Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex...

53

Transcript of Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex...

Page 1: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced
Page 2: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

2

Wessex Water’s Grid - overview

• Wessex Water’s largest ever construction project• Valued at over £220M• Commenced in 2010, due to complete in 2017• Long term strategic vision to address existing and

potential water supply and customer issues:• Security of supply and resilience• Reduction in abstraction licence• Supply demand balance• Quality issues• Presentation not focussed on modelling but Project

contains all the elements used in modelling

Page 3: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

3

Presentation structure

• Development of the concept– Strategic objectives– What do customers want?– Why do we need a grid?– Is it the best solution?– How catchment management fits in

• Design & construction– Team structure– Project objectives & Scope of works– Environmental constraints– Concept development– Programme

Page 4: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

4

Strategic objectives

• To address customer priorities• To align investments with our strategic direction statement• To resolve three key issues:

– Meeting demand for water over next 25 years– Improving security of supply– Maintaining drinking water quality

Page 5: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

5

What do customers want?

Willingness to pay for improvements

0.0

0.2

0.4

0.6

0.8

1.0

1.2

1.4

1.6

1.8

2.0

Leakagereduction

Security ofsupply

Reducing

greenhousegas em

issions

Drinking w

aterquality

Taking water

from rivers

Internal flooding

River w

aterquality

Beaches &

bathing waters

External

flooding

Pollution

incidents torivers

£ pa

for 1

0% c

hang

e

Indicative cost benefit ratios

0

0.5

1

1.5

2

Leakagereduction

Security ofsupply

Reducing

greenhousegas em

issions

Drinking w

aterquality

Taking water

from rivers

Internalflooding

River w

aterquality

Beaches &

bathing waters

External

flooding

Pollution

incidents torivers

• Our research shows that customers want us to ‘get the basics right’ and deliver our services in a sustainable way

• Improvements in security of supply and drinking water quality ranked very highly in the detailed willingness to pay surveys

Page 6: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

6

Wessex Water supply area

Page 7: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

7

• Why do we need a grid?– Standalone sources (21%)– 23.5 Ml/d of low flow reduction (4%)– 43 Ml/d of high nitrate sources (8%)– Growing peak demand

Page 8: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

8

This couldn’t happen to us?

Page 9: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

9

Stand alone sources

B R

E L

Bristol

BathChippenham

Salisbury

Bournemouth

Poole

Dorchester

Taunton

Bridgwater

Yeovil

Existing network

Stand alone sources

LEGEND

Page 10: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

10

Low flows reductions

R. Wylye

R. Avon

-5 Ml/d -6 Ml/d -1.5 Ml/d

-11 Ml/d

-23.5 Ml/d

Low Flow licence reductions

Brixton Deverill Codford

Newton Toney

Clarendon

R. Wylye

R. Avon

-5 Ml/d -6 Ml/d -1.5 Ml/d

-11 Ml/d

-23.5 Ml/d

Low Flow licence reductions

-5 Ml/d -6 Ml/d -1.5 Ml/d

-11 Ml/d

-23.5 Ml/d

Low Flow licence reductions

Brixton Deverill Codford

Newton Toney

Clarendon

Page 11: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

11

Deteriorating raw water - nitrates

Fonthill Bishop Nitrate Trend

0

2

4

6

8

10

12

14

1985

1986

1987

1988

1989

1990

1991

1992

1993

1994

1995

1996

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

Nitr

ate

as m

g/l a

s N

Page 12: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

12

At risk nitrate sources

Existing network

Sources at risk of exceeding nitrate limits

LEGEND

B R

E L

Bristol

BathChippenham

Salisbury

Bournemouth

Poole

Dorchester

Taunton

Bridgwater

Yeovil

Page 13: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

13

Increasing demand

300

350

400

450

500

550

600

1980 1985 1990 1995 2000 2005 2010 2015 2020 2025 2030 2035

Dis

trib

utio

n in

put (

Ml/d

)

