Water and Wastewater Servicing Assessment and Wastewater Servicing Assessment Final Report Prepared...
Transcript of Water and Wastewater Servicing Assessment and Wastewater Servicing Assessment Final Report Prepared...
Tremaine Road Secondary Plan Water and Wastewater Servicing Assessment Final Report
Prepared for: Region of Halton Prepared by: AECOM Canada Limited 105 Commerce Valley Drive West Markham, Ontario L3T 7W3 September 2009 Project No 105443
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page ii
Table of Contents
1 INTRODUCTION..............................................................................................................................................3 1.1 PURPOSE ..................................................................................................................................................3 1.2 SCOPE OF WORK .........................................................................................................................................4
2 MODELLING METHODOLOGY ..................................................................................................................5 2.1 POPULATION ALLOCATION AND DEMAND CALCULATION FOR THE TREMAINE ROAD DEVELOPMENT .........5 2.2 WATER DEMANDS AND SEWAGE LOADS CALCULATION .............................................................................6 2.3 HYDRAULIC IMPACT ASSESSMENT BASIS .................................................................................................8
2.3.1 Water System .........................................................................................................................................8 2.3.2 Sanitary System......................................................................................................................................8
3 HYDRAULIC MODELLING ANALYSIS AND RESULTS .........................................................................8 3.1 WATER SYSTEM...........................................................................................................................................8
3.1.1 External Servicing Plan .........................................................................................................................8 3.1.2 Internal Servicing Plan..........................................................................................................................9 3.1.3 Water System Hydraulic Analysis Results ...........................................................................................10 3.1.4 Water Storage Requirement (Zone 3) ..................................................................................................12 3.1.5 Water Treatment Plan Capacity ..........................................................................................................12 3.1.6 Water Infrastructure Interconnection between Tremaine Road and North Oakville West ..................13
3.2 WASTEWATER SYSTEM..............................................................................................................................13 3.2.1 External Servicing Plan .......................................................................................................................13 3.2.2 Internal Servicing Plan........................................................................................................................14 3.2.3 Wastewater System Hydraulic Analysis Results ..................................................................................15 3.2.4 Mid Halton Treatment Plant Capacity.................................................................................................16 3.2.5 Wastewater Infrastructure Interconnection between Tremaine Road and North Oakville West .........17
4 DEVELOPMENT CHARGES IMPACT.......................................................................................................18 4.1 WATER SYSTEM ........................................................................................................................................18 4.2 WASTEWATER SYSTEM..............................................................................................................................18
5 CONCLUSIONS & RECOMMENDATIONS ..............................................................................................19 5.1 WATER SYSTEM ........................................................................................................................................19 5.2 WASTEWATER SYSTEM..............................................................................................................................20
APPENDICES
I ROAD DEVELOPMENT LAYOUTS II INTERNAL WATERMAIN SIZING III CALCULATION INFORMATION IV DETAILED HYDRAULIC ANALYSIS RESULTS V AREA SERVICING PLAN REGIONAL REQUIREMENTS
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 3
1 INTRODUCTION 1.1 PURPOSE AECOM was retained by the Regional Municipality of Halton (RMOH) to undertake a hydraulic
analysis for both the water system and the sanitary sewer system for a proposed development
referred to as Tremaine Road as shown in Figure 1.1.
Figure 1.1 – Proposed Development Area
The purpose of the hydraulic analyses was to evaluate the serviceability of the proposed
development via existing and proposed infrastructure in the RMOH’s water distribution system
and sanitary sewer system. This report presents the results of the hydraulic analyses
undertaken for the water distribution system and reports on the available pressure under
different options of development landuse demand conditions as well as during fire flow
conditions for the proposed development. This report also presents the results from the
hydraulic analysis performed on the sanitary system and reports on the available capacity for
different options of the proposed development landuse as well as identifying infrastructure
deficiencies and improvement works required to accommodate additional loading associated
with the proposed development.
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 4
To perform the hydraulic analysis, AECOM used the recently updated hydraulic models.
AECOM had previously completed model updates for the RMOH in 2006/2007. These models
were developed in InfoWater for the water system and in InfoSewer for the sanitary system.
1.2 SCOPE OF WORK Based on discussions with the Regional Municipality of Halton, the following tasks were to be
completed as part of this study:
Review the latest Water and Wastewater Master Plan and incorporate planned infrastructure
into the hydraulic models.
Calculate sanitary sewer loads and water demands for the entire Region of Halton
(excluding the communities of Georgetown and Acton) based on the projected population
information provided and the RMOH’s water consumption rate and wastewater sewage
generation rate design criteria.
Calculate water demands and sewage loads for each of the three different landuse
development options within the Tremaine Road development. Demand/load conditions were
not calculated for the intermediate build out condition since no information was provided for
an interim design year.
Propose specific watermain and sewermain sizes for each landuse development option
within Tremaine Road development site.
Perform hydraulic analyses for both water and wastewater systems and identify additional
infrastructure requirements (if any) within the existing systems and which would be triggered
by the Tremaine Road development.
Perform a fire flow analysis based on the Region’s design criteria on the water distribution
mains within the Tremaine Road development boundary.
Prepare a Technical Memorandum to summarize the methodology, the results of the
analyses and provide conclusions.
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 5
2 MODELLING METHODOLOGY In performing the hydraulic analyses, the general methodology followed is described below:
Reviewed the South Halton Master Plan to identify future infrastructure planned within
the water and wastewater systems, and incorporated this infrastructure into the model.
Allocated future (2021) Traffic Zone population to the demand nodes and loading
manholes in the water system and wastewater system respectively. The Traffic Zones
within the Tremaine Road development area were excluded from this process because
more detailed population number used for this development area.
Undertook hydraulic analyses for three different internal servicing
watermains/sewermains infrastructure within Tremaine Road development area as per
the three landuse development options provided by the Steering Committee and
incorporated them into the hydraulic models
Calculated future (2021) Average Day, Maximum Day, and Peak Hour water demand
and peak wastewater load conditions based on the Region of Halton’s Master Plan
Design Criteria for the entire Region of Halton and for the three different landuse
options.
Performed hydraulic analyses to assess system serviceability.
2.1 POPULATION ALLOCATION AND DEMAND CALCULATION FOR THE TREMAINE ROAD DEVELOPMENT
The projected population data and proposed development layout for three different landuse
options within the Tremaine Road area were provided to AECOM by the RMOH and other
stakeholders. The three servicing options assessed are as below:
1. Option 1: Employment Option
2. Option 2: Residential Option
3. Option 3: Mixed Use Option
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 6
The available population information is summarized in Table 2.1 while the road and
development layouts for each option are presented in Appendix I. Table 2.1 – Tremaine Road Population Figures
Option Landuse Total Area (Ha)
Equivalent Population
Density (Persons/Ha)
Total Equivalent Population
Option 1 Employment 23.9 1,050 43.9 1,050 Residential 18.7 2,398 128.2 Option 2
Employment 2.5 120 48.0 2,518
Residential 5.8 1,277 220.2 Option 3 Employment 9.8 540 55.1
1,817
2.2 WATER DEMANDS AND SEWAGE LOADS CALCULATION Based on the allocated population numbers, the water demands and sanitary loads at each
junction were then calculated based on the RMOH’s Master Plan Design Criteria for the water
system and wastewater system respectively presented in Table 2.2a and Table 2.2b.
