Welding Quality and Inspection

download Welding Quality and Inspection

of 16

Transcript of Welding Quality and Inspection

  • 8/10/2019 Welding Quality and Inspection

    1/16

    By Duane K. Miller, Sc.D., P.E.

    The James F. Lincoln Arc Welding Foundation

  • 8/10/2019 Welding Quality and Inspection

    2/16

    The serviceability of a product or structure utilizing the type of information presentedherein is, and must be, the sole responsibility of the builder/user. Many variables

    beyond the control of The James F. Lincoln Arc Welding Foundation or The Lincoln

    Electric Company affect the results obtained in applying this type of information.These variables include, but are not limited to, welding procedure, plate chemistry

    and temperature, weldment design, fabrication methods, and service requirements.

    This guide makes extensive reference to the AWS D1.1 Structural Welding Code-Steel,

    but it is not intended to be a comprehensive review of all code requirements, nor is itintended to be a substitution for the D1.1 code. Users of this guide are encouraged to

    obtain a copy of the latest edition of the D1.1 code from the American Welding Society,550 N.W. LeJeune Road, Miami, Florida 33126. (800) 443-9353.

    This information has been provided by

    The James F. Lincoln Arc Welding Foundationto assist the general welding industry.

  • 8/10/2019 Welding Quality and Inspection

    3/16

    By Duane K. Miller, Sc.D., P.E.Manager, Engineering ServicesThe Lincoln Electric Company

    Cleveland, Ohio

    In a mature industry such as weldedsteel construction, it is reasonable to

    believe that the role of the various indi-viduals involved with a given project

    will be well understood and welldefined. Unfortunately, experienceindicates that there is a great deal of

    confusion in this area. Perhaps this isa reflection of misperceptions about

    the technology itself. Too many other-wise knowledgeable people still regard

    welding as a black art, rather than ascience that can be understood andcontrolled. The level of understanding

    among many Engineers regarding thisimportant construction process is limit-

    ed. Regardless of the reason,Engineers frequently do not perform

    their professional responsibilities asthey relate to welding. Too often, they

    delegate this authority to Inspectors.

    Over-zealous Inspectors frequentlyoverstep their role, making judgment

    calls that should be the purview of theEngineer. Furthermore, Fabricators do

    not always take full advantage ofcode-provided latitude for the resolu-tion of many problems. In the end,

    Owners often pay too much for struc-tures that have been plagued by

    delays, unnecessary repairs, andextraneous activities that add little or

    no value to the project.

    Many problems result when the proper

    roles of the various individuals on theproject are not understood. The most

    serious infractions occur when peopleaccept responsibility for areas in which

    they have no authority or qualifica-tions. This can result in disaster, but

    fortunately such cases are rare. M

    frequently, key individuals fail to caout all of their appropriate respons

    ties, causing costly delays.

    With the design-build approach commonly used in Europe, communica

    is enhanced because one organizahas financial responsibility for theentire project. In the U.S.A., howev

    the common practice that separatethe design phase from the construc

    tion phase requires a clear under-standing of the responsibilities of th

    various parties. The roles are definin codes, specifications, and contradocuments. The AWS D1.1-98

    Structural Welding Code - Steel,defines such roles as they relate towelded construction. In addition to

    restating sections of the code itselfthis paper will outline a philosophy

    is conducive to increased cooperatand communication, and will foster

    creation of higher quality productswhile minimizing fabrication costs.

    This three-part series on ensuring weld quality in structural applicationscovers the following:

    Part I reexamines the roles of the Engineer, the Fabricator, and the

    Inspector, as they relate to welded construction. The proper roles aredefined, and misunderstandings corrected. First published in

    Welding Innovation, Vol. XIII, #2, 1996.

    Part II emphasizes the importance of effective visual inspection and itsvital role in achieving weld quality. First published in Welding Innovation,

    Vol. XIII, #3, 1996.

    Part III discusses alternate acceptance criteria and explains the Engineersresponsibility for invoking such criteria. First published in Welding

    Innovation, Vol. XIV, #1, 1997.

    Throughout the series, references have been updated to cite specificsections of the AWS D1.1-98 Structural Welding Code - Steel.

  • 8/10/2019 Welding Quality and Inspection

    4/16

    At the heart of the issue is the proper

    definition of the roles and the responsi-bilities of various individuals involved in

    welded fabrication. The following areaken from the AISC Code of StandardPractice and/or the AWS D1. 1-98

    Structural Welding Code - Steel:

    Owner:The owner of the proposed structure

    OR that individuals designated repre-sentatives, who may be the Architect,Engineer, General Contractor, Public

    Authority, or others.

    Architect/Engineer:The Owners designated representa-

    ive with the full responsibility for thedesign and integrity of the structure.

    General Contractor:The Owners designated representa-

    ive with the full responsibility for theconstruction of the structure.

    Fabricator:The party responsible for furnishing

    abricated structural steel.

    Erector:The party responsible for the erection

    of the structural steel.

    Verification Inspector:

    The duly designated person who actsfor, and on behalf of, the Owner or the

    Engineer in all inspection and qualitymatters within the scope of the con-

    tract documents. (In some codes, suchas AASHTO/AWS D1.5-96 BridgeWelding Code, this Inspector is known

    as the Q.A. Inspector, that is, theQuality Assurance Inspector.)

    Fabrication/Erection Inspector:

    The duly designated person who actsfor, and on behalf of, the Contractor inall inspection and quality matters with-

    in the scope of the contract docu-ments. (In D1.5, this Inspector is

    known as the Q.C. Inspector, that is,the Quality Control Inspector.)

    Inspector:When the term Inspector is used with-

    out further qualification, it appliesequally to both the Verification and

    Fabrication/Erection Inspector.

    For the purposes of this paper, com-ments directed toward the Fabricatorapply equally to the Erector. Since

    most or all of the welding will be per-formed by either the Fabricator or

    Erector, the General Contractor willnot be considered in this discussion.

    The term Engineer will be used in lieuof Architect/Engineer.

    The Engineer has the ultimate and fullresponsibility for the integrity of the

    structure. It is the Engineer who mustestablish the required quality level forall welded fabrications. This may be

    done by invoking a standard such as

    the D1.1 Code. It is imperative thatthe Engineer understand the require-ments, restrictions, and implications of

    the full code. The Engineer is respon-sible to ensure that the code provi-

    sions are adequate for the structure.Additional provisions may be requiredfor unique structures, and these

    requirements must be invoked incontract documents. The Engineer is

    responsible for determining and speci-fying the level of quality required. The

    Engineer is also responsible to ensure

    that the specified level of quality isdelivered by the Fabricator. The

    Engineer has a professional responsi-bility to the Owner to deliver the

    project in a timely fashion, and atan appropriate cost.

