Why Energy Extraction in the LHC ?

32
Why Energy Extraction in the LHC ? Why Energy Extraction in the LHC ? For the LHC 13 kA circuits of arc dipole and quadrupole chains: For the LHC 13 kA circuits of arc dipole and quadrupole chains: In case of a magnet quench a rapid current decay is required after transfer of the current to the cold diode in order to preserve the diode and its associated busbars. The alternative is a ‘Slow Power Abort’ (power restored to the Mains Network), which takes 20 min (-10 A/s) and is only possible for the dipole circuits (inversion possible as thyristor power converter, made for it). However too long in case of a quench, due to heating of diode and its associate busbars. The sa,me is true in case of no water circulation in power cables and FW path in the converter. The rapid current decay is obtained by switching external The rapid current decay is obtained by switching external resistance into the circuit. Almost the complete stored energy resistance into the circuit. Almost the complete stored energy shall be absorbed by the shall be absorbed by the external external dump resistors (99.5 % in the dump resistors (99.5 % in the LHC dipole chains and 92 % in the LHC quadrupole chains). LHC dipole chains and 92 % in the LHC quadrupole chains). The EE systems of a main magnet chains are being activated in The EE systems of a main magnet chains are being activated in case of a quench, an FPA, a UPS failure or an internal problem case of a quench, an FPA, a UPS failure or an internal problem in the EE facility itself. in the EE facility itself.

description

Why Energy Extraction in the LHC ?. For the LHC 13 kA circuits of arc dipole and quadrupole chains: In case of a magnet quench a rapid current decay is required after transfer of the current to the cold diode in order to preserve the diode and its associated busbars. - PowerPoint PPT Presentation

Transcript of Why Energy Extraction in the LHC ?

Page 1: Why Energy Extraction in the LHC ?

Why Energy Extraction in the LHC ?Why Energy Extraction in the LHC ?

For the LHC 13 kA circuits of arc dipole and quadrupole chains:For the LHC 13 kA circuits of arc dipole and quadrupole chains:

In case of a magnet quench a rapid current decay is required after transfer of the current to the cold diode in order to preserve the diode and its associated busbars.

The alternative is a ‘Slow Power Abort’ (power restored to the Mains Network), which takes 20 min (-10 A/s) and is only possible for the dipole circuits (inversion possible as thyristor power converter, made for it). However too long in case of a quench, due to heating of diode and its associate busbars. The sa,me is true in case of no water circulation in power cables and FW path in the converter.

The rapid current decay is obtained by switching external resistance into the The rapid current decay is obtained by switching external resistance into the circuit. Almost the complete stored energy shall be absorbed by the circuit. Almost the complete stored energy shall be absorbed by the externalexternal dump resistors (99.5 % in the LHC dipole chains and 92 % in the LHC dump resistors (99.5 % in the LHC dipole chains and 92 % in the LHC quadrupole chains).quadrupole chains).

The EE systems of a main magnet chains are being activated in case of a The EE systems of a main magnet chains are being activated in case of a quench, an FPA, a UPS failure or an internal problem in the EE facility itself.quench, an FPA, a UPS failure or an internal problem in the EE facility itself.

Page 2: Why Energy Extraction in the LHC ?

Why Energy Extraction in the LHC Why Energy Extraction in the LHC (contd.)?(contd.)?

For the LHC 600 A corrector magnet circuits:For the LHC 600 A corrector magnet circuits: No quench heaters nor by-pass diodes are installed for the

corrector magnets, even when several of these are series-connected in a chain.

Apart from the presence of parallel resistors across certain corrector magnets, protection relies on the operation of an energy extraction system

Particularly important: Short reaction time and low value of the time constant for the current decay is required due to small thermal margins for the superconducting busbars.

Two different energy extraction systems are foreseen: Medium-voltage, separate extraction facilities Low-voltage, converter-integrated systems

Page 3: Why Energy Extraction in the LHC ?

Stored Energy in the various LHC Stored Energy in the various LHC circuitscircuits

Maximum values, corresponding to 13000 A and 600 A respectively:Maximum values, corresponding to 13000 A and 600 A respectively:In one Arc Dipole Chain (one Sector, 154 dipoles in series):

1318 MJ Equivalent to the kinetic energy of a fully loaded airbus at 800 km/h or a

TGV at 300 km/h.In one Chain of Main Quads (one Sector, 51 quadrupoles in series): 20 MJin a 600A Corrector Circuit: 1.8 kJ - 22 kJ

Equivalent to the kinetic energy of a standard car at the speed of 60 km/h.