Table 2.2a - Water System Master Plan Design Criteria
Landuse Rates Unit Max Day Factor
Peak Hour Factor
Residential 330 lpcd Industrial 302 lpcd Commercial 213 lpcd Institutional 74 lpcd
1.9 3
Fire Flow Residential 5,500 l/min Industrial/Commercial/Institutional 15,000 l/min
Table 2.2b – Wastewater System Master Plan Design Criteria
Landuse Rates Unit Residential 365 lpcd Industrial 410 lpcd Commercial 260 lpcd Institutional 135 lpcd Inflow/Infiltration
Milton 0.24-1(1) l/ha/s Oakville Southwest 0.4-3(1) l/ha/s Burlington 0.35-0.65(1) l/ha/s Other 0.286(2) l/ha/s
(1) Highest rates were applied to the system (2) Regional design criteria
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 7
It should be noted that the Region of Halton’s design criteria for residential average Dry
Weather Flow (DWF) is 275 lpcd. The 365 lpcd residential rate stated in the Master Plan Update
is used when assessing the treatment plant capacity. Nevertheless, this rate was still used in
this study in order to adopt a conservative approach.
In order to calculate the peak DWF, a peaking factor was applied to the Average DWF. The
Harmon formula was utilized to calculate the peaking factor, and a minimum peaking factor of 2
was applied as per MOE Design Guideline. The estimated water demands and wastewater
loads for the proposed development area in Tremaine Road are shown in Table 2.3a and Table 2.3b.
Table 2.3a – Estimated Water Demand Within Tremaine Road Development
Water Demand Option Landuse Total Area
(Ha) Population Avg Day (L/s)
Max Day (L/s)
Peak Hour (L/s)
Option 1 Employment (1) 23.9 1,050 3.7 7.0 11.0 Residential 18.7 2,398 9.2 17.4 27.5 Employment (1) 2.5 120 0.4 0.8 1.3 Option 2 Subtotal 21.2 2,518 9.6 18.2 28.8 Residential 5.8 1,277 4.9 9.3 14.6 Employment (1) 9.8 540 1.9 3.6 5.7 Option 3 Subtotal 15.6 1,817 6.8 12.9 20.3
(1) Industrial water consumption rate and sanitary loading rate was used for more conservative results
Table 2.3b – Estimated Wastewater Load Within Tremaine Road Development
Wastewater Load
Option Landuse Total Area (Ha) Population Avg
DWF (L/s)
Peak DWF (L/s)
I/I (L/s)
Peak WWF (L/s)
Option 1 Employment (1) 23.9 1,050 5.0 18.9 6.8 25.7 Residential 18.7 2,398 10.1 35.5 5.3 40.9 Employment (1) 2.5 120 0.6 2.0 0.7 2.7 Option 2 Subtotal 21.2 2,518 10.7 37.5 6.0 43.6 Residential 5.8 1,277 5.4 19.5 2.0 21.6 Employment (1) 9.8 540 2.6 9.3 3.0 12.3 Option 3 Subtotal 15.6 1,817 8.0 28.8 5.0 33.9
(1) Industrial water consumption rate and sanitary loading rate was used for more conservative results
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 8
2.3 HYDRAULIC IMPACT ASSESSMENT BASIS 2.3.1 Water System The hydraulic analysis results were assessed in accordance with the water distribution design
guidelines provided by the Ministry of the Environment (MOE). As stated in the MOE Guidelines,
water supply systems should be designed to satisfy the greater of either of a Maximum Day plus
Fire Flow demand condition, or a Peak Hour (maximum hourly) demand condition. Fire flow
varies with municipality and the nature of the development. For the purpose of this study, fire
flow requirement stated in Table 2.2b were used.
According to MOE Guidelines, water distribution systems should be designed so that the normal
operating pressure ranges between 350 kPa and 700 kPa (50-100 psi) under conditions of
maximum day demand and not less than 275 kPa (40 psi) under peak hour demand. Under
conditions of simultaneous maximum day and fire flow demands, the pressure should not be
less than 140 kPa (20 psi).
2.3.2 Sanitary System In general, a sewermain should be able to convey a flow associated with peak Wet Weather
Flow (WWF) conditions. For safety reasons, a pipe that reaches 90 percent of its full capacity
during WWF condition should be flagged and should be considered for twinning or replacement.
3 HYDRAULIC MODELLING ANALYSIS AND
RESULTS 3.1 WATER SYSTEM 3.1.1 External Servicing Plan
There are currently no existing watermains in the vicinity Tremaine Road that could be utilized
as the supply point for the proposed development in this area. Following a review of Region of
Halton’s Master Plan, four (4) trunk watermains within the vicinity of Tremaine Road were
identified that could be used as main trunk lines to provide water to this development. These
were:
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 9
1. A 900 mm diameter watermain along Dundas Street, from Appleby Line to Tremaine
Road (Regional ID: 3812);
2. A 1200 mm diameter watermain along Dundas Street, from Tremaine Road to Bronte
Road (Regional ID: 5851).
3. A 600 mm diameter watermain along Tremaine Road, from Dundas Street to
approximately 950 m north of Dundas Street (Regional ID: 5853); and
4. A 600 mm diameter watermain through North Oakville Lands from Tremaine Road to
Bronte Road (Regional ID: 5627).
The 1200 mm diameter watermain along Dundas Street would provide the necessary supply for
Tremaine Road development. The construction of this trunk watermain is the preferred option to
service the Tremaine Road development area. In addition, the 600 mm diameter watermain on
Tremaine Road would also need to be constructed in advance of the Tremaine Road
development to provide the necessary looping for the internal servicing plan within Tremaine
Road development. The locations of these trunk watermains are shown in Figure 3.1.
Figure 3.1 – External Watermains as per Master Plan (directly adjacent to Tremaine Road
Development)
3.1.2 Internal Servicing Plan
The total water demand estimated for the proposed Tremaine Road development was allocated
according to the landuse map available for each proposed development option. The internal
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 10
watermains within Tremaine Road development were sized to satisfy the minimum pressure
requirements as per MOE Design guidelines. In addition, where possible pipe looping was
maintained to minimize dead-end conditions and to potentially improve water quality in the
system. The size of the watermains required to service this development area range from 250
mm to 300 mm for Option 1, and from 150 mm to 300 mm for Options 2 and 3. Further details of
the proposed internal watermain sizes within the area for each landuse option are provided in
Appendix II, Figures A2.1 to A2.3.
3.1.3 Water System Hydraulic Analysis Results
The pressure conditions within the water system, in particular within Pressure Zone Oakville 3
(O3), were assessed as summarized in Tables 3.1 for each development landuse option.