Normal year demand forecast Dry year demand forecastPeak week demand forecast Weekly historic demandAnnual average demand Available resources

Page 14: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

14

Presentation structure

• Development of the concept– Strategic objectives– What do customers want?– Why do we need a grid?– Is it the best solution?– How catchment management fits in

• Design & construction– Team structure– Project objectives & Scope of works– Environmental constraints– Concept development– Programme

Page 15: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

15

Strategic options

Issue Plan A Holistic solution

Plan BIndividual solutions

Meeting demand and low flows

Grid New water resource developments

Drinking water quality

Grid & catchment management

Additional water treatment plants

Security of supply Grid Local network improvements

Page 16: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

16

Costs and benefits

Plan A Holistic solution

Plan BIndividual solutions

Net benefits (present value) £m

162 - 52

Cost beneficial? Yes NoOperating cost £m pa 2.0 3.1

Operational carbon emissions C02e thousand tonnes pa

4.4 6.1

Security of supply – number of consumers no longer at risk of supply restrictions

150,000 35,000

Page 17: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

17

How the grid addresses the key issuesLocal links omitted for clarity

Existing networkProposed pipelinesSources at risk of exceeding nitrate limitsStand alone sourcesLow flow sourceArea of supply demand deficit

LEGEND

B R

E L

Bristol

BathChippenham

Salisbury

Bournemouth

Poole

Dorchester

Taunton

Bridgwater

Yeovil

Page 18: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

18

How the grid addresses the key issuesLocal links shown

Existing networkProposed pipelinesSources at risk of exceeding nitrate limitsStand alone sourcesLow flow sourceArea of supply demand deficit

LEGEND

B R

E L

Bristol

BathChippenham

Salisbury

Bournemouth

Poole

Dorchester

Taunton

Bridgwater

Yeovil

.MAIN

Page 19: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

19

The projects will deliver multiple outputs

• Ofwat– Final determination

• Environment Agency – National Environment plan

• Drinking Water Inspectorate – Undertakings

Page 20: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

20

Key dates - 8 year programme with interim milestones

Activity Date

Project Launch 1 April 2010Blashford WTW DWI undertaking March 2014Nitrate schemes DWI undertakings March 2015Elimination of stand alone sources March 2015Completion of integrated grid allowing low flows licences to be revoked

March 2018Commissioning in 2017

Page 21: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

21

How catchment management fits in

Fonthill Bishop Nitrate Trend

0

2

4

6

8

10

12

14

1985

1986

1987

1988

1989

1990

1991

1992

1993

1994

1995

1996

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

Nitr

ate

as m

g/l a

s N

Page 22: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

22

Catchment management activity

• Reduce risk whilst grid is implemented• Ensure long term supply of compliant

water & optimise operating costs• Advocacy• Nitrates

– Continue 4 AMP4 sites– 8 further sites that may fail in AMP5

• Pesticides– Friar Waddon

• Farmer has agreed to move pesticide activity to another site

Page 23: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

23

Presentation structure

• Development of the concept– Strategic objectives– What do customers want?– Why do we need a grid?– Is it the best solution?– How catchment management fits in

• Design & construction– Team structure– Project objectives & Scope of works– Environmental constraints– Concept development– Programme

Page 24: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

2424

Project Team Structure

Wessex Water Services Ltd

Wessex Engineering and Construction Services

Atkins Ltd

Designer

Trant ConstructionCivil & MEICA

Contractor

May GurneyCivil & MEICA

Contractor

Work stream

Page 25: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

25

Programme Manager& CDMc

TRANT MAY GURNEY ATKINSProject

ManagementTeam

CommercialManagerPlannerDesign

Co-ordinators

GroupCommercial Manager

QuantitySurveyors Design PMs

Environmental ServicesEstates

ICAEstimating

Operations Support Team

Network Experts

Grid Workstream

Page 26: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

26

Project objectives

• Improve security of supply

• Provision for reduction in abstraction licences

• Provision for deteriorating raw water quality

• Meet future water supply demand

Page 27: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

27

Concept Development

• Original concept – called GC1• Revised concept – GC2• Updated GC2 November 2012

