Whole Production Schedule for Rolling Rims Advert
Week Number
What needs doing? How will it be done? When will it be done?
126/1/15
Pre Production Paperwork.
Proposal budget and projected profit.
Web Banner Poster.
Working out a basic budget plan and an advanced budget plan once finalised plans have been made.Also create a MelonBurst web banner and poster.
15/2/15
22/2/15
Pre Production Paperwork.
Finish other script types.
Storyboards.Self promotion work
Business Card. Company
Brochure.
Creating a detailed storyboard ready for a folder to take to the filming locations.Also create a MelonBurst business card and company brochure.
15/2/15
39/2/15
Pre Production Paperwork.
Shot Lists.Self Promotion Work
Website
Using the storyboards create a detailed shot list ready for the production folder. Also create a website for Melonburst and complete any left over self promotion work needed to do.
15/2/15
416/2/15
Production Paperwork.
Location reports
Risk Assessments
Call Sheets
The risk assessments will need to include photographs of the business yard and potential risks/problems and how to solve.
15/2/15
523/2/15
Filming Weekend. Travelling to the yard and other filming locations to film the advert.
1/3/15
6 Uploading footage and Looking through all 8/3/15
2/3/15 Contingency Filming. filmed footage and sorting. If any extra shots need doing that will be done in this week.
79/3/15
Adding Motion graphics to clips.
Looking up tutorials and practising with different motion graphics to get the desired effect.
29/3/15
816/3/15
Adding Motion graphics to clips.
Practising motion graphics on more clips.
29/3/15
923/3/15
Adding Motion Graphics to clips.
Final say on the motion graphics.
29/3/15
1030/3/15
Editing other clips. Beginning to edit and colour correct final clips.
12/4/15
116/4/15
Editing other clips. Placing clips together and colour correcting.
12/4/15
1213/4/15
Placing clips together and rendering.
Colour correction completed and render.
19/4/15
1320/4/15
Contingency Week Completing any paperwork/editing that needs to be completed for hand in.
Hand in date28th APRIL 2015
1427/4/15
Contingency Week Completing any extra paperwork/editing that needs to be completed for hand in.
Hand in date28th APRIL 2015