It is not foreseen to recover the stored energy in case of extraction. It is not foreseen to recover the stored energy in case of extraction.

Reasons:Reasons: With the sectorisation of the LHC machine only the sector with

a problem will be subjected to the extraction process. The energy to be safely recovered is, therefore, limited to the above values.

Although the energy in one dipole sector appears to be large, the cost of this energy is small (40 CHF/sector).

Page 4: Why Energy Extraction in the LHC ?

When will Energy Extraction be When will Energy Extraction be activated in the LHC?activated in the LHC?

Energy Extraction is a part of the Energy Extraction is a part of the normal operating proceduresnormal operating procedures in the LHC in the LHC machinemachine

Energy Extraction will Energy Extraction will NOTNOT be used for the ordinary de-excitation of the be used for the ordinary de-excitation of the magnet chains. Energy recuperation is possible in some of the circuits magnet chains. Energy recuperation is possible in some of the circuits (e.g. in the Main Dipole circuits). Operating the converters in inversion will (e.g. in the Main Dipole circuits). Operating the converters in inversion will allow power feedback to the Mains Grid.allow power feedback to the Mains Grid.

Energy Extraction Energy Extraction willwill be used in following cases: be used in following cases: In the event of a quench in a magnet coil or a superconducting

busbar or a current lead, i.e. when a In the event of a risk of damage to other components in the power

circuit (e.g. no water flow for a certain time in the 13 kA water-cooled cables or problems in the by-pass crowbar system or failure in the extraction switches)

Energy Extraction Energy Extraction maymay be used in the following cases: be used in the following cases: In dipole chains in the event of Mains failures which trip the power

converter In the dipole chains in the event of a failure in the Crowbar power

converter failure

Page 5: Why Energy Extraction in the LHC ?

PrincipalPrincipal requirements and parametersrequirements and parameters

Current DecayCurrent Decay: : After transfer of the current to the After transfer of the current to the extraction resistor the decay will follow a modified extraction resistor the decay will follow a modified exponential. exponential.

The shift is due to the presence of semiconductors The shift is due to the presence of semiconductors in the circuit (FWT and Cold Diode)in the circuit (FWT and Cold Diode)

The ‘modulation’ of the exponential is due to the The ‘modulation’ of the exponential is due to the significant temperature elevation of the resistor significant temperature elevation of the resistor body during the extraction. This modification will body during the extraction. This modification will depend of the mass and choice of material for the depend of the mass and choice of material for the resistor body. resistor body.

Design criteria:Design criteria: Neither the voltage nor the current decay rate

should at any time during the discharge exceed the initial value.

Page 6: Why Energy Extraction in the LHC ?

Choice of Circuit TopologyChoice of Circuit TopologySeries- or Parallel Inserted Systems?Series- or Parallel Inserted Systems?

In a In a SERIESSERIES system the dump resistor is bridging the extraction switches. One system the dump resistor is bridging the extraction switches. One or more such systems are inserted in series with the load or parts of itor more such systems are inserted in series with the load or parts of it

In a In a PARALLELPARALLEL system the dump resistor is bridging the magnet chain, the system the dump resistor is bridging the magnet chain, the opening switches being located at the terminals of the power converteropening switches being located at the terminals of the power converter

The SERIES TOPOLOGY requires:The SERIES TOPOLOGY requires: a by-pass with adequate current rating across the power converter two current leads for every load segment in case of multiple systems space along the chain for insertion of the systems

The SERIES TOPOLOGY allows:The SERIES TOPOLOGY allows: a breakdown into smaller sub-systems, enabling

a significant reduction of the maximum voltage to ground a sharing of the total dissipated energy between the sub- systems

The PARALLEL TOPOLOGY requires:The PARALLEL TOPOLOGY requires: particular measures for suppression of the leakage current through the

dump resistor (always in circuit). Displacement of the DCCT to a position downstream of dump resistor may be sufficient in low-voltage systems with large Rdump

space for complete extraction system at converter terminals The PARALLEL TOPOLOGY allows:The PARALLEL TOPOLOGY allows:

to operate without by-pass across the power converter

Page 7: Why Energy Extraction in the LHC ?

Series- or Parallel Inserted Systems? Series- or Parallel Inserted Systems? (contd)(contd)

Further disadvantages of a PARALLEL system for LHC dipole Further disadvantages of a PARALLEL system for LHC dipole circuits:circuits:

Although being disconnected by the switches the power converter will rise to half the peak extraction voltage (980 V) for the duration of the difference in opening times. In the double-series topology it will never rise to more than a quarter of the peak voltage.