Table 3.1 – Pressure Condition Within Tremaine Road Development Area
Average Day Max Day Peak Hour Location Min
Pressure (psi)
Max Pressure
(psi)
Min Pressure
(psi)
Max Pressure
(psi)
Min Pressure
(psi)
Max Pressure
(psi) Option 1 46.01 64.4 43.31 61.8 39.81 58.3 Option 2 45.91 64.3 43.21 61.7 39.61 58.2 Option 3 46.0’ 64.3 43.41 61.8 40.2 58.6
1 Outside MOE recommended normal operating pressure range of 50 psi to 100 psi.
Tables 3.1 indicates that the minimum pressure for each development option was below the
MOE recommended minimum operating pressure under average and maximum demand
conditions. During the hydraulic analysis, under all scenarios, the Hydraulic Grade Line (HGL)
was maintained at the design HGL of this zone (currently 198 m). The potential low pressure
issue within the Tremaine Road development would be attributed to the high ground elevations
within the proposed development. Figure 3.3 shows potential low pressure areas within
Tremaine Road development area.
During the hydraulic analyses, the pressure within Oakville Zone 3 was assessed under pre-
and post-development conditions. This assessment showed that there was no negative impact
triggered by the development to the overall pressure conditions within Oakville Zone 3.
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 11
Figure 3.3 – Potential Low Pressure Areas within the Study Area
Since the ground elevation information for this analysis was obtained from the Region’s Digital
Elevation Model (DEM), it is recommended that the modeling analysis be revised when the
grading for this development site is finalized.
Fire Flow Analysis The system’s response under Maximum Day conditions plus Fire Flow was also assessed to
confirm the serviceability of this new proposed development area. The fire flow used for this
analysis was 250 L/s for Employment, High Density Residential and Mixed Use Landuse areas
and 91.7 L/s for Medium Density Residential Landuse areas. The minimum pressure in the
system should not be lower than 20 psi as per the MOE Design Guideline presented previously.
The summary of the minimum pressure within the development area is presented in Table 3.2.
Table 3.2 – Fire Flow Analysis Results
Servicing Option Min
Residual Pressure
(psi)
Max Available Flow to Maintain
20 psi (L/s)
Option 1 (employment landuse) 25.3 278.9 Option 2 (residential landuse) 32.2 136.0 Option 3 (mixed landuse) 27.3 228.3
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 12
Based on the results from the hydraulic simulations, the three proposed internal servicing
options within Tremaine Road development would have sufficient hydraulic capacity to sustain
simultaneous maximum day demand plus fire flow conditions.
3.1.4 Water Storage Requirement (Zone 3) Storage requirement calculations were conducted based on the MOE’s design guideline to size
water storage facilities. Table 3.3 shows the calculation summary conducted to compare
storage requirements with and without Tremaine Road development in place. More detailed
calculation information is presented in Appendix III.
Table 3.3 – Storage Requirement Calculation (Zone 3)
Design Scenario 2021
Without Tremaine Road
2021 + Option 1
2021 + Option 2
2021 + Option 3
A. Fire Storage (ML) 8.2 8.2 8.2 8.2
B. Equalization Storage (ML) 23.0 23.1 23.4 23.4
C. Emergency Storage 25% of A + B (ML) 7.8 7.8 7.9 7.9
Total Storage Requirement (ML) 39.0 39.1 39.5 39.5
Total Existing Storage (ML) 54.6 54.6 54.6 54.6
Storage Surplus (+) / Deficit (-) 15.6 15.5 15.1 15.1
Table 3.3 shows that no storage upgrades would be required within pressure zone 3 in order to
service the additional water demand from the proposed Tremaine Road development. This table
also shows that Option 1 will reduce the available Zone 3 storage capacity by approximately
1.3%, while Options 2 and 3 will reduce the available Zone 3 storage capacity by 3.2%.
3.1.5 Water Treatment Plan Capacity In addition to assessing the storage requirement, the future water purification plant capacity in
the system was also assessed. Table 3.4 shows the total plant capacity in the system by 2021
as per the latest master plan information and compares treatment plant requirements with and
without Tremaine Road development.
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 13
Table 3.4 – 2021 Future Plant Capacity System 2021
Without Tremaine Road2021
+ Option 12021
+ Option 2 2021
+ Option 3
Burlington WPP (MLD) 263 263 263 263
Oakville WPP (MLD) 109 109 109 109
Burloak WPP (MLD) 165 165 165 165
Milton Groundwater (MLD) 16 16 16 16
Total Plant Capacity (MLD) 553 553 553 553
Maximum Day Demand (MLD) 476 476.6 477.6 476.5 Treatment Plant Surplus Capacity (MLD) 77 76.4 75.4 76.5
Table 3.4 shows that no water treatment plant capacity upgrades would be required in order to
service the additional water demand from the Tremaine Road development. This table also
shows that Option 1 will reduce the available treatment plant capacity by approximately 0.8%,
Option 2 will reduce the capacity by 2.1%, and Option 3 will reduce the capacity by 0.7%.
3.1.6 Water Infrastructure Interconnection between Tremaine Road and North Oakville West
The same transmission watermains identified in Section 3.1.1 would be utilized to service both
the Tremaine Road and the North Oakville West proposed developments. The analyses
undertaken for this study show that there is enough capacity available on these transmission
watermains to service the North Oakville West development. With regards to available pressure
within North Oakville West, the final grading/elevation within North Oakville West would need to
be confirmed to develop the appropriate pressure zone servicing boundary.
3.2 WASTEWATER SYSTEM 3.2.1 External Servicing Plan The trunk sanitary system, in particular from the Tremaine Road development area to Mid-
Halton WWTP was assessed as part of the present study. The capacity of the trunk sewers for
this section were reviewed under pre and post-development conditions.
There are currently no existing sewermains directly adjacent to the proposed Tremaine Road
development. The latest Master Plan drainage area plan shows that the Tremaine Road
development area would be serviced by a 450 mm diameter sewermain (approximately 900 m
in length) on Dundas Street (Regional ID: 3706) which will be connected to the existing 600 mm
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 14
diameter trunk sewermain on Colonel William Parkway. The location of these trunk sewers is
shown in Figure 3.4. Under this servicing strategy, the 450 mm diameter sewermain on Dundas
Street would need to be constructed prior to any development on Tremaine Road. Additionally,
a sewermain with a diameter of 250 mm (for Option 1) or 375 mm (for Options 2 and 3) would
be needed in order to connect the internal sewer pipes within Tremaine Road to the future 450
mm diameter sewer pipe on Dundas Street.
Figure 3.4 – External Servicing Plan
App
leby
Lin
e
Hwy 407
Bro
nte
Roa
d
Dundas St 450mm
/
600m
m
300m
m
825m
m
675m
mCol
Will
iam
Pkw
y
Valle
y R
idge
Gra
nd O
ak
675m
m
Trem
aine
Roa
d
250mm sewermain (Option 1)375mm sewermain (Option 2 and Option 3)
Development Area Boundary
Future Proposed Pipes Adjacent to Development Area
External Servicing Sewermain Required
Existing Trunk Sewermains
Roads
Development Area Boundary
Future Proposed Pipes Adjacent to Development Area
External Servicing Sewermain Required
Existing Trunk Sewermains
Roads
3.2.2 Internal Servicing Plan The total sanitary load estimated for the proposed Tremaine Road development was allocated
according to the landuse map available for each proposed development option. The internal
sewermains within the Tremaine Road development were sized so that the peak flow/full pipe
flow ratio (q/Q ratio) would not be greater than 90% while maintaining pipe depth less than 10
m. The size of the sewermain required to service this development area ranges from 150 mm to
250 mm for Option 1, 150 mm to 375 mm for Option 2 and 150 mm to 300 mm for Option 3.
