WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL LESSONS LEARNED…. BUT NOT WHAT YOU LEARNED IN SCHOOL CHRISTOPHER BURNS, PH.D., P.G. CHA CONSULTING, INC. MAY 2015

Transcript of WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of...

Page 1: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

WHY IT TOOK HALF

A CAREER TO

CLOSE A LANDFILL LESSONS LEARNED….

BUT NOT WHAT YOU LEARNED IN SCHOOL

CHRISTOPHER BURNS, PH.D., P.G.

CHA CONSULTING, INC.

MAY 2015

Page 2: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

MAIN POINTS

• THIS IS MOSTLY ALL TRUE

• SOME POINTS MAY BE RELEVANT

• I WILL LIKELY OFFEND SOMEONE

Page 3: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

CHALLENGES

• 8 Town Boards

• 5 Property Owners

• 4 DEC Attorneys

• 3 DEC Project Managers

• 3 Town Supervisors

• 2 Utility Companies

• 2 Regulatory Agencies (DEC and EPA)

And

• 1 Stream running through the Landfill

Page 4: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

SALINA LANDFILL – NEAR SYRACUSE, NY

Salina Landfill

Page 5: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

PROPERTY OWNERSHIP

Salina Landfill

1

1

2

3

3

3

2

2

4

5

4

1

Page 6: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

• 1950’S–1974 Active Landfill • 1982 Soil Cap Installed • 1990’s DEC Preliminary Assessments • 1996 Named Class 2 and NPL subsite • 1997 Town Signs Consent Order • 1998 - 2000 Remedial Investigation • 2000 - 2002 Feasibility Study • 2007 1ST DEC/EPA ROD • 2007 - 2010 Remedial Design • 2010 Amended ROD • 2010 - 2013 Part 360 Cap Installed • 2013 Collection Trench Installed • 2014 - 2015 Pretreatment Plant Constructed • 2015 Remedial Action Complete

CB Starts

SITE CHRONOLOGY

18 Years

Page 7: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Lesson #1

Background Data should come from Off-Site

1964

1972

Ley Creek

Page 8: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Lesson #2

A Record of Decision Can Say Funny Things

Comment on Proposed Plan: “The Natural Gas

Pipeline cannot be under the cap”.

DEC Response in ROD: “The landfill cap will not

be placed over the gas line and access will be

maintained during and after construction of the

remedy”.

Page 9: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Lesson #3

How to “Negotiate” with a Utility Company

(or the story of pipes, small wires and big wires)

Page 10: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Lesson #4

Wetland Impacts

(something EPA really cares about)

Page 11: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Lesson #5

Site Redevelopment is a cool idea

but NYSDEC

Regional Directors

have no

Imagination

Page 12: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Lesson #6

Running Out of Money

Before Construction Starts

is a Bad Thing

DEC would limit annual

reimbursement to Town

Devised Construction Phasing Plan

Divided work into 6 Parcels

Work would stretch over 6 years

Estimated Cost > $25M

Page 13: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Lesson #7

Politics Enters into Everything

Design Element included leachate collection trench.

Dilemma was how to dispose of leachate?

Obvious choice was to pretreat and discharge to County

sewer immediately adjacent to site.

But…..

Page 14: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Lesson #7

Politics Enters into Everything

Town with Democratic Majority and

County with Republican Majority

= NO DEAL

Town with Republican Majority and

County with Republican Majority

= DEAL!

Page 15: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Lesson #8

Lawyers Make More Money than

Engineers

(so why do they always want to do

engineering?)

Page 16: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Lesson #9

Time can be your friend!

Page 17: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Project Elements

National Grid Completed $900K Utility Relocation

Page 18: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Project Elements

Satisfied National Grid by installing clay cap in utility corridors

Page 19: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Project Elements

Reduced Landfill Footprint by 12.3 acres

Page 20: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Project Elements

Capped 3 cell areas with geomembrane

Page 21: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Project Elements

Re-routed major drainage swale beyond limit of waste

Page 22: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Project Elements

Mitigated wetlands at 1:1 ratio and

created more contiguous habitat

Page 23: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Project Elements

Installed 2,100 foot long leachate collection trench

Page 24: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Project Elements

Constructed 2,400 sq ft Pretreatment Building

Page 25: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Lesson #9

Time can be your friend!

Project Completed in 2 Phases

Remediation took 4 years

Original Estimated Cost = $25M

Final Cost = $15.5M

Page 26: WHY IT TOOK HALF A CAREER TO CLOSE A LANDFILL Burns… · Ley Creek . Lesson #2 A Record of Decision Can Say Funny Things Comment on Proposed Plan: ... Final Cost = $15.5M . Thank

Thank You