The first opening switch will be subjected to the full peak extraction voltage until the second switch opens.

A DOUBLE SERIES TOPOLOGY HAS BEEN CHOSEN FOR A DOUBLE SERIES TOPOLOGY HAS BEEN CHOSEN FOR THE LHC DIPOLE AND QUADRUPOLE CIRCUITSTHE LHC DIPOLE AND QUADRUPOLE CIRCUITS

The LHC dipole circuit has two symmetrically placed, 660 MJ sub-The LHC dipole circuit has two symmetrically placed, 660 MJ sub-systems, one in the even point, at neg. pole of power converter systems, one in the even point, at neg. pole of power converter and one in the odd point, at electrical circuit midpoint. With circuit and one in the odd point, at electrical circuit midpoint. With circuit earthing in the electrical midpoint of one of the two dump earthing in the electrical midpoint of one of the two dump resistors the maximum voltage to ground can be divided by 4! resistors the maximum voltage to ground can be divided by 4! (490 V instead of 1960 V). Also the voltage rating of the switches (490 V instead of 1960 V). Also the voltage rating of the switches can be reduced.can be reduced.

Page 8: Why Energy Extraction in the LHC ?

Series- or Parallel Inserted Systems? Series- or Parallel Inserted Systems? (contd)(contd)

Also for the LHC QF/QD circuits, with only one extraction system Also for the LHC QF/QD circuits, with only one extraction system required, a parallel topology has been favored, because:required, a parallel topology has been favored, because:

By-pass diodes are anyway foreseen for the power converter The low value of dump resistance would require additional

blocking diodes in a parallel system

For the 600 A Extraction Facilities, with their low ramping voltage For the 600 A Extraction Facilities, with their low ramping voltage and high dump resistance, both topologies are acceptable. and high dump resistance, both topologies are acceptable. However, for the external, individual extraction system, a series-However, for the external, individual extraction system, a series-topology is preferred, astopology is preferred, as

the converter already has a crowbar by-pass mounting of the DCCT’s downstream of the extraction

system causes practical problems. For the converter-integrated facilities, a parallel system is For the converter-integrated facilities, a parallel system is

preferable. preferable.

Page 9: Why Energy Extraction in the LHC ?

Updated on 16-Jul-06 Version 1 600A EE CERN - AT / MEL 1

Energy ExtractionEnergy Extraction

Page 10: Why Energy Extraction in the LHC ?

The Principal Energy Extraction The Principal Energy Extraction Switches Switches

The extraction switch system shall be able to carry permanently the The extraction switch system shall be able to carry permanently the full system current. It shall be capable of reliably interrupting currents full system current. It shall be capable of reliably interrupting currents in the complete current range for transfer to the extraction resistor. in the complete current range for transfer to the extraction resistor. If several switches are used in parallel for current sharing, each individual switch shall have the capability to interrupt the complete system current.

Two different types of switches can be used for energy extraction:Two different types of switches can be used for energy extraction:

Semiconductor based (Thyristor or GTO -with anti-parallel diodes)

Electro-mechanical DC circuit breakers

CERN has almost 10 years of experience with both types of switches CERN has almost 10 years of experience with both types of switches and combinations for the purpose of energy extraction (LHC test and combinations for the purpose of energy extraction (LHC test benches).benches).

SELECTION CRITERIA: Reliability, long life-time, low losses, radiation SELECTION CRITERIA: Reliability, long life-time, low losses, radiation hardness.hardness.

Page 11: Why Energy Extraction in the LHC ?

Selection Criteria for the 13 kA Energy Selection Criteria for the 13 kA Energy Extraction switch-gearExtraction switch-gear

ADVANTAGES / SHORTCOMINGS of the two types:ADVANTAGES / SHORTCOMINGS of the two types: Electro-mechanical breakers can be equipped with two totally

independent release systems, one passive (de-energizing of a ‘holding’ coil) and one active (pulsed release), whereas the semiconductor devices entirely rely on a single, active system to turn off (forced commutation by reverse cathode voltage application or gate current injection)

The voltage drop across a mechanical breaker is typically 60 mV at 4kA, against 1.4 V for a conducting power Thyristor or GTO. A complete array of mechanical breakers for 13 kA would have power losses eight times lower than an equivalent Thyristor switch array (5 kW against 38 kW). For the LHC the difference would be 1.3 MW !!

