Learning outcome
• Basic techniques of road construction• Plant and equipment selection• Types of pavements• Construction sequences• Mass haul diagram
![Page 3: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/3.jpg)
PLANT & EQUIPMENTEARTHMOVING MACHINERY• DOZERS• SCRAPERS• EXCAVATORS • TIP TRUCKS
COMPACTION EQUIPMENT• SHEEPSFOOT ROLLERS• TAMPING ROLLERS• SMOOTH-DRUM VIBRATORY SOIL COMPACTORS• PAD-DRUM VIBRATORY SOIL COMPACTORS• PNEUMATIC TIRED ROLLERS
![Page 4: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/4.jpg)
PLANT & EQUIPMENT (CONT.)
OTHER PLANT & EQUIPMENT
• WATER DISTRIBUTOR• DRILL & BLAST EQUIPMENT • PAVING MACHINES• BITUMEN SPRAYERS & EQUIPMENT• DE-WATERING EQUIPMENT
![Page 5: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/5.jpg)
100101
101102
102
103
106
105
104
No cut / no fill line
CUTTING FILL
Elevation
Plan
ROAD DESIGNNatural surface
Road gradeline
![Page 6: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/6.jpg)
Cross SectionExcavation (Cut)
ROAD DESIGN
Cross SectionEmbankment (Fill)
![Page 7: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/7.jpg)
Subgrade
Cross SectionFlexible Pavements (Typical)
Wearing CourseAsphalt / Bitumen Seal)
Base course
Sub-base course
Lower Sub-base course
Subgrade
Batter
![Page 8: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/8.jpg)
Subgrade strength
• Removing poor material in cutting and replacing with selected fill.
• Ensure compaction to a high dry density.• Providing adequate subsoil drainage.
![Page 9: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/9.jpg)
Why we need Subsoil Drainage
![Page 10: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/10.jpg)
Drainage pipe
![Page 11: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/11.jpg)
Sub soil drain
![Page 12: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/12.jpg)
Subsoil drainage location
![Page 13: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/13.jpg)
Soil stabilisation
• Stabilisation refers to any treatment of the soil that increases its strength.
• Stabilisation may be achieved by various agents, which include cement, lime, bitumen.
![Page 14: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/14.jpg)
California bearing ratio
C.B.R. = Test load/Standard load
![Page 15: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/15.jpg)
Types of pavements
![Page 16: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/16.jpg)
Flexible pavement
• Flexible pavement
Consists of several layers of materials Flexible pavement distributes loads over a
smaller area. It relies on a combination of layers for
transmitting load to the subgrade
![Page 17: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/17.jpg)
Rigid pavement
Rigid Pavement Consists of a concrete slab resting on subbase
material Distribute the load over a relatively wide area of
subgrade
![Page 18: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/18.jpg)
Contraction joints
A contraction joint is provided to controlcracking in rigid pavementsTransverse contraction joints can be cut at
right angles or skewed to the direction oftraffic flow to help with load transferDowel bars are used to transfer loads
across the joints.
![Page 19: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/19.jpg)
Expansion joints
• Expansion joints are constructed to allow pavements to expand and contract without damage to adjacent pavements or structures
![Page 20: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/20.jpg)
Construction joints
• A construction joint is a joint between slabs that results when concrete is placed at different times.
• This type of joint can be further broken down into transverse and longitudinal construction joints
![Page 21: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/21.jpg)
CONSTRUCTION SEQUENCEESTABLISHMENT• COMPOUNDS AND OFFICES
ROADWORKS• SURVEY• INVESTIGATION WORKS • ENVIRONMENTAL WORKS• CLEARING / STRIP VEGETATION & STOCKPILE
TOPSOIL• INSTALL MAJOR DRAINAGE STRUCTURES• BULK EARTHWORKS (CUTS AND FILLS)• INCLUDE IMPORT FILL (SHORTFALL FROM CUTS)• BOX FOR PAVEMENTS
![Page 22: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/22.jpg)
CONSTRUCTION SEQUENCE (CONT.)ROADWORKS (CONT.)