    To assist in the quality issues, theEngineer may employ the services of

    a Verification Inspector. Under D1.1,this is left up to the Engineers discre-

    tion. A Verification Inspector may beengaged either to duplicate the ser-

    vices of the Fabrication Inspector, orto supply spot checks. However, theEngineer may choose to rely solely

    upon the Fabrication Inspector toensure the necessary quality is

    achieved. Many factors enter into thisdecision, including:

    the complexity of the structure; the degree of redundancy involved;

    and

    the relative level of confidence theEngineer has in the Fabricator.

    The Fabricator is responsible for deliv-

    ering a quality product to the Engineer.While the Engineer must be responsi-ble to ensure the level of quality is

    achieved, it is ultimately theFabricators responsibility to produce a

    quality product. To this end, theFabricator will employ Fabrication

    Inspectors (Q.C. Inspectors) to monitorthe welding operations and inspect the

    Effective visual inspection requires that the Inspector be present when welding

    s being performed.

  • 8/10/2019 Welding Quality and Inspection

    5/16

    final product. Under a shop qualifica-tion program, it is required that the

    inspection functions be kept organiza-tionally separate from the manufactur-

    ing operations, in order to give theQ.C. Inspectors the necessary authori-ty to carry out their responsibilities.

    It is important to understand that sincethe Fabricator does all the welding,only the Fabricator can produce quali-

    ty welds. Inspectors cannot improvethe quality of the product that has

    been produced. The Inspector simplymeasures the level of quality achieved,and accepts those products that are

    within conformance.

    Inspectors are responsible to ascertainthat all fabrication and erection by

    welding is performed in accordance

    with the requirements of the contractdocuments. When contract docu-

    ments invoke certain specifications orcodes, the Inspector must ensure that

    all such requirements are met. It is

    important to note that the emphasis is

    placed on acceptance and compli-ance to the specification. A prevail-ingbut mistakenimpression of

    Inspectors is that their primary respon-sibility is to reject out-of-compliance

    work. This is more than an issue ofsemantics. The ability to reject a par-

    ticular weldment is ultimately theEngineers responsibility. TheInspectors responsibility is to accept

    materials that are in compliance.

    While this approach may seem new orrevolutionary to some people, the

    author believes that it is the primaryphilosophy presented in codes. And,to eliminate any dispute or potential

    misrepresentation of code intentions, itis the authors opinion that this should

    be the philosophy of the code evenwhen it is not, because it will result in

    optimum value to the Owner.

    The belief that the primary function of

    Inspectors is acceptance of productsthat are within established criteria isgenerally supported by the D1.1 Code,

    although deviation from this general

    philosophy is sometimes expressed inthe code. In the authors opinion, thisis more a reflection of poor wording on

    the part of the code writers than a rep-resentation of overall philosophy. The

    examples that conflict with the generaltrend will be cited, and proposedrefinements presented.

    The following references with appropri-

    ately highlighted portions support thecontention presented above:

    Fabrication/erection ... inspection

    and tests shall be performed ... toensure that materials and workman-

    ship meet the requirements of thecontract documents (6.1.2.1).

    The Inspector shall ascertain thatall fabrication and erection by weld-

    ing is performed in accordance withthe requirements of the contractdocuments (6.1.5).

    The Inspector shall make certainthat only materials conforming to

    the requirements of the code areused (6.2).

    The Inspector shall verify that allWPSs have been approved by theEngineer in conformance with 4.1.1

    (6.3.1). The Inspector shall inspect the weld-

    ing equipment to be used for thework to make certain that it con-

    forms to the requirements of 5.11(6.3.2).

    The Inspector shall permit welding

    to be performed only by welders ...who are qualified ... or shall make

    certain that each welder ... has pre-viously demonstrated such qualifica-

    tion under other acceptablesupervision and approved by theEngineer (6.4.1).

    The Inspector shall make certainthat the sizes, length, and location of

    welds conform to the requirementsof this code... (6.5.1).

    The Inspector shall examine thework to make certain that it meets

    the requirements of this code.

    Other acceptance criteria, differefrom those thus provided in the

    code, may be used when approby the Engineer [Note: the

    Engineer has the authority to utilalternate acceptance criteria](6.5.5).

    Table 6.1 lists Visual Inspection

    Acceptance Criteria.

    The foregoing passages make it cl

    that the emphasis is on acceptingproducts within compliance, and m

    ing certain that proper proceduresare followed. It can be argued thatwhen the Inspector refuses to acce

    a part, it is equivalent to rejecting tpart. The code writers, however, h

    not chosen to use this language.Ultimately, all projects must be acc

    ed. This is the role of the Inspecto

    In two notable examples, the D1.1-

    Code deviates from this general prple. The provisions of Section 6.1.

    state that, Inspectors responsible facceptance or rejection of material

    and workmanship shall be qualifiedThis paragraph fits under the headInspector Qualification Requireme

    Clearly, the emphasis is not on thefunction of the Inspector, but rather

    the lnspectors qualification. Had tcode writers deleted the words or

    rejection, the provision would havebeen consistent with the rest of thecode. In the authors opinion, this

    wording is unfortunate, since it is nin the same spirit as the rest of the

    code. The second deviation from toverall philosophy of acceptance

    occurs in Section 6.6 Obligations othe Contractor. The provisions of 6require that The contractor shall c

    ply with all requests of the Inspectoto correct deficiencies in materials

    workmanship as provided in the cotract documents. Notice, however,

    this provision is under the heading the Obligations of the Contractor.

    Even though these two referencesdeviate slightly from the general

    concept of acceptance, they do nocontradict the overall philosophy.

    Moreover, because of their locationthey do not present a strong case fan alternate approach.

  • 8/10/2019 Welding Quality and Inspection

    6/16

    A modification to these provisions of6.1.4.1 that would delete the words or

    ejection would clarify the situation.Also, in Section 6.6.2, the following

    phrase would be a proposed improve-ment: The Contractor shall complywith all requests of the Engineer to

    correct deficiencies in materials and

    workmanship as provided in the con-ract documents. This language wouldeaffirm the proper role of the

    Engineer. However, it is obvious thator minor nonconformances, the

    Engineer should not be consulted on aoutine basis. Once again, this falls

    within the discretion of the Contractor.

    f the Inspector was being granted theull authority to direct all the activities

    of the Contractor, this would certainlyhave been included under a different

    heading.

    t is interesting to note that the equiva-

    ent provision in the D1.5-96 BridgeWelding Codechanges the word from

    he all-inclusive Inspectors used inD1.1 to QA Inspectors. While the

    D1.1 provisions apply equally to bothabrication and verification inspection,he D1.5 words are exclusively applied

    o QA (verification) inspection. Thiswording is probably more correct, but

    since verification inspection is optionalunder D1.1, alternate words were

    selected.

    Abuses of, and deviations from, the

    philosophy outlined here are wide-spread. They can be perpetrated by

    Engineers, Inspectors or Fabricators.For instance, the Engineer may dele-gate engineering authority to the

    nspector. The rationale for this typeof decision appears to be fairly

    straightforward: the Engineer may notbe familiar with the intricacies of the

    code and/or fabrication process, andherefore may empower the Inspectoro make decisions on his/her behalf.

