What is Commissioning? - Mechanical & Electrical Design ...

61

Transcript of What is Commissioning? - Mechanical & Electrical Design ...

Page 1: What is Commissioning? - Mechanical & Electrical Design ...
Page 2: What is Commissioning? - Mechanical & Electrical Design ...

What is Commissioning?

New building commissioning (Cx) is a means to

ensuring, through design reviews, functional testing,

system documentation, and operator training–that

systems and equipment in new buildings are

operating properly.

– BCA Best Practices

Page 3: What is Commissioning? - Mechanical & Electrical Design ...

Commissioning

USS Ronald Regan Commissioning Ceremony

2-1/2 years to commission.

Page 4: What is Commissioning? - Mechanical & Electrical Design ...

What is Commissioning?

Risk management technique

Helps insure owners get what they pay for

Provides early detection of problems through

design reviews and detailed testing

Enhances operator training and system

documentation

Energy and/or whole-building focus

Mechanical, electrical, lighting, plumbing, life

safety, building envelop

Page 5: What is Commissioning? - Mechanical & Electrical Design ...

What is Commissioning?

1984 ASHRAE HVAC Commissioning Guideline Committee formed

1988 ASHRAE publishes HVAC Commissioning Guideline

1992 U.S. GSA develops HVAC Functional Inspection & Testing Guide

1993 U.S. Army Corps of Engineers develops Cx guide specification

1994 Executive Order 12902 requires a Cx program for federal agencies

1994 U.S. Army Corps of Engineers develops HVAC Commissioning

Procedures

1995 U.S. GSA publishes Building Commissioning Guide, Version 1

1996 ASHRAE publishes Guideline 1-1996: The HVAC Commissioning

Process

Page 6: What is Commissioning? - Mechanical & Electrical Design ...

Terms Defined

New Building

Commissioning (Cx)

Existing Building

Retrocommissioning (RCx)

Recommissioning (RCx)

On-going commissioning (CCx/MBCx)

Page 7: What is Commissioning? - Mechanical & Electrical Design ...

What is Existing Building Cx & Tune-Up?

Applying the commissioning process to improve the current

conditions/operations of an existing building

Typically focuses on:

• HVAC Systems

• HVAC Controls

• Lighting Controls

Evaluates building operation:

• What were the building systems originally designed to do?

• What are the building systems doing now?

• How can the building systems be optimized for current needs?

Page 8: What is Commissioning? - Mechanical & Electrical Design ...

Benefits

Reduced operational cost and GHG emissions

Improved comfort

Mitigated indoor air quality problems

Increased operations staff knowledge

Increase occupant satisfactions/productivity

Increased property asset value

Utility incentives

Page 9: What is Commissioning? - Mechanical & Electrical Design ...

Benefits – Survey ResultsNEMI Building Commissioning TAB Market Research Study (2005)

Page 10: What is Commissioning? - Mechanical & Electrical Design ...

Industry Profile

Existing

$200M industry

660 Million SF

<1% building segment

Potential

$4B annual market

$30B energy savings potential (340 megatons CO2)

NEMI Building Commissioning TAB Market Research Study (2005)

Mills, 2009, Building Commissioning - Based on DOE/EIA (2003) energy

consumption, demand growth per the US EIA 2007 Annual Energy Outlook median

Cx energy savings of 16%.

Page 11: What is Commissioning? - Mechanical & Electrical Design ...

Why Commission?

“The results demonstrate that commissioning is

arguably the single-most cost-effective strategy for

reducing energy, costs, and greenhouse-gas

emissions in buildings today.”

Building Commissioning: A Golden Opportunity for Reducing

Energy Costs and Greenhouse Gas Emissions” –

Lawrence Berkeley National Laboratory July 2009

Page 12: What is Commissioning? - Mechanical & Electrical Design ...

Industry Profile

NEMI Building Commissioning TAB Market Research Study (2005)

Page 13: What is Commissioning? - Mechanical & Electrical Design ...

Typical Costs and Benefits

332 EBCx + 77 NBCx projects = 643 buildings

Mills, E., et al, 2009, Building Commissioning

Commissioning Analysis

of 643 Buildings Cost

$/Sq. Ft.

Benefit

$/Sq. Ft.

