Edition 1: November 2014
Project Start Date: 25th July 2014
Project Completion Date: End of Summer
2016
Project value: £2.4M
Project Funders: Ards Borough Council
and the Department for Social
Development
Welcome to our first
Newsletter for the Comber
Public Realm Project
As the Comber Public Realm Project nears
Christmas, we would like to thank all the
businesses, residents and shoppers for their
understanding and cooperation as the scheme
progresses through the town.
FP McCann Ltd are required under contract to
cease all works on the streets to facilitate the
Christmas trading period in the town. As a
result, works will stop towards the end of
November, they will recommence on 5th
January 2015.
To facilitate this Regional Embargo period FP
McCann Ltd will minimise the fencing and
barriers on the streets. No excavations will be
left open and all areas that have been worked
on will be finished to concrete pavement
foundation, with some temporary tar
reinstatements around manholes and raised
ironwork. Regular inspections will be carried
out of all these areas during the Embargo
period and the Christmas Holidays. All area
will be made safe for pedestrian usage over
the Christmas period.
Please note that access to all trading
businesses and residential properties will be
maintained throughout.
Progress to date:
Castle Street
Castle Lane to Tim Martin Estate
Agents
The Public Realm has progressed well in this
area. Excavation, placement of services and
laying of the concrete pavement foundation
has been completed. Kerbing and paving at
this location will commence after the
Christmas period in January 2015.
A temporary tarmac surface has been laid at
this location to facilitate safe passage on the
footpath until paving commences.
Edition 1: November 2014
Strains to opposite Smith’s Bookmakers
As with the opposite side, excavation,
placement of services and laying of the
concrete pavement foundation has been
completed, with kerbing and paving to
commence after the Christmas period in
January 2015.
Bridge Street
Darragh Rd Junction to Stepping
Stones
The Public Realm works including excavation,
placement of services and laying of the
concrete pavement foundation has been
completed. A section of NIE cable on the
bridge was carefully exposed and covered as
per the instructions of NIE. Kerbing and
paving at this location will commence after
the Christmas period in January 2015.
Stepping Stones to Bridge St Link
The Public Realm works including excavation,
placement of services and placement of
concrete pavement foundation has been
completed with the exception of the driveway
into Comber Methodist Church. This will be
completed in January 2015. Kerbing and
paving at this location will commence after
the Christmas period in January 2015.
Bridge Street Link
RA Glass Opticians to Tropical Chinese
& Thai Cuisine
Excavation, placement of services and laying
of the concrete pavement foundation has been
completed. Kerbing and paving at this
location will commence after the Christmas
period in January 2015.
Street Lighting
Placement of street lighting ducting,
excavation and placement of street light
sockets and reinstatement of the footpath
surface has been completed on the following
streets in areas beyond the paving footprint of
the scheme:
Mill Street, High Street and Killinchy Street
Edition 1: November 2014
Upcoming Works:
After the Christmas period the programme
will progress within the following areas.
Work will include:
Areas Concreted Kerbing and paving to commence on areas
concreted.
Bridge Street Excavation, placement of services, and the
laying of the concrete pavement foundation is
due to commence Jacksons on Bridge St
towards The Square.
Castle Street Excavation, placement of services, laying of
the concrete pavement foundation is due to
continue on this street towards The Square
Events held to date:
Upcoming Events: Trader and Residents information session to
be held in Comber leisure Centre on Tuesday
2nd December 2014 at 5.30pm, to update on
progress made to date and programmed
works for early 2015.
Contact details: FP McCann will continue to liaise with all the
businesses and residents within the footprint
of the scheme to minimise disruption during
the period of the scheme. Those affected will
be contacted directly by the Contractor prior
to works commencing.
If you have any queries please contact the
Project Office on 028 7954 9165.
You can also call into the Project Office
located at 3 Castle Street, Comber (Yumms
Edition 1: November 2014
Deli) or alternatively via the project email
address: [email protected];
If you have a query outside of office hours
please do not hesitate to contact our 24hr
contact number 028 7954 9090.
The programme information outlined above is
subject to change, and is dependent upon
approval from ABC and Transport NI.