    On the surface, this appears to be avery logical approach, particularly

    when the Inspector is highly qualified,perhaps an Engineer by training. On

    he other hand, another Inspector maynot have the background necessary to

    make these types of decisions.Moreover, rarely will the Inspector

    have the benefit of understanding theoverall structural implications of vari-

    ous decisions. For example, a filletweld has been sized based upon theminimum prequalified fillet weld sizes.

    This fact obviously should enter into

    the considerations regarding theacceptability of a slightly undersizedfillet weld. In the absence of this

    design data, the Inspector does nothave the necessary information to

    make the most responsible decision.

    The descriptions assigned to various

    Inspectors by Fabricators generally fitinto one of two categories: First, there

    are the Inspectors who are reason-able, practical, someone we can

    work with, etc. The second category

    would cover those who are a realstickler for details, see everything as

    black or white, or cut us no slack, etc.

    The implication is that the first groupof Inspectors utilize some judgment

    call when making their decision. Theycan negotiate, bargain, and give trade-offs. These are hardly the terms asso-

    ciated with the engineering profession.Fabricators may love this type of

    Inspector, but are the Engineers oblig-ations to the Owner fulfilled if such an

    Inspector compromises quality in acritical area?

    The second type of Inspector seeseverything as falling into one of two

    categories: acceptable or unaccept-able. This individual knows every code

    provision and requires strict adher-ence to these requirements. On thesurface, this may seem to be the opti-

    mum type of Inspector, from theOwners point of view. However, two

    things must be considered: First, anEngineers full dependence on this

    type of Inspector eliminates theEngineers opportunities to utilizecode-permitted engineering evalua-

    tions of situations that deviate from thecode requirements. Secondly, this

    approach may unnecessarily increasecosts, cause delays, and necessitate

    weld repairs that can actually impairthe quality of the overall project.

    These implications will be developedand discussed in detail in Part III of

    this series, Alternate AcceptanceCriteria.

    Inspectors are not immune from errorseither. Some are all too eager to

    assume responsibility and authority

    beyond their role qualifications. SomeInspectors are fond of pointing outtheir interpretation of code provi-

    sions. Codes are meant to be fol-lowed, not interpreted. The term

    interpretation has a very specificmeaning when applied to codes. Aninterpretation, or more properly, an

    official interpretation, is the decisionrendered by the code-writing body that

    may, in the extreme, constitute a newcode requirement. Only the code-writ-

    ing body has the authority to issue an

    interpretation.

    Inspectors should see that the code isfollowed, and report nonconformance

    to the Engineer. When the coderequires that the Engineer be notified

    prior to some action, it is not theInspector who should be notified.Inspectors are not in the business of

    deciding new acceptance criteria.That is the Engineers responsibility.

    Inspectors should not be determiningwhether code provisions are adequate

    or overly restrictive. They are chargedwith following the established codeprovisions.

    Many Inspectors feel they are the

    ultimate authority on the project. It isimportant to note that the Engineer

    has the authority to review theInspectors credentials. Although theFabrication Inspector is paid by the

    Fabricator, that lnspectors credentialsand capabilities are subject to

    approval by the Engineer. TheEngineer directly employs the

    Verification Inspector, who obviouslyis responsible to the Engineer.

    Fabricators also make errors. Somecompanies will attempt to hide prob-

    lems from the Inspector. More blatantabuses include offering bribes to

    Inspectors. Such activities are illegal,immoral, and unprofessional. The

  • 8/10/2019 Welding Quality and Inspection

    7/16

    entire industry is hurt when a smallminority thus abuses its responsibility.

    The Fabricator may also err by failingto utilize provisions within the code

    which permit deviation from standardacceptance criteria. Fabricators mustknow the entire code and understand

    what is mandatory, what is permitted,

    and what can be changed. Withoutreading the complete code,Fabricators will frequently apply one

    set of provisions in a universal fashion,believing it to be all-encompassing.

    Unnecessary increases in fabricationcosts usually result. It is imperativethat the whole code be understood in

    its entirety in order to meet the qualityrequirements at a reasonable cost.

    Engineers are responsible for thor-

    oughly understanding the code, the

    fabrication processes, and the properroles of the Inspector and the

    Fabricator. If the Engineer of Recordis not familiar with the intricacies of the

    welding processes or those of weldingcodes, it is imperative to consult a

    Welding Engineer, another profession-al, separate and distinct from the

    Inspector. The Inspector must under-stand how to enforce the application of

    the code, accept work that conformsto code requirements, and report tothe Fabricator deviations from these

    requirements. The Inspector mustknow the whole code, and apply it to

    the situation, not interpret it.

    The Fabricator must know the entirecode, accept the lnspectors report ofdeficient work, and either repair defi-

    ciencies or propose an alternative tothe Engineer. With the report of non-

    conformance, the Engineer can applyengineering judgment to resolve the

    problem. This approach leaves theultimate responsibility for the project

    with the Engineer of Record, where itmust remain. The Inspector has not

    exercised engineering judgment, theFabricator has gained all the latitude

    necessary, and ultimately, the result isa project of the required quality at areasonable cost.

    To illustrate the ideal application,

    consider the following situation which(unfortunately) is true. Details have

    been changed slightly to protect boththe innocent and the guilty!

    Field erection of a steel frame buildinghad progressed several stories when

    the Inspector reported to the Engineerthat no preheat was being employed

    for the welding procedures. The

    Fabricator claimed he did not knowpreheat was required. The Inspector

    then announced that the buildingwould have to be systematically disas-

    sembled and re-erected. TheEngineer did not know what to think

    but was wise enough to consult aWelding Engineer for advice. TheEngineer was obviously concerned

    about the integrity of the structure, butwas also worried about the significant

    delays that would be incurred if thestructure was disassembled. The

    tremendous cost could have resultedin bankruptcy of the Fabricator/Erector. On every front, the project

    was a mess.

    Before a resolution of this project ispresented, a review of the mistakes

    made is appropriate. The Fabricator/Erector had selected to use weldingprocedures (or more correctly welding

    procedure specifications, usuallyabbreviated WPSs) that could be pre-

    qualified under the provisions of D1.1.These WPSs are exempt from the

    mechanical testing requirements thatapply to WPSs that are qualified bytest. Prequalification of WPSs, howev-

    er, does not eliminate the need for awritten WPS. During the creation of

    the WPS, the Fabricator would havebeen forced to evaluate the require-

    ments for preheat. However, the firsterror was that written WPSs were notemployed (3.6).

    The Inspector is responsible for thereview of all WPSs. An important

    of the Inspector is to make sure theWPSs are complete and followed.

    the WPS was never written, it obvioly could not have been approved.Therefore, erection welding should

    never have begun (6.3.1).