Page 28: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

28

Grid Concept 1Local links shown

Blandford

Shaftesbury

Existing networkProposed pipelinesSources at risk of exceeding nitrate limitsStand alone sourcesLow flow source

LEGEND

B R

E L

Bristol

BathChippenham

Salisbury

Bournemouth

Poole

Dorchester

Taunton

Bridgwater

Yeovil

.MAIN

Grid Concept 1

Grid Concept 1As PR09 business plan, new link north from Blashford with alternative route around Salisbury

Page 29: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

29

Grid Concept 2Local links shown

Blandford

Existing networkProposed pipelinesSources at risk of exceeding nitrate limitsStand alone sourcesLow flow source

LEGEND

B R

E L

Bristol

BathChippenham

Salisbury

Bournemouth

Poole

Dorchester

Taunton

Bridgwater

Yeovil

.MAIN

Grid Concept 2

Grid Concept 2Synergies with other schemes along Stour valley & new link north to Whitesheets SR

Shaftesbury

Page 30: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

30

B R

E L

Bristol

BathChippenham

Salisbury

Bournemouth

Poole

Dorchester

Taunton

Bridgwater

Yeovil

.SPINE

Grid Concept 2Local links shown + updated routes

Existing networkProposed pipelineSource at risk of exceeding nitrate limitsStand alone sourceLow flow source

LEGEND BlandfordForum

Shaftesbury

Page 31: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

31

Programme of works

• More than 25 individual projects

• Value ranging from £ 0.5 – 30M

• 150km of new Pipelines

• 30 new / uprated Pumping Stations

• 11 new Service Reservoirs

Page 32: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

32

Corfe Mullen to Salisbury transfer scheme – 65km

32

Page 33: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

33

Environmental constraints

7 AONBs2 National Parks539 Sites of special scientific interest6819 County Wildlife sites4500 Scheduled Monuments41748 Listed Buildings36000+ Records of Protected Species3 World Heritage Sites1 Heritage Coastline

Page 34: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

34

Environmental Factors

34

Page 35: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

35

Environmental Factors

35

Page 36: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

36

Typical Pipeline Easement

36

Page 37: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

37

Considerate Construction and waste management

• Spoil to be re-used where possible as trench backfill material

• Use excess trench spoil at other sites for service reservoir landscaping etc

• Trenchless technology to be used to cross ;– Rivers and watercourses– Railways– Trunk roads and A roads

Page 38: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

38

Considerate Construction

• Traffic management plans to reduce impact of construction traffic on the local road systems

• Minimise construction traffic on roads by using pipeline easements instead

• Minimise volume of construction traffic by avoiding double handling, location of compounds etc

• Minimise construction durations through effective planning

Page 39: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

39

New Infrastructure

Page 40: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

40

Booster Pumping Stations

40

Page 41: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

41

Considerate Construction

41

Page 42: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

42

Considerate Construction

42

Page 43: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

43

Aerial photo’s (from Wessex Drone)

Page 44: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

44

Page 45: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

45

Page 46: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

46

Page 47: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

47

Page 48: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

48

Ground photo’s

Page 49: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

49

Page 50: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

50

Page 51: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

51

Delivery Programme

AMP 5 AMP 6

2010 2011 2012 2013 2014 2015 2016 2017

Options

Outline design

Detailed design

Construction

Page 52: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

52

Water supply grid website(www.wessexwater.co.uk/grid)

Page 53: Wessex Water’s Grid - overview · 04/02/2017  · 2 Wessex Water’s Grid - overview • Wessex Water’s largest ever construction project • Valued at over £220M • Commenced

Conclusion

– Wessex Water’s largest and most complex project

– The only Water Industry project spanning two AMPs

– Aligns with 25 year vision

– Delivers customer priorities

53