WisDOT use ofFieldManager® Suite

David Castleberg, PEWisconsin Department of TransportationBureau of Project Development

Field Management TAG, October 7, 2008

David Castleberg, PEWisconsin Department of TransportationBureau of Project Development

Field Management TAG, October 7, 2008

Page 2: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

WisDOT and FieldManager®

History

Statistics

WisDOT Process

Beyond FieldManager®

History

Statistics

WisDOT Process

Beyond FieldManager®

Page 3: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

History

1994 WisDOT evaluates Trns.port (BAMS) Include look at Iowa FieldBook®

1997 Implement Trns.port and FM/FB 1.97 Required 20 diskettes for FM/FB install First FieldNet® service managed by

Info Tech 375 users (255 DOT, 120 consultants)

1994 WisDOT evaluates Trns.port (BAMS) Include look at Iowa FieldBook®

1997 Implement Trns.port and FM/FB 1.97 Required 20 diskettes for FM/FB install First FieldNet® service managed by

Info Tech 375 users (255 DOT, 120 consultants)

Page 4: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

WisDOT Contract Management WisDOT Contract Management SystemSystem

Page 5: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

History

1999 upgraded to FM/FB 3.0 (ITI/MDOT)1999 upgraded to FM/FB 3.0 (ITI/MDOT) First state to “beta” test in productionFirst state to “beta” test in production 410 users410 users

2003 migrated from Mainframe to C/S2003 migrated from Mainframe to C/S Discontinued ITI FieldNetDiscontinued ITI FieldNet®® service service Implemented FieldNetImplemented FieldNet®® in-house in-house 440 users (215 DOT, 225 consultants)440 users (215 DOT, 225 consultants)

2008 upgraded to FM 4.4a, FN 3.0a2008 upgraded to FM 4.4a, FN 3.0a 490 users (240 DOT, 250 consultants)490 users (240 DOT, 250 consultants)

1999 upgraded to FM/FB 3.0 (ITI/MDOT)1999 upgraded to FM/FB 3.0 (ITI/MDOT) First state to “beta” test in productionFirst state to “beta” test in production 410 users410 users

2003 migrated from Mainframe to C/S2003 migrated from Mainframe to C/S Discontinued ITI FieldNetDiscontinued ITI FieldNet®® service service Implemented FieldNetImplemented FieldNet®® in-house in-house 440 users (215 DOT, 225 consultants)440 users (215 DOT, 225 consultants)

2008 upgraded to FM 4.4a, FN 3.0a2008 upgraded to FM 4.4a, FN 3.0a 490 users (240 DOT, 250 consultants)490 users (240 DOT, 250 consultants)

Page 6: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

Statistics

300+ LET contracts in 2007300+ LET contracts in 2007

$750 mil program$750 mil program

5 region offices5 region offices

40+ vouchers processed daily40+ vouchers processed daily

300+ LET contracts in 2007300+ LET contracts in 2007

$750 mil program$750 mil program

5 region offices5 region offices

40+ vouchers processed daily40+ vouchers processed daily

Page 7: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

Product Users

WisDOTWisDOT ConsultantConsultant TotalsTotals

FieldManagerFieldManager®® 250250 240240 490490

FieldBookFieldBook®® 7575 4545 120120

FieldPadFieldPad®® 00 33 33

FieldNetFieldNet®® 250250 240240 490490

Page 8: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

WisDOT ProcessWisDOT Process

Page 9: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

F ie ld O fficeFieldManager1 -3 co n tra c tsF ie ld O fficeF ie ld O fficeF ie ld O fficeF ie ld O ffice

R e g io n O fficeCAS

re g ion co ntra c ts

F ie ld O fficeFieldManager1 -3 co n tra c tsF ie ld O fficeF ie ld O fficeF ie ld O fficeF ie ld O ffice

R e g io n O fficeCAS

re g ion co ntra c ts

F ie ld O fficeFieldManager1 -3 co n tra c tsF ie ld O fficeF ie ld O fficeF ie ld O fficeF ie ld O ffice