Detailed proposed internal sewermain size information for each landuse option is provided in
Appendix II, Figures A2.4 to A2.6.
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 15
3.2.3 Wastewater System Hydraulic Analysis Results Based on the external servicing plan explained in the previous sections, under all landuse
options, the load generated from Tremaine Road development would be conveyed by the 450
mm diameter sewermain on Dundas and its downstream connected sewermains which
ultimately connected to Mid Halton WWTP, as shown in Figure 3.5.
Figure 3.5 – Existing and Proposed Trunk Sewermains Impacted by Tremaine Development
Dundas St
Hwy 407
Bro
nte
Rd
Dundas St
Col
Will
iam
Pkw
y
Westoak Trails
Upper Middle Rd
Mid Halton WWTP
/
Trem
aine
Rd
250mm sewermain (Option 1)375mm sewermain (Option 2 and Option 3)
Development Area Boundary
Future Proposed Pipes Adjacent to Development Area
External Servicing Sewermain Required
Existing Trunk Sewermains
Roads
Dundas St
Hwy 407
Bro
nte
Rd
Dundas St
Col
Will
iam
Pkw
y
Westoak Trails
Upper Middle Rd
Mid Halton WWTP
/
Trem
aine
Rd
250mm sewermain (Option 1)375mm sewermain (Option 2 and Option 3)
Development Area Boundary
Future Proposed Pipes Adjacent to Development Area
External Servicing Sewermain Required
Existing Trunk Sewermains
Roads
Development Area Boundary
Future Proposed Pipes Adjacent to Development Area
External Servicing Sewermain Required
Existing Trunk Sewermains
Roads
The hydraulic analysis conducted showed that there would be enough capacity along these
trunk sewermains to convey the load generated by the Tremaine Road development under all
landuse development options. Table 3.5 shows the summary of the results, while detailed
hydraulic analysis results are provided in Appendix IV.
Table 3.5 – Peak Flow vs. Pipe Capacity (q/Q) Results Landuse Option Minimum q/Q Maximum q/Q
Option 1 - Employment 0.05 0.71 Option 2 - Residential 0.08 0.72 Option 3 - Mixed 0.12 0.74
During the analysis, pipe spare capacity along the affected sewermains was also calculated.
The spare capacity of a sewermain was calculated based on the following formula:
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 16
Spare Capacity (L/s) = 90% x Full Pipe Capacity – Peak WWF Conveyed
The results of this calculation are summarized in Table 3.6.
Table 3.6 – Spare Capacity on 450 mm Sewermain on Dundas Street and Its Downstream
Sewerlines
Landuse Option Maximum Spare Capacity (L/s)
Without Tremaine Road Development 164 Option 1 - Employment 138 Option 2 - Residential 120 Option 3 - Mixed 97
The table above shows that Option 1, Option 2 and Option 3 would reduce the available
sewermain spare capacity by 16%, 26.8% and 40.9% respectively.
3.2.4 Mid Halton Treatment Plant Capacity The proposed development area would be serviced by the Mid Halton Treatment Plant. Table 3.7 shows ultimate Mid Halton Treatment Plant capacity as identified in the Master Plan and
compares the plant’s available capacity to treat extra loading from Tremaine Road development.
Table 3.7 – Mid Halton Treatment Plant Capacity
System 2021 Without
Tremaine Road
2021 + Option 1
2021 + Option 2
2021 + Option 3
Average DWF (MLD) 113 113.4 113.9 114.2
Mid Halton Treatment Plant Capacity (MLD) 125 125 125 125
Treatment Plant Surplus Capacity (MLD) 12 11.6 11.1 10.8
Table 3.7 shows that there is enough capacity available at the treatment plant to treat the
expected average DWF under 2021 load conditions for all the landuse options within the
Tremaine Road development. This table also shows that Option 1 will reduce the Mid Halton
surplus treatment capacity by 3%, Option 2 will reduce 7.5% of the capacity, while Option 3
shows a reduction of approximately 10%.
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 17
3.2.5 North Halton Pumping Station Capacity North Halton pumping station is located enroute to Mid Halton WWTP. Due to greater sanitary
load conditions, 2021 Peak wet weather flows relating to the Tremaine Road development
would increase through this pumping station. Table 3.8 summarizes the existing capacity and
required pumping capacity of the North Halton Pumping Station.
Table 3.8 – North Service Road Pumping Station Capacity
RMOHID / Oper. ID 85 / H-2
WWTP Drainage Area Mid Halton WWTP
No. of Pumps 4
Pump Sizes (1) 385.7 L/s, (2) 385.7 L/s, (3) 385.7 L/s, (4) 385.7 L/s
Design Firm Capacity (L/s) 1157 I & I (L/s/ha) 0.252 Proposed Expansion as per Master Plan (L/s) 2314 (200 ML/d) Future Total Capacity (L/s) 3424 Estimated Future Firm Capacity (L/s) 3054
Total WWF (L/s) With
Tremaine Road
Capacity Surplus (+) / Deficit (-)
(L/s)
Without Tremaine
Road
Capacity Surplus (+) / Deficit (-)
(L/s) Option 1 – Employment 3398.2 -344.2 3330.5 -276.5
Option 2 – Residential 3416.1 -362.1 3348.4 -294.4
Option 3 – Mixed Use 3372.5 -318.5 3304.8 -250.8
Based on the capacity assessment presented in Table 3.8, the future firm capacity was not
sufficient to accommodate the projected peak wet weather flow even without the Tremaine
Road development. It is recommended that the Region review the proposed future expansion
of the North Halton Pumping Station with the consideration of the preferred growth option for the
Tremaine Road development.
3.2.6 Wastewater Infrastructure Interconnection between Tremaine Road and
North Oakville West Based on the analyses conducted, the proposed 450 mm sewermain on Dundas Street and its
downstream connection sewermains have enough capacity to convey the peak flow generated
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 18
from the Tremaine Road development regardless of the landuse options. Section 3.2.4 above
discussed the spare capacity along these sewermains which ranges from 120 L/s to 137 L/s
depending on the type of landuse option selected to be developed in Tremaine Road. Based on
this analysis, some portion of the development within North Oakville West area could also be
serviced by these trunk sewermains, subject to more detailed final grading/elevation analysis.
4 DEVELOPMENT CHARGES IMPACT 4.1 WATER SYSTEM The hydraulic modelling and analysis undertaken as part of this present project suggest that the
pipe infrastructure upgrades identified previously in the Master Plan (relevant to the study area)
are adequate to service the Tremaine Road development for build-out conditions. The three
different landuse options that have been assessed for Tremaine Road will not have any
detrimental impact on Regional/DC planned water infrastructure.
However, the construction timing of adjacent future infrastructure may need to be adjusted to
accommodate water servicing to this development area, and this is explained in more detail in
Section 3.1.1. The Region of Halton Finance department may need to be consulted regarding
this matter.
