WEEK4A_INSTRUMENT AND STATIONARY .ppt
-
Upload
mariam-mustafa -
Category
Documents
-
view
217 -
download
0
Transcript of WEEK4A_INSTRUMENT AND STATIONARY .ppt
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
1/30
The Basics ofMeasurement
Fara Diva MustapaAssoc. Prof Dr. Rosli Abd. Rashid
Department of Quantity SurveyingFaculty of Built EnvironmentUniversiti Teknologi Malaysia
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
2/30
The Fundamental of
MeasurementBefore proceedings to the next level oftaking- of work, one should know what arethe tools or the instruments needed tocarry out such process. Hence, thislecture is an introduction to the dimensionpapers, calculators, scale rules and colour
pencils before further explaining thedimensions papers.
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
3/30
The instruments and
stationary used in a processof measurement
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
4/30
It is a sheet of paper that consists of few
column that represent the item/element thathas been measured. Each column has its ownfunctions and share almost equal importance to aquantity surveyor. It is a standard format usedworldwide.
The next slide will show you a sample ofdimension paper.
A) Dimension papers
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
5/30
Project: Bill No. Element/Trade. Page No.
Heading
Description Unit
Quantity
Taker-off
Squaring
The taking-off sheet
Dewan-Dwgs/12 WBLFF 1
Vibrated Reinforced Concrete Grade 25 as described incolumn stump
m3
0.800.430.20
----------
2
FDM
1
0.14----------
0.14
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
6/30
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
7/30
B) Ink Pen The most basic tools of all which requires a goodattention. One should use only black or blue ink to write
down all the elements in the dimension paper. Whilst the red ink is used only to
SUBSTACTS/DEDUCTIONS of any items in thedimension papers. One should never writes in pencil as it can be
easily erased which further bring difficulty intracing down the measurement in future.
If one makes a mistakes during the taking-offprocess, simply crossed/slash the mistakes andDO NOT USE LIQUID PAPER.
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
8/30
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
9/30
C) Scale Rules
A scale rules is used to measure thedrawings if there is no dimensionstated in the drawings. It comes in
different scales such as 1:100, 1:1,1:200, 1:20, 1:50, 1:5, 1:1250 and soon.
One should use the appropriate scaleas mentioned in the drawings.
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
10/30
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
11/30
D) Calculator Calculator is used to either adding,
omitting, squaring, dividing and othercalculation needs
A small size of calculator with a basicfunction is very useful to carry around. P/S: A quantity surveyor is very synonym
with calculator that one shouldnt be
regard as a one if he or she does not carryone around.
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
12/30
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
13/30
Colour pencils are very useful todifferentiate different items orelements in a drawings.
As there is so many items to bemeasured, by coloring andhighlighting, it shall ease the taking-off process
E) Colour pencils
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
14/30
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
15/30
Introduction to
Dimension Paper As mentioned earlier, each column in thedimension paper represents certaininformation with regards to the itemmeasured and even the drawings.
Please pay good attention as the next fewslides will explains each column which
incorporates the dimension paper
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
16/30
Project: Bill No. Element/Trade. Slip No.
Heading
Description Unit
Quantity
Taker-off
Squaring
Dewan-Dwgs/12 WBLFF 1
Vibrated Reinforced Concrete Grade 25 asdescribed in column stump
m3
0.800.430.20
----------
2
FDM
1
0.14----------
0.14
1 2 3 4
14
5
6
7
8
9
13
101112
Project/drawings no.1
Sequence of elements2
Elements measured3
Sequence of taking-off4
5 Description of item
6 Unit measured as per SMM 2
7 The total no. of item measured
8 The name of persons responsible for taking -off
9 The name of persons responsible for squaring
F1
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
17/30
Project: Bill No. Element/Trade. Slip No.
