Watts Bar Unit 2 Startup Simulations with VERA 1-03 Godfrey... · Watts Bar Unit 2 Startup...

26
Watts Bar Unit 2 Startup Simulations with VERA John Ritchie Tennessee Valley Authority Andrew Godfrey Oak Ridge National Laboratory Joint IC/SC Meeting Oak Ridge National Laboratory October 11, 2016

Transcript of Watts Bar Unit 2 Startup Simulations with VERA 1-03 Godfrey... · Watts Bar Unit 2 Startup...

Watts Bar Unit 2 StartupSimulations with VERA

John RitchieTennessee Valley Authority

Andrew GodfreyOak Ridge National Laboratory

Joint IC/SC MeetingOak Ridge National LaboratoryOctober 11, 2016

2

– Dec. 2015 – Fuel Load– May 23, 2016 – Initial criticality– June 3, 2016 – On the grid

Watts Bar Nuclear Plant – Unit 2

• First new nuclear plant in U.S. since 1996 (WB1)

• Traditional four-loop Westinghouse PWR

• 3411 MWth initial rated thermal power

• Current burnup: ~30 EFPD

Image courtesy of TVANotable Dates:

3

WBN2 Cycle 1 Design• 193 Westinghouse RFA2

17x17 fuel assemblies– 12’ active fuel height– IFM spacer grids

• Three enrichment regions– 2.1%, 2.6%, 3.1%

• Low enriched 6” axial blankets• IFBA/WABA burnable poisons• ~400 EFPD cycle length

Radial Slice through WBN1 Reactor Vessel

17x17 Assembly Layout with IFBA and WABA

Images courtesy of TVA

5

Power Ascension Testing

6

Power History for PAT

Turbine generatorcoupling making excessive noise (5/28/2016)

Automatic trip and safety injection on steam pressure low (6/5//2016)

Automatic trip from Lo-Lo level in number 4 steam generator(6/20/2016)

Planned 10% load rejection

Manual trip due to low steam generator levels caused by a loss of feedwater flow from mainfeedwater pump (8/23/2016)

Planned loss of offsitepower trip from 30% (7/14/2016)

Loss of bushingcooling due to excessive hydrogen leak, unable to exceed 75% power

Turbine trip from a main bank transformer failure (8/30/16)

50% load rejection

Turbine trip (6/26/2016)

Planned trip from outside of MCR (8/3/2016)

8

VERA Methods• MPACT

– 2D/1D deterministic neutron transport based on MoC/SP3

– 47g ENDF/B-VII.0 subgroup library– 50 axial planes in the fuel/ 58 tota l– 4,234 parallel spatial domains

• COBRA-TF– Two phase coolant T/H – 14,000 channels– Cross flow between channels– 193 parallel domains (4 per assembly)

• ORIGEN– Explicit isotopic depletion and decay– 263 isotopes in 1.9 million regions

• BISON– Volume average full temperature tables as a functions of power

and burnup

• SHIFT (BOC HZP only)– Continuous-energy Monte Carlo neutron transport– Doppler broadening and thermal scattering treatments– Massively parallel demonstrated up to 300,000 processors

HZP BOC Fission Rate Distribution in WB2 (quarter core)

10

0.6% 0.8%

3.1%

-0.7%

3.1%

0.8% 1.0%

-0.7%

0.9%

-10%

-8%

-6%

-4%

-2%

0%

2%

4%

6%

8%

10%

D C B A SD SC SB SA Total

Bank

Wor

th D

iffer

ence

(%)

RCCA Bank

Startup Results*Measured MPACT

DifferenceShift

DifferenceInitial Critical Boron Concentration (ppmB) 1089 -14 -2

Isothermal Temperature Coefficient (pcm/ºF) -5.31 -0.15 --

Total Worth Error < 1%

*Measurements courtesy of TVA

Control Bank Worths

11

Miscellaneous Evaluations• Applications of VERA providing higher fidelity

capabilities than current methods

Effects of Primary and Secondary Source Rods On Full Core Radial Power Distribution in WBN2

Fission distribution for shutdown margin calculation, All-Rods-In + Worst Stuck Rod Out

12

Power Ascension Testing• Power escalation began May 23, 2016• Plan requires ~90 days from criticality to commercial

operations• TVA has provided power history data and measurements• VERA has been used to follow the startup procedure with

hourly statepoints• Oak Ridge Leadership Computing Facility has supported

all calculations over the last 3½ months with priority on Eos supercomputer

• Comparisons to measured data have included:– Critical boron concentrations at operating conditions– Subsequent critical conditions after shutdowns– Measured neutron flux distributions at certain checkpoints

The Largest Simulation Ever Performed by CASL!