4.2 WASTEWATER SYSTEM The hydraulic analyses conducted suggest that the pipe infrastructure identified previously in
the Master Plan (relevant to the study area) is sufficient to service the proposed Tremaine Road
development. The three different landuse options would not impact the Regional/DC planned
wastewater infrastructure.
It should be noted that the future 450 mm diameter sewermain on Dundas Street has to be in
place in order to convey the sanitary load generated by this development area. A connection of
either 250 mm or 375 mm in diameter would be required between the Tremaine Road
development and the 450 mm on Dundas. The Region of Halton Finance may need to be
consulted should there be any adjustment to the construction timing of this infrastructure as
opposed to that identified in the master plan.
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 19
5 CONCLUSIONS & RECOMMENDATIONS Hydraulic analysis has been conducted using the latest RMOH’s water and wastewater models.
In this study, future (2021) population, water demand, and sanitary load conditions were
incorporated into the models accordingly and the Tremaine Road development serviceability
was assessed.
It should be noted that this report does not satisfy all the requirements of an Area Servicing Plan
as defined by the Region of Halton. Therefore, there will be policies that will be required in the
secondary plan that identify the requirement for an Area Servicing Plan and that this plan would
need to be based on the Area Servicing Plan Terms of Reference, a copy of which is provided
in Appendix V. Also, it should be noted that new infrastructure required to service the Tremaine
Road development was assessed from a hydraulic analysis point of view only and therefore
land and easement issues would need to be reviewed addressed where necessary to fully
appreciate infrastructure costs.
5.1 WATER SYSTEM For the water system, all three different landuse options were analyzed and their impact to the
existing and future/proposed infrastructure was also assessed. In general, the Tremaine Road
development is located within Zone 3 pressure zone and therefore will be serviced through this
pressure zone. There will likely be some low pressure areas within the development regardless
of the type of landuse development put in place, since the low pressure issue is mainly
attributed to high elevation that may be resolved through re-grading.
With regards to the external servicing strategy, the future 1200 mm diameter watermains on
Dundas Street from Tremaine Road to Bronte Road, as well as the future 600 mm diameter
watermain on Tremaine Road are the preferred feedermains to supply the development area.
Therefore, these watermains would need to be in place prior to any development within
Tremaine Road.
With regards to internal servicing, the required pipe size ranges from 250 mm to 300 mm for
Option 1, and it ranges from 150 mm to 300 mm for Options 2 and 3. Under all three different
landuse options, there would not be any additional infrastructure required other than that
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 20
already identified in the Master Plan, providing either re-grading the high spots or not building
on the high spots, is adopted. In general, due to greater water demand conditions, Option 3
would have the greatest impact in reducing the treatment plant capacity and Zone 3 storage
tank capacity than the other landuse options.
Based on our hydraulic analysis, no storage upgrades would be required in order to service the
additional water demand from the proposed Tremaine Road development under all landuse
development options. In addition to assessing the storage requirement, no water treatment plant
capacity upgrades would be required in order to service the additional water demand from the
Tremaine Road development.
Recommendations: 1. Conduct a detail topographic analysis on Tremaine Road development area.
2. Based on the hydraulic analysis, the maximum elevation that could be serviced by
pressure zone 3 is 162 m so that the minimum pressure allowed of 50 psi is maintained.
Should any of the development area be higher than 162 m, there are three possible
servicing options that are recommended:
a. Appropriate surface grading should be implemented where possible, or
b. Avoid having development in these high spots and allocate more development in
other surrounding areas within Tremaine Road development, or
c. Provide local booster pump station for the high ground areas above 162m
3. Consult the Region of Halton Finance with regards to the timing adjustment that would
be needed in order to accommodate the Tremaine Road development.
4. Undertake a further hydraulic analysis once the grading within the development site is
defined, so that any potential low pressure servicing areas below the minimum operating
pressure of 50 psi can be corrected through revision of final grading.
5. Review the hydraulic analysis once the Tremaine Road development timing is defined.
5.2 WASTEWATER SYSTEM All three different landuse options were analyzed to assess its impact to both internal and
external servicing strategies. With regards to the external servicing plan, as identified in the
latest Master Plan, the Tremaine Road development area would be serviced by the future 450
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 21
mm diameter sewermain on Dundas Street which would be connected to the existing
sewermain on Colonel William Parkway and ultimately convey the sewage loads to Mid Halton
WWTP. An additional sewermain (250 mm for Option 1 and Option 2, 375 mm for Option 3)
would be needed to connect the internal sewermains within the Tremaine Road development to
the 450 mm sewermain on Dundas Street. Hydraulic analysis was conducted to assess the
capacity of all the trunk sewermains downstream of the Tremaine Road development
connection point. The results show that there would be enough capacity along these trunk
sewermains to convey the additional sanitary load from Tremaine Road.
The hydraulic analysis conducted showed that trunk sewermains provide sufficient capacity to
convey the load generated by the Tremaine Road development under all landuse development
options. Furthermore, the Mid Halton Treatment Plant has the available capacity to treat the
expected average DWF under 2021 load conditions for all the landuse options for the
development.
Based on the capacity assessment of the North Halton Pumping Station, the future firm capacity
was not sufficient to accommodate the projected peak wet weather flow even without the
Tremaine Road development.
With regards to internal servicing, the required pipe size for Tremaine Road development
ranges from 150 mm to 250 mm for Option 1 and from 150 mm to 375 mm for Option 2 and
Option 3.
It should be noted that choosing the residential versus employment development option does
not have any impact on external (outside of the development area) infrastructure, and therefore
neither would be preferable to the other through servicing requirements
Recommendations: 1. Conduct detail topographic analysis on Tremaine Road development area.
2. Consult with the Region of Halton Finance with regards to the timing adjustment that
would be needed in order to accommodate Tremaine Road development.
3. Refine hydraulic analysis once the final grade within the development site is finalized
and Tremaine Road development timing is defined.
Tremaine Road Water & Wastewater Secondary Plan Servicing Assessment
Page 22
4. Review the pumping capacity and proposed future expansion of the North Halton
Pumping Station with the consideration of the preferred growth option for the Tremaine
Road development.
