Washington, DC 20585 APR 2 1993 - nrc.gov · Los Alat os February 1993 Highlights Preliminary...

106
Department of Energy Washington, DC 20585 APR 2 1993 . ,. Mr. Joseph J. Holonich, Director Repository Licensing and Quality Assurance Project Directorate Division of High-Level Waste Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555 Dear Mr. Holonich: The enclosed Yucca Mountain Site Characterization Project participant monthly status reports are forwarded for your information. If you have any questions on the enclosed reports, please contact Priscilla Bunton at (202) 586-8365. Linda J. Desell, Chief Regulatory Integration Branch Office of Civilian Radioactive Waste Management Enclosures: X 4d 4 (1) EG&G/EM Remote Sensing Laboratory Support to the Yucca Mountain Site Characterization Project, February 1993 Progress Report (2) Los Alamos National Laboratory Monthly Activity Report Highlights, February 1993 (Revised) (3) Lawrence Livermore National Laboratory Yucca Mountain Project Status Report, February 1993 13I3S6Z 9304130246 930402 PDR WASTE WM 11 PDR

Transcript of Washington, DC 20585 APR 2 1993 - nrc.gov · Los Alat os February 1993 Highlights Preliminary...

Department of EnergyWashington, DC 20585

APR 2 1993. ,.

Mr. Joseph J. Holonich, DirectorRepository Licensing and Quality Assurance

Project DirectorateDivision of High-Level Waste ManagementOffice of Nuclear Material Safety

and SafeguardsU.S. Nuclear Regulatory CommissionWashington, DC 20555

Dear Mr. Holonich:

The enclosed Yucca Mountain Site Characterization Project

participant monthly status reports are forwarded for your

information. If you have any questions on the enclosed reports,

please contact Priscilla Bunton at (202) 586-8365.

Linda J. Desell, ChiefRegulatory Integration BranchOffice of Civilian RadioactiveWaste Management

Enclosures: X 4d 4(1) EG&G/EM Remote Sensing Laboratory Support to the Yucca

Mountain Site Characterization Project, February 1993Progress Report

(2) Los Alamos National Laboratory Monthly Activity ReportHighlights, February 1993 (Revised)

(3) Lawrence Livermore National Laboratory Yucca MountainProject Status Report, February 1993

13I3S6Z9304130246 930402PDR WASTEWM 11 PDR

2

cc:(w/out encl.)C. Gertz, YMPO(w/encl.)Ken Hooks, NRCT. J. Hickey, Nevada Legislative CommitteeR. Loux, State of NevadaD. Bechtel, Las Vegas, NVEureka County, NVLander County, Battle Mountain, NVP. Niedzielski-Eichner, Nye County, NVW. Offutt, Nye County, NVC. Schank, Churchill County, NVF. Mariani, White Pine County, NVV. Poe, Mineral County, NVJ. Pitts, Lincoln County, NVJ. Hayes, Esmeralda County, NVB. Mettam, Inyo County, CA

February 1993

Highlights from Los Alamos

WBS 1.2.3.2.1.1.1 (Mineralogy/Petrology)

D. Vaniman visited the Sample Management Facility on 2/23-2/24 to describe portions of drillcore UE-25 UZ-16 for sampling. The samples will be used for two studies important to themineralogy of transport pathways: (1) systematic samples at spacings less than 20 ft. will beused to define vertical variations in mineralogy, and (2) distributed bulk samples of the lowerTopopah Spring Member and of the tuff of Calico Hills will be used to concentrate traceminerals for sorption studies. In contrast to previous sampling of other drill cures for XRDmineralogy, sample spacing for new core is closer and is particularly focused on the criticalbarriers between the welded Tiva and Topopah units and between the potential repositoryhorizon and the water table. About half of UZ-16 was described; the remainder will bedescribed for sampling after drilling is completed.

D. Vaniman continued to work on the review of the Erosion topical report.

B. Carlos examined fractures in core from UE-25 UZ-16 at the SMF and selected samples forfurther analysis.

D. Bish S. Chipera, and G. Guthrie continued to prepare the LAMS report on the distributionof hazardous minerals at Yucca Mountain (Milestone 3352),R. Raymond and G. Guthriecollected several dust samples in the vicinity of UZ-16 in order to assess the background levelsof dust and the changes to the background that may have resulted from operations at UZ-16.Arrangements were also made to have air-filter samples collected by D. Chapman of SAIC.

G. Guthrie responded to inquiries by TRW about the potential hazards associated withmordenite at Yucca Mountain . The TRW data banks suggested that mordenite wascarcinogenic. However, Guthrie prepared a memo discussing the available data on mordenite,none of which indicate that the mineral is carcinogenic.

WBS 1.2.3.2.1.1.2 (Mineralogic and Geochemical Alteration)

D. Bish and S. Levy attended a workshop to discuss thermal loading concerns with LLNLpersonnel. In particular, we discussed; the assumptions inherent in the calculations performedby T. Buscheck and J. Nitao and how mineralogical and petrological features are important inthe modeling. Bish presented data on the mineralogic effects of short- and long-term heatingof zeolites, smectite, and glass and emphasized that these phases can be affected simply bychanging the water vapor pressure. Levy talked about natural hydrothermal alteration thatoccurred during the cooling of Topopah Spring pyroclastic deposit as a self-analog forrepository effects. The workshop identified numerous experimental and modeling needs thatare important in understanding the behavior of a "hot repository."

Los Alat os February 1993 HighlightsPreliminary data-do not reference

WBS 1.2.3.2.3.lA (Volcanism)

Revised probability calculations of the recurrence rate of volcanic events (El), the disruptionratio (E2) and the probability of magmatic disruption of the repository, the controlled area,and the Yucca Mountain region (Pr(E2 given El)Pr(El)) have been completed. The emphasisof the revised calculations is to assess the most likely, the minimum and the maximum valuesof the probability attributes in preparation for simulation modeling to establish probabilitydistributions. This is different from previous work where the calculations were designed toestablish probability bounds. The most likely value of the probability of magmatic disruptionof the repository is < 1 in 10,000 in 10,000 years. The most likely values of the probability ofmagmatic disruption of the controlled area and the Yucca Mountain region are > 1 in 10,000in 10,000 years. Three samples were analyzed for cosmogenic helium during the month. Themeasured cosmogenic He age of the sample is 35 + 5 ka.

WBS L2.3.4.L2.1 (Batch Sorption Studies)

This month we performed batch sorption experiments to study the effect of organic coatings onmetal sorption onto minerals available in the tuff at Yucca Mountain.

The results indicate that the sorption of Cd onto Fe oxide is enhanced by the presence of theorganic coating, however, Cd sorption onto Al oxide decreases as the amount of organic coatingincreases. The enhancement or decrease of Cd sorption was not very large (20%).

WBS L23.4.1.3 (Radionuclide Retardation by Precipitation Process)

P. Palmer, a technician working on the Los Alamos YMP Radionuclide Solubility Task teamfor the past 9 years, has recently received the American Chemical Society's NationalTechnician of the Year Award for his outstanding work. Palmer received recognition by theNew Mexico regional ACS in 1991.

We have obtained results for our UV/Vis absorption study on NpO2 species in (bi)carbonatemedia. At least three species have been observed (consistently) for 0.4 mM Np at 0.9 M(bi)carbonate concentrations from pH 8.4 to 13. This information will serve as a starting pointfor parallel NMR studies as well as bicarbonate concentration and temperature dependentUv/VIS experiments.

The neptunium undersaturation experiment at pH 8.5 was concluded by examining the last ofthe supernatant by adsorption spectroscopy. All of the Np(V) in the pH 8.5 solution wascomplexed by carbonate.

Most task members will be attending the 205th National Meeting of the American ChemicalSociety to be held in Denver, CO, March 28 - April 2, 1993. Palmer will receive his NationalTechnician of the Year Award at this meeting.

WBS L2.3.4.4.11.2 (Radionuclide Retardation by Dispersive, Diffusive, andAdvective Process)

This month we initiated two sets of experiments to further study the transport of Np throughYucca Mountain tufs. The first set consists of studying the kinetics of sorption of Np using

Los Alamos February 1993 HighlightsPreliminary data-do not reference 2

wafers made of intact tuff which are placed in contact with a Np solution in water from thewell J-13 or UE-25 p#l. Aliquots from the Np solution in contact with the tuff wafer aretaken as a function of time so that the uptake of Np by the wafer can be determined. Thewafers were made of tuffs: G4-270 and G4-1532. Next month we will report the results ofthese studies.

The second set of experiments involves eluting a Np solution through crushed tuff columns inorder to determine whether Np sorption onto tuff is reversible, linear, and instantaneous inwaters from the wells J-13 and UE-25 p#1. Four crushed tuff columns are in preparation fromtuffs: G4-270 and G4-1506. This month we are establishing flow rates through the columnswith waters from the well J-13 and UE-25 p#1.

WBS 1.2..3.5 (Technical Database Input)

Submitted Erosion Data to the technical database.

Los Alamos February 1993 HighlightsPreliminary data-do not reference 3

Lawrence Livermore National Laborato

- ' H I; J'J .'d;

LLYMP9303015 WBS 1.2.9March 9, 1993 "QA: N/A"

Carl Gertz, Project Manager cDepartment of Energy wYucca Mountain Project OfficeP.O. Box 98518 JLas Vegas, Nevada 89193-8518

SUBJECT: Yucca Mountain Project Status Report - February 1993SCP: N/A

Attached is the February Project Status Report for LLNL's participation in theYucca Mountain Project.

If further information is required, please contact Elizabeth Campbell of my staffat 510-422-7854 or Jim Blink in Las Vegas at 702-794-7157.

Sincerely,

c]~~~~~~~~~~~ .Y - o

W. L. ClarkeCLn > LLNL Technical Project Officer

C ~~~~~ ~for YMP

WC/EC N.

Distribution

fiEC D) ~i YEAP,

3//- 5/3 ~ DISCLAIMER

The LLNL Yucca Mountain Project cautions that any information is preliminaryand subject to change as further analyses are performed or as an enlarged andperhaps more representative data base is accumulated. These data andinterpretations should be used accordingly.

ENCLOSURE3-1,5: ' "- ? ^'" : 0'' 0 l rE9~u9i~e .t- , . . ................. ln! .. , ilt1-.Q55'*ef'fSz*'oj , , -_x^rv , _';.'-~~ * 9',ye~~s*"~~'~' a~~h'j. * BG>, EOC - '-'-mcF~ Caokr'nj 94557, Th er', e .! r.:;..