    Furthermore, the Engineer has theresponsibility to judge the suitability

    the prequalified joints to the application. The specific joint detail is defi

    in the WPS, but, once again, in theabsence of a written welding procedure, this obviously was not done (

    The structure certainly should not

    have progressed to the height of seeral stories before the discovery of

    oversight. The Inspector is respon

    ble to ensure proper procedures arutilized (6.5).

    While everyone bears some of the

    fault here, the Engineer did executhis responsibilities appropriately w

    the available alternatives were invegated. By consulting an expert in tfield, he was able to obtain a profe

    sional, unbiased opinion regarding implications and possible corrective

    actions. In this particular situation,minimum prequalified preheat leve

    would have been 150 degrees F.Construction had taken place durinthe summer when the ambient tem

    ature was typically 70 degrees F.

    Without question, the deviation in pheat requirements prohibited the

    Inspector from being able to accepthese welds, regardless of the finaquality. The Engineer did have the

    tude, however, to employ alternateacceptance criteria. The consultan

    pointed out that the preheat levelswere minimum requirements for pre

    qualified procedures. The code itsindicates that under some conditioof restraint, base metal compositio

    and levels of weld metal hydrogencontent, higher preheat levels wou

    be required. Moreover, the codeadmits that in some situations, low

    levels of preheat could be employe(3.5). WPSs that are qualified by te

  • 8/10/2019 Welding Quality and Inspection

    8/16

    under the provisions of Section 4 ofhe code do not mandate the prequali-

    ied minimum preheat temperatures.Rather, an alternate preheat level

    could be selected if the procedureswere qualified by test. Therefore, if aprocedure qualification test duplicating

    he conditions actually used were

    employed, and if the mechanicallyested specimens exhibited the ductili-y, strength, and soundness required

    by the code, a WPS could be qualifiedby a test that utilized a 70 degree F

    or ambient) preheat level. This wouldbe in complete compliance with thecode, except that normally, the proce-

    dure would have been qualified beforeabrication began.

    n addition to requiring a procedure

    qualification test, the Engineer was

    advised to employ extra measures ofnondestructive testing. The disconti-

    nuity of greatest concern is a weld

    crack. When adequate preheat levelsare not maintained, cracking is the

    most obvious expected discontinuity.Therefore, the nondestructive testing

    method with the greatest ability todetect cracks was employed, that is,ultrasonic inspection, which also lends

    itself well to field inspection. Spot

    inspections were recommended.Locations were selected based uponwork records reflecting which joints

    were likely to be welded on the coldestdays and times during the project.

    The welding procedure qualificationtest was successful. Ultrasonic

    inspection revealed no cracks on thejoints examined, which constituted

    approximately 25% of the total. Theproject was able to proceed, although

    preheat was mandated for subsequent

    fabrication. In spite of the problems,the situation was resolved with a mini-

    mum amount of cost and delay

    because in this case, the Engineerexercised his responsibilities.

    In many situations involving welding,Engineers simply do not have the

    background or experience necessary

    to perform all of the engineeringresponsibilities essential to the suc-cess of a given project. Therefore, it is

    incumbent upon the professionalEngineer to admit the limits of his or

    her knowledge and consult an expertin the field. While both Inspectors andFabricators have essential roles to

    play, the Engineer is responsible forthe structural integrity of the project.

    Therefore, the Engineer must see to itthat all other essential individuals fulfill

    their functions toward that end, no less

    and no more.

    Visual inspection is the most powerfulool that can be employed to ensureweld quality. The more technologically

    sophisticated nondestructive process-es, such as ultrasonic or radiographic

    nspection, can only verify that thedesired quality is present once welding

    s complete. Effective visual inspectionexamines each step of the weldingprocess, well before the weld is com-

    pleted. According to A. M. Gresnight ofDelft University, the Netherlands, Most

    serious failures in performance are dueo gross error; e.g., wrong consum-

    ables or omission of preheat, and notminor non-compliances.

    Everyone involved in a welding projectcanand shouldparticipate in in-

    process visual inspection, includingthe welders, Inspectors, foremen, etc.Minor discontinuities can be detected

    and corrected during the fabricationprocess, precluding the need for more

    expensive and complicated repair afterthe fabrication is complete. In order

    to be effective, visual inspection musttake place prior to, during, and afterwelding. Obviously, visual inspection

    requires good eyesight and good light-ing. Frequently, good lighting is scarce

    in a fabrication shop or even in certainparts of a construction site, so a sim-

    ple flashlight can be a valuable aid tovisual inspection.

    To understand how visual inspectioncan be utilized to improve weld quality,

    consider the approach used in therestaurant industry. A perfectly good

    steak is delivered on a plate, accentedby appropriate side dishes and gar-

    nish. The customer applies a visualinspection to satisfy his/her desire fora high-quality meal. Dirty dishes,

    burned edges on the meat, and inap-propriate sizing of portions would

    detract from an image of quality. It isalso important to note that the steak is

    complete; that is, a test portion of thesteak has not been removed for exam-

  • 8/10/2019 Welding Quality and Inspection

    9/16

    ination in the kitchen. It is strange toeven consider the notion that a wedge

    of meat might be removed for inspec-tion or testing. The steak has not

    received either nondestructive ordestructive testing. Rather, theprocess of creating the dinner has

    been carefully controlled by regular

    visual inspections at each step in thepreparation.

    Examining the process in total, thedinner starts with meat that has been

    graded by a suitable governmentagency. The kitchen facility has beenapproved by the Board of Health. The

    chef has appropriate training and cre-dentials. The recipe has been taste-

    tested and time-proven. All theingredients involved with the meal are

    suitably controlled, with the proper

    amount of each added at the proper

    time. The temperature of the broiler,and the amount of time the beef will

    be cooked, are both carefully con-trolled and regularly verified. The fin-

    ished product is visually inspected bythe chef, the waiter, and finally by theconsumer. Without visual inspection,

    most people would be unable to detecta poorly prepared piece of meat

    before it is consumed. However, bythe application of visual inspection

    throughout the process, the desiredresults are achieved.

    The same approach can be used in

    welding because, like cooking, weldingis a process.The fabrication shop isroutinely inspected and approved by

    some outside agency such as theAISC Shop Certification Program.

    The steels employed are governedby agencies such as ASTM, and the

    Certificates of Conformance ensure

    product integrity. Welders are requiredto pass operator qualification tests to

    verify their ability. Like the chef, theyare trained to carry out specific opera-

    tions. In the welding industry, thewelding procedure specification (WPS)is like a recipe. In the WPS, specific

    welding parameters are set forth,

    including preheat and interpass tem-peratures, wire feed speeds, voltageused, travel speeds, etc. Finally, the

    completed welds are required to bevisually inspected. With the major

    exception of gas metal arc/short arctransfer, visually acceptable weldsroutinely exhibit the required quality

    for their application.