900mm
1200mm
60
0m
m
1.0
0.7
0.3
1.0
0.7
0.3
600mm
1.7
1.0
0.6
1.7
1.0
0.6
0.6
0.4
0.2
0.6
0.4
0.2
1.2
0.8
0.4
1.2
0.8
0.4
0.4
0.2
0.1
0.4
0.2
0.1
2.6
1.6
0.9
2.6
1.6
0.9
1.0
0.6
0.3
1.0
0.6
0.3
1.7
1.1
0.6
1.7
1.1
0.60.9
0.6
0.3
0.9
0.6
0.3
300mm Proposed mains within development area 250mm Proposed mains within development areaFuture mains as per Master Plan
1.7
1.1
0.6
1.7
1.1
0.6 Avg Day Demand (L/s)
Max Day Demand (L/s)
Peak Hour Demand (L/s)
Figure A2.1 – Proposed Watermains and Estimated Water Demands (Option 1)
900mm1200mm
60
0m
m
5.3
3.3
1.8
5.3
3.3
1.8
600mm
2.8
1.8
0.9
2.8
1.8
0.9
1.9
1.2
0.6
1.9
1.2
0.6
0.8
0.5
0.3
0.8
0.5
0.3
0.4
0.3
0.1
0.4
0.3
0.1
0.7
0.4
0.2
0.7
0.4
0.2
1.5
0.9
0.5
1.5
0.9
0.5
3.3
2.1
1.1
3.3
2.1
1.1
1.1
0.7
0.4
1.1
0.7
0.4
2.6
1.7
0.9
2.6
1.7
0.9
6.0
3.8
2.0
6.0
3.8
2.0
0.8
0.5
0.3
0.8
0.5
0.3
1.4
0.9
0.5
1.4
0.9
0.5
300mm Proposed mains within development area
250mm Proposed mains within development area200mm Proposed mains within development area
150mm Proposed mains within development area
Future mains as per Master Plan
1.7
1.1
0.6
1.7
1.1
0.6 Avg Day Demand (L/s)
Max Day Demand (L/s)
Peak Hour Demand (L/s)
Figure A2.2 – Proposed Watermains and Estimated Water Demands (Option 2)
900mm1200mm
600
mm
1.7
1.1
0.6
1.7
1.1
0.6 Avg Day Demand (L/s)
Max Day Demand (L/s)
Peak Hour Demand (L/s)
1.1
0.7
0.4
1.1
0.7
0.4
600mm
1.3
0.8
0.4
1.3
0.8
0.4
0.2
0.2
0.1
0.2
0.2
0.1
0.5
0.3
0.2
0.5
0.3
0.2
0.4
0.2
0.1
0.4
0.2
0.1
0.2
0.1
0.1
0.2
0.1
0.1
0.3
0.2
0.1
0.3
0.2
0.1
0.5
0.3
0.2
0.5
0.3
0.2
0.6
0.4
0.2
0.6
0.4
0.2
0.1
0.1
0.1
0.1
0.1
0.10.8
0.5
0.3
0.8
0.5
0.3
0.6
0.4
0.2
0.6
0.4
0.2
300mm Proposed mains within development area 250mm Proposed mains within development area150mm Proposed mains within development area
Future mains as per Master Plan
Figure A2.3 – Proposed Watermains and Estimated Water Demands (Option 3)
5.15.1 1.11.1
2.82.80.80.8
3.73.7
2.12.1
3.93.9
6.16.1
150mm Proposed mains within development area200mm Proposed mains within development area
250mm Proposed mains within development area375mm Proposed mains within development area
3.73.7 Peak WWF (L/s)
Proposed servicing strategy
Figure A2.4 – Proposed Sewermains and Estimated Sewage Loads (Option 1)
9.59.5 5.35.3
2.32.3
5.75.7
0.40.4
3.33.3
3.83.8
2.82.8
3.53.5
3.03.0
3.93.9
150mm Proposed mains within development area
200mm Proposed mains within development area250mm Proposed mains within development area
375mm Proposed mains within development area
3.73.7 Peak WWF (L/s)
Proposed servicing strategy
150mm Proposed mains within development area200mm Proposed mains within development area
250mm Proposed mains within development area
375mm Proposed mains within development area
3.73.7 Peak WWF (L/s)
Proposed servicing strategy
Figure A2.5 – Proposed Sewermains and Estimated Sewage Loads (Option 2)
6.76.71.91.9
2.92.9
2.32.3
1.41.4
2.42.4
1.21.2
0.70.7
0.10.1
0.80.8
0.50.5
150mm Proposed mains within development area200mm Proposed mains within development area
250mm Proposed mains within development area375mm Proposed mains within development area
3.73.7 Peak WWF (L/s)
Proposed servicing strategy
Figure A2.6 – Proposed Sewermains and Estimated Sewage Loads (Option 3)
Table A3.1 – Storage Requirement Calculation (Zone 3)
Design Scenario 2021
Without Tremaine Road
2021 + Option 1
2021 + Option 2
2021 + Option 3
A. Fire Storage
- Fire Flow (L/s) 378 378 378 378
- Duration (hr) 6 6 6 6
Total Fire Storage (ML) 8.2 8.2 8.2 8.2
B. Equalization
Oakville Zone 3 (ML/d) 55.01 56.71 55.62 56.58
Burlington Zone 3 (ML/d) 36.94 36.94 36.94 36.94
Total Zone 3 Max Day Demand (ML/d) 91.95 93.65 92.56 93.52
Total Equalization Storage (25% of MDD) (ML) 22.99 23.41 23.14 23.38
C. Emergency
Total Emergency Storage (25% of A + B) (ML) 7.79 7.89 7.83 7.89
Total Storage Requirement (ML) 38.98 39.47 39.13 39.43
Existing Storage (ML)
6th Line Tank (O3) 32 32 32 32
Headon Res (B3) 18 18 18 18
Tyandaga Res (B3) 4.6 4.6 4.6 4.6
Total Existing Storage (ML) 54.6 54.6 54.6 54.6
Storage Surplus (+) / Deficit (-) 15.66 15.13 15.47 15.17
Option 1 – Employment Landuse q/Q Results for 450 mm Sewermains on Dundas Street and Its Downstream Connection
ID Diameter
(mm) Length
(m) Slope
Total Flow (L/s)
Velocity (m/s)
d/D q/Q
28201 600 43.518 0.009 91.919 1.528 0.265 0.154
28202 600 18.758 0.003 92.148 1.04 0.351 0.265
28203 675 44.192 0.005 143.57 1.322 0.343 0.253
28206 675 37.573 0.005 144.619 1.324 0.344 0.255
28208 675 69.493 0.005 145.655 1.335 0.344 0.255
28209 675 10.387 0.008 146.042 1.608 0.301 0.197
28210 675 45.665 0.005 146.142 1.385 0.336 0.243
28218 675 17.037 0.015 154.756 2.09 0.26 0.148
28219 675 95.408 0.005 150.638 1.389 0.343 0.253
28220 675 39.665 0.014 155.728 2.039 0.266 0.155
28223 675 84.665 0.005 146.798 1.378 0.338 0.246
28224 675 6.626 0.005 147.831 1.364 0.342 0.252
28225 675 65.687 0.005 148.73 1.383 0.341 0.25
30937 600 90.541 0.003 91.237 0.951 0.372 0.295
30938 600 103.687 0.002 91.533 0.94 0.377 0.302
30957 600 71.356 0.002 56.981 0.783 0.304 0.201
30958 600 108.685 0.003 60.701 0.946 0.278 0.169
30960 600 103.968 0.005 61.946 1.052 0.261 0.15
30961 600 43.22 0.002 84.17 0.792 0.402 0.34
30962 600 72.277 0.003 84.757 0.93 0.359 0.275
30963 600 85.3 0.003 85.416 1.014 0.338 0.247
30973 600 9.533 0.003 62.203 0.926 0.287 0.18
30995 600 148.448 0.003 56.702 0.936 0.267 0.156
30996 600 57.209 0.003 56.9 0.937 0.267 0.156
SP-00324-O 600 73.32 0.003 56.702 0.982 0.258 0.146
SP-00326-O 600 86.18 0.004 56.702 1.001 0.254 0.142
SP-00320-O 600 70.9 0.003 56.702 0.95 0.264 0.153
SP-00322-O 600 27.4 0.005 56.702 1.162 0.229 0.115
SP-00314-O 600 59.262 0.004 56.702 1.011 0.253 0.14
SP-00316-O 600 45.1 0.007 56.702 1.245 0.218 0.104
SP-00318-O 600 89.9 0.003 56.702 0.977 0.259 0.147