-11' . I ~~ " io~ - - I - ~E I L SUR 5. / t'

LAWRENCE LIVERMORE NATIONAL LABORATORY YUCCA MOUNTAIN PROJECTFEBRUARY 1993 TECHNICAL HIGHLIGHTS AND STATUS REPORT

TABLE OF CONTENTS

1.2.1 Systems.WBS 1.2.1.1WBS 1.2.1.5WBS 1.2.1.6

1.2.2 Waste PackageWBS 1.2.2.1WBS 1.2.2.2WBS 1.2.2.2.1

WBSWBSWBSWBS

1.2.2.2.21.2.2.2.31.2.2.2.41.2.2.2.5

Systems Engineering Coordination and PlanningSpecial StudiesConfiguration Management (Blink)

Waste Package Coordination and Planning (Wilder)Waste Package Environment (Wilder)Chemical & Mineralogical Properties of the Waste PackageEnvironment (Glassley)Hydrologic Properties of Waste Package Environment (Buscheck)Mechanical Attributes of the Waste Package Environment (Blair)Engineered Barrier System (EBS) Field Tests (Lin)Characterization of the Effects of Man-Made Materials on Chemical &Mineralogical Changes in the Post-Emplacement Environment (Meike)

Waste Form & Materials Testing (Stout/McCright)Waste Form Testing - Spent Fuel (Steward)Waste Form Testing - Glass (Bourcier)Metal Barriers (McCright)Other Materials (McCright)Integrated Testing (Viani)Integrated Radionuclide Release: Tests and Models (Viani)Thermodynamic Data Determination (Silva)Nonmetallic Barrier Concepts (McCright)

WBS 1.2.2.3WBS 1.2.2.3.1.1WBS 1.2.2.3.1.2WBS 1.2.2.3.2WBS 1.2.2.3.3WBS 1.2.2.3.4WBS 1.2.2.3.4.1WBS 1.2.2.3.4.2WBS 1.2.2.3.5

WBS 1.2.2.4WBS 1.2.2.4.3

WBS 1.2.2.5

Design, Fabrication, and Prototype TestingContainer/Waste Package Interface Analysis

Waste Package - Special Studies

1.2.3 Site InvestigationsWBS 1.2.3.2WBS 1.2.3.2.1.2.1WBS 1.2.3.4WBS 1.2.3.4.2WBS 1.2.3.10

1.2.5 Regulatory

GeologyNatural Analogue of Hydrothermal Systems in Tuff (Glassley)Geochemistry (Glassley)Geochemical Modeling (Wolery)Altered Zone Characterization

Site Characterization Program (Blink)Geologic and Engineering Materials Bibliography of ChemicalSpecies (GEMBOCHS) (Johnson)Technical Data Base Input (Revelli)

Performance Assessment (Halsey)Waste Package Performance Assessment (O'Connell/Maclntyre)

WBSWBS

1.2.5.2.21.2.5.3.4

WBS 1.2.5.3.5

WBS 1.2.5.4WBS 1.2.5.4.2

1.2.9 Project ManagementWBS 1.2.9.1 Management and Coordination (Clarke)WBS 1.2.9.1.2 Technical Project Office Management (Clarke)WBS 1.2.9.2 Project Control (Podobnik)WBS 1.2.9.2.2 Technical Project Office Management (Podobnik)

1.2.11 Quality AssuranceWBS 1.2.11.1 Quality Assurance Coordination and PlanningWBS 1.2.11.2 Quality Assurance Program DevelopmentWBS 1.2.11.3 Quality Assurance VerificationWBS 1.2.11.3.1 Quality Assurance Verification - AuditsWBS 1.2.11.3.2 Quality Assurance Verification - Surveillance

WBS 1.2.11.5 Quality Assurance - Quality Engineering

1.2.12 Information ManagementWBS 1.2.12.2.2 Local Records Center Operation (LRC) (Bryan)WBS 1.2.12.2.5 Document Control (Bryan)

1.2.13 Environment. Safety and HealthWBS 1.2.13.1 Environment, Safety and Health Coordination and Planning (Blink)

1.2.15 Support ServicesWBS 1.2.15.2WBS 1.2.15.3

Administrative Support (Campbell)YMSCP Support for the Training Mission (Bryan)

LAWRENCE LIVERMORE NATIONAL LABORATORY(LLNL)

YUCCA MOUNTAIN PROJECT (YMP) STATUS REPORT

FEBRUARY 1993

EXECUTIVE SUMMARY(Items Proposed for Reporting in YMPO or OGD Reports)

1)1.2.1.5 (Special Studies). V-TOUGH input files were transmitted to C. Newbury atYMPO on February 22. These files will be forwarded to other participants who willrun code-to-code benchmark calculations as a means of partially validating LLNL'sextended dry calculations.

2) 1.2.2.2.1 (Chemical and Mineralogical Properties of the Waste PackageEnvironment). B. Christenson, W. Giggenbach and A. Reyes from New Zealandvisited LLNL on February 5 to discuss potential sites for conducting EQ3/6validation activities. Several sites were identified as likely locations, based on dataavailability, observable or inferred processes at the sites, and accessibility. Plans weredeveloped to have LLNL researchers visit these sites in late March to go through theavailable data to determine if the data are complete enough to actually start thesimulations. The group also visited the Project Office and the Yucca Mountain siteon February 8.

3) 1.2.2.2.2 (Hydrologic Properties of the Waste Package Environment). Theexperiment continued to determine the effect of fracture surface coatings on theimbibition of water into the matrix. Eight Topopah Spring Tuff samples machinedfrom outcrops from Busted Butte were prepared for this purpose. Preliminaryresults indicate that fracture surface coatings decrease the water imbibition rate intothe matrix by a factor of 0.15 to 3 x 10-5, depending on the coating thickness. Thesefindings agree with results obtained by S. Thoma, D. Smith (University of NewMexico) and D. Gallegos (SNL) (1992) on Tiva Canyon and Paintbrush Tuff samples.The mineralogy of the coating material and the pore size distribution in the coatinglayers will be determined.

4) 1.2.2.2.3 (Mechani-al Attributes of the Waste Package Environment). Study Plan8.3.4.2.4.3, Rev. 0, "Characterization of the Geomechanical Attributes of the WastePackage Environmient" was approved and distributed as a controlled document.

5) 1.2.2.2.5 (Characterization of the Effects of Man-Made Materials on Chemical &Mineralogical Changes in the Post-Emplacement Environment). The search of theGEMBOCHS thermodynamic database that supports the EQ3/6 codes for aqueousspecies, glass, and solids that contain carbon has been completed. The search fororganic compounds was expanded in recognition of the important role that carbonbearing compounds play in the following three mechanisms, all of which mayoperate within the ESF and the potential repository site:

1) aerobic microbial degradation of hydrocarbon compounds may increasecarbonate species and thus significantly alter pH,

2) abiotic thermal degradation of organic compounds may generate largeamounts of carbon dioxide that may also significantly alter pH, and

LLNL-February Status Report I

3) carbonate complexation.These mechanisms are particularly important to the determination of spent nuclearfuel solubility.

6) 1.2.2.2.2 (Hydrologic Properties of the Waste Package Environment). Becauselarge-scale, buoyant, gas-phase convection cells do not fully develop in the UZ untilabout 1000 yrs, for sub- to marginal-boiling conditions, above-boiling heater testswill be needed to resolve repository horizon condensate flow issues for low arealmass loading.

1.2.1 SYSTEMS ENGINEERING

1.2.1.1 Systems Engineering Coordination and Planning

No significant activities.1.2.1.5 Special Studies

V-TOUGH input files were transmitted to C. Newbury at YMPO on February 22.These files will be forwarded to other participants who will run code-to-codebenchmark calculations as a means of partially validating LLNL's extended drycalculations.

1.2.1.6 Configuration Management

No significant activities.1.2.2 WASTE PACKAGE

1.2.2.1 Waste Package Coordination and Planning

B. Viani participated in the February Geochemistry Integration Task (GIT)teleconference meeting.

W. Lin attended the (SOC) Sample Overview Committee meeting at NTS onFebruary 9.

-k-. 1.2.2.2 Waste Package Environment

The final respornse to technical review comments on the Preliminary Near FieldEnvironment Report was submitted to YMPO on February 22. After acceptance ofthese comments, the report will be resubmitted for AP 1.3 programmatic review.

1.2.2.2.1 Chemical and Mineralogical Properties of the Waste Package Environment

B. Christenson, W. Giggenbach and A. Reyes from New Zealand visited LLNL onFebruary 5 1o discuss potential sites for conducting EQ3/6 validation activities.Several sites were identified as likely locations, based on data availability, observableor inferred processes at the sites, and accessibility. Plans were developed to haveLLNL researchers visit these sites in late March to go through the available data todetermine if the data are complete enough to actually start the simulations. Thegroup visited the Project Office and the Yucca Mountain site on February 8.

LLNL-February Status Report 2

B. Christensen also spent several days working with LLNL scientists in the use ofEQ3/6. Several specific problems regarding the New Zealand hydrothermal systemwere run on the code.

Newly installed software on the Silicon Graphics Indigo/XS-24 system enhancescapabilities to model equilibrium/disequilibrium domains in the vicinity of wastepackages. This software was used to develop a saturation grid for ambientconditions which will be used, along with ambient mineralogical data, to developmodels of mineral evolution in the vicinity of waste packages.

W. Glassley participated in the workshop to coordinate activities between variousproject participants regarding coupling of geochremical and hydrological processes.This workshop was held February 1-3 at Asilomar, CA. An outline of theconceptual model for geochemical evolution of the altered zone was developed.Discussions also outlined potential problems to be addressed.

1.2.2.2.2 Hydrologic Properties of the Waste Package Environment

-Study Plan 8.3.4.2.4.2 "Laboratory Study of Hydrological Properties of the Near FieldEnvironment" has completed the first phase of internal technical review and hasbeen returned to the author for comment resolution. The initial issue of the StudyPlan will cover the laboratory experiment portion of the study; modeling will beadded during a subsequent revision.

Model Calculations

The Use of Hypothesis Testing in Model Validation

The subject of hydrological model validation has generated considerable debate.LLNL/YMP agrees with scientists who believe that the terms "model validation"and "verification" are misleading in groundwater science and should be replacedwith the process:

1) using models to obtain a better fundamental understanding of the systembeing modeled,

2) utilizing this understanding to formulate fundamental hypotheses which arethe basis of the conceptual model and performance attributes of the system and,

3) perform analyses and experiments in an attempt to test or invalidate theconceptual moders (or hypotheses).

Past monthly reports have described calculations of repository-heat-drivenhydrothermal flow in the repository-unsaturated zone (UZ)-saturated zone (SZ)system to a broad range of thermal loading design parameters, thermo-hydrologicalproperties, and boundary conditions. A broad range of parameters have been, andcontinue to be, investigated in order to identify:

1) distinct regimes of thermo-hydrological performance, and2) conditions that invalidate the following hypotheses:

a) repository-driven heat flow will be dominated by heat conduction,b) the region of above-boiling temperatures surrounding the repository

corresponds to the absence of liquid water in the waste package (WP) environment,

LLNL-February Status Report 3

c) fracture density and connectivity are sufficient to promote rock dry-outdue to boiling and condensate shedding, and

d) re-wetting of the dry-out zone lags significantly behind the end of theboiling period.

In addressing these hypotheses, it will be asked whether hydrothermal-geochemical-geomechanical coupling must be dynamically accounted for in performance modelsor whether it can be conservatively accounted for by bounding analyses. A primarygoal of site characterization, laboratory tests, and in situ heater tests will be to lookfor conditions or processes that have been identified as potentially invalidating anyof the fundamental hypotheses. Knowledge of such conditions, e.g., a highlyfractured fault zone, will be valuable in selecting the location of the repository orWPs.

