STUDY AREA

PROJECT PURPOSE

• Analyze structure of the bridge and prepare short term remediations

• Analyze the long-term multi-modal capacity improvements that include the future operating requirements of high-speed and intercity passenger rail, commuter rail, transit, bike and pedestrian, and freight services over the Potomac River

• Analyze multi-modal connectivity and operational improvements

Data Collection

Public Involvement

Agency and Bridge User Involvement

Transportation Analysis & Evaluation

Alternatives Development

Environmental Screening

Recommendations

PROJECT SCOPE

PROJECT NEEDS

Needs Your Preference

Multi-modal Access

Inter-Modal Connectivity

Long-term Capacity

Transportation Demand

Support Existing & Future Land Use

Operational Improvements

System Linkages

Improve Structural Conditions

Other

SCHEDULE

Milestone Date

Data Collection, Analysis and Evaluation Fall 2012 / Winter 2013

Bridge Alternatives and Conceptual Engineering

Environmental Review Spring 2013 / Summer 2013

Final Report Summer 2013

Winter 2013 / Spring 2013

PUBLIC INVOLVEMENT

Anticipated Meeting Dates

Public Meeting #1 November 13, 2012

Public Meeting #2 Winter 2013 / Spring 2013

Public Meeting #3 Summer 2013

Please give us your comments:

■ At a public meeting

■Website: www.longbridgeproject.com