Return on

Your

Investment

%

Simple

Payback

Period

Years

Whole

Building

Energy

Savings

Existing Building Cx 0.30$ 0.27$ 91% 1.1 16%

New Building Cx 1.16$ 0.28$ 23% 4.2 13%

Page 14: What is Commissioning? - Mechanical & Electrical Design ...

Typical Costs and Benefits

Page 15: What is Commissioning? - Mechanical & Electrical Design ...

Barriers to Market Expansion

Lack of owner awareness to need and value

Insufficient provider consistency of service

Varied and competing certification programs

Lack of mandates (i.e. codes, policy, etc.)

Low energy prices

Cost

Page 16: What is Commissioning? - Mechanical & Electrical Design ...

The Tune-Up Process

Source: California

Commissioning

Collaborative

(BCA and NEBB list

similar processes)

Persistence

Page 17: What is Commissioning? - Mechanical & Electrical Design ...

Summary of Deliverables by Phase

Source: California

Commissioning

Collaborative

Page 18: What is Commissioning? - Mechanical & Electrical Design ...

PlanningGood Candidates for Tune-Ups

Unjustified high energy use

Frequent failure of energy systems

Excessive occupant comfort complaints

Buildings with energy management systems

Motivated owners / operators

Outdated building documentation, lack of

training on systems

Building staff knows problems, but lacks

time to fix

Page 19: What is Commissioning? - Mechanical & Electrical Design ...

Opportunities

Page 20: What is Commissioning? - Mechanical & Electrical Design ...

Investigation – Sources of Issues

Overrides due to other issues (warm-up time, poor comfort, etc.)

Hardware issues –actuator operation, controls linkage, sensor calibration

Improper control sequence, changes in space use

New Buildings Institute: 64% of economizers tested required adjustment

Page 21: What is Commissioning? - Mechanical & Electrical Design ...

Top Opportunities – PCD Experience

1. Optimize equipment scheduling

2. Optimize outside airflow control (free-cooling & minimum ventilation)

3. Reset/reduce supply air static pressure

4. Reset air and water temperatures

5. Return VFDs to variable speed operation – Restoring Auto Control

6. Repair inoperable controls hardware (dampers & valves)

7. Optimize plant sequencing (including lockout control)

8. Calibrate sensors

9. Fix leaks

10. Clean heat transfer surfaces

Page 22: What is Commissioning? - Mechanical & Electrical Design ...

Investigation

Review documentation and historical data

Interview personnel

Perform site observations

Data trending (DDC and/or portable loggers)

Point to point controls checkout & calibration (select points)

Functional performance tests (selective)

Test and balance measurements (selective)

Page 23: What is Commissioning? - Mechanical & Electrical Design ...

Investigation – Trend Data

Potential Savings

Page 24: What is Commissioning? - Mechanical & Electrical Design ...

Investigation – Inspection hall of fame

Restricted flow

Page 25: What is Commissioning? - Mechanical & Electrical Design ...

Investigation – Inspection hall of fame

When freezing isn’t cold enough

Wash Me!

36.1°F

Page 26: What is Commissioning? - Mechanical & Electrical Design ...

Investigation – Inspection hall of fame

When all else fails, put it in ‘hand’!!!

EO 13423 -Reduce use of ‘hand’ by 30% by 2015

Page 27: What is Commissioning? - Mechanical & Electrical Design ...

Persistence – Strategies for Success

PO&M Plan

Equipment Lists

O&M and Systems Manuals

Points List and Sequence of Operation

System Diagrams

Equipment life and expected/documented efficiency

Maintenance schedule and task descriptions

Form for data tracking and collection

Training – plan and execute and periodic refreshers

Ongoing discussion with occupants and O&M personnel

Performance tracking

Page 28: What is Commissioning? - Mechanical & Electrical Design ...

Persistence – Performance Tracking

Benchmark energy use (i.e. Energy Star or Utility Tracking

Software)

Performance and End-Use Monitoring

Trend key system parameters (chiller efficiency, system

pressure, run-time, etc)

Diagnostic and Reporting Software

y = 2.2041x - 89.443R² = 0.7974

-20

0

20

40

60

`80

100

120

140

160

180

200

0 50 100 150

Tons Delivered to Building

OSA Deg,F

Chiller Tons Delivered

tons

Linear (Series1)

Page 29: What is Commissioning? - Mechanical & Electrical Design ...