A DC breaker is significantly more radiation tolerant than the semiconductor device.

The semiconductor switch needs water-cooling, the mechanical breaker is natural-air cooled.

DC breakers are by nature a protection device, built to protect highly valuable equipment against short-circuits and are, therefore, utmost reliable components.

Page 12: Why Energy Extraction in the LHC ?

The LHC 13 kA Extraction Switch SystemThe LHC 13 kA Extraction Switch SystemParticular CERN requirementsParticular CERN requirements

LHC application as Energy Extraction Switch requires:LHC application as Energy Extraction Switch requires: Very high reliability No mechanical Catch and Latch system. The ‘on-state’ shall be

maintained only by excitation of the ‘Holding Coil’ Two completely independent release systems The required high number of cycles shall be taken into account

in the design and construction of the breaker designed for separation of the main contacts without arc, use of easily replaceable arcing contacts

Magnetic displacement of the arc for fast and reproducible arc extinction (magnetic wind)

High overload and breaking capability Low voltage drop and losses Protection by overload detector Design based on industrial components, which have been in

current production for at least 10 years No existing breaker on the marked satisfies all these demands !!No existing breaker on the marked satisfies all these demands !!

Page 13: Why Energy Extraction in the LHC ?

VAB49VAB49

A development was undertaken (1998) with the DC Circuit Breaker A development was undertaken (1998) with the DC Circuit Breaker Department of Russian company “Uralelektrotyazhmash’, Department of Russian company “Uralelektrotyazhmash’, EkaterinburgEkaterinburg

The design comprised components from 3 existing DC breakers The design comprised components from 3 existing DC breakers presently protecting sub-stations, locomotives and steel works in presently protecting sub-stations, locomotives and steel works in all former USSR Republics, China and Indiaall former USSR Republics, China and India

The design is based on a unique, 3-limb magnetic circuit, common The design is based on a unique, 3-limb magnetic circuit, common for the four functions: closing, holding, slow- and fast releasefor the four functions: closing, holding, slow- and fast release

The slow release is based on removal of the ‘holding’ current, the The slow release is based on removal of the ‘holding’ current, the fast release is based on application of a capacitor discharge pulsefast release is based on application of a capacitor discharge pulse

The design features re-designed Arc Shutes and Mufflers. The design features re-designed Arc Shutes and Mufflers. Two versions were made: A 1500 V model for the LHC Arc Two versions were made: A 1500 V model for the LHC Arc Dipole circuits and a 200 V version for the Main Quadrupoles.Dipole circuits and a 200 V version for the Main Quadrupoles.

The result is a fast breaker, with typical total opening times (I.e. to The result is a fast breaker, with typical total opening times (I.e. to full arc extinction at rated voltage and no parallel resistor) of 5 ms full arc extinction at rated voltage and no parallel resistor) of 5 ms +-1 ms for the pulsed release and 20 ms +-2 ms for the under-+-1 ms for the pulsed release and 20 ms +-2 ms for the under-voltage release.voltage release.

Page 14: Why Energy Extraction in the LHC ?

Modeling and Computer Simulation ofModeling and Computer Simulation of the Breaker the Breaker Behavior for Determination of Principles and Ratings Behavior for Determination of Principles and Ratings

of the Control Electronics Modulesof the Control Electronics Modules

Optimization of the controls parameters of the strongly non-linear electro-magnetic Driving Mechanisms Optimization of the controls parameters of the strongly non-linear electro-magnetic Driving Mechanisms of the switch was obtained by computer simulations (a BINP / CERN / ‘Uralelektro’ collaboration).of the switch was obtained by computer simulations (a BINP / CERN / ‘Uralelektro’ collaboration).

The Simulations were based on elaboration of The Simulations were based on elaboration of electrical modelselectrical models of: of: the magnetic circuits, including the saturation effects (piecewise linear models) the varying air gaps of the magnetic circuit (variable controlled resistors, model with signal

amplifiers) the mechanical systems (springs, levers, armatures). All mechanical springs operate in their linear

ranges. matching between the equivalent representations of the magnetic circuits and the coils required

introduction of a further equivalent circuit, representing the stored magnetic energy (representation by current-controlled voltage sources) and a feedback loop

After determination and representation of the initial conditions of the various systems, the complete model (120 elements) was constituted.

The work is presented in the Conference Paper: “Modeling and Computer Simulation of the Pulsed Powering of Mechanical D.C. Circuit Breakers for the CERN/LHC Superconducting Magnet Energy Extraction System”, ICAP2000, Heidelberg.

