WEEK4A_INSTRUMENT AND STATIONARY .ppt

download WEEK4A_INSTRUMENT AND STATIONARY .ppt

of 30

Transcript of WEEK4A_INSTRUMENT AND STATIONARY .ppt

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    1/30

    The Basics ofMeasurement

    Fara Diva MustapaAssoc. Prof Dr. Rosli Abd. Rashid

    Department of Quantity SurveyingFaculty of Built EnvironmentUniversiti Teknologi Malaysia

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    2/30

    The Fundamental of

    MeasurementBefore proceedings to the next level oftaking- of work, one should know what arethe tools or the instruments needed tocarry out such process. Hence, thislecture is an introduction to the dimensionpapers, calculators, scale rules and colour

    pencils before further explaining thedimensions papers.

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    3/30

    The instruments and

    stationary used in a processof measurement

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    4/30

    It is a sheet of paper that consists of few

    column that represent the item/element thathas been measured. Each column has its ownfunctions and share almost equal importance to aquantity surveyor. It is a standard format usedworldwide.

    The next slide will show you a sample ofdimension paper.

    A) Dimension papers

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    5/30

    Project: Bill No. Element/Trade. Page No.

    Heading

    Description Unit

    Quantity

    Taker-off

    Squaring

    The taking-off sheet

    Dewan-Dwgs/12 WBLFF 1

    Vibrated Reinforced Concrete Grade 25 as described incolumn stump

    m3

    0.800.430.20

    ----------

    2

    FDM

    1

    0.14----------

    0.14

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    6/30

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    7/30

    B) Ink Pen The most basic tools of all which requires a goodattention. One should use only black or blue ink to write

    down all the elements in the dimension paper. Whilst the red ink is used only to

    SUBSTACTS/DEDUCTIONS of any items in thedimension papers. One should never writes in pencil as it can be

    easily erased which further bring difficulty intracing down the measurement in future.

    If one makes a mistakes during the taking-offprocess, simply crossed/slash the mistakes andDO NOT USE LIQUID PAPER.

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    8/30

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    9/30

    C) Scale Rules

    A scale rules is used to measure thedrawings if there is no dimensionstated in the drawings. It comes in

    different scales such as 1:100, 1:1,1:200, 1:20, 1:50, 1:5, 1:1250 and soon.

    One should use the appropriate scaleas mentioned in the drawings.

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    10/30

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    11/30

    D) Calculator Calculator is used to either adding,

    omitting, squaring, dividing and othercalculation needs

    A small size of calculator with a basicfunction is very useful to carry around. P/S: A quantity surveyor is very synonym

    with calculator that one shouldnt be

    regard as a one if he or she does not carryone around.

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    12/30

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    13/30

    Colour pencils are very useful todifferentiate different items orelements in a drawings.

    As there is so many items to bemeasured, by coloring andhighlighting, it shall ease the taking-off process

    E) Colour pencils

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    14/30

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    15/30

    Introduction to

    Dimension Paper As mentioned earlier, each column in thedimension paper represents certaininformation with regards to the itemmeasured and even the drawings.

    Please pay good attention as the next fewslides will explains each column which

    incorporates the dimension paper

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    16/30

    Project: Bill No. Element/Trade. Slip No.

    Heading

    Description Unit

    Quantity

    Taker-off

    Squaring

    Dewan-Dwgs/12 WBLFF 1

    Vibrated Reinforced Concrete Grade 25 asdescribed in column stump

    m3

    0.800.430.20

    ----------

    2

    FDM

    1

    0.14----------

    0.14

    1 2 3 4

    14

    5

    6

    7

    8

    9

    13

    101112

    Project/drawings no.1

    Sequence of elements2

    Elements measured3

    Sequence of taking-off4

    5 Description of item

    6 Unit measured as per SMM 2

    7 The total no. of item measured

    8 The name of persons responsible for taking -off

    9 The name of persons responsible for squaring

    F1

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    17/30

    Project: Bill No. Element/Trade. Slip No.