SP-00308-O 600 47.5 0.003 25.701 0.767 0.176 0.067
SP-00312-O 600 53.238 0.004 56.702 1.006 0.254 0.141
SP-00300-O 600 230 0.007 25.701 1 0.146 0.046
SP-00304-O 600 27.5 0.003 25.701 0.786 0.173 0.065
SP-00306-O 600 65.1 0.003 25.701 0.763 0.177 0.068
SP-11 450 898.342 0.009 25.701 1.069 0.209 0.095
16468 1,200.00 200.155 0.003 1,436.02 1.947 0.621 0.707
16509 1,200.00 224.458 0.007 1,438.43 2.825 0.461 0.434
16511 2,400.00 231.696 0.003 3,205.88 2.302 0.347 0.258
16510 2,400.00 301.489 0.003 3,210.80 2.309 0.346 0.258
ID Diameter
(mm) Length
(m) Slope
Total Flow (L/s)
Velocity (m/s)
d/D q/Q
16512 1,500.00 31.427 0.005 1,502.83 2.437 0.38 0.307
20686 2,400.00 300.237 0.003 3,216.56 2.378 0.339 0.248
29150 2,400.00 258.64 0.002 3,231.26 2.175 0.363 0.282
29151 2,400.00 280.811 0.002 3,238.87 2.269 0.353 0.267
29152 2,400.00 289.601 0.002 3,248.11 2.246 0.356 0.272
29153 2,400.00 245.946 0.002 3,254.37 2.291 0.352 0.265
Min 0.046
Max 0.707
Option 2 – Residential Landuse q/Q Results for 450 mm Sewermains on Dundas Street and Its Downstream Connection
ID Diameter
(mm) Length
(m) Slope
Total Flow (L/s)
Velocity (m/s)
d/D q/Q
28201 600 43.518 0.009 109.768 1.608 0.291 0.184
28202 600 18.758 0.003 109.997 1.092 0.386 0.316
28203 675 44.192 0.005 161.42 1.365 0.365 0.285
28206 675 37.573 0.005 162.468 1.368 0.366 0.287
28208 675 69.493 0.005 163.505 1.379 0.366 0.286
28209 675 10.387 0.008 163.892 1.661 0.32 0.222
28210 675 45.665 0.005 163.991 1.43 0.357 0.273
28218 675 17.037 0.015 172.605 2.157 0.275 0.165
28219 675 95.408 0.005 168.487 1.432 0.364 0.283
28220 675 39.665 0.014 173.577 2.103 0.281 0.173
28223 675 84.665 0.005 164.647 1.423 0.359 0.276
28224 675 6.626 0.005 165.681 1.408 0.364 0.283
28225 675 65.687 0.005 166.58 1.427 0.362 0.28
30937 600 90.541 0.003 109.086 0.998 0.41 0.353
30938 600 103.687 0.002 109.383 0.986 0.415 0.36
30957 600 71.356 0.002 74.83 0.846 0.351 0.264
30958 600 108.685 0.003 78.551 1.017 0.318 0.219
30960 600 103.968 0.005 79.795 1.131 0.298 0.193
30961 600 43.22 0.002 102.019 0.834 0.447 0.412
30962 600 72.277 0.003 102.606 0.98 0.397 0.333
30963 600 85.3 0.003 103.265 1.069 0.374 0.298
30973 600 9.533 0.003 80.052 0.994 0.327 0.232
30995 600 148.448 0.003 74.552 1.012 0.307 0.205
30996 600 57.209 0.003 74.75 1.013 0.307 0.205
SP-00324-O 600 73.32 0.003 74.552 1.062 0.296 0.191
SP-00326-O 600 86.18 0.004 74.552 1.083 0.292 0.186
SP-00320-O 600 70.9 0.003 74.552 1.027 0.304 0.201
SP-00322-O 600 27.4 0.005 74.552 1.258 0.263 0.151
SP-00314-O 600 59.262 0.004 74.552 1.093 0.29 0.184
SP-00316-O 600 45.1 0.007 74.552 1.348 0.25 0.137
SP-00318-O 600 89.9 0.003 74.552 1.057 0.298 0.193
SP-00308-O 600 47.5 0.003 43.55 0.896 0.228 0.114
ID Diameter
(mm) Length
(m) Slope
Total Flow (L/s)
Velocity (m/s)
d/D q/Q
SP-00312-O 600 53.238 0.004 74.552 1.088 0.291 0.185
SP-00300-O 600 230 0.007 43.55 1.169 0.189 0.078
SP-00304-O 600 27.5 0.003 43.55 0.918 0.224 0.111
SP-00306-O 600 65.1 0.003 43.55 0.891 0.229 0.115
SP-11 450 898.342 0.009 43.55 1.246 0.272 0.161
16468 1,200.00 200.155 0.003 1,453.87 1.952 0.626 0.716
16509 1,200.00 224.458 0.007 1,456.28 2.834 0.464 0.44
16511 2,400.00 231.696 0.003 3,223.73 2.306 0.348 0.26
16510 2,400.00 301.489 0.003 3,228.65 2.313 0.347 0.259
16512 1,500.00 31.427 0.005 1,520.68 2.445 0.383 0.311
20686 2,400.00 300.237 0.003 3,234.41 2.382 0.34 0.249
29150 2,400.00 258.64 0.002 3,249.11 2.178 0.365 0.284
29151 2,400.00 280.811 0.002 3,256.72 2.273 0.354 0.269
29152 2,400.00 289.601 0.002 3,265.96 2.249 0.357 0.274
29153 2,400.00 245.946 0.002 3,272.21 2.294 0.353 0.267
Min 0.078
Max 0.716
Option 3 – Mixed Use Landuse q/Q Results for 450 mm Sewermains on Dundas Street and Its Downstream Connection
ID Diameter
(mm) Length
(m) Slope
Total Flow (L/s)
Velocity (m/s)
d/D q/Q
28201 600 43.518 0.009 133.967 1.701 0.322 0.225
28202 600 18.758 0.003 134.196 1.152 0.431 0.385
28203 675 44.192 0.005 185.618 1.419 0.394 0.327
28206 675 37.573 0.005 186.667 1.420 0.395 0.329
28208 675 69.493 0.005 187.703 1.433 0.394 0.328
28209 675 10.387 0.008 188.090 1.727 0.344 0.254
28210 675 45.665 0.005 188.190 1.486 0.384 0.313
28218 675 17.037 0.015 196.804 2.240 0.294 0.189
28219 675 95.408 0.005 192.685 1.486 0.391 0.323
28220 675 39.665 0.014 197.776 2.183 0.301 0.197
28223 675 84.665 0.005 188.845 1.478 0.387 0.317
28224 675 6.626 0.005 189.879 1.461 0.392 0.324
28225 675 65.687 0.005 190.778 1.481 0.389 0.320
30937 600 90.541 0.003 133.285 1.053 0.459 0.431
30938 600 103.687 0.002 133.581 1.039 0.464 0.440
30957 600 71.356 0.002 99.028 0.913 0.408 0.350
30958 600 108.685 0.003 102.749 1.096 0.366 0.286
30960 600 103.968 0.005 103.994 1.218 0.342 0.251
30961 600 43.220 0.002 126.218 0.881 0.505 0.509
30962 600 72.277 0.003 126.804 1.037 0.447 0.412
30963 600 85.300 0.003 127.464 1.131 0.420 0.368
30973 600 9.533 0.003 104.251 1.069 0.377 0.302
30995 600 148.448 0.003 98.750 1.094 0.356 0.271
ID Diameter
(mm) Length
(m) Slope
Total Flow (L/s)
Velocity (m/s)
d/D q/Q
30996 600 57.209 0.003 98.948 1.095 0.356 0.272
SP-00324-O 600 73.320 0.003 98.750 1.150 0.343 0.254
SP-00326-O 600 86.180 0.004 98.750 1.173 0.338 0.247
SP-00320-O 600 70.900 0.003 98.750 1.111 0.352 0.266
SP-00322-O 600 27.400 0.005 98.750 1.364 0.303 0.200
SP-00314-O 600 59.262 0.004 98.750 1.184 0.336 0.244
SP-00316-O 600 45.100 0.007 98.750 1.461 0.289 0.182
SP-00318-O 600 89.900 0.003 98.750 1.143 0.345 0.255
SP-00308-O 600 47.500 0.003 67.749 1.018 0.285 0.178
SP-00312-O 600 53.238 0.004 98.750 1.177 0.337 0.245
SP-00300-O 600 230.000 0.007 67.749 1.331 0.236 0.122
SP-00304-O 600 27.500 0.003 67.749 1.043 0.281 0.172
SP-00306-O 600 65.100 0.003 67.749 1.012 0.287 0.179
SP-11 450 898.342 0.009 67.749 1.412 0.342 0.251