It is LLNL/YMP's position that hypothesis testing can be more readily applied tomodels that predict the period of radionuclide containment in WPs beforeradionuclide mobilization, release, and transport, than to models that predict howradionuclides are isolated by the natural barriers during the period of radionuclidemigration. For sub- or marginal-boiling conditions, the episodic infiltration ofmeteoric water and condensate drainage are controlled, by the heterogeneousdistribution of hydrological properties, while for above-boiling conditions, they arelargely determined thermodynamically by the heat capacity of the rock. Therefore, itis believed that hypothesis testing is more readily applied to high Areal MassLoadings (AMLs, expressed in metric tons of uranium per acre, MTU/acre) thatproduce long-term, above-boiling conditions surrounding the repository.

Impact of Buoyant, Gas-Phase Convection on Thermo-Hydrological Performance

LLNL/YMP's recent investigations have focused on the impact of large-scale,buoyant, gas-phase convection on thermo-hydrological performance. It is importantto appreciate the fundamental distinction between moisture redistribution drivenby above-boiling conditions and that driven by sub- to marginal-boiling conditions.The performance of the ambient hydrological system is critically dependent onwhether vertically connected fracture pathways exist with sufficient aperture togenerate fracture-dominated flow to the repository horizon (and possibly to thewater table). Similarly, fracture networks of sufficient aperture and connectivity arerequired for repository heat to drive buoyant convection of water vapor from hotterto cooler locations, where condensation occurs. For AMLs that generate sub- ormarginal-boiling conditions at the repository horizon, whether condensate candrain back to the repository horizon is determined by the highly heterogeneousdistribution of fracture and matrix hydrological properties. For high AMLs, as longas a large enough zone of above-boiling conditions surrounds the repository,condensate drainage is unlikely at WP locations. However, after the boiling period,large-scale buoyant convection of water vapor has the potential to eventuallygenerate enough condensate to result in nonequilibrium fracture flow at therepository horizon. Even for low AMLs, large-scale buoyant convection of watervapor in highly fractured zones could generate enough condensate to drivenonequilibrium fracture flow to the repository horizon for tens of thousands ofyears.

LLNL-February Status Report 4

*The potential for large-scale, buoyant convection of water vapor to generate enoughcondensate to drive nonequilibrium fracture flow to the repository horizon isinfluenced by the following factors:

1) whether condensate. drainage is primarily controlled by hydrologicalheterogeneity or thermodynamically,

2) the temperature gradients driving large-scale, buoyant, gas-phase convection,3) the availability of liquid water,4) the connectivity and permeability of fracture networks between locations

where water is evaporating and where it is condensing, and5) the connectivity and permeability of preferential fracture pathways between

locations where water vapor is condensing and the repository horizon.

If a large enough zone of above-boiling conditions surrounds the repository,condensate drainage is extremely unlikely at the repository horizon. Futurecalculations will focus on how factors (2) through (5) impact post-boilingperformance. It is useful, therefore, to compare conditions just as the boiling periodends. With respect to factor (2), the temperature gradients associated withintermediate AMLs are found to be steeper than those associated with high AMLs.Therefore, the driving force for the post-boiling period, buoyant convection of watervapor, increases with decreasing AML.

Both during and after the boiling period, factors (3) and (4) depend on the verticalthickness of the dry-out zone, hdz. Large-scale, buoyant, gas-phase convectiondepends on the large-scale connectivity of fracture networks which generallydecreases with increasing distance between two points (e.g., from the lower to theupper dry-out front), with the tortuosity of the connected fracture pathwaysincreasing. Note that even while the dry-out zone is subjected to above-boilingconditions, large-scale buoyant convection eventually dominates the local boilingpressure gradients (t >1000 yr), resulting in the buoyant convection of water vaporfrom the lower to the upper dry-out front. The water vapor that is evaporated fromthe lower dry-out zone is at least partially replenished by water imbibed from the SZ.The actual distribution, of fracture permeability and connectivity is probablyextremely heterogeneous. The assumption that kb is homogeneous and isotropicoverpredicts the transport of water vapor. Therefore, LLNL/YMP's models of highAMLs conservatively predict the time it takes the upper dry-out front to retreat backto the repository horizon.

For post-boiling- period performance, a critical consideration is the value of hdz atthe end of the boiling period. Similarly, factor (5) is dependent on the distance fromthe upper dry-out front to the repository horizon, which is roughly half of hdz. Atthe end of the boiling period for the reference kb case (2.8x10-13m 2 or280 millidarcy), hdz is 14.4, 110, and 248 m for AMLs of 49.2, 77.4, and154.7 MTU/acre, respectively. Therefore, the potential for post-boiling perioddrainage of condensate to the repository horizon is greater for low AMLs associatedwith small dry-out zones.

LLNL-February Status Report 5s

Impact of UZ Flow on Thermo-Hydrological Performance

In examining the sensitivity of heater test performance to kb, it was found that thereare three distinct categories of thermo-hydrological performance. The low-kb casecorresponds to a situation in which fracture density and connectivity throttle therate of boiling and dry-out. The intermediate-kb case corresponds to a situation inwhich the fracture density and connectivity are sufficient to promote boiling that isno longer throttled by flow resistance in the fractures. However, the intermediate-kb is not sufficiently large to promote substantial large-scale buoyancy-drivenconvection; therefore, local boiling pressure gradients dominate the large-scale,buoyancy-driven, gas-phase pressure gradients, resulting in steam flow andcondensate generation that is vertically symmetrical about the heater horizon.Consequently, heat flow continues to be symmetrical about the heater horizon. Theheat convective effects in the heat-pipe zone have a local, transient effect on thetemperature distribution, but because convection does not significantly enhance theheat loss from the boiling zone to the far-field, the duration of boiling conditions isnot significantly reduced. The high-kb case (kb > 10 darcy or l11m2 ) corresponds toa situation in which fracture density and connectivity are sufficiently large to allowlarge-scale, buoyancy-driven gas-phase gradients to dominate the local boilingpressure gradients, causing significant asymmetry in the vertical temperaturedistribution. Although far-field convection may completely dominate the directionof steam flow, causing 100% of the steam to be driven to the upper condensationzone, heat flow can still dominated by heat conduction, and the duration of theboiling period, t, can be negligibly reduced.

For an AML of 77.4 MTU/acre the lower end of the intermediate-kb range is about10 millidarcy (l 14m 2). Therefore, for kb > 10 millidarcy, significant dry-out occursdue to boiling. For an AML of 154.7 MTU/acre, significant dry-out occurs even if kbis as low as 10 microdarcy (lO-17m 2). Even though AML was only increased by afactor of two, the range of kb for significant dry-out due to boiling is increased bythree orders of magnitude. For an AML of 154.7 MTU/acre, the maximum verticalthickness of the dry-out zone, hdz, is 372 m for the reference-kb case (280 millidarcyor 2.8 x 10-13m 2) at t = 2000 yr. The dry-out front corresponds to the location wherethe normalized liquid saturation equals 0.9. The normalized liquid saturation is theliquid saturation (Si) divided by the initial liquid saturation. In other words, thedry-out front occlrs where Si is 10% drier than ambient. For kb values of10 microdarcy, 100 microdarcy, 1 millidarcy, 1 darcy and 5 darcy (a range from 10-17to 5 x lIG 12 m 2), the dry-out zone thickness is 132, 199, 283, 384, and 387 m. The dry-out thickness varies by only 30%, a factor of two, and a factor of three for kb ranges ofnearly 4, 5, and 6 orders of magnitude. Therefore, high AMLs, such as154.7 MTU/acre, are required in order to achieve significant dry-out at very low kb(< 10 microdarcy).

The Need for Above-Boiling Heater Tests for Low to Medium AMLs

Low to medium AMLs generate sub- to marginal-boiling conditions. Under suchconditions, the large-scale buoyant convection of water vapor in highly fracturedzones can cause condensate drainage at the repository horizon that is orders ofmagnitude greater than the recharge flux due to a pluvial climate. It was found that

LLNL-February Status Report6 6

large-scale buoyant convection of water vapor can also significantly influencerepository temperatures. This effect only occurs if water vapor is convected in verylarge quantities from below the repository to cooler locations above the repository,where it condenses and drains back towards the repository. The analysis of Ross etal. indicates that it requires about 1000 yr for large-scale, buoyant, gas-phaseconvection cells to fully develop in the UZ. LLNL/YMP's calculations also indicatethat it requires about 1000 yr for convection cells to impact sub-boiling performance.Therefore, it will not be possible to observe such effects during either:

1) heater tests conducted under sub- to marginal-boiling conditions, or2) the period of performance confirmation.

In order to assess the potential for large-scale buoyant vapor flow to result incondensate drainage at the repository horizon under sub-boiling conditions, it willbe necessary to rely on heater tests conducted under above-boiling conditions. Thereare very distinct differences in the vertical temperature profile between theintermediate- and high- kb heater test cases. The high kb case uses the same value ofkb (84 darcy or 8.4 x 101 1m 2) which produced very large condensate drainage fluxesfor AMLs of 49.2 and 27.1 MTU/acre. Such large fluxes could result innonequilibrium fracture flow at the repository horizon for tens of thousands ofyears. The potential for significant condensate flow at the repository horizon cannotbe resolved without above-boiling heater tests.

Code Development

S. Daveler developed an input "checker" for V-TOUGH to look for input which isobviously incompatible with input format. She continues to work on thedocumentation for V-TOUGH.

T. Quinn released Version 5.6 of V-TOUGH which has:1) a new option (14) for the relative permeability and capillary pressure curves

and2) an interrupt capability for the SUN and IBM workstations.

The new interrupt capability allows V-TOUGH to write an "emergency" restart file ifit senses that the operating system is about to abort the run. There is also an optionfor the user to produce a restart file by typing in a control-C which then terminatesthe run after creating the restart file. Option 14 prevents the gas-phase relativepermeability frorp being reduced to zero as a liquid saturation of 1.0 is approached.This option may be applicable to unsaturated fracture flow. Heterogeneouscondensate drainage in fractures will probably make it very unlikely that 100% ofthe fracture porosity could be saturated with liquid, particularly above therepository. This option translates the original relative permeability curve to a curvewhich approaches a maximum liquid-phase saturation which is less than one. Afinite gas-phase relative permeability will remain at all times. This option willallow more conservative investigation of the potential thermo-hydrological effectsof large-scale, buoyant, gas-phase convection.