    Heading

    Description Unit

    Quantity

    Taker-off

    Squaring

    Dewan-Dwgs/12 WBLFF 1 1

    Vibrated Reinforced Concrete Grade 25 asdescribed in column stump

    m3

    0.14

    FDM

    0.14----------

    0.800.430.20

    ----------

    101112

    2

    13

    14

    F1

    10 The total of calculations

    11 The process ofcalculation the

    dimension attainedfrom the drawings

    12 The total no. ofsame item/elementappeared in the

    drawings13 Side

    cast/annotations

    14 Explanation onthe item/elementsmeasured. Notnecessarily filled.Should refer toSMM2 forfurtherexplanations

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    18/30

    Sequence of

    measurement Usually a project consists of a few differentbuildings with different designs and even finishes.Hence, the measurement should be differentiatedin order to ease measurement.

    For a buildings work, the measurement can bedivided into elements, item or trade.

    However, measurements according to trade hasnot been practiced as it was according to SMM1which is very known for its complicatedness ofmeasuring process

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    19/30

    An example of measurement according toelements/work, the samples of distributionsare as follows:

    Piling works Work below low floor

    finish Structure Upper floor Roof Staircase External wall External doors andwindows

    Internal wall andpartitions

    Internal doors andwindows

    Internal wall finishes Internal floor finishes Internal ceiling

    finishes

    External finishes Ect.

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    20/30

    Taking-off Lists Previously, it has been mentionedthat there are several items need to

    be measured. Hence, it should benoted at the beginning of taking-offprocess. Sample of taking of listsare as next slides.

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    21/30

    Project: Bill No. Element/Trade. Page No.

    Heading

    Description Unit

    Quantity

    Taker-off

    Squaring

    Piling

    Pre Cast Concrete PilesTaking off list

    1. Bringing in & removing plant Item

    2. Maintaining plant on site Item

    3. Initial piles No.

    4. Driven depth m.

    5. Pile extension No.

    6. Extension piles n.e. 3.00 long m

    7. Extention piles exceedg. 3.00 ling m

    8. Cut-off pile heads No.

    9. Preliminary load tests Item

    10.Subsequent load test Item

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    22/30

    Principals of taking-off

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    23/30

    How to measure A normal practice of taking-off areas follows:

    - horizontal dimension as length- vertical dimension as width, height,

    or depth

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    24/30

    How to write dimensions

    in the taking-off paper.. All dimension in the drawings should

    be transferred in the t/off paperand should follow the following order;

    Length , width, height/depth

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    25/30

    3D drawings of a ground

    beam

    200

    430

    800

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    26/30

    How to transfer dimension into t/offpaper

    800

    430

    Ground beam depth: 200

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    27/30

    Project: Bill No. Element/Trade. Slip No.

    Heading

    Description Unit

    Quantity

    Taker-off

    Squaring

    0.14----------

    0.800.430.20

    ----------

    2

    Height/depth

    width

    length

    m3No. ofrepetition

    of sameitemappearedindrawings

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    28/30

    And later after compilationof all taking-off, a sample

    of Bills of Quantities shouldlook like the following slide

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    29/30

    Description Unit Qty Rates Amount No.

    Excavating trench for foundationStarting from ground level, maximumdepth not exceeding 0.25m

    Formwork to edge of concrete notExceeding 250mm high

    Foundation in concrete Grade 20

    Walll, 225mm thick in common bricksin English bond in cement and sand(1:6) mortar

    Plate, 75mm x 50mm in wrot pressuretreated group B timber

    m3 0.14 10.00

    a.

    b.

    c.

    d.

    e.

    Bench top, 225mm x 25mm in wrotpressure treated Group B timber

    m 5 22.00

    m3 0.14 170.00

    m2 1 48.00

    m 1 16.00

    m2 1 24.00

    Apply two coats of timber tone and onecoat of varnish m2 1 6.50

    f.

    g.

    TO COLLECTION

    1.40

    110.00

    23.80

    48.00

    16.00

    24.00

    6.50

    BILL NO. 1 SMALL BENCH

    229.70

    Cost of each work item(By multiplying thequantity and the rate)

    The quantity of eachwork item(Obtained from theTaking-off sheet)

    The rate(Obtained fromsupplier orschedule of rates)

    Total cost of the bench(By adding the cost ofall the items in the list)

  • 8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt

    30/30

    The EndThank You