Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1...

18
Partnering with clients to achieve excellence in design WUSD PROJECT 1- Board Schematic Design Presentation Weaver Union School District December 11, 2013

Transcript of Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1...

Page 1: Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1 SCHEMATIC DESIGN PRESENATION Weaver Middle School Site Plan E CHILDS AVE T 1. Campus

Partnering with clients to achieve excellence in design

WUSD PROJECT 1- Board Schematic Design Presentation

Weaver Union School District

December 11, 2013

Page 2: Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1 SCHEMATIC DESIGN PRESENATION Weaver Middle School Site Plan E CHILDS AVE T 1. Campus

Page 2

Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1

SCHEMATIC DESIGN PRESENATION

Weaver Middle School Site Plan

E CHILDS AVE

S C

OFF

EE S

T

1. Campus Gateway 2. New Classroom Wing 3. District Office 4. Modernized Classrooms 5. Modernized Administration 6. Multi-use Renovation 7. Portables to Remain 8. Relocated Portable

9. New Dropoff & Parking 10. New Bus Dropoff 11. New Courtyard 12. New Hardcourts 13. Resurface Hardcourt 13. Existing MOT 14. Existing Hardcourt

14

S C

OFF

EE S

T

E CHILDS AVE

1

2

2

3

3

5 6

4

4

4

4

4

4

4 4

7 7

7 7

9

10

11

12

13

8

4 7 7

7 7

15

Page 3: Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1 SCHEMATIC DESIGN PRESENATION Weaver Middle School Site Plan E CHILDS AVE T 1. Campus

Page 3

Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1

SCHEMATIC DESIGN PRESENATION

Weaver Middle School Add Alt Site Plan

1. Campus Gateway 2. New Classroom Wing 3. District Office 4. Modernized Classrooms 5. Modernized Administration 6. Multi-use Renovation 7. Portables to Remain 8. Relocated Portables

9. New Dropoff & Parking 10. New Bus Dropoff 11. New Courtyard 12. New Hardcourts 13. Resurface Hardcourts 14. Repair Athletic Fields 15. New Parking

14

S C

OFF

EE S

T

E CHILDS AVE

1

2

2

3

3

5 6

4

4

4

4

4

4

4

4

4

7 7

7 7

7 8 8 8 8

9

10

11

12

12

13 15

Page 4: Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1 SCHEMATIC DESIGN PRESENATION Weaver Middle School Site Plan E CHILDS AVE T 1. Campus

Page 4

Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1

SCHEMATIC DESIGN PRESENATION

Weaver Middle School Phase Plan

E CHILDS AVE

Phase 1- June 2015/Sept 2015 • Repurpose Buildings B & C for District

Administration • Bus dropoff loop

Phase 2- June 2015/Dec2016 • New Campus Gateway • New Classroom Wings • New Parking & Drop-off • New Courtyard • Demolish Parking Lot, Replace with New

Hardcourt • Improve Hardcourts • Remove Portables 1-3, 5-9 • Relocate Portable 4 • Demolish District Office- Building A • Demolish Pump House- Building N

Phase 3- Jan 2016/July 2016 • Modernize Buildings D-F, H-M

Phase 4- June 2016/Aug 2016 • Modernize Central Administration • Multi-use Renovation

Phase 4 Additive Alternate- June 2016/Aug 2016 1. Relocate Portables 14, 15 & 16 2. New hardcourt 3. Repair of existing athletic fields 4. Demolish Maintenance, Operation and

Transportation (MOT) facility 5. Resurface parking lot 6. Repair Athletic Fields North of MOT

PHASE 2

PHASE 4 ADD ALT

PHASE 3

PHASE 3

PHASE 1

PHASE 1

PHASE 4

S C

OFF

EE S

T

2

4 ALT

Page 5: Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1 SCHEMATIC DESIGN PRESENATION Weaver Middle School Site Plan E CHILDS AVE T 1. Campus