LLNL-February Status Report 7

Laboratory Experiments

Work continued on electrical resistivity measurements as a function of moisturecontent of Topopah Spring Tuff samples from U3hg-1 and GU-3 holes at roomtemperature, using J-13 -water as pore fluid. The purpose of the experimentalprocedure is to determine the effect of the electrical conductivity of pore fluid on therelationship between the bulk electrical conductivity of a rock sample and the degreeof saturation in it. At this point in the wetting phase of the measurement, thesamples have reached a saturation level of about 50%. The measured bulkresistivity using J-13 water as pore fluid is the same as when distilled water is used.Investigations are underway to understand this phenomenon. One possibleexplanation is that, at low levels of water saturation, the continuous layer of wateron the mineral surface is dominating the conduction of electrical energy in the bulkrock and the chemical reaction between distilled water and the minerals within thislayer is very efficient. This work will have significant implications for rock-waterinteractions.

Work continued on the investigation of different imbibition rates of water into arock sample when the sample is either in a vapor environment or in liquid water.To understand the mechanism of the imbibition, capillary. tubes of various insidediameters (ID) were placed in a constant humidity chamber which is set at variouslevels of humidity. The imbibition rate of water into each capillary tube will bedetermined. It was determined that even capillary tubes with an ID as small as33 microns do not imbibe moisture in a 95 - 100% relative humidity environment.The effect of nucleation on the imbibition will be investigated by placing a partiallyfilled capillary tube in a vapor environment.

The experiment continued to determine the effect of fracture surface coatings on theimbibition of water into the matrix. Eight Topopah Spring Tuff samples machinedfrom outcrops from Busted Butte, NV were prepared for this purpose. Preliminaryresults indicate that fracture surface coatings decrease the water imbibition rate intothe matrix by a factor of 0.15 to 3 x 10-5, depending on the coating thickness. Thesefindings agree with results obtained by S. Thoma, D. Smith (University of NewMexico) and D. Gallegos (SNL) (1992) on Tiva Canyon and Paintbrush Tuff samples.The mineralogy of the coating material and the pore size distribution in the coatinglayers will be determined.

Work has started to prepare Topopah Spring Tuff samples from the G4 hole fordetermining the moisture retention curve and one-dimensional imbibition at hightemperatures.

Meetings

D. Wilder, T. Buscheck, and D. Chesnut met with the LANL staff at Los Alamos onFebruary 24 to discuss the effect of heat on repository performance.

The abstract by J. Roberts and W. Lin entitled "The Effects of Water Saturation andWater Chemistry on the Electrical Conductivity of Topopah Spring Tuff" wassubmitted to YMPO for review. It will be presented at the American GeophysicalUnion meeting in Baltimore, MD on May 24-28.

LLNL-February Status Report 8

1.2.2.2.3 Mechanical Attributes of the Waste Package Environment

Study Plan 8.3.4.2.4.3, Rev. p, "Characterization of the Geomechanical Attributes ofthe Waste Package Environment" was approved and distributed as a controlleddocument.

A revision was prepared and forwarded to YMPO to correct several typo's noted inthe document.

The setup of initial computations of stress in the near field environment for theextended dry concept has been started. This is in response to the suggestion byW. Simecka (YMPO) that the near field environment team gather relevantinformation on the extended dry concept.

Personnel were interviewed for laboratory support of the geomechanicalexperiments to be conducted in concert with the Large Block tests.

1.2.2.2A Engineered Barrier System (EBS) Field Tests

Study Plan 8.3.4.2.4.4, "Engineered Barrier System Field Tests" has completed initialinternal technical review and has been returned to the author for commentresolution.

J. Blink met with G. Danko (University of Nevada, Reno) in Reno on February 5 todiscuss use of Prof. Danko's REKA instrument on the Large Block Test and on EBSfield tests in the ESF.

Large Block Test (LBT)

The Scientific Investigation Plan for Large Block Testing of Coupled Thermal-Mechanical-Hydrological-Chemical Processes is in internal technical review.

The preliminary moisture content of some small pieces of Topopah Spring Tufffrom the Fran Ridge outcrop has been determined to be about 30%. Work willcontinue to refine the moisture content determination. This information will beused in the design of the Large Block Tests.

J. Blink, Y. Chan, W. Lin, and D. Wilder met with M. Voegele (SAIC) on February 9to discuss issues related to the large block cutting and testing. The initial design ofthe loading frame has been completed. A drawing of the design will be available forbidding next month.

J. Blink, Y. Chan, W. Lin, J. Roberts, and D. Wilder met with REECo and Sandiapersonnel at NTS on February 23 to discuss issues related to the isolation andprotection of the large block. A SANL will be initiated next month for theprocurement of Sandia's service of cutting the block(s).

LLNL-February Status Report 9

1.2.2.2.5 Characterization of the Effects of Man-Made Materials on Chemical &Mineralogical Changes in the Post-Emplacement Environment

Revision of the draft Study Plan 8.3.4.2.4.5 "Characterization of the Effects of Man-Made Materials on the C-hemical and Mineral Changes in the Post EmplacementEnvironment" continues.

The search of the GEMBOCHS thermodynamic database that supports the EQ3/6codes for aqueous species, glass, and solids that contain carbon has been completed.The search for organic compounds was expanded in recognition of the importantrole that carbon bearing compounds play in the following three mechanisms, all ofwhich may operate within the ESF and the potential repository site:

1) aerobic microbial degradation of hydrocarbon compounds may increasecarbonate species and thus significantly alter pH,

2) abiotic thermal degradation of organic compounds may generate largeamounts of carbon dioxide that may also significantly alter pH, and

3) carbonate complexation.These mechanisms are particularly important to the determination of spent nuclearfuel solubility.

As a consequence of these results, the following actions are being taken.1) The database is being evaluated to identify the organic compounds that are

likely to be introduced into the ESF and the potential radioactive waste repositoryfor which the thermodynamic and kinetic properties are not well established.

2) An experimental plan for the organic materials study program is beingdeveloped.

3) Lab facilities for these experiments are being assembled.

A final version of the position paper summarizing the chemical concerns for theintroduction of Man-Made Materials to the ESF was provided to the M&O.

1.2.2.3 Waste Form and Materials Testing

1.2.2.3.1 Waste Form

1.2.2.3.1.1 WasteForm Testing - Spent Fuel

Scientific Investigation Plan SIP-WF-O1, Rev. 1.0, "YMP Spent Fuel Waste FormTesting" was completed and sent to YMPO for acceptance.

The revised PNL FY93 workscope proposal was submitted to LLNL for review andapproval.

R. Stout (LLNL), D. Harrison (YMPO), and H. Benton (M&O) met with J. Bates(ANL) at ANL on February 3 to present ANL's range of experimental and analyticalcapabilities, along with their interests in support of the YMP waste package effort.

LLNL-February Status Report I10

I Spent Fuel Dissolution

The flow-through dissolution tests on U0 2 at LLNL are continuing. The 2% oxygenroom temperature runs ere completed. The very low (0.2% oxygen) roomtemperature runs were continued because of difficulties in maintaining the correctflow rate and oxygen level. The higher temperature, low oxygen experiments arebeing set up and will be finished in several weeks. This will conclude the originaltest matrix for U0 2 dissolution tests over a range of temperature, pH, oxygen, andcarbonate/bicarbonate aggressive water chemistries.

In addition, two long-term, room temperature, flow-through dissolutionexperiments have been ongoing since October 1992. These dissolution tests use U0 2powder provided by PNL for similar experiments. The first buffer composition is0.02M sodium bicarbonate at a pH of 8. The second composition is saline with 0.01Msodium bicarbonate and 0.1M sodium chloride; the pH is not being controlled. Afterseveral months, the uranium dissolution rate for the non-saline solution is about1 mg/m2 /day. The uranium dissolution rate in the saline solution is somewhathigher at about 3 mg/m2 /day.

Equipment for measuring BET surface areas has been installed in the PNL Bldg. 325hot cells, and measurements have been successfully completed on a few spent fuelspecimens.

Flow-through dissolution tests at PNL have been started on ATM-106 fuel (PWRfuel with burnup -48 MWd/kgM and fission gas release 18%) in both oxidized(O/M -2.4) and unoxidized forms following BET measurements of their surfaceareas.

Spent Fuel Oxidation

The abstract by R. Stout, E. Kansa and A. Wijesinghe entitled "Kinematics andThermodynamics Across a Propagating Non-Stoichiometric Oxidation Phase Frontin Spent Fuel Grains" was approved by YMPO for presentation at the ASMEMicromechanical Random Media Conference at the University of Virginia onJune 6-9.

Dry Bath Testing

R. Einziger (PNL) visited LLNL to discuss plans for the startup of a new dry bathoxidation test. This test, to be performed at 2550C, will be used to determine theU 409 to U308 transition. A test plan addendum was completed and sent to LLNLfor review and approval.

Plans are being finalized to bring B. Hanson, a graduate student from UC Berkeley,to PNL. He will conduct thermogravimetric apparatus (TGA) tests to elucidate theU409 to U 30 8 transition and develop a methodology for measuring the transition atlow temperatures.

The dry bath oxidation tests continue to run without problem.

LLNL-February Status Report I I

Materials Characterization Center (MCC) Hot Cell Activities

The comments to the PNL report entitled "Methodology for Determining MCCSpent Fuel Acquisitions" are being resolved. The report should be resubmitted forfinal approval in March. -

1.2.2.3.1.2 Waste Form Testing - Glass

A draft was completed of the Technical Implementing Procedure "Procedure forFlow-Through Leach Experiments" which will be reviewed and submitted forapproval as a controlled document.

The abstract by W. Bourcier, S. Carroll, B. Phillips (LLNL), J. Bates and W. Ebert,(ANL) entitled "Modeling 202-SRL Glass Dissolution: Combined Constraints fromVarying SA/V, Flow-Through, Surface Titration, AEM, and NMR Experiments"was submitted to YMPO for approval. This paper will be presented at the AmericanCeramic Society meeting in Cincinnati, OH, April 18-22.

D-20-27 Unsaturated Testing of WVDP and DWPF Glass

The N2 tests (SRL actinide-doped glass) continue with no sampling period occurringthis month. These tests have been in progress for 360 weeks. The N3 tests (ATM-10,a West Valley actinide-doped glass) continue and have been in progress for278 weeks.

1.2.2.3.2 Metal Barriers

D. McCright was appointed Technical Area Leader for the EBS MaterialsCharacterization Technical Area on February 1. Members of this technical area metwith representatives of YMPO and the M&O on February 11 to discuss recentdevelopments in waste package designs, fabrication, and materials. An outline for alimited amount of experimental work was developed; the purpose of this work is tosupport thermal load decisions on the extended dry concept for long termcontainment.

At the request of RmFish (M&O), J. Mitchell provided estimates of the material costsfor the three materials recommended for the YMP Conceptual Design (single,material, thin-walled container); nickel-rich Alloy 825, nickel-base Alloy C-4, andGrade 12 titanium. The costs were based on manufacturing estimates for plate stock.

Work is continuing on compiling information on carbon steels, low alloy steels, andcast irons for a degradation mode survey on this class of materials. Thick sections ofthese iron-base materials could be used as an overpack for multiple purposecontainers, and their use would be consistent with strategies toward high thermalloads to keep the near field environment "dry" for an extended period of time.

