing a
community of 2,000 new residents and all of the services, spaces, and activities needed for a fully-functional neighborhood
• 1,300 district parking spaces / 600 in freeway lid and connected buildings
• 1/3-mile green pedestrian mall that links district assetsand places, emphasizing pedestrian and street activity overvehicular movement
• 60’-tall facade / 20’-wide sidewalks define outdoor “street rooms” as places of energy, light, and living
Edina Grandview Lid
![Page 35: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/35.jpg)
Nicollet Avenue Lid Project
![Page 36: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/36.jpg)
Privately owned underutilized land
MnDot land
![Page 37: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/37.jpg)
Existing Freeway and Embankments
Nic
olle
t Av
e
I-94
Convention Center
![Page 38: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/38.jpg)
Structural SystemWith a span of 80 feet and a depth of up to 14 feet, concrete trusses can easily span ahighway and efficiently create logical configurations for typical housing and retail patterns.
![Page 39: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/39.jpg)
1
3
Assembly
2
4
![Page 40: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/40.jpg)
Phase 1: Inhabited Bridge19,500 sf retail66 units @ 900-1,600 sf ea 185,000 sf total development
Nic
olle
t Av
e
I-94
I-94
![Page 41: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/41.jpg)
Phase 2: New Development Generated by Phase 1 lid+ 225,000 sf of new development on adjacent vacant properties
Nic
olle
t Av
e
I-94
I-94
![Page 42: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/42.jpg)
Phase 3: Expand to neighboring bridges+ 2 new lids: 180,000 sf ea+ redeveloped adjacent parcels
Nic
olle
t Av
e
I-94
I-94
![Page 43: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/43.jpg)
View North on Nicollet Ave
![Page 44: Work from the Metropolitan Design Center and Department of … · 2019-03-28 · Lid Projects Urban Systems Work from the Metropolitan Design Center and Department of Architecture](https://reader033.fdocuments.net/reader033/viewer/2022042309/5ed70c5562136e72fb7bbc97/html5/thumbnails/44.jpg)
Nicollet Ave
Retail 6,000 sf Retail 2,000 sf
7,000 sf
Lobby
Lobby
Lobby
Services
Services
Lobby
Retail
Site Plan
N