Page 5

Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1

SCHEMATIC DESIGN PRESENATION

Weaver Middle School Phase 1

E CHILDS AVE

1

Phase 1- June 2015/Sept 2015

1. Repurpose Buildings B

2. Repurpose Building C for the District Server & Psychology office

3. Bus dropoff loop

S C

OFF

EE S

T

3

2

Page 6: Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1 SCHEMATIC DESIGN PRESENATION Weaver Middle School Site Plan E CHILDS AVE T 1. Campus

Page 6

Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1

SCHEMATIC DESIGN PRESENATION

District Office Relocation Classrooms 1-4

classroom classroom classroom classroom

utility utility

Page 7: Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1 SCHEMATIC DESIGN PRESENATION Weaver Middle School Site Plan E CHILDS AVE T 1. Campus

Page 7

Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1

SCHEMATIC DESIGN PRESENATION

District Office Relocation Classrooms 5-8

Classroom 5 Classroom 6 Classroom 7 Classroom 8

utility utility

Classroom 5 Classroom 6 Psychology Office

Server Room

utility utility

Office

Work Room

EXISTING CLASSROOM WING

RENOVATED CLASSROOM WING

Page 8: Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1 SCHEMATIC DESIGN PRESENATION Weaver Middle School Site Plan E CHILDS AVE T 1. Campus

Page 8

Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1

SCHEMATIC DESIGN PRESENATION

8

Phase 2- June 2015/Dec2016 1. New Campus Gateway 2. New Classroom Wings 3. New Parking & Drop-off 4. New Courtyard 5. Demolish Parking Lot, Replace with New Hardcourt 6. Improve Hardcourts 7. Remove Portables 1-3 & 5-9 8. Relocate Portable 4 9. Demolish District Office- Building A 10. Demolish Pump House- Building N

Weaver Middle School Phase 2 Plan

1

2

2 3

4

5

6

Page 9: Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1 SCHEMATIC DESIGN PRESENATION Weaver Middle School Site Plan E CHILDS AVE T 1. Campus

Page 9

Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1

SCHEMATIC DESIGN PRESENATION

Campus Gateway CAMPUS ENTRY & SCHOOL ADMINISTRATION

Covered

Covered

Page 10: Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1 SCHEMATIC DESIGN PRESENATION Weaver Middle School Site Plan E CHILDS AVE T 1. Campus

Page 10

Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1

SCHEMATIC DESIGN PRESENATION

Childs Avenue Classroom Wing

1 1 1 1 1 1

2 3

5 4

1. Classroom - 960 2. Girls restroom 3. Boys restroom

4. Staff – Women’s restroom 5. Staff – Men’s restroom

2 3

5 4

1 1 1 1 1 1

Additive Alternatives

Page 11: Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1 SCHEMATIC DESIGN PRESENATION Weaver Middle School Site Plan E CHILDS AVE T 1. Campus

Page 11

Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1

SCHEMATIC DESIGN PRESENATION

Coffee Street Classroom Wing

1 1 1 1 2 2 7

8 8

7 3 4

5 6

1. Classroom - 960 SF 2. Lab - 1200 SF 3. Girls restroom 4. Boys restroom

5. Staff - Women’s restroom 6. Staff - Men’s restroom 7. Lab Storage - 200 SF 8. Utility closet

3 4

5 6

2

8

7

2 7

8

1 1 1 1

Additive Alternatives

Page 12: Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1 SCHEMATIC DESIGN PRESENATION Weaver Middle School Site Plan E CHILDS AVE T 1. Campus

Page 12

Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1

SCHEMATIC DESIGN PRESENATION

ADDITIVE ALTERNATIVES MATERIAL & POP-OUT ALTERNATIVES

With Additive Alternatives

Without Additive Alternatives

UPDATE 3d IMAGE

Page 13: Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1 SCHEMATIC DESIGN PRESENATION Weaver Middle School Site Plan E CHILDS AVE T 1. Campus

Page 13

Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1

SCHEMATIC DESIGN PRESENATION

Inside the Classroom STAFF RECOMMENDATIONS

• 40’ of Magnetic Dry Erase Boards

• Projector Screen

• Low built in storage & teacher wardrobe

• Tack board walls

• Carpet floors

• Ceiling mounted Projector (NIC)