Laboratory equipment was moved and re-installed in readiness for performingsome experimental work. A purchase order for a thermogravimetric apparatus(TGA) system was submitted for a capital equipment purchase. The TGA system

LLNL-February Status Report 1 2

will be used for sensitively determining the corrosion and oxidation rates of metalsas a function of temperature and humidity.

At the request of the Peiformance Analysis Technical Area, J. Mitchell providedestimates of the reduction of container wall thickness of carbon steel engineeredbarrier overpacks for 10,000 years based on the extended dry waste package designconcept. These estimates were based on low temperature oxidation of steel as theoperable degradation mode.

1.2.2.3.3 Other Materials

This WBS element has not been funded in FY93.

1.2.2.3.4 Integrated Testing

12.23.4.1 Integrated Radionuclide Release: Tests and Models

Determination of Elemental Profiles in Rocks, Minerals, and Glasses using the IonMicroscope

Secondary ion mass spectroscopy (SIMS) analysis has begun.

The preparation and characterization of Clinoptilolite samples to be used for hightemperature cation exchange experiments has begun.

Interactions of Actinide-bearing Solutions with Rock Core Samples

The balance, data logging cables and Lab View software options for automating flowrate measurements were installed on the flow-through apparatus. Work continueson altering the balance to accept the effluent feed tube.

1.2.2.3.4.2 Thermodynamic Data Determination

Information was provided to A. Simmons and R. Levich of YMPO on the status ofU.S. contributions to NEA work.

1.2.2.3.5 Nonmetallic Barrier Concepts

This WBS element has not been funded in FY93.

L 2.2.4 Design, Fabrication, and Prototype Testing

1.2.4.3 Container/Waste Package Interface Analysis

This WBS element has not been funded in FY93.

LLNL-February Status Report 1 3

1.2.3 SITE INVESTIGATIONS

1.2.3.1 Site Investigations Coordination and Planning

This WBS element has not been funded in FY93.

1.2.3.2 Geology

1.2.3.2.1.2.1 Natural Analogue of Hydrothermal Systems in Tuff

This WBS element has not been funded in FY93.

1.2.3.4 Geochemistry

1.2.3.4.2 Geochemical Modeling

Activities continued to set up the 486 PC as a second host platform for EQ3/6 ADOS emulator was set up on the Sun SPARCstation to perform UNIX to DOSconversions (the emulator is roughly equivalent to a 286 PC). The SPARC is nowcapable of writing compressed DOS files on DOS-formatted floppies. Version 7.1 ofEQ3/6 was transferred to the 486 PC in this manner. It is being ported onto thismachine using the Lahey F77L EM/32 Fortran compiler.

Rev. 0 of the "Software Design Documentation for EQ3/6, Version 8" is beingreviewed.

L2.3.10 Altered Zone Characterization

YMPO has notified LLNL of its decision to fund this WBS element with FY92underrun funds; however, the funds have not yet been furnished to LLNL in anApproved Financial Plan (AFP).

1.2.5 REGULATORY

L2.5.1 Regulatory Coordination and Planning

This WBS element has not been funded in FY93.

1.2.5.2 Licensing

1.2.5.2.2 Site Characterization Program

LLNL participated in the Integration Group meeting to review draft responses tocomments from the NRC, the State of Nevada and affected counties on the "Report'of Early Site Suitability Evaluation of the Potential Repository Site at YuccaMountain, Nevada". Participant representatives met with YMPO staff in Las Vegason February 23 to finalize comment responses.

LLNL-February Status Report 1 4

1.2.5.3 Technical Data Management

1.2.5.3.4 Geologic and Engineering Materials Bibliography of Chemical Species(GEMBOCHS)

The prototype development of a WINDOWS/4GL (mouse-driven) version ofDOOUT was completed. This program facilitates interactive point-and-clickgeneration of thermodynamic datafiles for EQ3/6, GT and other geochemicalmodeling packages. The program is currently undergoing local beta testing.

Several new modifications were incorporated to CNGBOCHS (and the associatedCNGREQ database). These will greatly simplify the planned use of this automatedchange-request package by other LLNL/YMP research groups (in addition toGEMBOCHS and EQ3/6, for whom the package was originally designed).

A dedicated directory was established on the GEMBOCHS sparcstation2 (node s60 ofthe local Sun network) where the new generation of GUI (Graphical User Interface)GEMBOCHS software will reside; the DOOUT prototype will be the first suchprogram available.

A customized, composite thermodynamic datafile that contains only carbon-bearingspecies was generated for use with EQ3/6.

1.2.5.3.5 Technical Data Base Input

J. Johnson attended the Ingres Education Course "INGRES for ApplicationDevelopers (INGRES/Embedded SQL)" at Ingres headquarters in Alameda, CA onFebruary 1-5.

1.2.5.4 Performance Assessment

1.2.5.4.2 Waste Package Performance Assessment

The LLNL EBS/NFE performance assessment staff began a series of meetings todiscuss issues and ideas for a source term description incorporating explicit thermaleffects. LLNL hosteda two day visit by the Total System Performance Assessment(TSPA) staff from SNL to discuss the source term scope for TSPA-2. A preliminaryscope has been- prepared to elicit feedback from other participants. A series oftechnical work sessions has begun with Waste Form, Waste Package Materials, andNear Field Environment personnel to develop mechanistic process descriptions tobe abstracted into the improved source term.

The modeling of thermal response was extended for drift-emplaced-packagerepository design concepts, to calculate container temperature history as well ascladding temperature history. The model is a parameterization of detailedcalculations done in other tasks as described in last month's progress report. Thecontainer material has not been selected, and therefore the upper temperature limithas not been selected. Trial analyses show that feasible design parameters can meettemperature limits in the 200 to 3000C range with different areal mass loadings. Oneselection has 155 MTU/acre and a container temperature limit of 3000C; another has

LLNL-February Status Report 1I15

-

92 MTU/acre and a container temperature limit of 2000C. A container temperaturelimit even of 3000C is more of a constraint than is a cladding temperature limit of3500C. This is not an optimization study; it is a feasibility study to select anappropriate design as the subject of a performance assessment.

Revisions are being made to the PANDORA theoretical manual "PANDORA 1.1User's Manual" by L. Lewis and C. Hardenbrook as a result of reviewers' comments.

1.2.9 PROJECT MANAGEMENT

1.2.9.1 Management and Coordination

1.2.9.1.2 Technical Project Office Management

W. Clarke attended a dry run of the briefing for L. Barrett (OCRWM) in Las Vegas onFebruary 2.

LLNL responded to a request for feedback on the use and/or improvement of theSite Atlas. There were no comments at this time.

M. Revelli reviewed the draft and final reports to the Assessment Team on theNatural Barriers Evaluation Workshop. Comments were forwarded to A. Van Luik(M&O) in Las Vegas.

W. Clarke, B. Bryan and M. Revelli hosted R. Hughey and G. Peterson (DOE/SAN)on February 3. In addition to a tour of facilities at LLNL supported by the YuccaMountain Site Characterization Project, the visit included discussions withLLNL/YMP management and principal investigators.

D. Stahl, P. Gottlieb (M&O) and M. Smith (YMPO) met with LLNL staff inLivermore on February 11 to discuss FY93 budget and workscopes. D. Harrison(YMPO) and H. Benton (M&O) met with LLNL staff on February 18 for furtherdiscussions.

J. Blink (LLNL) and members of the YMPO and M&O staff met with C. DiBella of theNuclear Waste Technical Review Board (NWTRB) staff on February 16-17 inLas Vegas. Several LLNL papers to be presented at the upcoming IHLRWMconference were given to Dr. DiBella.

J. Blink attended the Quality Integration Group Meeting in Las Vegas onFebruary 19. J. Blink participated in the Infrastructure Cost Reduction committeemeeting in Las Vegas on February 12.

J. Blink met with T. Statton (M&O) on February 22 to discuss LLNL input to theFY94 Annual Plan for Site Characterization. J. Blink provided input to the SRG-5drilling meeting in Las Vegas on February 24; core was requested to support LLNLStudy Plans.

J. Blink presented hands-on science lessons to 560 elementary school students atHuffaker School in Reno, NV and Bijou School in South Lake Tahoe, CA on

LLNL-February Status Report 1 6

February 2-4. He also served as an NTS-YMP tour guide for 45 students and adultsfrom the Booker Sixth Grade Center (of Las Vegas) on February 11. Finally, hepresented hands-on science lessons to 140 students at the Meadows ElementarySchool in Las Vegas on February 26 and March 1.

J. Blink participated in Nevada Regional Science Bowl Training in Las Vegas onFebruary 12 and served as a moderator for eight matches on February 28. At the"Science Bowl Pizza Party" that evening, J. Blink supervised a speed-of-lightmeasurement contest for the students.

129.2 Project Control

1.2.9.2.2 Participant Project Control

The January FTE cost report was submitted to YMPO. The January actual scheduleprogress and costs to PACS reporting system were submitted via the PACS reportingsystem. A variance analysis explanation was developed for several P&S accountsfor activities undertaken in January.

The Cost Plan was updated to include January actuals.

The capital acquisition plan is still under development. The plan addresses threecomputing systems: a Silicon Graphics Computer, two Sun SPARCstations1OMod4l, and a Model 54 Sun SPARCstation. A revised list of FY93 capitalequipment requirements was submitted to YMPO.

A response was generated to a YMPO request for additional (BOE) Basis of Estimatessheets for Mission 2001 planning. Several WBS elements list LLNL as a responsibleparticipant. However, since LLNL does not contemplate activity under theseelements, BOE records have not been developed.

J. Podobnik and P. Krantz attended Performance Management Training inIdaho Falls, ID, February 23-26. The course was conducted by PerformanceManagement Associates. The first two days covered systems and techniques forearned value measurement. The second half of the course focused on schedulingtechniques, and wa's attended by P. Krantz, a newly assigned Project Controltechnician, as part of her indoctrination/training.

The FY95 Field Work Proposal (FWP) is being developed. This annual planningdocument is a DOE requirement placed on the entire Laboratory and is submitteddirectly to DOE through the San Francisco Field Office (SAN). YMPO is not directlyinvolved. This year's submission will cover FY93-95.

Work continues to automate transfer of data between laboratory financial systemsand the PACS workstation. The FTE calculation module is approximately 80%complete. The remaining modules are labor dollars and other direct charges.

LLNL-February Status Report 1 7

12.11 QUALITY ASSURANCE

1.2.11.1 Quality Assurance Coordination and Planning

The Trend Analysis Report for calendar year 1992 was completed in accordance withthe requirements of QP 16.2. The report was approved and distributed onFebruary 19.

1±11.2 Quality Assurance Program Development

Following a thorough internal review of the DOE/RW-0333P QARD (Rev. 0), LLNLcompleted a draft QARD Implementation Matrix, an Impact Analysis and aTransition Plan. This material was transmitted to the YMQAD office onFebruary 10. Work continues at LLNL to develop those changes to internalprocedures that have been identified as necessary to fully implement the QARD.

1.2.11.3 Quality Assurance Verification

CAR-LLNL-009 was completed, verified and transmitted to the YMQAD office.

1.2.11.3.1 Quality Assurance Verification - Audits

No significant activities.