    Over the years, welding has beendescribed as both an art and a sci-

    ence. While it is both, there has been

    a disproportionate emphasis on the artof welding. Welding is a complex sci-

    ence involving the interaction of manydisciplines. Nevertheless, the welding

    process is subject to certain physicaland chemical laws that allow it to be

    controlled and the results predicted.

    The quality of a completed weld is pre-

    dictable, providing the input variablesare known. Unfortunately, input vari-

    ables (even critical input variables) areoften misunderstood, ignored, or

    uncontrolled, resulting in welds ofunpredictable quality. Variables maybe overlooked for several reasons.

    During procedure qualification testing,for example, it is essential that critical

    welding parameters be evaluated andidentified. During the qualification and

    testing of welders, the unique require-ments of the specific application mustbe communicated to them. When all

    input variables are properly identifiedand controlled, welds of the required

    quality will be consistently achieved.Effective visual inspection can ensure

    that significant variables are con-trolled, resulting in welds of therequired quality.

    Discontinuities in welds do not occur

    by mere chance. They are the result offailing to identify and control for one or

    more critical variables. (Authors note:

    In our formal training, many of ushave been taught the scientific

    method, a system by which onevariable is examined at a time.

    Experience demonstrates that vari-ables rarely exist in isolation. First,most applications, problems will be

    attributed to more than one variable

    Secondly, the interaction of multiplevariables is often overlooked. Themore complex, but much more accu

    rate methods associated with thedesign of experiments address the

    situations.) Even when critical variables are identified, they are frequeignored or not properly communica

    to the individuals involved.

    While visual inspection is a powerftool, its potency may be questioned

    because of past experience. For

    example, if a visual inspection is sopowerful, why are weld discontinuit

    and defects routinely found by nonstructive testing methods?

    One plausible explanation is that v

    al inspection is rarely properly per-formed. Welding is a process, and process must be observed through

    its application. If an Inspector arrivon the job site after the welds are

    complete, it is impossible to properapply visual inspection. Because t

    nondestructive testing methods evaate completed welds, Inspectors artrained to focus on finished produc

    Attention must be refocused on visly inspecting the process, not mere

    the finished result.

    Fillet weld sizes can be measured w

    gages. (Photo courtesy of G.A.L. Ga

  • 8/10/2019 Welding Quality and Inspection

    10/16

    To provide practical information abouthe requirements for conducting visualnspections, the American Welding

    Society has published a concise, 28-

    page document, AWS B1.11, entitledGuide for Visual Inspection of Welds.

    Consistent with the philosophy already

    presented in this series of articles,AWS B1.11 emphasizes the impor-

    ance of inspection prior to welding,during welding, and after welding.Practical suggestions, presented in a

    checklist format, are offered for eachphase.

    n Section 3.2 of B1.11, the following

    tems are highlighted as part of

    nspection prior to welding:. Review drawings and specifications.

    2. Check qualifications or proceduresand personnel to be utilized.

    3. Establish checkpoints.4. Set up a plan for recording results.

    5. Review materials to be utilized.6. Check for base metal

    discontinuities.

    7. Check fitup and alignmentof welded joints.

    8. Check preheat, if required.

    When appropriate attention is paid tohese issues, the quality of the yet-to-

    be-made weld can be expected to

    mprove as a result of the pre-weldingnspection. For example, when fitup

    and alignment of the joint are carefullynspected, consistent uniform fusion to

    he root of the weld and avoidance ofexcessive distortion and/or residualstresses can be achieved.

    tem No.3 discusses checkpoints. This

    s particularly critical on large weld-ments or complex projects when sub-

    sequent fabrication activities maypreclude further inspection of the fabri-cation process. Concurrent with this

    dea is the establishment of holdpoints where approval is required

    before further fabrication can be con-

    tinued. This must be coordinated withthe various contractors involved so

    that the overall project can proceed asexpected. Establishment of hold

    points, and communication with allparties involved, are critical to main-taining both quality and the job sched-

    ule.

    In Section 3.3 of B1.11, items thatshould be inspected during welding

    are outlined. These include:1. Quality of weld root bead.

    2. Joint root preparation prior to weldingthe second side.

    3. Preheat and interpass temperatures.

    4. Sequence of welding passes.5. Subsequent layer for apparent

    weld quality.6. Cleaning between passes.

    7. Conformance with the applicable

    procedure.

    The root pass, often the most criticalpart of the weld, is often made under

    the most difficult conditions.Maintenance of the proper preheat

    and interpass temperatures is criticalfor the metallurgical integrity of boththe weld metal and the heat affected

    zone. Inspection of intermediate weld

    layers, including removal of slag

    between layers, is absolutely essentialfor applications where only visual

    inspection will be applied.Conformance with the maximum layerthicknesses and bead widths as gov-

    erned by the applicable welding codeor WPS requirements can be visually

    verified at this point.

    The requirements for post-weldinspection are covered in Section 3.4of B1.11. Before the checklist is pro-

    vided, the following statement is made:Many people feel that visual inspec-

    tion commences once the welding hasbeen completed. However, if all of the

    previously discussed steps have beentaken before and during welding, this

    final phase of visual inspection will beaccomplished easily. It will simply pro-

    vide a check to be sure that the stepstaken have resulted in a satisfactoryweld. This statement endorses the

    power of an effective visual inspection.

    The checklist of items to inspect afterwelding includes the following:1. Final weld appearance.

    2. Final weld size.3. Weld length.

    4. Dimensional accuracy.5. Amount of distortion.6. Post-weld heat treatment.

    The importance of these issues is self-

    evident. The appearance of the weldis a strong indicator of the suitability of

    the actual welding procedure used,

    and the ability of the individual welder.More than merely a cosmetic issue,

    weld appearance provides someinsight into how the weld was made.

    Inspecting the work in process is not a

    new concept, but rather is part of thestandard codes already. Take, for

    example, the D1.1-98 StructuralWelding Code - Steel. In that code,

    visual inspection is mandated by 6.9,which states: All welds shall be visu-ally inspected.... In the chapter on

    Inspection, the following directions aregiven to the Inspector:

    The Inspector shall make certain

    that only materials conforming to therequirements of this code are used(6.2).

    The Inspector shall verify that all

    WPSs have been approved by theEngineer in conformance with 4.1.1

    (6.3.1).

    The Inspector shall inspect all weld-

    ing equipment to be used in the workto make certain that it conforms to

    the requirements of 5.11 (6.3.2).

  • 8/10/2019 Welding Quality and Inspection

    11/16

    Discontinuity Category and Inspection Criteria

    (1) Crack Prohibition

    The weld shall have no cracks.

    (2) Weld/Base-Metal Fusion

    Thorough fusion shall exist between adjacent layers of weld metal and between weld

    metal and base metal.

    (3) Crater Cross Section

    All craters shall be filled to the full cross section of the weld, except for the ends of

    intermittent fillet welds outside of their effective length.

    (4) Weld Profiles

    Weld profiles shall be in conformance with 5.24.