The associated control electronics was developed at CERN.The associated control electronics was developed at CERN.

Page 15: Why Energy Extraction in the LHC ?
Page 16: Why Energy Extraction in the LHC ?

Milestones related to the 13 kA switch-Milestones related to the 13 kA switch-geargear

280 units of 4.5 kA DC breakers and 140 over-current detectors are 280 units of 4.5 kA DC breakers and 140 over-current detectors are required for the LHC machine, half for the arc dipoles, other half for the required for the LHC machine, half for the arc dipoles, other half for the main quadrupoles. main quadrupoles.

Prototypes of both 1500 V and 200 V versions were successfully type Prototypes of both 1500 V and 200 V versions were successfully type tested in Russia, using the CERN prototype controls electronics.tested in Russia, using the CERN prototype controls electronics.

Off-load, mechanical reliability tests (20’000 cycles) were successfully Off-load, mechanical reliability tests (20’000 cycles) were successfully performed at the premises of the manufacturer also using the CERN-made performed at the premises of the manufacturer also using the CERN-made power electronics module.power electronics module.

Prototypes of both versions were subjected to Certification tests of their Prototypes of both versions were subjected to Certification tests of their commutation capabilities over the current range 200 - 13’000 A. The tests commutation capabilities over the current range 200 - 13’000 A. The tests were carried out according to IEC 60947-1 at an independent High-Power were carried out according to IEC 60947-1 at an independent High-Power Laboratory (Zkusebnictvi Institute, Prague, CZ).Laboratory (Zkusebnictvi Institute, Prague, CZ).

An endurance test program has been conducted, during which 4 breakers An endurance test program has been conducted, during which 4 breakers were individually subjected to 2000 cycles with breaking of 13.5 kA at were individually subjected to 2000 cycles with breaking of 13.5 kA at 1000V.1000V.

CERN has undertaken a mechanical lifetime program, also using 4 pre-CERN has undertaken a mechanical lifetime program, also using 4 pre-series breakers, powered from a pre-series electronics module from ECIL, series breakers, powered from a pre-series electronics module from ECIL, India.India.

Page 17: Why Energy Extraction in the LHC ?

Milestones (continued)Milestones (continued)

In an attempt to evaluate failure probabilities during the various phases of In an attempt to evaluate failure probabilities during the various phases of operation, a operation, a global risk analysisglobal risk analysis for the complete 13 kA switch facility is for the complete 13 kA switch facility is presently being initiated at CERN. presently being initiated at CERN.

The supervision of the quality assurance scheme during production of the The supervision of the quality assurance scheme during production of the breakers in the Urals as well as assistance during routine testing has been breakers in the Urals as well as assistance during routine testing has been entrusted the Prague High-Power Test Institute. entrusted the Prague High-Power Test Institute.

The production of the series of 256 units was completed at the end of 2004.The production of the series of 256 units was completed at the end of 2004. All the produced breakers are being tested in the complete set-ups All the produced breakers are being tested in the complete set-ups

including all the other components of an extraction facility.including all the other components of an extraction facility. Installation of the first switch assemblies in the LHC tunnel started in May Installation of the first switch assemblies in the LHC tunnel started in May

2005.2005.

Page 18: Why Energy Extraction in the LHC ?

The current-equalizing BuswayThe current-equalizing Busway

Each set of four parallel connections of each two series-connected 4.5 kA Each set of four parallel connections of each two series-connected 4.5 kA breakers will be fed through a water-cooled power Busway.breakers will be fed through a water-cooled power Busway.

The principal requirements to the Busway are:The principal requirements to the Busway are: to provide a balanced distribution of the total circuit current (13 kA)

between the four branches to do the job of current distribution with a minimum of voltage drop

and losses (reasonably 4 kW at 13 kA) to minimize the stray field outside the bus

These requirements lead to a These requirements lead to a quasi-coaxial design (fig) (fig) Both a short and a long version are neededBoth a short and a long version are needed

SHORT version (30 units) is symmetrical with 2 branches on each side

LONG version (2 units, for installation in the LHC tunnel, point 3) has all eight switches on one side only (co-existence with LHC vacuum chambers)

Hydraulically, the Busway is a part of the water-cooled cable circuit. Hydraulically, the Busway is a part of the water-cooled cable circuit. A specially developed, 13 kA conical connector assures electrical (0.6A specially developed, 13 kA conical connector assures electrical (0.6) ) and hydraulic connection to the 2000 mmand hydraulic connection to the 2000 mm22 power cable. power cable.

