Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant...
Transcript of Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant...
![Page 1: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/1.jpg)
Westside Treatment Plant Update
May 14, 2018 Vancouver City Council Workshop
Dan Swensen, Engineering and Construction Services Manager
Frank Dick, Senior Civil Engineer
![Page 2: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/2.jpg)
• Overview of Westside Wastewater Treatment Plant • Recap of events from Fall 2017 and progress since • Regulatory response to events • Influent Pumps Bypass Project • Other related Capital Improvement Projects (CIP) in process • Informational presentation – No action being requested
Presentation Overview
Westside Treatment Plant Update - 2
![Page 3: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/3.jpg)
• Absolutely must work 24 / 7 / 365 • Treats 10 million gallons per day on average – 7000 GPM (gallons per minute)
• Westside handles the solids removed from the City’s two wastewater plants • Treatment theory is straight forward – Complexity comes from the high
volume required through these facilities and the need for process reliability. • Treatment relies heavily on electricity to move large amounts of water
through the treatment process.
Overview – Westside Treatment Plant
Westside Treatment Plant Update - 3
![Page 4: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/4.jpg)
Five steps of treatment • Screening • Primary clarification • Biological treatment • Secondary clarification • Disinfection
Overview – Westside Treatment Plant continued
Westside Treatment Plant Update - 4
![Page 5: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/5.jpg)
Screening
Westside Treatment Plant Update - 5
![Page 6: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/6.jpg)
Primary Clarifiers
Westside Treatment Plant Update - 6
![Page 7: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/7.jpg)
Biological Treatment
Westside Treatment Plant Update - 7
![Page 8: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/8.jpg)
Secondary Clarifiers
Westside Treatment Plant Update - 8
![Page 9: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/9.jpg)
Ultraviolet Light Disinfection
Westside Treatment Plant Update - 9
![Page 10: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/10.jpg)
• September 30 event – Caused initially by a power interruption • October 25 event – During routine calibration of sensors • Causes of these two events were unrelated. • Steps taken since these events occurred
• Immediate actions • Some steps involve capital improvement projects
Events of Fall 2017
Westside Treatment Plant Update - 10
![Page 11: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/11.jpg)
• Our regulator is Washington Department of Ecology (Ecology). • With our complete cooperation, Ecology is investigating. • To date: Waiting to hear back. No results yet communicated to
the City.
Regulatory Response
Westside Treatment Plant Update - 11
![Page 12: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/12.jpg)
• “Bypass” is the ability to use an different route from influent control to treatment processes; bypassing influent pumps in the case of a power failure.
• Vulnerability was highlighted during operator contract procurement process. • Operator’s financial assistance was negotiated as part of the City contract. • Project design is moving toward 50 percent. • Creates an emergency pumping system independent of electric utility.
Bypass Project - Estimated $2 million
Westside Treatment Plant Update - 12
![Page 13: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/13.jpg)
![Page 14: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/14.jpg)
![Page 15: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/15.jpg)
![Page 16: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/16.jpg)
• Modernizing SCADA (System Control and Data Acquisition) - $12.5 M
• Electrical System Overhaul - $ 10 M (pre-design estimate) • Supply into the plant • Distribution throughout the plant • Emergency Switch Gear
Other Related Capital Projects
Westside Treatment Plant Update - 16
![Page 17: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/17.jpg)
• Vancouver and CH2M take environmental protection and public trust in our wastewater treatment operations very seriously.
• Vancouver’s wastewater treatment processes function reliably to treat wastewater effectively.
• Vancouver’s treatment processes are highly regulated by the Washington State Department of Ecology.
• Vancouver’s two treatment plants are professionally run by a dedicated team of professional operators.
Takeaways
Westside Treatment Plant Update - 17
![Page 18: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/18.jpg)
• Our experience through these events highlights a much more engaged partnership with our operator.
• CH2M has demonstrated a high level of transparency within their operations.
• Events demonstrate the need for ongoing capital investment and reinvestment in our infrastructure.
Takeaways continued
Westside Treatment Plant Update - 18
![Page 19: Westside Treatment Plant Update - Vancouver, Washington · 2018-05-10 · Westside Treatment Plant Update - 17 • Our experience through these events highlights a much more engaged](https://reader033.fdocuments.net/reader033/viewer/2022050310/5f71f388678a7560c45a6515/html5/thumbnails/19.jpg)
Questions and Discussion
Dan Swensen, Engineering/Construction Services Manager (360)487-7750
Frank Dick, Senior Civil Engineer (360)487-7179
Westside Treatment Plant Update - 19