    (5) Time of Inspection

    Visual inspection of welds in all steels may begin immediately after the completedwelds have cooled to ambient temperature. Acceptance criteria for ASTM A514 and

    A517 steels shall be based on visual inspection performed not less than 48 hours

    after completion of the weld.

    (6) Underrun

    A fillet weld in any single continuous weld shall be permitted to underrun the

    nominal fillet size specified by 1/16 in. (1.6 mm) without correction, provided that

    the undersize portion of the weld does not exceed 10% of the length of the weld.

    On web-to-flange welds on girders, no underrun is permitted at the ends for a length

    equal to twice the width of the flange.

    (7) Undercut

    (A) For material less than 1 in. (25.4 mm) thick, undercut shall not exceed 1/32 in.

    (1 mm), except that a maximum 1/16 in. (1.6 mm) is permitted for an accumulated

    length of 2 in. (50 mm) in any 12 in. (305 mm). For material equal to or greater than

    1 in. thick, undercut shall not exceed 1/16 in. for any length of weld.

    (B) In primary members, undercut shall be no more than 0.01 in. (0.25 mm) deep

    when the weld is transverse to tensile stress under any design loading condition.

    Undercut shall be no more than 1/32 in. (1 mm) deep for all other cases.

    (8) Porosity

    (A) Complete joint penetration groove welds in butt joints transverse to the direction

    of computed tensile stress shall have no visible piping porosity. For all other groove

    welds and for fillet welds, the sum of the visible piping porosity 1/32 in. (1 mm) or

    greater in diameter shall not exceed 3/8 in. (10 mm) in any linear inch of weld and

    shall not exceed 3/4 in. (19 mm) in any 12 in. (305 mm) length of weld.

    (B) The frequency of piping porosity in fillet welds shall not exceed one in each 4 in.

    (100 mm) of weld length and the maximum diameter shall not exceed 3/32 in.(2 mm). Exception: for fillet welds connecting stiffeners to web, the sum of the

    diameters of piping porosity shall not exceed 3/8 in. (10 mm) in any linear inch of

    weld and shall not exceed 3/4 in. (19 mm) in any 12 in. (305 mm) length of weld.

    (C) Complete joint penetration groove welds in butt joints transverse to the direction

    of computed tensile stress shall have no piping porosity. For all other groove welds,

    the frequency of piping porosity shall not exceed one in 4 in. (100 mm) of length and

    the maximum diameter shall not exceed 3/32 in. (2 mm).

    1. An X indicates applicability for the connection type; a shaded area indicates non-applicability.

    Reprinted, with permission, from ANSI/AWS D1.1-98, Structural Welding Code, Steel.

    Statistically

    Loaded

    Nontubular

    Connections

    X X X

    X X X

    X X X

    X X X

    X X X

    X X X

    X

    X X

    X

    X X

    X X

    Cyclically

    Loaded

    Nontubular

    Connections

    Tubular

    Connections

    (All Loads)

    Table 6.1Visual Inspection Acceptance Criteria1 (see 6.9)

  • 8/10/2019 Welding Quality and Inspection

    12/16

    The Inspector shall permit welding tobe performed only by welders, weld-

    ing operators, and tack welders whoare qualified in accordance with the

    requirements of Section 4 (6.4.1).

    The Inspector shall make certain

    that only welding procedures are

    employed which meet the provisionsof Section 3 or Section 4 (6.5.2).

    The Inspector shall make certainthat electrodes are used only in the

    positions and with the type of weld-ing current polarity for which theyare classified (6.5.3).

    The Inspector shall, at suitable inter-

    vals, observe joint preparation,assembly practice, the welding

    techniques, and performance of

    each welder, welding operator, andtack welder to make certain the

    applicable requirements of this codeare met (6.5.4).

    These code requirements make it

    obvious that visual inspection mustake place well before the work is

    completed. This may deviate from the

    approach used by many Inspectors,but it is the only approach that can

    actually prevent the formation of weld-ng defects. For example, when the

    base materials being used are exam-ned, the Inspector can prevent theuse of the wrong type of material in a

    specific application. Careful examina-ion of welding procedures will reveal

    he suitability of a specific procedureor a particular application. The

    welders credentials will help deter-mine the suitability of that individual forhe specific application.

    Most of the emphasis to this point has

    been upon process inspection. Thequality of a completed weld can alsobe visually determined in many situa-

    tions. The single exception to this, as

    previously noted, is gas metal arc/short arc transfer. With this process, aweld may have an excellent appear-

    ance and lack the essential fusionnecessary for all forms of welding. In

    this case, extra emphasis on processinspection and nondestructive testingwill be warranted. A good-looking

    weld is generally a good weld. A poor-

    appearing weld may or may not be apoor weld. However, the presence ofvisually discernible criteria that deviate

    from good appearance is generally anindication that one or more variables

    are not being properly addressed. Forexample, excessive spatter may not

    detract from the quality of the weld.However, it is a sign that the processis not being controlled sufficiently.

    In a meeting several years ago, a

    series of fatigue and brittle fracturesthat occurred on highway bridges was

    being examined. The organizer of themeeting was attempting to establishthe need for more rigorous welded

    fabrication requirements. Hydrogencracking, brittle fracture, fracture

    mechanics, and fatigue details were alldiscussed. Most revealing in the

    meeting, however, was a commentmade by a very skilled technician, a

    welder, who had no formal engineeringtraining. His comment was as follows:

    I dont understand fracture mechan-ics, fatigue, or hydrogen embrittlement.

    However, from what I see in thesephotographs, none of these welds thatfailed would have met the visual

    acceptance criteria of the code. The

    silence in the room was deafening.The welder was correct. All of thetechnical issues that were being dis-

    cussed had entered into these failures,but none of the welds should have

    ever been accepted based on simplevisual inspection criteria.

    The traditionally understood inspectionresponsibilities are summarized con-

    cisely in Table 6.1 of the D1.1-98code, reproduced on the previous

    page.

    Welding is a process. Only by properly

    controlling every element of the processcan product quality be controlled. It is

    essential, however, that all the inputvariables be properly identified and con-trolled. During procedure qualification

    testing, critical variables can be identi-fied. During welder qualification and

    training, important parameters must beappropriately stressed. Effective visual

    inspection can ensure that the variablesare properly controlled and identified.

    There are applications where additionalnondestructive testing methods should

    be specified. However, in all situations,effective visual inspection must be

    employed to ensure weld quality. It isincumbent upon Engineers to properlydirect Inspectors attention to those

    issues that will contribute to higherquality products. When this is done,

    the quality of welding will improve, thecost will be reduced, and the Owners

    best interests will be served.

  • 8/10/2019 Welding Quality and Inspection

    13/16

    Quality is tied to a given specification.The specification must be suitable to

    meet the needs of the ultimate Owner.For most welded construction, the

    AWS D1.1-98 Structural Welding Code

    - Steelprovides adequate acceptancecriteria for welded construction.

