Wilshire Grand Redevelopment Project

66
www.jacobs.com | worldwide Wilshire Grand Redevelopment Project Project Highlights December 15, 2016

Transcript of Wilshire Grand Redevelopment Project

www.jacobs.com | worldwide

Wilshire Grand Redevelopment ProjectProject Highlights

December 15, 2016

Wilshire GrandRedevelopment Project

WILSHIRE GRAND PROJECT

• Facility Overview• Construction Highlights• Mass Concrete – Thermal Control• Structural Design – Seismic• Foundation Settlement & Tower

Shortening• Pre-Loading of Upper BRBs

Facility Overview

4

PROJECT LOCATION 900 Wilshire Blvd

Size: 2,100,000 SF

73-stories

892 key hotel

16 stories of offices – 365,000 SF

7 levels of podium (amenities)

5 levels below grade parking

Completion: 2nd Quarter 2017

Owner: Hanjin International Corp/Korean Air Lines

Architect: A.C. Martin Partners

StructuralEngineers: Brandow & Johnston

Thornton TomasettiProject Manager: Martin Project Mgmt

General Contractor: Turner

Level 70 Sky Lobby

Level 70 Sky Lobby

Level 70 Bar

Level 70 Club Lounge

Level 73 Sky Deck

Level 5 Pre-function Area

Level 5 Grand Ballroom

Level 7 Ballroom

Level 7 Health & Fitness Club

Level 7 Shower & Spa

Level 7 Pool

View from Figueroa Street

Level 1 Porte Cochere

Construction Highlights

20

January 2013

21

May 2013

22

June 2013

23

November 2013

24

The Grand Pour – Feb 15, 2014

25

Rebar Erection

EFCO FORM SYSTEM

June 2014

29

Year-end 2014

30

Mid-year 2015

31

3rd Quarter 2015

32

Year-end 2015

33

Summer 2016

34

Current – Dec 2016

35

Mass Concrete - Thermal Control

36

Mass concrete is the performance definition of such concrete placement, that may develop potentially detrimental high absolute temperature and/or temperature difference due to:• volume and shape• specific amount and rate of heat generation upon hydration and

hardening, and • boundary conditions,

37

The Grand Pour – Feb 15, 2014

38 Saturday, February 15, 2014

Largest Continuous Concrete Pour

39 Guinness World Record

40

Thermal Control Measures

• Cooling Pipe System with Recirculating Chilled Water

• Thermal Blanket Insulation

• Curing Procedure

• QC Temperature Monitoring

41

• Maximum temperature is limited through proper thermal control measures in order to prevent delayed ettringite formation (DEF).

• Maximum temperature difference is limited through proper thermal control measures in order to prevent cracking due to thermal stresses.

42

Structural Design

43

SLDE Service Level Design EQ– Frequent occurrence (43-yr return period EQ)

– Performance Objective: Designed to stay linear in ‘elastic limit’

– Lateral system rebounds to zero deformation w/ limited arch & structdamage, remains serviceable

– Moderate EQ (475-yr return period) damage reparable

MCE Maximum Considered EQ Event ‘Major Event’ – Extreme / Severe (2475-yr return period EQ)

– Performance Objective: Designed to prevent collapse, mitigate loss of life

– Lateral system utilizes ductility, performs numerous cycles ‘plastic yield’ demand

PERFORMANCE CRITERIA

PERFORMANCE BASE DESIGNDesigned for known local seismicity

– Design consideration: 29 major faults deemed active distance from 0.2 mi. to 46 mi. from site

– Nearest quake considered is from Upper Elysian Park Thrust Fault (0.2 mi)

– Largest quake considered is from San Andreas Fault (46 mi.)

Wind Design – 1700-yr cycle, 160 mph, 3-sec gusts– Wind Tunnel Studies and Computer Simulation

– Rigid enough for comfort service-level wind loads

– No ‘Tuned Mass Damper’ required, adequate lateral stiffness for comfort

PERFORMANCE BASE DESIGNPeer Review Approach Favorable over CBC Prescriptive Design

– Peer Review Panel members

– Establish Performance Objectives with SEOR

– PRP Provided Comprehensive Code Compliance Check

– Requires full ‘redundant back-up’ system in addition to ‘Core Wall Design’

– Typically results in Conventional Tube Steel Frame with ‘deep girders’ + ‘closer columns’

Benefits Early Collaboration of PRP w/ SEOR = Early Delivery

Upper Outrigger Trusses – 3 Stories10 bays-1BRB w/2200 k each

Middle Outrigger Trusses – 6 Stories10 bays-Total 12 BRBs w/800 kips each

Lower Outrigger Trusses – 3 Stories10 bays-Cluster 4-BRBs w/2200 kips each

Structure: • Concrete Core w/4 Vertical Cells

• Steel Floor Frame w/ Composite Metal Deck

Structural Statistics:• Steel: 19,000 tons (17.2 million kg)

• Concrete: 160,000 cu yds = 16,000 trucks (122K cu m)

• Rebar: 70 million lbs = 35,000 tons (31.7 million kg)

METRICS – STRUCTURAL OVERVIEW

LA Live (NYA)

BRB’sSpecialty structural brace element consisting of an axial force resisting steel core encased by a system that prevents buckling of the steel core.

50

51

Lower Outriggers

52

Upper Outriggers

53

LOWER OUTRIGGER EMBED ERECTED

Foundation Settlement &Tower Shortening

55

Adjustments Due to Foundation Settlement & Tower Shortening

233’

582’

869.5’

1053.5’

1125.5’

1210.2’

1384’Spire

Sail

70th

53rd

28th

Top ofMat

Foundation Settlement- Differential settlement

Core Walls- Reinforced Concrete- Strain due to loading - Shrinkage and Creep

Exterior Columns- Built-Up Structural Steel Box Columns - Filled with Concrete- Strain due to loading

Tower Axial ShorteningDesign accounted for axial displacements due to:• sequential loading phases during construction• and long term effects (shrinkage and creep)

Prevent undue stresses different from design values

Perform periodic on‐site measurements 

57

58

Pre-Loading Upper BRBs

59

Adjustments Due to Long Term Creep

233’

582’

869.5’

1053.5’

1125.5’

1210.2’

1384’Spire

Sail

70th

53rd

28th

Top ofMat

• Single 2,200 kips BRBs

• Sensitive to differential movements due to elastic shortening, shrinkage and creep.

• Pre-compressing BRBs

Pre-loading with Hydraulic Jacks

61

Protect the building from permanent deformation in the 50-yr windevent

At 50-yr wind event, the BRB strains are approximately 50% ofyield strain

Pre-compressing the BRB eliminates permanent deformation after50 years of creep and shrinkage

62

63

Top of Spire – Prior to Beacon Installation

64

www.jacobs.com | worldwideJanuary 9, 2017

© Copyright Jacobs

Thank you

Q&A