Making Tune-Ups Cost Effective

Use in house resources to reduce costs

Gather building documentation

Perform focused PM tasks prior to launching RCx

Assist with trending / sequence testing

Install/Remove short term data logging equipment

Perform/Manage repairs/improvements

Track/trend measures following implementation

Page 30: What is Commissioning? - Mechanical & Electrical Design ...

Selection Process

RFP or RFQ?

Define - Scope, systems, focus, goals, process

Qualifications, competence, previous

performance, and availability

Page 31: What is Commissioning? - Mechanical & Electrical Design ...

Selecting a Tune-Up Provider

Third party or in-house objective provider

Direct, relevant experience

Communication / conflict resolution skills

Organization skills

Forensic personality

Independent viewpoint

Rapport

Availability

Page 32: What is Commissioning? - Mechanical & Electrical Design ...

Retrocommissioning and LEED

EAp1 – Energy Efficiency BMPs

PM plan, Buidling Operation Plan, ASHRAE Level 1 Audit

EAp2 – Minimum Energy Performance

Energy Star > 69

EAc1 – Optimize Energy Performance

EAc2

Complete RCx process meeting LEED-EB guidelines

Investigation, Implementation, Ongoing Commissioning

EAc3 - Performance Measurement

Energy system end-use metering

Innovation in Operations – Unique O&M Strategy

Page 33: What is Commissioning? - Mechanical & Electrical Design ...

Lessons Learned – Tune Ups

Communications and coordination with team is paramount.

Provider verifies to confirm operation.

Document, document, document.

Close coordination to track issues to resolution.

Provider raises level of facility performance and installing contractor performance.

O&M warranty documentation and training invaluable.

Page 34: What is Commissioning? - Mechanical & Electrical Design ...

Case Study (RCx)

Optimize equipment scheduling

Duct static pressure reset

Supply air temperature reset

Optimize OA economizer

Hot water temperature reset

Optimize ventilation volume

Page 35: What is Commissioning? - Mechanical & Electrical Design ...

Case Study (RCx)

Optimize ventilation volume

Optimize equipment scheduling

Temperature resets

CAV to VAV MZU conversion

Chiller replacement

Boiler retrofit

1M Square Feet (33 buildings)

U.S. Army

Fort Bragg, NC

Page 36: What is Commissioning? - Mechanical & Electrical Design ...

Case Study (RCx)

Reduce VAV box min. settings

Turn off exhaust fans at night

Static pressure/Temperature resets

Optimize IDEC system

Fix data center air distribution

Obviate chiller spiking

$16,400 Implementation Cost

$23,000 Savings

133,000 Square Feet

Agilent Technologies

Loveland, CO

Page 37: What is Commissioning? - Mechanical & Electrical Design ...

Case Study (RCx)

Optimize HVAC scheduling

Duct static pressure reset

Optimize IDEC operation

Clean condenser coils

Relocating MA sensor

Correct over-pressurization

Page 38: What is Commissioning? - Mechanical & Electrical Design ...

Case Study (MBx)

Permanent Monitoring Systems

Identify ongoing savings – early detection

Continuous benchmarking

24 CA university campuses (UC, CSU systems)

46 buildings, 7M SF

10% ongoing energy savings

2.5 year payback on initial investment

$1 per SF costs

Page 39: What is Commissioning? - Mechanical & Electrical Design ...

Getting Started

Get informed about RCx

Identify contractors/consultants

Identify facilities / benchmark

Determine what local utility and government incentives are available

Have a budget

Page 40: What is Commissioning? - Mechanical & Electrical Design ...

Evaporative Cooling

Two-Stage Evaporative Cooling (Airside)

Head Start Learning Center (Commercial

Packaged)

Savings of up to 75% versus compressor-based

cooling

Application: Locations where average daily wet-

bulb range is fully below average daily drybulb

Range (i.e. Colorado, Utah, New Mexico…).

Two-Stage Evaporative Cooling (Water Side)

Useful for direct feeding high temperature cooling

applications

Increased efficiency for compressor-based cooling

systems

Peak demand savings.

Source: Wescor

Page 41: What is Commissioning? - Mechanical & Electrical Design ...

Ground Source Heat Pumps

Ground Source Heat Pumps

Takes advantage of cool ground temperatures

Reduces peak demand by up to ~40% over existing /base efficient

systems

Consider hybrid with tower if:

space constrained site

to correct load imbalance

high drilling cost exists

Utilize a Ground Water “Economizer” function

DR friendly

Page 42: What is Commissioning? - Mechanical & Electrical Design ...