    Unusual structures, however, maydemand additional requirements. D1.1

    criteria may be overly restrictive forsome lesser structures. For noncon-

    formances to a standard specification,alternate acceptance criteria may beutilized in order to avoid unnecessary

    weld repairs. It is the Engineersresponsibility to evaluate the appropri-

    ateness of an alternate acceptancecriterion before invoking it for a

    specific project.

    One of the currently popular definitions

    of a quality product is as follows: Aquality product is one that meets spec-

    ification requirements. By this defini-tion, quality is integrally linked to theapplicable specification. As long as

    the product meets those requirements,it is deemed quality. Unfortunately, if

    the specification is incorrect or inap-propriate, conformance to those

    requirements may satisfy this definitionbut would not satisfy the wants anddesires of the ultimate customer. Only

    when a proper specification is utilized,and when the product integrity meets

    or exceeds those specification require-ments, will a true quality product have

    been produced that meets customerrequirements. Therefore, a moreappropriate definition of quality would

    include the concept of meeting cus-tomer expectations in addition to the

    standard specification requirements.This philosophy is summarized by

    A.M. Gresnight of Delft University, theNetherlands, as follows:

    A good weld is any weld which

    does the job it is intended for dur-ing the service life of the structure.

    In the structural field, the customer

    (Owner) has a representative (theEngineer) who develops the necessaryspecifications (contract documents

    and cited codes and standards) thatenable the manufacturer (Fabricator)

    to deliver a quality product. In the caseof fabricated steel, the commonly cited

    standard for quality is the AWS D196 Structural Welding Code - Stee

    An understanding of the philosophybehind the D1.1 Code will help the

    Engineer to determine whether it wadequately address the needs of thOwner. Section 6.8, Engineers

    Approval for Alternate AcceptanceCriteria, states: The fundamental

    premise of the code is to provide geral stipulations applicable to most

    uations. The emphasis is significaIt is important to consider the scopthe D1.1 Code, which covers struc

    tures that are static and dynamic: oand off-shore applications that utiliz

    plate, rolled shapes, and tubular mbers. The products covered range f

    Heavy sections may require especially rigorous alternate acceptance criteria

  • 8/10/2019 Welding Quality and Inspection

    14/16

    simple single story metal-framed build-ngs to 100-story-plus skyscrapers and

    offshore drilling platforms. In somecircumstances, these general stipula-

    ions may be overly restrictive, and inother situations, they may not ade-quately address the demands of the

    structure. Evaluating the suitability of

    he specification for the application iscertainly the responsibility of theEngineer.

    n the commentary to Section 6.8 of

    he code, the following can be found:The criteria provided in section 5,

    Fabrication, are based upon knowl-

    edgeable judgment of what is achiev-able by a qualified welder. The criteria

    n Section 5 should not be considered

    as a boundary of suitability for service.Suitability for service analysis would

    ead to widely varying workmanshipcriteria unsuitable for a standard code.

    Furthermore, in some cases, the crite-ia would be more liberal than what is

    desirable and producible by a qualified

    welder. In general, the appropriatequality acceptance criteria and whether

    a deviation produces a harmful productshould be the Engineers decision.

    When modifications are approved,evaluation of suitability for serviceusing modern fracture mechanics tech-

    niques, a history of satisfactory servicen similar structures, or experimental

    evidence is recognized as a suitablebasis for alternate acceptance criteria

    or welds. This commentary makes itclear that the code has utilized what isachievable as the acceptance criterion,

    not what is necessary for the particularapplication. This is a reasonable

    approach for a standard specification,and as is indicated in the commentary,

    precludes the need for widely varying

    fabrication standards which would bedifficult to monitor in a typical fabrica-

    tion facility. When the weld qualitydoes not meet these standards, how-

    ever, it is inappropriate to automaticallyassume that the weld will be unaccept-able for service. This should, however,

    drive the Engineer to look to fitness-

    for-service type criteria for furtherevaluation.

    Few Engineers recognize that theD1.1 code permits the use of alternate

    acceptance criteria for welds.According to Section 6.8: Acceptancecriteria for production welds different

    from those specified in the code maybe used for a particular application,

    provided they are suitably documentedby the proposer and approved by the

    Engineer. These alternate acceptance

    criteria can be based upon evaluationof suitability for service using past

    experience, experimental evidence, orengineering analysis concerning mate-

    rial type, service load effects, andenvironmental factors.

    These provisions permit the Engineerto utilize alternate acceptance criteria.

    Since quality is integrally linked to theapplicable specification, the accep-

    tance criteria will have a major impacton the final product. The Engineers

    responsibility is to assess the suitabili-ty of a standard specification to a par-ticular project, as well as to approve

    an alternate should the need arise.

    There are three areas in which alter-nate acceptance criteria should be

    considered: First, there are situationswhere standard acceptance criteria

    are inadequate to the demands of thestructure. Secondly, standard accep-

    tance criteria may be overly restrictivefor a particular application. Finally,there are cases in which fabrication is

    routinely performed to a standardspecification, with minor noncompli-

    ances that can be accepted throughthe use of an alternate acceptance cri-

    terion. All three are significant issuesand will be addressed here.

    Certain structures make unusualdemands upon welds and weld quality.

    When new materials are employed,significant deviations from standard

    material thicknesses are utilized, newwelding processes are employed,and/or when the design of the struc-

    ture involves a significant departure

    from established practices, it is pru-dent for the Engineer to critically eval-uate the suitability of standard

    specifications.

    For example, the steel fabricationindustry learned many lessons whenjumbo sections were initially applied

    to tension applications in trusses.Standard materials (hot rolled, carbon

    and/or low alloy steel shapes) inunusual thicknesses (flanges exceed-

    ing 5 in thickness) were being used in

    new applications (direct tension con-nections). The common workmanship

    criteria set forth in the various codesand specifications, as well as normally

    acceptable workmanship criteria,proved to be inadequate in a number

    of structures. In hindsight, it wouldhave been prudent to employ morerigorous alternate acceptance criteria

    for these types of structures. Sincethat time, provisions have been written

    to address these situations and havebeen presented in a variety of techni-

    cal journals. Indeed, the standardspecifications now include more rigor-ous requirements.

    The second situation occurs when the

    standard acceptance criteria are moredemanding than is justified for the par-

    ticular application. An example in thestructural field would be in the fabrica-tion of steel joists. These components

    in steel buildings are usually coveredby another specification that is more

    applicable to the particular productinvolved. Application of the same

    acceptance criteria as are applied toother fabricated steel structures andmandated by D1.1 would be overly

    restrictive, justifying alternate accep-tance criteria. The Engineer should be

    careful when routinely suggesting thatalternate acceptance criteria be

    employed which deviate from, or are

  • 8/10/2019 Welding Quality and Inspection

    15/16

    less rigorous than, a national consen-sus standard such as D1.1. This prac-

    tice would be recommended only forspecific applications for components

    where well established, time-provenpractices that have a history of ade-quacy have been used, and where

    deviation from these practices would

    constitute a major hardship. The D1.1code, however, clearly gives theEngineer the authority to accept an

    alternate standard in these situations.