The 32 Busways will be produced at BINP, Novosibirsk, using the in-situ The 32 Busways will be produced at BINP, Novosibirsk, using the in-situ ‘Elsib’ brazing technique. Series production was completed by end of 2004.‘Elsib’ brazing technique. Series production was completed by end of 2004.

Page 19: Why Energy Extraction in the LHC ?

Current-equalizing Busways for distribution of Current-equalizing Busways for distribution of currents into the four branches of breakers.currents into the four branches of breakers.

Page 20: Why Energy Extraction in the LHC ?

Breaker Powering and Controls Breaker Powering and Controls ModulesModules

The modeling and simulations lead to the The modeling and simulations lead to the determination of the operational sequences, determination of the operational sequences, permissible ranges and safety margins of all permissible ranges and safety margins of all parameters of the powering and controls circuit. parameters of the powering and controls circuit.

A prototype module was developed and built at A prototype module was developed and built at CERN. Qualified during numerous tests at CERN and CERN. Qualified during numerous tests at CERN and abroad. abroad.

Also the Logic Controller Also the Logic Controller Interface ModuleInterface Module for Data for Data Acquisition was developed and built at CERN. Acquisition was developed and built at CERN.

A pre-series of 10 cabinets was built in Europe to A pre-series of 10 cabinets was built in Europe to satisfy urgent needs for testing the DC breakers.satisfy urgent needs for testing the DC breakers.

Series production of 70 cabinets were covered by a Series production of 70 cabinets were covered by a collaboration agreement with India and built by the collaboration agreement with India and built by the company ECIL in Hyderabad. The first units are now company ECIL in Hyderabad. The first units are now being installed in the LHC tunnel.being installed in the LHC tunnel.

Page 21: Why Energy Extraction in the LHC ?

The Dump Resistors for the LHC 13 kA The Dump Resistors for the LHC 13 kA CircuitsCircuits

In spite of the In spite of the large energy differencelarge energy difference (664 MJ per diode system and 22/24 (664 MJ per diode system and 22/24 MJ per quadrupole circuit) the two extraction resistor types have much in MJ per quadrupole circuit) the two extraction resistor types have much in common. The basic design criteria for both types are:common. The basic design criteria for both types are:

In order to maintain the peak voltage across the resistor at its lowest possible level, as defined by the resistance at room temperature, a ‘zero’ inductance concept shall be applied and an absorber material with low temperature coefficient shall be selected.

The resistor bodies shall be dimensioned for high temperature operation, but within safe margins for long term reliability of its materials and components. Typically, the operating temperature at the end of the energy deposit shall attain 200-350 oC.

The design shall assure a perfect short- and long term reliability. The resistor units shall be available for energy extraction without need of any

infrastructure, such as mains power and cooling water, during the extraction period.

The heat dissipation to the surrounding air shall be close to zero, due to underground installation. Connection to LHC de-mineralized cooling water circuit is therefore needed for evacuation of the heat.

A design, in which the resistor body is not immersed in water, has been favored. Direct cooling by forced air is a good choice, but requires an air-to-water heat exchange. Such a device shall be incorporated in the resistor assembly.

The unit shall have its own water reservoir with sufficient capacity to assure worst-case no-boiling conditions.

The normal cooling period shall be maximum 2 hours

Page 22: Why Energy Extraction in the LHC ?

Energy Extraction Resistors (contd.)Energy Extraction Resistors (contd.)

Particularly for the dipole resistors:Particularly for the dipole resistors: The design shall allow their installation under the LHC

vacuum chambers in the collider tunnel (odd points). This requirement also highlights the need for radiation resistance of all selected materials.

With an energy deposit of 664 MJ a single, 75 m unit would be 11 m long and have a mass of 8 tons. For reasons of space allocations and handling, the resistor will be composed of three individual, parallel connected sub-units. Vertical superposition is required in the UA’s for limitation of floor space.

Each sub-unit has its own, built-in combined heat exchanger/ low-pressure water reservoir. The pressure is ‘broken’ by creation of a separate, secondary cooling circuit, common for the three sub-resistor units.

The LHC requirements are: 48 resistor units + 5 spares, each 225 m +- 3 m, 221 MJ.

Page 23: Why Energy Extraction in the LHC ?

Dipole Dump Resistors under Dipole Dump Resistors under tests at IHEP, Protvino.tests at IHEP, Protvino.