Thermal Energy Storage

Thermal Energy Storage

Storage of cold water via ice or water based storage system

Demand savings: Replacing all or a portion of chiller operation during

peak demand periods with stored “cooling” from off-peak chilled water

production.

For winter peaking utilities, storage of heat.

Source: Poudre School DistrictSource: Steffes

Page 43: What is Commissioning? - Mechanical & Electrical Design ...

Dedicated Outdoor Air System with Energy Recovery

Dedicated Outdoor Air System with Energy Recovery

DOAS = decoupled ventilation load = reduced fan sizing, reduced duct

losses/leaks (1/5 airflow of typical VAV system).

ERV = Saving of 75% on outdoor air load

Demand savings: From reduction in peak cooling power draw

Couples with radiant cooling or heating technologies, displacement

ventilation, distributed heat pump technology.

Source: Mumma

Couples with radiant cooling or

heating technologies, displacement

ventilation, distributed heat pump

technology.

DOAS Application: Large amounts of

variably occupied space - office

buildings, hospitals or schools.

ERV Application: Buildings in hot-

Page 44: What is Commissioning? - Mechanical & Electrical Design ...

Variable Refrigerant Flow Systems

Application: Offices, schools, hotels, hospitals and other multi-room

buildings where personalize conditioning is desired. Historical

buildings where duct install is difficult or expensive.

Summer peak utilities can benefit - off-peak winter load that can

improve capital utilization and ROI. Decide to support based on local

rates, reserve margins, regulatory environment & other factors

Demand savings: Marginal, mostly part-load energy savings and

savings through ability to simultaneously heat/cool.

DR friendly

Page 45: What is Commissioning? - Mechanical & Electrical Design ...

Displacement Ventilation

Application: Buildings with high ceilings, moderate peak cooling load

densities (<13 Btu/hr-ft2), large annual cooling energy consumption,

and require small quantities of fresh air with high air quality, such as

offices, public buildings.

Demand savings: Up to 20% on ASHRAE design ventilation

requirements.

Page 46: What is Commissioning? - Mechanical & Electrical Design ...

Radiant Cooling / Chilled Beam

Application: Tight buildings with high sensible cooling loads, located

in low-humidity cooling climates.

Not buildings with appreciable latent loads (e.g., health/fitness clubs,

pools).

Demand Savings: Higher chilled water temperatures = increase cooling

efficiency. Also fan energy savings.

Active Chilled Beam- Source: Rumsey

Page 47: What is Commissioning? - Mechanical & Electrical Design ...

Variable Refrigerant Flow Systems

Application: Offices, schools, hotels, hospitals and other multi-room

buildings where personalize conditioning is desired. Historical

buildings where duct install is difficult or expensive.

Summer peak utilities can benefit - off-peak winter load that can

improve capital utilization and ROI. Decide to support based on local

rates, reserve margins, regulatory environment & other factors

Demand savings: Marginal, mostly part-load energy savings and

savings through ability to simultaneously heat/cool.

DR friendly

Page 48: What is Commissioning? - Mechanical & Electrical Design ...

Barriers To Adoption

May take 10-20 years to achieve any significant market penetration

after a technology is introduced into the market.1

Higher equipment costs compared to other, less efficient, technologies.

New technologies do not achieve market penetration unless SPB < 2

years. 1

Installation-specific design and difficulty evaluating the suitability of

individual installation sites.

Lack of knowledge base in design, operation, servicing and

maintenance and ownership costs (Education and Research).

Perception and natural resistance to change.

Performance uncertainties.

Manufacturer support and spare parts availability.

1Tiax, LLC – “Energy Consumption Characteristics of Commercial Buildings” (2002)

Page 49: What is Commissioning? - Mechanical & Electrical Design ...

Mapleleaf Orthopedics

8,000 SF medical office, completed Dec 2007

Southern Colorado’s 1st

LEED Building –LEED 2.2 Gold

CRES award winnerwww.cres.org

Page 50: What is Commissioning? - Mechanical & Electrical Design ...