1.2.11.3.2 Quality Assurance Verification - Surveillance

No significant activities.

1.2.11.4 Field Quality Assurance/Quality Control

This WBS element has not been funded in FY93.

1.2.11.5 Quality Assurance - Quality Engineering

Support continued for the Waste Form Characterization area.

1.2.12 INFORMATION MANAGEMENT

1.2.12.2 Records Management

1.2.12.2.2 Local Records Center Operation (LRC)

No new revisions or change notices were issued by Document Control.

1.2.12.23 Participant Records Management

A total of 216 items were logged into the LLNL-YMP tracking system. This includes29 records/records packages that were processed through to the CRF. Ten actionitems were closed.

LLNL-February Status Report 1 8

Approximately half of the 1992 records have been cross referenced from the databaseto microfilm.

L2.12.2.5 Document Control

LLNL received no funding under this WBS. Work performed to complete LLNL'sobligation in this WBS is funded under WBS 1.2.12.2.2.

1.2.13 ENVIRONMENT, SAFETY AND HEALTH

1.2.13.1 Environment, Safety and Health Coordination and Planning

The M&O was informally notified of LLNL resource requirements in this"element".

Changes were submitted to the PEARL directory.

1.2.15 SUPPORT SERVICES

1.2.15.2 Administrative Support

No significant activities.

1.2.153 Yucca Mountain Site Characterization Project (YMP) Support for theTraining Mission

A response was sent to YMPO regarding the training of personnel in the starter"- tunnel. LLNL personnel would be treated as visitors who would only require an

hour or two per visit to observe geologic features. They would be escorted by trainedmining personnel.

Forty four different self-study assignments were issued, and 138 people were trainedto these assignments. Currently, there are 70 participants on the project who are tobe trained and/or tracked.

B. Bryan and T. Holmes attended the Training Coordinator's meeting in Las Vegason February 23-25. Two days of this meeting were devoted to Performance BasedTraining.

J. Blink completed General Employee Radiological Training in Las Vegas onFebruary 17.

LLNL-February Status Report 1 9

LLNL PROJECT STATUS REPORT DISTRIBUTION

EXTERNAL

PRELIMINARY STAMPDr. J. BatesChemical Technology DivisionArgonne National Laboratory9700 S. Cass AvenueArgonne, Illinois 60439

H. Benton/D. StahlSte P110101 Convention Center DriveLas Vegas, Nevada 89109

A. Berusch (RW-20)OCRWMForrestal BuildingWashington, DC 20585

. BlanchardYucca Mountain Project OfficeU.S. Department of EnergyP. O. Box 98518Las Vegas, Nevada 89193-8518

T. BlejwasSandia National LaboratoriesP.O. Box 5800Albuquerque, NM 87185

J. BlinkLLNL/Las Vegas101 Convention Center Drive,Suite 820Las Vegas, NV 89109

BoakYucca Mountain Project OfficeU.S. Department of EnergyP. 0. Box 98518Las Vegas, Nevada 89193-8518

S. BodnarTRW, Mail Stop 423101 Convention Center DriveLas Vegas, Nevada 89109-2005

M. BrodeurScience Applications Int'l Corp101 Convention Center Dr. # 407Las Vegas, NV 89109-2005

J. CanepaLos Alamos National LaboratoryP.O. Box 1663/N-5, MS J521Los Alamos, NM 87545

P. ClokeScience Applications Int'l Corp101 Convention Center Dr. # 407Las Vegas, NV 89109-2005

,,-W DixonYucca Mountain Project OfficeU.S. Department of EnergyP.O. Box 98518Las Vegas, Nevada 89193-8518

A.-DyerYucca Mountain Project OfficeU.S. Department of EnergyP.O. Box 98518Las Vegas, Nevada 89193-8518

PRELIMINARY STAMPR. EinzigerBattelle-Pacific NorthwestP.O. Box 999/MS P714Richland, WA 99352

L. D. FoustTechnical Project OfficerCRWMS M&O101 Convention Center DrivePhase II, Suite P110Las Vegas, NV 89109

C. GertzYucca Mountain Project OfficeU.S. Department of EnergyP.O. Box 98518Las Vegas, Nevada 89193-8518

Er-Harrison _.Yucca Mountain Project OfficeU.S. Department of EnergyP.O. Box 98518Las Vegas, Nevada 89193-8518

L. HayesU.S. Geological SurveyBox 25046/MS 425Denver Federal CenterDenver, Colorado 80225

R. HugheyNuclear Energy DivisionUSDOE/SAN1333 BroadwayOakland, CA 94612

IorriYucca Mountain Project OfficeU.S. Department of EnergyP.O. Box 98518Las Vegas, Nevada 89193-8518

C. JohnsonM&O101 Convention Center DrivePhase II, Suite P110Las Vegas, NV 89109

P. JustusNuclear Regulatory Commission301 E. Stewart Ave.*#203Las Vegas, NV 89101

H. KaliaLANL/LV101 Convention Center Drive #1024Las Vegas, NV 89109-2005

PRELIMINARY STAMPS. Marschman, P7-14Battelle, Pacific NorthwestP.O. Box 999Richland, WA 99352

M. MardifTRW, Mail Stop 423101 Convention Center DriveLas Vegas, Nevada 89109-2005

J. NelsonScience Applications Int'l Corp101 Convention Center Dr. # 407Las Vegas, NV 89109-2005

P. OsborneScience Applications Int'l Corp101 Convention Center Dr. # 407Las Vegas, NV 89109-2005

R. L. RobertsonTRW-Metro Place2650 Park Tower Dr.Suite 800Vienna, VA 22180

,,AV SimeckaYucca Mountain Project OfficeU.S. Department of EnergyP.O. Box 98518Las Vegas, Nevada 89193-8518

SimmonsYucca Mountain Project OfficeU.S. Department of EnergyP.O. Box 98518Las Vegas, Nevada 89193-8518

L. SnowRoy F. Weston, Inc.955 L'Enfant Plaza, S.W.Washington, DC 20024

H. SpiekerNuclear Waste Mgmt SystemM&O101 Convention Center DriveSuite #P110Las Vegas, NV 89109-2005

n EGaG ENERGYMEASUREMENTS WBS 1.2.5.3.6

Las Vegas Area Operations /SQA: NAEG&G ENERGY MEASUREMENTS INC.. P.O. BOX 1912. LAS VEGAS. NEVADA 89125 TEL(702) S

March 15, 1993NV-93-192

0

Mr. Carl P. Gertz, Project ManagerU.S. Department of EnergyYucca Mountain Site Characterization Project Office101 Convention Center DriveLas Vegas, NV 89109

FEBRUARY 1- FEBRUARY 28, 1993 PROGRESS REPORT - EG&G/ENERGYMEASUREMENTS REMOTE SENSING LABORATORY SUPPORT TO THEYUCCA MOUNTAIN SITE CHARACTERIZATION PROJECT

Enclosed is a progress report on the EG&G Energy Measurements (EG&G/EM)Remote Sensing Laboratory (RSL) support to the Yucca Mountain Site CharacterizationProject (YMP) for February 1, 1993 through February 28, 1993.

The progress report for EG&G/EM RSL support to YMP includes the followingsections:

o Work Accomplishedo Expenditureso Status of Deliverables

If you have any questions, please contact Elaine Ezra at (702) 794-7449.

mes Michael, ManagerNV Program

CE/ns;2 $CE:ns )ib_~ / i-. God )

Enclosures

Carl P. GertzFEBRUARY 1- FEBRUARY 28, 1993 PROGRESS REPORT - EG&G/ENERGYMEASUREMENTS REMOTE SENSING LABORATORY SUPPORT TO THEYUCCA MOUNTAIN SITE CHARACTERIZATION PROJECTMarch 15, 1993Page 2

cc: S.M.S.W.M.R.KJ.C.A.M.A.D.W.

Ronshaugen, DOE/NV EMD (w/o encl)Blanchard, DOE/YMP (w/o encl)Bodnar, M&O (w/o encl)Dixon, DOE/YMP (w/o encl)Dockter, DOE/NV (w/o encl)Dyer, DOE/NV (w/o encl)Grassmeier, DOE/YMP (w/o encl)Lorenz, REECo/YMPNewbury, DOE/YMPRobison, DOE/YMP (w/o encl)Ryder, DOE/YMP (w/o encl)Simmons, DOE/YMPWilliams, DOE/YMP (w/o encl)Wilson, DOE/YMP

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO IMPWork Accomplished

WBS 12.3 SITE INVESTIGATIONS

WBS 1.2.3.1 SITE INVESTIGATIONS COORDINATION AND PLANNING

REPORT PERIOD: February 1, 1993 - February 28, 1993

REPORT DATE: March 10, 1993

RESPONSIBLE INDIVIDUAL: D.W. Brickey

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. An element of the YMP 3-D modeling efforts is for EG&G/EM to attempt toconvert a 3-D stratigraphic model developed using Lynx software into DynamicGraphics 3-D modeling software. Jim Nelson (SAIC-Golden) has been tasked tosend an ASCII formatted cross-section file generated using the Lynx Geosystemssoftware and Garth Kirkham (Lynx) will send a WaveFront formatted 3D modelexport file so that the Dynamic Graphics conversion effort can be initiated.

WaveFront files were received from Garth Kirkham at Lynx, however, the fileswere unreadable. The files had been produced on an IBM RS6000 system.Kirkham will regenerate the files on a SUN system. Jim Nelson has not yetprovided the example cross-section files.

2. David Brickey attended a meeting with Dr. Angelo Yfantis, (UNLV ComputerScience) during the first week in February. In attendance at the meeting wereRuss Dyer, Claudia Newbury (DOE/YMP), Chris Rautman (SNL), and JohnGauthier (M&O/WC). The topics of discussion included numerical modelingmethods and the use of fractal models in visualization.

3. Jeffrey Schwalm (Dynamics Graphics) provided demonstrations of the newEarthVision 1.0 software at the YMPSO facility. On February 22, Schwalmloaded EarthVision onto a R4000 Indigo, which he demonstrated for DaveBrickey, and John Gauthier and Cady Johnson (M&O/WC).

On February 26, Schwalm demonstrated the EarthVision software throughout theday at the YMPSO facility. Attending the demonstrations were Claudia Newbury,Mark Tynan, Tom Fortner and Dennis Williams (DOE/YMP); Doug Duncun(DOE/NV); Dwight Hoxie and Joe Rousseau (USGS); Les Shephard (SNL);

1

Alfred Balch (Colorado School of Mines); Angelo Yfantis (UNLV); and JohnGauthier (M&O/WC).

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. In order to initiate the Lynx to Dynamic Graphics conversion, exampleWaveFront cross-section files have to be received from Garth Kirkham (Lynx). Itis expected that these files will be received during early March. If the files arenot received, it is unlikely that the conversion can be completed in April.