Page 24: Why Energy Extraction in the LHC ?
Page 25: Why Energy Extraction in the LHC ?

Energy Extraction Resistors (contd.)Energy Extraction Resistors (contd.)

Particularly for the quadrupole resistors:Particularly for the quadrupole resistors: The energy level of 22/24 MJ allows a rack-mounted design. All resistor units shall be installed outside radiation areas, in

the UA galleries, next to the associated 13 kA switch system. The basic principles are the same as for the dipole resistors,

except that the smaller water storage allowed the reservoir to be a high-pressure vessel with direct connection to the LHC cooling circuits.

The required quantity for the LHC is 16 + 6 spares. Half of these shall have a resistance of 6.6 m (circuits with 47 series-connected quadrupoles), the other half shall have a resistance of 7.7 m (51 series-connected quadrupoles). The discharge time constant is in both cases 42 s. The system voltage is low (100 V).

Page 26: Why Energy Extraction in the LHC ?

600 A Energy Extraction Facilities for 600 A Energy Extraction Facilities for the LHC the LHC

History of the ProjectHistory of the Project

The project started in September 1999 with the The project started in September 1999 with the invitation to two Russian Institutes (BINP & IHEP) to invitation to two Russian Institutes (BINP & IHEP) to prepare preliminary proposals for a design and prepare preliminary proposals for a design and choice of components.choice of components.

It was finally the Institute BINP in Novosibirsk which It was finally the Institute BINP in Novosibirsk which was selected for the definitive design and was selected for the definitive design and production of the series of 205 systems.production of the series of 205 systems.

60 systems have been supplied so far. The 60 systems have been supplied so far. The remaining numbers are in production.remaining numbers are in production.

The first 16 systems were installed in the LHC The first 16 systems were installed in the LHC machine late May 2005.machine late May 2005.

Page 27: Why Energy Extraction in the LHC ?
Page 28: Why Energy Extraction in the LHC ?

600 A Extraction 600 A Extraction Constructional DetailsConstructional Details

Separate facilities, located outside the associated power converter.Separate facilities, located outside the associated power converter. Two systems will share one standard Euro-rack.Two systems will share one standard Euro-rack. The chosen topology is a The chosen topology is a Series-inserted system with two main breakers, Series-inserted system with two main breakers,

operated simultaneouslyoperated simultaneously.. Short opening time is here a big issue. Short opening time is here a big issue. In both proposals, the extraction switch is based on Standard 3-pole In both proposals, the extraction switch is based on Standard 3-pole

electro-mechanical AC breakers, retro-fitted with DC Arc Shutes and electro-mechanical AC breakers, retro-fitted with DC Arc Shutes and Capacitive Snubber Circuits for arc suppression. The capacitor bank, Capacitive Snubber Circuits for arc suppression. The capacitor bank, bridging the switches, will strongly reduce the contact erosion (no bridging the switches, will strongly reduce the contact erosion (no additional arcing contacts), it will reduce the noise and it will shorten the additional arcing contacts), it will reduce the noise and it will shorten the arcing time. The ‘military’ version of these breakers are selected.arcing time. The ‘military’ version of these breakers are selected.

The 600 A will be shared by the three poles in parallel.The 600 A will be shared by the three poles in parallel. As it was the case for the 4.5 kA DC breaker, also these AC switches have As it was the case for the 4.5 kA DC breaker, also these AC switches have

two independent modes of release, herewith providing a four-fold two independent modes of release, herewith providing a four-fold redundancy.redundancy.

The system controls are made as a joint venture between the Russian The system controls are made as a joint venture between the Russian Institute and CERN. The control system includes the interface to the Power Institute and CERN. The control system includes the interface to the Power Permit link and the data transmission gateway. However, the Power Abort Permit link and the data transmission gateway. However, the Power Abort Link is common with the associated power converter. Link is common with the associated power converter.

All cards are made as SMD and burnt-in.All cards are made as SMD and burnt-in.

Page 29: Why Energy Extraction in the LHC ?