Mapleleaf Orthopedics

30kW PV System meets 90%+ of energy

needs

Ground source heat

pumps (GSHP) 350%+ heating efficiency

23 EER cooling

Energy recovery

ventilator (ERV) reduces ventilation load by

75%

90% of spaces are daylit,

Dimming and occupancy

based lighting controls

ERV

GSHP

Lighting

Page 51: What is Commissioning? - Mechanical & Electrical Design ...

Mapleleaf Orthopedics –Performance Metrics

Source: EIA CBECS 2003: Table C.12 Consumption and Gross Energy Intensity by Year Constructed for Sum of Major Fuels for Non-Mall Buildings, 2003

Period March 2008 - August 2008 Extrapolated

kWh Used/Year 51,360

kWh Produced/Year 47,854

Net kWh Used/Year 3,506

Energy Use Intensity (Btu/Square Foot/Year) 16.5

CBECS: Office US 1990-2003* 88.0

CBECS: West Mountain Region 1990-2003* 81.2

Mapleleaf Orthopedics Performs 80% Better Than a Typical Building

$/Year $ 5,187

$/SF/Yr $ 0.65

Page 52: What is Commissioning? - Mechanical & Electrical Design ...

Resources

Building Commissioning Association

http://www.bcxa.org/

CA Commissioning Collaborative

http://www.cacx.org/

Green California

http://www.green.ca.gov/CommissioningGuidelines/default.htm

Database of State Incentives for Renewables/Efficiency

http://www.dsireusa.org

Procedural Standards for Retro-Commissioning of Existing Buildings

http://www.nebb.org

Page 53: What is Commissioning? - Mechanical & Electrical Design ...

Thank You

Questions?

Peter D’Antonio, PCD Engineering

303-678-1108 x707, [email protected]

Page 54: What is Commissioning? - Mechanical & Electrical Design ...

Net Zero Energy

Yet, how realistic is this vision?

How close do NZEBs come to realizing their design goals?

How much does it cost to design and build a net zero energy building?

Page 55: What is Commissioning? - Mechanical & Electrical Design ...

Getting Started

Energy Independence and Security Act of 2007 (EISA 2007)

Goal of net zero energy for all new commercial buildings by 2030

Specifies a zero-energy target for 50% of U.S. commercial buildings by 2040

Net zero for all U.S. commercial buildings by 2050

ASHRAE Vision 2020 report (ASHRAE 2008) sets out

requirements for developing the tools by 2020

The AIA 2030 Challenge (AIA 2009) calls for

incrementally reducing energy use, starting with a 50%

reduction over existing buildings’ energy use and

increasing savings up to 2030

Page 56: What is Commissioning? - Mechanical & Electrical Design ...

Getting There (Demand – Supply)

Build Tight…Ventilate Right

Daylighting

Insulation 10/20/40/60

Passive solar heating / control gain

High-efficiency HVAC equipment

Energy reuse

Natural ventilation / ‘Free’ cooling

Evaporative cooling

Ground-source heat pumps

Ocean water cooling

Page 57: What is Commissioning? - Mechanical & Electrical Design ...

ZEB Database

9 projects

<20,000 SF

1 or 2 story commercial

http://zeb.buildinggreen.com/

High performance buildings database

Page 58: What is Commissioning? - Mechanical & Electrical Design ...

Movement Climbing Gym

Carbon Neutral

Daylighting

Air source heat pumps

Evaporative cooling

Solar Thermal

Solar PV

Page 59: What is Commissioning? - Mechanical & Electrical Design ...

DHA

LEED-H Platinum

Building 50%+ better than code

LPD 25% better than code, advanced lighting controls

PV handles 22% of electric usage

GSHP, Heat Recovery

Page 60: What is Commissioning? - Mechanical & Electrical Design ...

Hyland Village Community

Get informed about RCx

Identify contractors/consultants

Identify facilities / benchmark

Determine what local utility and government incentives are available

Have a budget

Page 61: What is Commissioning? - Mechanical & Electrical Design ...

Defining Net Zero Energy

Zero net site energy useIn this type of ZNE, the amount of energy provided by on-site renewable energy sources is equal to the amount of energy used by the building. In the United States, “zero net energy building” generally refers to this type of building.Zero net source energy useThis ZNE generates the same amount of energy as is used, including the energy used to transport the energy to the building. This type accounts for losses during electricity transmission. These ZNEs must generate more electricity than zero net site energy buildings.Net zero energy emissionsOutside the United States and Canada, a ZEB is generally