WHY IT TOOK HALF
A CAREER TO
CLOSE A LANDFILL LESSONS LEARNED….
BUT NOT WHAT YOU LEARNED IN SCHOOL
CHRISTOPHER BURNS, PH.D., P.G.
CHA CONSULTING, INC.
MAY 2015
![Page 2: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/2.jpg)
MAIN POINTS
• THIS IS MOSTLY ALL TRUE
• SOME POINTS MAY BE RELEVANT
• I WILL LIKELY OFFEND SOMEONE
![Page 3: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/3.jpg)
CHALLENGES
• 8 Town Boards
• 5 Property Owners
• 4 DEC Attorneys
• 3 DEC Project Managers
• 3 Town Supervisors
• 2 Utility Companies
• 2 Regulatory Agencies (DEC and EPA)
And
• 1 Stream running through the Landfill
![Page 4: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/4.jpg)
SALINA LANDFILL – NEAR SYRACUSE, NY
Salina Landfill
![Page 5: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/5.jpg)
PROPERTY OWNERSHIP
Salina Landfill
1
1
2
3
3
3
2
2
4
5
4
1
![Page 6: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/6.jpg)
• 1950’S–1974 Active Landfill • 1982 Soil Cap Installed • 1990’s DEC Preliminary Assessments • 1996 Named Class 2 and NPL subsite • 1997 Town Signs Consent Order • 1998 - 2000 Remedial Investigation • 2000 - 2002 Feasibility Study • 2007 1ST DEC/EPA ROD • 2007 - 2010 Remedial Design • 2010 Amended ROD • 2010 - 2013 Part 360 Cap Installed • 2013 Collection Trench Installed • 2014 - 2015 Pretreatment Plant Constructed • 2015 Remedial Action Complete
CB Starts
SITE CHRONOLOGY
18 Years
![Page 7: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/7.jpg)
Lesson #1
Background Data should come from Off-Site
1964
1972
Ley Creek
![Page 8: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/8.jpg)
Lesson #2
A Record of Decision Can Say Funny Things
Comment on Proposed Plan: “The Natural Gas
Pipeline cannot be under the cap”.
DEC Response in ROD: “The landfill cap will not
be placed over the gas line and access will be
maintained during and after construction of the
remedy”.
![Page 9: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/9.jpg)
Lesson #3
How to “Negotiate” with a Utility Company
(or the story of pipes, small wires and big wires)
![Page 10: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/10.jpg)
Lesson #4
Wetland Impacts
(something EPA really cares about)
![Page 11: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/11.jpg)
Lesson #5
Site Redevelopment is a cool idea
but NYSDEC
Regional Directors
have no
Imagination
![Page 12: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/12.jpg)
Lesson #6
Running Out of Money
Before Construction Starts
is a Bad Thing
DEC would limit annual
reimbursement to Town
Devised Construction Phasing Plan
Divided work into 6 Parcels
Work would stretch over 6 years
Estimated Cost > $25M
![Page 13: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/13.jpg)
Lesson #7
Politics Enters into Everything
Design Element included leachate collection trench.
Dilemma was how to dispose of leachate?
Obvious choice was to pretreat and discharge to County
sewer immediately adjacent to site.
But…..
![Page 14: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/14.jpg)
Lesson #7
Politics Enters into Everything
Town with Democratic Majority and
County with Republican Majority
= NO DEAL
Town with Republican Majority and
County with Republican Majority
= DEAL!
![Page 15: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/15.jpg)
Lesson #8
Lawyers Make More Money than
Engineers
(so why do they always want to do
engineering?)
![Page 16: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/16.jpg)
Lesson #9
Time can be your friend!
![Page 17: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/17.jpg)
Project Elements
National Grid Completed $900K Utility Relocation
![Page 18: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/18.jpg)
Project Elements
Satisfied National Grid by installing clay cap in utility corridors
![Page 19: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/19.jpg)
Project Elements
Reduced Landfill Footprint by 12.3 acres
![Page 20: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/20.jpg)
Project Elements
Capped 3 cell areas with geomembrane
![Page 21: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/21.jpg)
Project Elements
Re-routed major drainage swale beyond limit of waste
![Page 22: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/22.jpg)
Project Elements
Mitigated wetlands at 1:1 ratio and
created more contiguous habitat
![Page 23: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/23.jpg)
Project Elements
Installed 2,100 foot long leachate collection trench
![Page 24: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/24.jpg)
Project Elements
Constructed 2,400 sq ft Pretreatment Building
![Page 25: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/25.jpg)
Lesson #9
Time can be your friend!
Project Completed in 2 Phases
Remediation took 4 years
Original Estimated Cost = $25M
Final Cost = $15.5M
![Page 26: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank](https://reader033.fdocuments.net/reader033/viewer/2022050214/5f5ffaa6fa2da84771472c35/html5/thumbnails/26.jpg)