Other Basic ParametersOther Basic Parameters

Typical total opening time with active release: 11 - 17 msTypical total opening time with active release: 11 - 17 ms Typical total opening time with under-voltage release: 20 - 22 msTypical total opening time with under-voltage release: 20 - 22 ms Total opening time with motor drive / electromagnetic driver: 65 ms!Total opening time with motor drive / electromagnetic driver: 65 ms! Maximum DC voltage across one breaker during opening: Maximum DC voltage across one breaker during opening:

Rated value: 420 V , but successfully tested up to the double.Rated value: 420 V , but successfully tested up to the double. Required Snubber Capacitance: 320 Required Snubber Capacitance: 320 F.F. Extraction Resistor: 0.7 Extraction Resistor: 0.7 up to 1 up to 1 . Made from material with low . Made from material with low

temperature coefficient of resistivity, e.g. FeCrAl or SS.temperature coefficient of resistivity, e.g. FeCrAl or SS. Equalizing resistors maybe required for current balance through the multi-Equalizing resistors maybe required for current balance through the multi-

pole breakers (depending on the choice of switch).pole breakers (depending on the choice of switch). All elements are natural-air cooled.All elements are natural-air cooled. Cooling time of Rdump after complete discharge with max. energy (108 kJ): Cooling time of Rdump after complete discharge with max. energy (108 kJ):

Typically 20 min.Typically 20 min. Local controls and the supervision electronics mounted in a single 3U Local controls and the supervision electronics mounted in a single 3U

Euro-chassis.Euro-chassis.

For the unlikely event of a switch-opening failure of the two main breakers, For the unlikely event of a switch-opening failure of the two main breakers, a third, identical switch is inserted in series with the two main devices and a third, identical switch is inserted in series with the two main devices and operated only in the case of a non-opening of operated only in the case of a non-opening of bothboth main breakers. main breakers.

Page 30: Why Energy Extraction in the LHC ?

Operational Aspects - related to the 13 Operational Aspects - related to the 13 kA SystemskA Systems

During powering of the associated magnet chain, the energy extraction During powering of the associated magnet chain, the energy extraction facility shall facility shall always be operationalalways be operational, ready for extraction, independent of the , ready for extraction, independent of the state of any infrastructure.state of any infrastructure.

The local powering and controls are fed from UPS. Only closing of the DC The local powering and controls are fed from UPS. Only closing of the DC breakers rely on the Mains network.breakers rely on the Mains network.

The DC breakers are OPENING SWITCHES, not closing switches. Repetitive The DC breakers are OPENING SWITCHES, not closing switches. Repetitive closing with current may cause damage to the breaker contacts. Several closing with current may cause damage to the breaker contacts. Several precautions are taken to avoid closing with current:precautions are taken to avoid closing with current:

Re-closing is inhibited as long as there’s voltage across the extraction resistor(s)

Re-closing is inhibited as long as the temperature of the resistor body is above 50 oC.

Time-out of 10 min after an opening prevent re-closing during extraction.

The facility is a part of the power enabling chain (Power Permit) as well as The facility is a part of the power enabling chain (Power Permit) as well as of the Fast Power Abort chain. of the Fast Power Abort chain.

During the closing process, all 8 switches must close and remain closed During the closing process, all 8 switches must close and remain closed for at least 5 s. As the breaker rating allows continued operation with only for at least 5 s. As the breaker rating allows continued operation with only 3 branches, one branch may fall out (opening by accident) without 3 branches, one branch may fall out (opening by accident) without jeopardizing the operation. In the case that more than one branch is being jeopardizing the operation. In the case that more than one branch is being opened all the other breakers of the system will be forced open and we opened all the other breakers of the system will be forced open and we have extraction.have extraction.

Page 31: Why Energy Extraction in the LHC ?

Operational Aspects - 600 A FacilitiesOperational Aspects - 600 A Facilities

The control of the 600 A systems are generally based on the same The control of the 600 A systems are generally based on the same fundamental principles as the 13 kA facilities. Only a few particularities fundamental principles as the 13 kA facilities. Only a few particularities affects the operation of these systems:affects the operation of these systems:

No logic is required for supervision of current branches, the 3 poles of the switches are mechanically interconnected.

There are no over-current relays The ‘Switch-Opening-Failure’ Interlock will react on an identical DC

breaker, located inside the extraction system itself.

Page 32: Why Energy Extraction in the LHC ?

Conclusions and Final RemarksConclusions and Final Remarks

The 200 Energy Extraction Systems represent 296 Tons of The 200 Energy Extraction Systems represent 296 Tons of ComponentsComponents

89 % is procured through contributions from Non-Member 89 % is procured through contributions from Non-Member States (11 % from European Industry)States (11 % from European Industry)

All components has now been type tested and approved All components has now been type tested and approved by CERNby CERN

The total cost of the systems is 18 MCHF (the European The total cost of the systems is 18 MCHF (the European Reference Price). Reference Price).