13

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

5/23 5/30 6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12

Core

Pow

er L

evel

(%)

Date

Power History

Measured Power Distributions

~2750 hours total

14

Bank D History

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0

23

46

69

92

115

138

161

184

207

230

5/23 5/30 6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12

Core

Pow

er (%

)

Bank

D P

ositi

on (S

teps

With

draw

n)

Date

15

Inlet Temperature History

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

530

535

540

545

550

555

560

565

570

575

580

5/23 5/30 6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12

Core

Pow

er (%

)

Inlet

Tem

pera

ture

(F)

Date

16

Zero Power Criticality Measurements • Criticality Measurements taken at HZP conditions

following shutdowns• Include various Bank D positions and transient Xenon-135

conditions

-14 -16 -17 -17-20 -20

-22-18

-2-6 -7 -6

-9 -9-12

-8

-50

-40

-30

-20

-10

0

10

20

30

40

50

1 2 3 4 5 6 7 Average

Criti

cal B

oron

Diff

eren

ce (p

pmB)

Criticality

MPACT

SHIFT

17

Boron Concentrations

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

650

700

750

800

850

900

950

1,000

1,050

1,100

1,150

5/23 5/30 6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12

Core

Pow

er (%

)

Solu

ble B

oron

Con

cent

ratio

ns (p

pmB)

Date

18

Boron Concentrations

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

650

700

750

800

850

900

950

1,000

1,050

1,100

1,150

5/23 5/30 6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12

Core

Pow

er (%

)

Solu

ble B

oron

Con

cent

ratio

ns (p

pmB)

Date

Measured

VERA

19

Boron Concentration Differences

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

-50

-40

-30

-20

-10

0

10

20

30

40

50

5/23 5/30 6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12

Core

Pow

er (%

)

Solu

ble B

oron

Con

cent

ratio

ns D

iffer

ence

s (pp

mB)

Date

Boron Difference = -19 +/- 8 ppmHZP Bias = -18 ppm

20

Xe-135 Concentration

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0.E+00

1.E-09

2.E-09

3.E-09

4.E-09

5.E-09

6.E-09

5/23 5/30 6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12

Core

Pow

er (%

)

Core

Ave

rage

Xen

on-1

35 C

once

ntra

tion

Date

21

Sm-149 Concentration

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0.E+00

5.E-09

1.E-08

2.E-08

2.E-08

3.E-08

3.E-08

4.E-08

5/23 5/30 6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12

Core

Pow

er (%

)

Core

Ave

rage

Sam

ariu

m-1

49 C

once

ntra

tion

Date

22

Np-239 Concentration

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0.E+00

1.E-07

2.E-07

3.E-07

4.E-07

5.E-07

6.E-07

7.E-07

8.E-07

9.E-07

5/23 5/30 6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12

Core

Pow

er (%

)

Core

Ave

rage

Nep

tuni

um-2

39 C

once

ntra

tion

Date

23

Pu-239 Concentration

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0.E+00

1.E-06

2.E-06

3.E-06

4.E-06

5.E-06

6.E-06

7.E-06

8.E-06

5/23 5/30 6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22 8/29 9/5 9/12

Core

Pow

er (%

)

Core

Ave

rage

Plu

toni

um-2

39 C

once

ntra

tion

Date

24

Measured Power Distributions(in progress)

• 88% Power Map• 5 level vanadium

detectors• 2 segments flagged

as inoperable

25

Preliminary Radial Power Comparison

MPACT – Measured Axial Integrated Instrument Responses

Radial RMS = 2.9%

R P N M L K J H G F E D C B A

1 3.1% 2.4%

2 1.8% -1.1% -3.3%

3 1.5% 1.8% 2.3% 1.6%

4 3.4% 2.2% -1.3%

5 -3.1% -3.0% -2.0% -1.6%

6 2.7% 4.2% -4.4% -3.9% -3.7%

7 2.1% -3.1% 0.7% -4.4%

8 4.4% 2.6% 1.0% 0.6% -3.6% -3.4% 0.2% -5.6%

9 5.2% -1.4% -3.7% 0.1%

10 0.8% 2.2% -7.0%

11 2.7% -2.1% 0.7% -4.0% 0.2%

12 -1.7% 2.8% -1.8%

13 3.5% -1.0% 1.4% 0.3%

14 2.3% 3.2% -1.6% 2.2%

15 2.6% 3.0%

R P N M L K J H G F E D C B A1 0.6% 1.8%

2 2.4% 0.1% -2.9%

3 1.7% 2.9% 4.0% 1.8%

4 5.3% 4.4% -0.6%

5 -0.6% -1.4% 0.0% 0.3%

6 2.3% 5.8% -2.8% -2.4% -4.1%

7 3.1% -2.0% 0.5% -4.7%

8 2.7% 2.9% 1.4% 0.5% -3.1% -4.3% -1.1% -7.6%

9 4.9% -1.2% -4.0% -4.0%

10 1.2% 1.8% -7.5%

11 1.5% -0.3% -0.2% -4.4% -2.3%

12 -0.8% 1.5% -2.1%

13 5.5% 0.5% 0.0% -0.8%

14 2.3% 1.7% -3.4% 2.0%

15 0.9% 0.2%

BEACON – Measured Radial Shape

1st Flux Map26.7% power

In progress

26

COBRA-TF Solution @ 88% Power

Coolant Temperatures (shown at core exit) calculated by COBRA-TF for the 88% power map

27

VERA Runtime Performance• Each quarter-core calculation has used 4234 cores on

OLCF’s Eos supercomputer

• Currently completed:– 27 jobs– 2,429 hourly statepoints– 14,163 complete MPACT/CTF converged iterations– 11.6 days walltime– 1.2 million core-hours (33 years on my laptop!)– ~7 mins per statepoint

OLCF’s TITAN Supercomputer at Oak Ridge National Laboratory

28

Acknowledgements• ORNL

– Ben Collins– Cole Gentry– Ron Lee– Shane Stimpson– OLCF (Eos)

• TVA– Kathleen Cunningham– John Ritchie

• Westinghouse– Fausto Franceschini– David Salazar– Vefa Kucukboyaci

• INL– High Performance Computing (Falcon)

Leveraging CASL partnerships for this unique opportunity