2

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 1.2.5 REGULATORY

WBS 1.2.5.3.5 TECHNICAL DATABASE INPUT

REPORT PERIOD: February 1, 1993 - February 28, 1993

REPORT DATE: March 10, 1993

RESPONSIBLE INDIVIDUAL: C.E. Ezra

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. Digitizing of the 1:6,000 scale disturbance features that were mapped byEG&G/EM from the 1990 orthophotographs continued.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Digitizing of the EG&G/EM generated data will continue and preparation ofdata records packages will continue.

3

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 12.5 REGULATORY

WBS 12.5.3.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE536A GENISES TECHNICAL DATABASE

REPORT PERIOD: February 1, 1993 - February 28, 1993

REPORT DATE: March 10, 1993

RESPONSIBLE INDIVIDUAL: J. Beckett

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. Jim Beckett and Robert Lewis (M&O) travelled to USGS (Denver) during theweek of February 1 - 3 to discuss the technical data backlog, and impacts of theParameter Dictionary on previously submitted TDIFs.

2. Elaine Ezra attended the all day YMP Parameter Dictionary meeting onFebruary 9.

3. Jim Brune (University of Nevada at Reno (UNR) Seismological Laboratory)visited YMPSO to review available air photos. Brune expressed the need for animmediate air photo mission for his work with precariously balanced rocks atYucca Mountain.

4. David Von Seggern (University of Nevada at Reno Seismological Laboratory)visited the YMPSO on February 10 to discuss the GENISES TDB and to have ademonstration of the ArcView software.

5. A meeting was held with Norma Biggar (M&O) and Ardyth Simmons onFebruary 10 to discuss planned surface-based testing activities and a process forsubmitting information about these activities to the YMP Surface-basedInvestigations database.

6. Carl Johnson and Charles Malone (NWPO - State of Nevada) visited the YMPSOon February 12 to view map and image product catalogs to compile a request.

4

7. Elaine Ezra and Jim Beckett attended a meeting on February 17 with CamilleKerrigan (M&O Vienna), Ardyth Simmons, Steve Bodnar, Bob Lewis, TakazumiAsakura, and Jan Statler to discuss the Technical Data Management System andto assess the interrelationships with the total information architecture.

8. Elaine Ezra and Jim Beckett attended a series of meetings called by ArdythSimmons and also attended by Steve Bodnar and Bob Lewis. The purpose of themeetings was to initiate discussions for revisions to the YMP Technical DataManagement Plan document. The meetings were held on February 22, February23, and February 26.

9. The draft GENISES TDB design report is undergoing revisions to incorporatedecisions resulting from the above series of meetings which defined what"technical data" should be maintained in the GENISES Technical Database. Thedraft is scheduled for completion by the end of March.

10. Chris Menges (USGS) visited the YMPSO on February 23 to discuss "trench logs"that he will be submitting to the GENISES Technical Database.

11. Elaine Ezra and Jim Beckett attended a demonstration of the ParameterDictionary on February 25 to review the types of search and sort capabilities thesystem has been designed to support.

12. A Table of Contents for the SEPDB backlogged data record packages have beenprepared.

13. In order to improve communications between the GENISES Technical Databaseand participants submitting data, the GENISES Technical Database Administratornow notifies the participant in writing when a submission has been received, andalso when the submittal has been accepted into the GENISES TechnicalDatabase.

14. Preliminary YMP ArcView datasets were loaded onto Dennis Williams' personalcomputer and the EG&G/EM Environmental Sciences personal computer.

15. The following submittals to the GENISES Technical Database were received:

* Los Alamos Data Transmittal Package for "Cation Ratio Data for BounderDeposits on Yucca Mountain Area Hillslopes" received on February 1.

* SNL Data Transmittal Package for the following was received on February18:

SAND87-2380 "Statistical Analysis of Hydrologic Data forYucca Mountain"

5

SAND85-0703

SAND82-1314

"Uniaxial and Triaxial Compression Test Serieson the Topopah Spring Memeber from USWG-2, Yucca Mountain, Nevada"

"Uniaxial and Triaxial Compression Test Serieson Calico Hills Tuff'

16. The following submittal to the GENISES Technical Database was completed andaccepted:

* Los Alamos "Preliminary Fran Ridge Water Use Chart" accepted onFebruary 23.

6

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. A GENISES staff representative will attend a meeting with Martin Cummings(M&O/TRW/VA) on March 2 to discuss the Technical Data ManagementSystem and Configuration Management.

2. A demonstration of the GENISES Technical Database will be provided to theTechnical Data Manager's staff on March 2.

3. Jim Beckett will meet with Debbie Beiso-Lantor (LATA/SNL) on March 2 todiscuss SNL submittals to the GENISES Technical Database.

4. Jim Beckett will meet with Loretta Lopez (LANL) on March 3 to discuss LANLsubmittals to the GENISES Technical Database.

5. Jim Beckett will attend the March 4 Technical Data Working Group meeting.

6. Jim Beckett will meet with Pat McKinley (USGS) on March 4 to discusssubmittals to the GENISES Technical Database.

7. Jim Beckett will meet with the M&O on the Parameter Dictionary numberingsystem on March 5.

8. A GENISES staff representative will attend the March 19 meeting with UNLVprofessors to discuss possible support for technical data issues.

9. The SEPDB backlog report will be completed and provided to DOE/YMPO fordistribution to Participants.

7

---- --

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 12.5

WBS 12.5.3.6

SA OE536B

REGULATORY

GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SITE ATLAS

REPORT PERIOD:

REPORT DATE:

February 1, 1993 - February 28, 1993

March 10, 1993

RESPONSIBLE INDIVIDUAL: B. Kistler

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. Responses to the Site Atlas survey have been received and reviewed. Results ofthe survey will be provided to Ardyth Simmons.

2. A meeting with the Norma Biggar (M&O - Site Investigations) was held onFebruary 16 to explore cooperative activities associated with identifying andtracking planned surface-based investigations. Norma provided a copy of theAnnual Planing Report for planned FY93 activities, which has been comparedagainst information held in the Surface-based Investigations database.

3. Mock-ups of the data sheets for the Site Atlas companion report were preparedand reviewed with Norma Biggar (M&O).

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. 30 black-and-white copies of the FY92 Site Atlas will be completed.

2. The Table of Contents for the updated FY93 Site Atlas will be identified.

3. Data collection activities will continue.

8

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 1.2.5 REGULATORY

WBS 1.2.5.3.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE536C GIS, MAPPING AND ANALYSIS

REPORT PERIOD: February 1, 1993 - February 28, 1993

REPORT DATE: March 10, 1993

RESPONSIBLE INDIVIDUAL: C.E. Ezra

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. Miscellaneous GIS map products were generated to support project participantsand are detailed in the "Deliverables" statement.

2. Other "non-map" products include the following:

* Two color vugraphs of the following map were provided to Mark Tynan(DOE/YMPO) on February 1:

YMP-93-022.1 "YMP, Proposed Locations of Seismic ReflectionProfiles, 1993".

* 243 contact color duraflex prints were provided to Chris Fridrich (USGS -Denver) on February 5.

* Two color slides of the following maps were provided to Matt Walo(EG&G/EM ESD) on February 5:

YMP-93-040.0 Tortoise LocationYMP-93-013.1 YMP Figure 13

* Two blackline copies of the 1:6,000 scale 10 foot elevation contours mapsheet #15 were provided to Ed Cikanek (M&O/MK) on February 9.

* One color vugraph of the following map was provided to Mark Tynan(DOE/YMPO) on February 10:

YMP-93-022.1 "YMP, Proposed Locations of Seismic ReflectionProfiles, 1993".

9

* One complete set of bluelines for the 1:6,000 scale orthophotos (1-30) andelevation contours (1-30) and 1:12,000 scale orthophotos (1-36) andelevation contours (1-36) were provided to David Von Seggern (UNR -Seismological Laboratory) on February 10.

* Two color vugraphs of the following map were provided to Mark Tynan(DOE/YMPO) on February 10:

YMP-93-022.1 "Proposed Locations of Seismic Reflection Profiles,1993".

* One color vugraph of the following map was provided to Dierdre Boak(SAIC) on February 11:

YMP-93-047.0 "Existing Boreholes and UZ-16"

* One color vugraph of the following map was provided to Deirdre Boak(SAIC) on February 12:

YMP-93-047.1 "Existing Boreholes and UZ-16"

* A tabular listing of the seismic shotholes with the following attributes wasprovided to Jim Agnew (M&O/WCFS) on February 16:

Record #, shothole identifier, Nevada State Plane coordinate andelevation.

* One 8mm digital tape was generated for Frank Ennis (RSN) of thefollowing data in DXF file ASCII format on February 17:

Flood prone areasTwenty foot digital elevation contours

* One copy each of the Busted Butte and Crater Flat USGS 7.5" Quadranglemaps was provided to John Savino (SAIC) on February 23.

* One complete set of blacklines for the 1:6,000 scale orthophotos (1-30) andelevation contours (1-30) and 1:12,000 scale orthophotos (1-36) andelevation contours (1-36) were provided to Chris Menges (USGS) onFebruary 23.

* A listing of Nevada State Plane Coordinates and elevations for thefollowing boreholes was provided to Scott Sinnock (M&O/TRW) inFebruary 23:

USW GU-3, USW UZ-N53, USW UZ-N54 and USW UZ-N55.

* One blackline copy each of the 1:12,000 scale orthophotos and elevationcontours for map sheets #1-12 were provided to Larry Anderson (Bureauof Reclamation) on February 24.

10

* A tabular listing of lithostratigraphic picks for boreholes USW Hi, USWH5, USW G1, and USW G4 was provided to Albin Brandstetter (M&O)on February 24.

* One color copy of the YMP color infrared image map at 1:100,000 scalewas provided to Deirdre Boak (SAIC) on February 25.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Continued level-of-effort.

11

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 12.5 REGULATORY

WBS 1.2.5.3.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE536D REMOTE SENSING

REPORT PERIOD: February 1, 1993 - February 28, 1993

REPORT DATE: March 10, 1993

RESPONSIBLE INDIVIDUAL: C.E. Ezra

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. A letter to YMP Participants will be generated requesting input on any FY93aerial photography acquisition requirements. FY94 and beyond remote sensingdata acquisition requirements will also be addressed.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD: None.

12

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

SUBS 12.5

WBS 1.2.5.3.6

SA OE536E

REGULATORY

GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

COMPUTER SUPPORT

REPORT PERIOD:

REPORT DATE:

February 1, 1993 - February 28, 1993

March 10, 1993

RESPONSIBLE INDIVIDUAL: C.W. Logan

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. Continued progress was made on the hardware/software configuration plan.

2. The link between the INGRES Relational Database Management System andArc/Info was established. This will significantly improve the access to attributesstored in INGRES while processing within Arc/Info.

3. EarthVision 1.0, a new major integrated software release from Dynamic Graphics,Inc. was delivered. It will replace all previous Dynamic Graphics software by theend of CY93.

4. Explorer software was delivered on February 26.

5. Input to the FY94 IRM Short Range Plan was initiated. Elaine Ezra met withTerri Marrotta and Les Heilman (EG&G/EM ISD) to discuss the SRP guidance.