R e g io n O fficeCAS

re g ion co ntra c ts

F ie ld O fficeFieldManager1 -3 co n tra c tsF ie ld O fficeF ie ld O fficeF ie ld O fficeF ie ld O ffice

R e g io n O fficeCAS

re g ion co ntra c ts

F ie ld O fficeFieldManager1 -3 co n tra c tsF ie ld O fficeF ie ld O ffice

In spe c torFieldBook

F ie ld O ffice

In spe c torFieldBook

In spe c torFieldBook

F ie ld O ffice

R e g io n O fficeCAS

re g ion co ntra c ts

C e n tra l O fficeCAS

a ll co n tra c tsa d m in

OrganizationOrganization

Page 10: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

Contract Assignment

CO send awarded contracts to 5 regional office contacts:CAS>FN>FM

Regions transfer contract to project engineer: FM>FN>FM

Project engineer exports toFB and FP: FM>FB/FP

CO send awarded contracts to 5 regional office contacts:CAS>FN>FM

Regions transfer contract to project engineer: FM>FN>FM

Project engineer exports toFB and FP: FM>FB/FP

Page 11: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

Payment Estimates

Project engineer generates andsends estimate for approval: FM>FN

Supervisor or delegate approves estimate: FN>CAS

Voucher processes andrefresh sent toPE: CAS>FN>FM

Project engineer generates andsends estimate for approval: FM>FN

Supervisor or delegate approves estimate: FN>CAS

Voucher processes andrefresh sent toPE: CAS>FN>FM

Page 12: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

Contract Modifications

Project engineer generates and sends Cont. Mod. for approval: FM>FN

Supervisor or delegate approves Cont. Mod.: FN>CAS

OR

PE generates and approvesCont. Mod.: FM>FN>CAS

Project engineer generates and sends Cont. Mod. for approval: FM>FN

Supervisor or delegate approves Cont. Mod.: FN>CAS

OR

PE generates and approvesCont. Mod.: FM>FN>CAS

Page 13: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

Other Processes Used

Stockpiles

IDR’s

Daily diaries

FieldBook® for inspectors(as necessary)

Stockpiles

IDR’s

Daily diaries

FieldBook® for inspectors(as necessary)

Page 14: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

Other Notes

PC specification for consultants Hardware requirements Region IT support

installs/uninstalls software

DSL for FieldNet® connection Some by phone

Regional IT and contract specialist

PC specification for consultants Hardware requirements Region IT support

installs/uninstalls software

DSL for FieldNet® connection Some by phone

Regional IT and contract specialist

Page 15: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

Beyond FieldManagerBeyond FieldManager®®

Page 16: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

Field Information Tracking

Merged with FM database

Additional contract information

Used by project engineer

Merged with FM database

Additional contract information

Used by project engineer

Page 17: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

Field Information TrackingField Information Tracking

Page 18: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

Project Tracking

Contract data from CAS, FM, FIT View and update

DBE

Labor Compliance

Warranty

R/R

Contract data from CAS, FM, FIT View and update

DBE

Labor Compliance

Warranty

R/R

Page 19: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

Project TrackingProject Tracking

Page 20: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

Materials Information Tracking

Project data from CAS

5 standard field reports

Used by materials technician

Project data from CAS

5 standard field reports

Used by materials technician

Page 21: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

Materials Information Materials Information TrackingTracking

Page 22: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

Materials Tracking System

Physical test results Entry Verification

Used by central and consultant labs

Physical test results Entry Verification

Used by central and consultant labs

Page 23: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

Materials Tracking SystemMaterials Tracking System

Page 24: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

Materials Reporting System

Contractor entry of test results IRI ride Structures Pavement

Project engineer validation of test results

Contractor entry of test results IRI ride Structures Pavement

Project engineer validation of test results

Page 25: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.

Materials Reporting SystemMaterials Reporting System

Page 26: WisDOT use of FieldManager ® Suite David Castleberg, PE Wisconsin Department of Transportation Bureau of Project Development Field Management TAG, October.