16468 1200 200.155 0.003 1505.603 1.967 0.641 0.741
16509 1200 224.458 0.007 1508.007 2.859 0.474 0.455
16511 2400 231.696 0.003 3315.598 2.324 0.353 0.267
16510 2400 301.489 0.003 3320.516 2.330 0.353 0.266
16512 1500 31.427 0.005 1572.411 2.467 0.390 0.321
20686 2400 300.237 0.003 3326.276 2.402 0.345 0.256
29150 2400 258.640 0.002 3340.981 2.195 0.370 0.292
29151 2400 280.811 0.002 3348.588 2.289 0.359 0.276
29152 2400 289.601 0.002 3357.829 2.266 0.363 0.281
29153 2400 245.946 0.002 3364.084 2.313 0.358 0.274
Min 0.122
Max 0.741
Area Servicing Plan
Regional Requirements
1.0 General
Area Servicing Plans are required in accordance with the Regional Official Plan in
support of a Secondary Plan. The Area Servicing Plan shall have regard for the Halton
Region of Halton Water and Wastewater Area Plan and shall be in accordance with the
Region of Halton Design Criteria, Contract Specifications and Standard Drawings as well
as other Regional policies related to water and wastewater.
The Area Servicing Plan (ASP) will address water and wastewater infrastructure as
outlined below. The ASP will be completed following the principles of a Municipal
Class EA , in terms of considering and evaluating alternatives etc. The ASP will be
prepared by a Consulting Engineer in consultation with the Region of Halton and other
relevant agencies. The ASP will be prepared as a draft document first with a more
extensive circulation to the various agencies and the public through the balance of the
planning process.
2.0 Water Servicing
The following issues related to the provision of water servicing to the secondary plan area
should be addressed.
2.1 Evaluation of Existing Water System
The following considerations with respect to existing infrastructure should be reviewed:
• Outline of existing water system and Pressure Zone impacted by the Secondary
Plan.
• Improvements required to the existing water system infrastructure based on
forecasted growth in the secondary plan. Triggers for improvements should also
be identified.
2.2 Proposed Water system
The following elements with respect to the proposed water system should be examined:
• Preliminary servicing plan that shows the trunk water distribution system.
• Watermain modelling analysis of the proposed system which will include
preliminary sizing of mains, expected static pressures and fire flows.
• Watermain analysis will also assess impact of phasing on critical elements and
review alternatives.
• Review opportunities for system redundancies and watermain looping
2.3 Proposed Development Charge (DC) Water System Infrastructure
The ASP shall examine in further detail the following elements with respect to DC
infrastructure:
• Review land and easement requirements for DC watermain infrastructure.
• Review details with respect to cost and timing of DC infrastructure.
• Examine impact of phasing on cost and timing of DC infrastructure and review
alternatives related to DC infrastructure.
• Identify all DC projects that may potentially require a Municipal Class EA when
project specific details are better defined.
3.0 Wastewater Servicing
The following issues related to the provision of wastewater servicing to the secondary
plan area should be addressed.
3.1 Evaluation of Existing Wastewater System
The following considerations with respect to existing infrastructure should be reviewed:
• Outline of existing wastewater system and drainage areas impacted by the
Secondary Plan.
• Downstream constraints – pump stations, pipe capacity etc.
• Improvements required to the existing wastewater system infrastructure based on
forecasted growth in the secondary plan. Triggers for improvements should also
be identified.
3.2 Proposed Wastewater System
The following elements with respect to the proposed wastewater system should be
examined:
• Preliminary servicing plan that shows the trunk wastewater distribution system.
• Internal and external drainage area plans and preliminary design sheets for major
trunk sewers.
• Sanitary sewer analysis of the proposed system which will include preliminary
sizing of mains based on drainage areas.
• Analysis will also assess impact of phasing on critical elements and review
alternatives.
• Review size and location of pump station infrastructure including overflows and
environmental impacts.
• Provide analysis on size, location and number of pump stations verses depth of
trunk sewer infrastructure.
3.3 Proposed Development Charge (DC) Wastewater System Infrastructure
The ASP shall examine in further detail the following elements with respect to DC
infrastructure:
• Plan & Profile drawings for DC sewers based on preliminary grades (note:
maximum permissible depth is 10m).
• Review land and easement requirements for DC wastewater main infrastructure
including land requirements for pump stations.
• Review details with respect to cost and timing of DC infrastructure.
• Examine impact of phasing on cost and timing of DC infrastructure and review
alternatives related to DC infrastructure.
• Identify all DC projects that may potentially require a Municipal Class EA when
project specific details are better defined.
4.0 Conclusion
In conclusion, the Area Servicing Plan once approved will be a comprehensive document
that will set out the framework for infrastructure requirements for servicing the
Secondary Plan area. The document will be used by developers and their consultants as
well as municipal staff for the following purpose:
• To ensure that Functional Servicing Reports in support of individual draft plans of
subdivision are prepared and reviewed with regard to the ASP.
• To provide guidance with respect to timing and budgets for DC projects.
• To provide input into Financial Plans.