Heading
Description Unit
Quantity
Taker-off
Squaring
Dewan-Dwgs/12 WBLFF 1 1
Vibrated Reinforced Concrete Grade 25 asdescribed in column stump
m3
0.14
FDM
0.14----------
0.800.430.20
----------
101112
2
13
14
F1
10 The total of calculations
11 The process ofcalculation the
dimension attainedfrom the drawings
12 The total no. ofsame item/elementappeared in the
drawings13 Side
cast/annotations
14 Explanation onthe item/elementsmeasured. Notnecessarily filled.Should refer toSMM2 forfurtherexplanations
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
18/30
Sequence of
measurement Usually a project consists of a few differentbuildings with different designs and even finishes.Hence, the measurement should be differentiatedin order to ease measurement.
For a buildings work, the measurement can bedivided into elements, item or trade.
However, measurements according to trade hasnot been practiced as it was according to SMM1which is very known for its complicatedness ofmeasuring process
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
19/30
An example of measurement according toelements/work, the samples of distributionsare as follows:
Piling works Work below low floor
finish Structure Upper floor Roof Staircase External wall External doors andwindows
Internal wall andpartitions
Internal doors andwindows
Internal wall finishes Internal floor finishes Internal ceiling
finishes
External finishes Ect.
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
20/30
Taking-off Lists Previously, it has been mentionedthat there are several items need to
be measured. Hence, it should benoted at the beginning of taking-offprocess. Sample of taking of listsare as next slides.
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
21/30
Project: Bill No. Element/Trade. Page No.
Heading
Description Unit
Quantity
Taker-off
Squaring
Piling
Pre Cast Concrete PilesTaking off list
1. Bringing in & removing plant Item
2. Maintaining plant on site Item
3. Initial piles No.
4. Driven depth m.
5. Pile extension No.
6. Extension piles n.e. 3.00 long m
7. Extention piles exceedg. 3.00 ling m
8. Cut-off pile heads No.
9. Preliminary load tests Item
10.Subsequent load test Item
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
22/30
Principals of taking-off
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
23/30
How to measure A normal practice of taking-off areas follows:
- horizontal dimension as length- vertical dimension as width, height,
or depth
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
24/30
How to write dimensions
in the taking-off paper.. All dimension in the drawings should
be transferred in the t/off paperand should follow the following order;
Length , width, height/depth
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
25/30
3D drawings of a ground
beam
200
430
800
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
26/30
How to transfer dimension into t/offpaper
800
430
Ground beam depth: 200
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
27/30
Project: Bill No. Element/Trade. Slip No.
Heading
Description Unit
Quantity
Taker-off
Squaring
0.14----------
0.800.430.20
----------
2
Height/depth
width
length
m3No. ofrepetition
of sameitemappearedindrawings
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
28/30
And later after compilationof all taking-off, a sample
of Bills of Quantities shouldlook like the following slide
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
29/30
Description Unit Qty Rates Amount No.
Excavating trench for foundationStarting from ground level, maximumdepth not exceeding 0.25m
Formwork to edge of concrete notExceeding 250mm high
Foundation in concrete Grade 20
Walll, 225mm thick in common bricksin English bond in cement and sand(1:6) mortar
Plate, 75mm x 50mm in wrot pressuretreated group B timber
m3 0.14 10.00
a.
b.
c.
d.
e.
Bench top, 225mm x 25mm in wrotpressure treated Group B timber
m 5 22.00
m3 0.14 170.00
m2 1 48.00
m 1 16.00
m2 1 24.00
Apply two coats of timber tone and onecoat of varnish m2 1 6.50
f.
g.
TO COLLECTION
1.40
110.00
23.80
48.00
16.00
24.00
6.50
BILL NO. 1 SMALL BENCH
229.70
Cost of each work item(By multiplying thequantity and the rate)
The quantity of eachwork item(Obtained from theTaking-off sheet)
The rate(Obtained fromsupplier orschedule of rates)
Total cost of the bench(By adding the cost ofall the items in the list)
-
8/10/2019 WEEK4A_INSTRUMENT AND STATIONARY .ppt
30/30
The EndThank You