• Teacher desk (NIC)

• Flexible furniture (NIC)

• Amplified sound systems (NIC)

• Window shades (NIC)

* The image above is showing both views of a single classroom

Page 14: Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1 SCHEMATIC DESIGN PRESENATION Weaver Middle School Site Plan E CHILDS AVE T 1. Campus

Page 14

Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1

SCHEMATIC DESIGN PRESENATION

Weaver Middle School Phase 3

Phase 3- Jan 2016/July 2016

• Modernize Classroom Wings 3. Building 3- Exterior paint 4. Building 4- Exterior paint 5. Building 5- Exterior paint 6. Building 6- Exterior paint 7. Building 7- Exterior paint 8. Building 8- Exterior paint 9. Building 9- Exterior paint 10. Building 10- Add second exit, repair roof at storage shed in back, add

power and data, interior paint, provide acoustical ceiling in room, provide acoustical paneling, provide new carpet, exterior paint.

11. Covered walk- Slip resistant treatment (bead blast) 12. P10- Exterior paint 13. P11- Exterior paint 14. P14- Exterior paint 15. P15- Exterior paint 16. P16- Exterior paint 17. P17- Exterior paint 18. P18- Exterior paint 19. P19- Exterior paint * Other repairs and upgrades as budget allows

3

4

5

6

7

8

9

10

11

12 13

14 15

16 18 17

19

Page 15: Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1 SCHEMATIC DESIGN PRESENATION Weaver Middle School Site Plan E CHILDS AVE T 1. Campus

Page 15

Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1

SCHEMATIC DESIGN PRESENATION

Weaver Middle School Phase 4

Phase 4- June 2016/Aug 2016

1. Modernize Central Administration- Hazmat abatement; demolition of existing walls, doors, casework, utilities and HVAC ductwork / registers; new full height walls, new restrooms, new doors and windows, new casework, new ceilings, new exterior and interior paint and interior finishes, new lighting, new utilities, data, communications, IT, fire alarm, remodeled / new HVAC ductwork/registers.

2. Multi-use Renovation - Hazmat abatement; demolition of existing boys and girls shower walls, utilities and HVAC ductwork / registers; installation of new lockers, new ceilings, new exterior and interior paint and interior finishes, new lighting, new utilities, remodeled / new HVAC ductwork/registers. New Multi-use Room flooring; new accessible lift to Stage

1 2

Page 16: Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1 SCHEMATIC DESIGN PRESENATION Weaver Middle School Site Plan E CHILDS AVE T 1. Campus

Page 16

Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1

SCHEMATIC DESIGN PRESENATION

Central Administration Modernization

Page 17: Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1 SCHEMATIC DESIGN PRESENATION Weaver Middle School Site Plan E CHILDS AVE T 1. Campus

Page 17

Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1

SCHEMATIC DESIGN PRESENATION

Weaver Middle School Phase 4

Phase 4 ADD ALT- June 2016/Aug 2016 1. Relocate Portables 14, 15 & 16 2. New hardcourt 3. Repair of existing athletic fields 4. Demolish Maintenance, Operation and Transportation (MOT) facility 5. Resurface parking lot 6. Repair Athletic Fields North of MOT

1

2

3

4

5

6

1 1

Page 18: Weaver Union School District · Page 2 Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1 SCHEMATIC DESIGN PRESENATION Weaver Middle School Site Plan E CHILDS AVE T 1. Campus

Page 18

Weaver Union School District WEAVER MIDDLE SCHOOL- PROJECT 1

SCHEMATIC DESIGN PRESENATION

*NOTE: ALL OFFSITE & ONSITE UTILITIES (WATER, SEWER, SITE LIGHTING, POWER UPGRADES, ETC.) NOT FIGURED IN BUDGET AS CFW INDICATED THAT ADDITIONAL GRANTS ARE TO FUND THESE PORTIONS OF WORK