• INSTALL SUB-BASE PAVEMENTS • INSTALL BASE COURSE PAVEMENTS
(ALTERNATIVES ASPHALT OR CONCRETE PAVEMENTS)
• INSTALL PAVEMENT DRAINAGE• INSTALL WEARING SURFACE
(ASPHALT OR SPRAYED BITUMEN / AGGREGATE)• BATTER SLOPE PROTECTION (TOSOIL RE-
SPREAD & LANDSCAPING WORKS)• INSTALL ROAD HARDWARE / FURNITURE• LINE MARKING & ROAD SIGNS
![Page 23: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/23.jpg)
SURVEY
• SET OUT HORIZONTAL AND VERTICAL CURVES
• SET OUT SUPER ELEVATIONS (CROSSFALLS)
• MONITOR EARTHWORKS DURING CONSTRUCTION
• PREPARE “AS CONSTRUCTED” DRAWINGS
![Page 24: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/24.jpg)
EXISTING SUBSTRATE
PREPARING SUBSTRATE BENEATH FILLS(GROUND SURFACE TREATMENT)
150
PROOF ROLL EXISTING GROUND SURFACE
EXPOSE SOFT SPOTS
EXCAVATE SOFT SPOTS
FILL AND COMPACT SOFT SPOTS
REMOVE TOP SOIL & VEGETATION
TOP SOIL
CONSTRUCTION PROCEDURES
![Page 25: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/25.jpg)
EXCAVATIONS (CUTS) IN OTHERTHAN ROCK (OTR) AND IN ROCK
CONSTRUCTION PROCEDURES
DRILL AND BLAST
OTR EXCAVATION
REMOVED BY SCRAPERSDOZERS, EXCAVATORS
ROCK EXCAVATION
REMOVED BY DRILLINGAND BLASTING, RIPPING,LOADING OUT BY TRUCKS
![Page 26: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/26.jpg)
PREPARED SUBSTRATE
WIN FILL MATERIAL (FROM CUTS OR IMPORTED)
TRANSPORT FILL TO SITE
SPREAD FILL ON PREPARED SUBSTRATE
COMPACT FILL WHILE CONTROLLING MOISTURE
EMBANKMENTS (FILLS)
TRIM TO PROFILE
CONSTRUCTION PROCEDURES
![Page 27: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/27.jpg)
CUT OUT BOX
PREPARED SUBSTRATE
PLACE AND COMPACT GRAVEL SUB-BASE
GRAVEL PAVEMENTS
ROLL BOX / PREPARE SUBGRADE
PLACE & COMPACT GRAVEL BASE
FINAL TRIM TO GRAVEL PAVEMENTS
CONSTRUCTION PROCEDURES
COMPACTED EMBANKMENT
![Page 28: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/28.jpg)
CONSTRUCTION PROCEDURES
GUARD RAILS
DELINEATOR POSTS(GUIDE POSTS)
MULCHING OR GRASSING TOSTABLISE BATTERS
COMPACT ASPHALTPLACE ASPHALT WEARING COURSE
WEARING SURFACE AND ROAD FURNITURE
COMPLETED EMBANKMENT& GRAVEL PAVEMENTS
![Page 29: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/29.jpg)
SLOPE PAVING / PROTECTION
SURFACE DRAINS
PLACE & COMPACT PAVEMENTS & WEARING COURSE
CONSTRUCTION PROCEDURESIN EXCAVATIONS (CUTS)
ROLL BOX / PREPARE SUBGRADEROAD FURNITURE
SUB-SURFACE DRAINS
CATCH DRAINS
![Page 30: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/30.jpg)
REINFORCED CONCRETE BASE
BOX CULVERTWING WALLS
POROUSBACKFILL
HIGHLY COMPACTEDBACKFILL
COMPACTED BACKFILL
EMBANKMENT FORMATION
Plan
Section(Through Watercourse)
STREAM
BOX CULVERTS
![Page 31: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/31.jpg)
Box culvert
![Page 32: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/32.jpg)
Mass haul diagram
• The mass haul diagram is an excellent method of analysing linear earthmoving operation.
![Page 33: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/33.jpg)
MASS HAUL• CALCULATE QUANTITIES FOR CUT AND FILL FOR
SEGMENTS TYPICALLY AT REGULAR INTERVALS (EVERY 50m OR 100m)
• FOR EACH SEGMENT CALCULATE QUANTITY CUT TO FILL WITHIN SEGMENT
• FOR EACH SEGMENT CALCULATE QUANTITY EXCESS CUT OR SHORTFALL FILL
• DETERMINE MOST EFFICIENT HAULS FOR CUT TO FILL OPERATION
• TYPES OF EQUIPMENT SHOULD BE CONSIDERED FOR ACCOMPLISHING THE WORK.
![Page 34: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/34.jpg)
MASS HAUL DIAGRAM
Chainage (m)
0-100
100-200
200-300
300-400
400-500
500-600
600-700
700-800
Totals
Cut (m3) 200 1000 3000 2000 0 100 1000 0 7300 m3
Fill (compacted Vol m3)
500 300 0 500 3500 3500 500 500 9300 m3
Fill (m3) 575 345 0 575 4025 4025 575 575 10695 m3
Cut to Fill<100m
200 345 0 575 0 100 575 0 1795 m3
Cut less Fill i.e Excess Cut +ve shortfall Fill -ve
-375 280 3280 4705 680 -3245 -2820 -3395
![Page 35: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/35.jpg)
MASS HAUL DIAGRAM (CONT.)
![Page 36: Week 8 - Road Construction 1](https://reader033.fdocuments.net/reader033/viewer/2022051215/563dbb74550346aa9aad4d4f/html5/thumbnails/36.jpg)
Balanced line
• A balanced line is a horizontal line of specific length that intersects the mass diagram in two places.
• The balance line can be constructed so that its length is the maximum haul distance for different types of equipment.