    The most important use of alternateacceptance criteria, however, appliesto the third situation, where standard

    acceptance criteria have been utilizedfor the fabrication practice and minor

    nonconformances have been uncov-ered. Alternate acceptance criteria

    can be utilized to accept these non-

    conformances and eliminate the needfor unnecessary repairs. Obviously,

    the alternate acceptance criteria cho-sen must, as is true in the case of all

    engineering decisions, be applicableand appropriate for the application.

    Neither poor workmanship nor poorquality can be accepted. However,when the weld that does not conform

    to the standard specification is suitablefor the specific situation, alternate

    acceptance criteria may be employedto eliminate the need for a repair.

    There are many reasons why this maybe desirable for all (that is, the Owner,the Engineer, and the Fabricator).

    Unnecessary delays may be avoided.Costly repairs are avoided. Finally,

    and perhaps most importantly, anacceptable repaired weld may actual-

    ly be inferior to the weld initially reject-ed as unacceptable. Again,according to A.M. Gresnight:

    Standards for weld discontinuities

    traditionally are based on goodworkmanship criteria. By extending

    the traditional standards with thesecond quality level, based on fit-ness for purpose, unnecessary and

    potentially harmful repairs can beavoided.

    Weld discontinuities fit into two broadcategories: planar and volumetric.

    Planar discontinuities include cracksand lack of fusion. These are serious

    discontinuities that are unacceptable,and particularly critical in structuressubject to fatigue. Volumetric disconti-

    nuities include items such as porosity,slag inclusion, and undercut. These

    are less significant, and when heldwithin certain limits, are acceptable by

    most codes even under dynamic load-ing situations.

    Volumetric discontinuities are readilydiscernible by nondestructive testing

    methods and, in many cases, by visualinspection. Planar discontinuities are

    harder to detect, and may even beoverlooked by radiographic nonde-structive testing. It has been shown

    that, during initial fabrication, most dis-continuities are volumetric in nature.

    Under repair welding conditions, whichare more demanding than original fab-

    rication circumstances, planar disconti-nuities are more likely to develop.Notice the progression: readily

    detectable, less significant volumetricdiscontinuities observed in the original

    fabrication may be removed andreplaced with welds that contain less

    detectable, but more significant, planar

    discontinuities. This is not to say o

    imply that welds cannot be effectivrepaired. It does mean, however, t

    haphazard demands for weld repaimay actually result in a product of

    decreased value to the Owner. Itshould also be noted that the depotion of additional weld metal is like

    increase distortion and residual stres in the structure. When the nonc

    forming weld is adequate for theparticular application, the responsi

    approach is to utilize an alternateacceptance criterion to eliminate thunnecessary repair.

    Most Engineers are unsure of the s

    ability of alternate acceptance criteThe search for appropriate docume

    that employ the fitness for purposeapproach is generally a frustratingexperience. Apart from finding info

    mation regarding the methods thatmay be employed for analysis, prac

    cal ideas as they relate to welds arall too scarce. Mr. Robert E. Shaw,

    P.E., of Steel Structures TechnologCenter, Inc., (40612 Village OaksDrive, Novi, Michigan 48375-4462)

    has provided Engineers with a usesource of information regarding alte

    nate acceptance criteria. Shaw hasystematically evaluated specific d

    continuities, the D1.1 Code require

    The 7 in (180 mm) flanges of these transfer girders require careful consideraof the NDT acceptance criteria.

  • 8/10/2019 Welding Quality and Inspection

    16/16

    ments, and other standards that couldbe used as alternates. His summary

    s excellent and provides practicaloptions to Engineers.

    Undersized welds are a common prob-em. The situation is simple: the

    drawings call for a 5/16 in (8 mm) fillet

    weld and the welder deposits a 1/4 in6 mm) fillet. At least two options are

    available: first, additional weld metal

    can be deposited over the surface to

    build it up to the required size; second-

    y, an alternate acceptance criterioncould be employed that would allow

    hese welds to be acceptable asdeposited. It should be noted that theD1.1 Code would allow the welds to

    underrun the nominal fillet weld sizeby 1/16 in (1.6 mm) without correction

    provided that the undersized portion ofhe weld does not exceed 10% of the

    weld length (D1.1-98, Table 6.1, see

    Part II of this series). If the entireweld, however, is undersized, this pro-

    vision would not be applicable. Inmany cases, the deposition of addi-

    tional weld metal would be routine andwould not constitute a major problem.However, the initial weld may have

    been produced with an automatic,

    submerged arc welding machine whenthe travel speed happened to beslightly too high, resulting in a slightly

    undersized weld. The weld may bebeautiful and meet all criteria except

    for the size. To make the weld repair, agang of manual or semiautomaticwelders may be assigned to deposit

    the additional weld metal. The fin-ished product may be visually inferior,

    and subject to all of the potential dis-continuities of the starts and stops

    associated with manual and semiauto-

    matic welding.

    Has the product quality beenenhanced by the repair? First, it must

    be determined if the undersized weldwould have been acceptable. As is

    the case in many situations involvingfabricated plate girders, the weld sizemay have been based upon the mini-

    mum prequalified fillet weld size pre-scribed in the D1.1 Code. The design

    basis was not strength, but this mini-mum size. A quality, 1/4 in (6 mm)

    fillet weld would have provided all thenecessary strength in this particularsituation. The reasoning behind the

    minimum fillet weld size in the code isbased upon good workmanship prac-

    tices and controlling the heat input topreclude weld cracking. However, in

    this example, it has been assumed

    that the initial weld is a quality weld,free of cracks, with acceptable weld

    contours, etc. If this is the situation,leaving the undersized weld in place,

    unrepaired, is a more responsibleapproach than demanding the weld

    repair. The initial weld is probably ofhigher quality than the repaired weld

    would be, will have less distortion, isless costly, and will eliminate unneces-

    sary delays.

    The decision to invoke alternateacceptance criteria must be made bythe Engineer. In a separate article in

    this series, the roles of the Engineer,the Inspector, and the Fabricator are

    defined. The Inspector cannot makethis decision and neither can the

    Fabricator. Only the Engineer with anunderstanding of the loading, design

    assumptions, and overall structuralsignificance can make these types ofdecisions.

    For most applications, the AWS D1.1-98 Structural Welding Code - Steelprovides adequate acceptance criteria

    for welded construction. For weldsthat deviate from standard acceptance

    criteria, engineering judgment shouldbe applied before repairs are mandat-

    ed. If the weld will meet the structuralrequirements for the project withoutmodification, the responsible approach

    of the Engineer is to utilize alternateacceptance criteria and accept these

    welds. Ultimately, a product ofimproved quality at reasonable cost

    will be the result of this approach.