Wayne Salter, CERN IT-CO JCOP Roadmap JCOP External Review 10 th -12 th March 2003.
-
Upload
godwin-bryan -
Category
Documents
-
view
213 -
download
0
Transcript of Wayne Salter, CERN IT-CO JCOP Roadmap JCOP External Review 10 th -12 th March 2003.
Wayne Salter, CERN IT-CO
JCOP Roadmap
JCOP External Review10th-12th March 2003
22W. Salter JCOP External Review 10th-12th March 2003
OverviewCurrent situation and approach
On-going activitiesNew activitiesLooking forwardMajor milestones and resources
Summary
33W. Salter JCOP External Review 10th-12th March 2003
Current Situation CERN resources, both financial and
manpower, are continuing to decline In such an environment common
projects are very importantReduce overall development effortEase maintenance
Common projects imply some level of compromiseOnly activities which are required for the
majority of the experimentsJCOP works via consensus
44W. Salter JCOP External Review 10th-12th March 2003
ApproachEssentially to continue the approach adopted up-
to-now: Commercial solutions where possible
Reduce resources Ease maintenance
Where custom solutions are required Agreed support and maintenance concept (includes proper
documentation) Monitor work of other domains and collaborate
(where appropriate) to benefit from their work: Controls Board – standardisation at CERN and exchange
information with other controls domains, e.g. LHC/CPLHC Data Interchange Working Group (LDIWG) - DIPSASG - PVSS developments
LHC Cryogenics - UNICOS Computer Centre Supervision Project - Computer/process
monitoring
55W. Salter JCOP External Review 10th-12th March 2003
On-going Activities Complete current activities:
Provide the basic building blocks required by all experiments
Enhance the building blocks based on feedback from the sub-detector teams
Ensure that the documentation is appropriate Majority of key components (prototype)
should be available in 2003 Continue to clarify/agree the interaction
with external systems:Conditions and configuration databasesElectrical distribution, JCOV, magnet control, etc.DCS interfaces with rest of the experiment not part
of JCOP; but will there be any impact?
66W. Salter JCOP External Review 10th-12th March 2003
Sub-detector Interaction
Sub-detectors are now increasingly looking into controls issuesThis year’s test-beam campaigns are seen as crucialCollaboration with IT-CO contact people
Get sub-detectors using the technology in preparation for developing their final solutions
Tutorials/training for the JCOP componentsBasic PVSS and FW tutorials already existTraining courses exist for PVSS and the FW
Test technologies in an experiment environmentRefine experiment requirementsBetter tailor solutions to the needs of the experimentsValidate the technology
77W. Salter JCOP External Review 10th-12th March 2003
Future Activities - I Review of DSS prototype and agree on
implementation strategy and piquet Develop and agree the maintenance
concept for JCOP components and toolsGenerally accepted that this should be handled by
support groupsMust ensure that resources requirements are
known and availableHow do we maintain the required expertise?
Short-term versus long-term staffDevelopment versus pure maintenance
Support and maintenance for PVSS, OPC, PLCs and field buses already in place
88W. Salter JCOP External Review 10th-12th March 2003
Future Activities - II Propose strategy for configuration, operation
and maintenance of large PVSS distributed systems Scaling up PVSS project Discussions with ETM
Security (remote access) and networking (use of technical network?)
Continue to work with companies providing common technologies to enhance them, e.g. ETM for PVSS CAEN ISEG Wiener
Installation and monitoring of DCS computers (CCSP and LCG?)
99W. Salter JCOP External Review 10th-12th March 2003
Looking forward Are there other areas where
common solutions would be beneficial?The higher in the control system the more
commonality is possibleNonetheless experiments should try to
achieve as much commonality as possible even at the lower levels
As we move towards final systems the time is running out for defining new common items
1010W. Salter JCOP External Review 10th-12th March 2003
Major milestones for 2003
RCS Specification of PCB available 3rd quarter
DSS Prototype completed and review 2nd quarter Initial CMS system end of 3rd quarter Initial LHCb system 4th quarter
GCS ALICE TPC GCG completed in 2nd quarter with commissioning
in 3rd/4th quarter FW design completed in 3rd quarter
FW Prototypes for configuration and data storage and retrieval,
ISEG PS 2nd quarter Access control, mass configuration and web access 3rd
quarter 1st version for configuration, and data storage and retrieval
4th quarter
1111W. Salter JCOP External Review 10th-12th March 2003
Major milestones for 2004/2005
RCSSystem available as stores item early 2004
GCSFW completed in 1Q2004Instances 2004-2006
DSSInitial systems for ATLAS and ALICE in 2004Final systems for all experiments 2006
FWRCS, DIP interface, improved alarm reporting,
update of configuration and data storage and retrieval tools 2004
Interface to histogramming tool 2005
1212W. Salter JCOP External Review 10th-12th March 2003
Resource Situation Project resources from IT-CO and EP-ESS Many temporary staff
Lack of continuity Investment in training
In kind contributions from the experimentsSupport and maintenance
Just keeping our heads above waterAssuming we can maintain the current level of
resources Still to be addressed:
Resources for the implementation of the 23 gas control systems
Specialised support for DSSLong-term maintenance
1414W. Salter JCOP External Review 10th-12th March 2003
Summary
The more done by JCOP the easier is the task of the experiments
JCOP is one of the few, and earliest, common projects
Experiment approaches are differentBut still possible to deliver common
components
Maintenance still an issue long-termStrategy needs to be defined
Resources are at best very tight