6. Two 1.3GB SCSI disks were received and installed.

7. Three X-terminals were ordered.

8. One copy of PC ArcView was ordered.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

13

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Dynamic Graphics, Inc. updates to Directed Well Display 3.0 and Display FileOutput 2.0 software modules will be installed on the SGI 3-D modelingworkstation at the YMPSO.

2. EarthVision 1.0 and Explorer will be installed on the SGI 3-D modellingworkstation at the YMPSO facility.

3. Two additional ArcView licenses will be installed on the YMPSO GENISESsystem.

4. SUN Microsystems will visit the YMPSO and RSL/Nellis computer facilities onMarch 1 to review the systems and identify any recommendations for systemperformance improvements.

5. A meeting with a Solbourne vendor will be held on March 3 at the YMPSOfacility to discuss multiprocessing compute fileservers.

6. Memory upgrades for the SUN workstations will be purchased.

14

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 12.5

WBS 12.5.3.6

REGULATORY

GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE536F CAPITAL EQUIPMENT

REPORT PERIOD: February 1, 1993 - February 28, 1993

REPORT DATE: March 10, 1993

RESPONSIBLE INDIVIDUAL: C.W. Logan

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD: None.

1. Research on FY93 capital equipment items have been initiated.

2. As per Wayne Kozai, EG&G/EM FY93 capital equipment funds should beavailable in the April FIN plan.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Research on FY93 capital equipment items will continue.

15

PROGRESS REPORT FOR EG&G/EM RSL SUPPORT TO YMPWork Accomplished

WBS 12.5 REGULATORY

WBS 1.2.5.3.6 GEOGRAPHIC NODAL INFORMATION STUDY ANDEVALUATION SYSTEM (GENISES)

SA OE536G PROJECT MANAGEMENT

REPORT PERIOD: February 1, 1993 - February 28, 1993

REPORT DATE: March 10, 1993

RESPONSIBLE INDIVIDUAL: C.E. Ezra

SUMMARY OF WORK ACCOMPLISHED DURING REPORT PERIOD:

1. Reporting/Tracking

* EG&G/EM RSL January Progress report was compiled and submitted.

* January PACS input was compiled and submitted

* EG&G/EM RSL resource requirements through FY2001 were prepared,as per a request from Eric Lundgaard.

2. Meetings/Conferences/Training:

* Technical Data Managers staff meetings were held with Ardyth Simmons(YMPO), Steve Bodnar and Bob Lewis (M&O) and Elaine Ezra and JimBeckett on February 5, February 12, February 16, February 17, February19, February 22, February 23, February 25 and February 26.

* David Brickey attended the 9th Annual ERIM Thematic Conference onGeologic Remote Sensing during the week of February 8 - 11.

* Steve Kowalkowski attended a meeting of the Clark County GIS DataCommittee on February 18.

16

3. Staff Actions:

* Interviews for two Scientist II GIS analyst positions were initiated andscheduled for March.

* External postings were listed in early February for an INGRES relationaldatabase management specialist and a computer support technician.Outside applications are being processed and interviews will be establishedin the early March timeframe.

* Job requisitions for two Scientist I GIS analyst positions were initiated.

4. Records Management:

* The records management quality assurance procedure has been drafted andis under internal review.

5. Quality Assurance:

* Debbie Mogar was assigned full-time to the EG&G/EM YMP QAProgram. Eddie Godfrey was assigned half-time support.

* A schedule for rewriting, publication and implementation of theEG&G/EM YMP QA Program documents was developed and provided toYMPQA (Pearson to Spence, dated 2/16/93). The schedule identifies thedevelopment of the QARD Requirements matrix by 3/31/93; completionof corrective actions by 4/30/93; completion of implementing rewrite by6/30/93; publication and distribution of implementing procedures by7/31/93/ and completion of indoctrination and training on the newprocedures by 8/31/93.

The completion date of 4/30/93 for the CARs was approved (Spence toZavattaro, dated 2/22/93). The remainder of the proposed schedule hasnot yet been approved.

* Efforts to resolve the remaining Conditions Adverse to Quality willcontinue.

MAJOR PROBLEMS AND CORRECTIVE ACTION UNDERTAKEN: None.

ANTICIPATED SIGNIFICANT EVENTS PLANNED DURING NEXT REPORTPERIOD:

1. Interviews for the Scientist II, INGRES Technologist II and computer services

17

Technologist II positions will be conducted for qualified external applicants.

2. The QARD Requirements matrix will be completed.

18

Expenditures from January 25 to February 28, 1993(Dollars in thousands)

Task BudgetFebruary

Cost

$ 5.5

Total CostsTo Date

$ 5.5

Remaining

$ 49.5WBS 1.2.3Site Investigations

$ 55.0

WBS 1.2.5Regulatory

WBS 1.2.15Support Services

TOTALS

$2,320.0

$ 176.0

$2,551.0

$ 173.1

$ 11.5

$ 190.1

$ 676.0

$ 44.5

$ 726.0

$1,644.0

$ 131.5

$1,825.0

19

STATUS OF DELIVERABLES FOR EG&G/EM RSL SUPPORT TO YMPFebruary 1, 1993 through February 29, 1993

GIS MAP SUPPORT

Requested by/Organization

No. ofSize CopiesDescription Date Sent

YMP-93-021.0 Existing& Proposed Boreholeswithin 2 KM of UZ-16

YMP-92-293.0 ProposedSeismic Reflection LineLocations & Proposed DeepSeismic Shothole LocationsNE Area

YMP-92-294.0 ProposedSeismic Reflection LineLocations & Proposed DeepSeismic Shothole LocationsSE Area

YMP-92-295.0 ProposedSeismic Reflection LineLocations & Proposed DeepSeismic Shothole LocationsSW Area

YMP-92-296.0 ProposedSeismic Reflection LineLocations & Proposed DeepSeismic Shothole LocationsNW Area

YMP-93-014.0 Existing& Proposed Trenches

YMP-93-017.0 Existing& Proposed Test Pits

Bruch/M&O 2/1/93 Full 2

Goodwin/EG&G/EM 2/1/93

Goodwin/EG&G/EM 2/1/93

Goodwin/EG&G/EM 2/1/93

Goodwin/EG&G/EM 2/1/93

Full 1

Full 1

Full 1

Full 1

Brodsky/YMPO

Brodsky/YMPO

2/2/93

2/2/93

Full 1

Full 1

20

YMP-92-093.3 ExistingDrillholes

YMP-92-094.4 ProposedDrillholes

YMP-92-093.3 ExistingDrillholes

YMP-92-094.4 ProposedDrillholes

YMP-93-038.0 Environ-mental Sampling Locations

YMP-93-015.0 PotentiallyUseable Areas with ExistingBoreholes

YMP-93-016.0 PotentiallyUseable Areas with ProposedBoreholes

YMP-93-019.1 YM NearField Showing Faults

YMP-93-020.1 YM FarField, A

YMP-93-020.2 YM FarField, B

YMP-92-093.3 ExistingDrillholes

YMP-92-097.0 EEI TourMap

YMP-92-040.0 TortoiseLocation

YMP-93-098.0 EEI TourMap

Gauthier/M&O

Gauthier/M&O

Brickey/YMPSO

Brickey/YMPSO

Sowell/EG&G/EM

Brodsky/YMPO

Brodsky/YMPO

Bjerstedt/SAIC

Bjerstedt/SAIC

Bjerstedt/SAIC

Edwards/USGS

Inglett/SAIC

Walo/EG&G/EM

Inglett/SAIC

2/3/93

2/3/93

2/3/93

2/3/93

2/3/93

2/3/93

2/3/93

2/3/93

2/3/93

2/3/93

2/5/93

2/5/93

2/5/93

2/5/93

Full

Full

Full

Full

Page

Full

3

3

4

4

1

1

Full 1

Page

Page

Page

Full

Page

Page

Page

21

YMP-93-021.1 Existing& Proposed Boreholeswithin 2 KM of UZ-16

YMP-92-093.3 ExistingDrillholes

YMP-92-094.4 ProposedDrillholes

YMP-93-031.0 Home Rangeof Quail #9

YMP-93-032.0 Home Rangeof Quail #10

YMP-93-033.0 Home Rangeof Quail #5

YMP-93-034.0 Home Rangeof Quail #17

YMP-93-035.0 Home Rangeof Quail #25

YMP-93-036.0 Home Rangeof Quail #37

YMP-92-089.5 Flood ProneAreas

YMP-92-011.0 DigitalLine Graph Data

YMP-91-005.1 RoadsApproved for Use Based onCompleted Desert TortoiseSurveys

YMP-92-237.0 AirQuality and MeteorologyMonitoring Sites in theYM Area

Bruch/M&O

Gauthier/M&O

Gauthier/M&O

Cox/EG&G/EM

Cox/EG&G/EM

Cox/EG&G/EM

Cox/EG&G/EM

Cox/EG&G/EM

Cox/EG&G/EM

Ennis, RSN

Ennis, RSN

Rivera, SAIC

Rivera, SAIC

2/5/93

2/8/93

2/8/93

2/9/93

2/9/93

2/9/93

2/9/93

2/9/93

2/9/93

2/10/93

2/10/93

2/10/93

2/10/93

FullPage

Full

Full

Page

Page

Page

Page

Page

Page

Full

Full

Full

22

75

75

2

2

2

2

2

2

2

1

1

Full 1

22

YMP-92-251.0 AirQuality and MeteorologyMonitoring Sites

NNWSI-88-050.1 SmallMammal Sampling Traplines& Proposed Drillhole Locations

YMP-93-047.0 ExistingBoreholes & UZ-16

YMP-93-046.0 YMSCPSelected Existing Drillholes

YMP-93-019.2 ErosionReport

YMP-93-020.3 ErosionReport

YMP-93-039.0 SpotlightSurvey Routes

YMP-93-047.1 ExistingBoreholes & UZ-16

YMP-93-022.1 YMP, ProposedLocations of SeismicReflection Profiles 1993

YMP-93-018.0 Test &Waste Isolation EvaluationZone (Rev. 0)

YMP-93-044.0 TortoiseLocations

YMP-93-043.0 TortoiseObservation

YMP-93-045.0 EcologicalStudy Plot Number/AverageNumber of Vehicle PassesPer Day

Rivera, SAIC

Kistler/YMPSO

Boak/SAIC

Brandstetter/M&O

Bjerstedt/SAIC

Bjerstedt/SAIC

Cox/EG&G/EM

Boak/SAIC

Biggar/M&O

Biggar/M&O

RautenstrauchEG&G/EM

RautenstrauchEG&G/EM

Green/EG&G/EM

2/10/93

2/10/93

2/11/93

2/11/93

2/12/93

2/12/93

2/12/93

2/12/93

2/16/93

2/16/93

2/16/93

2/16/93

2/16/93

Full 1

Full 1

Page 3

Page 1

Page 2

Page 1

Page 2

Page

Page

Page

Page

Page

Page

23

YMP-92-089.5YMP-92-239.1YMP-92-256.0YMP-92-259.0YMP-92-260.0YMP-92-261.0YMP-92-262.0YMP-92-263.0YMP-92-264.0YMP-92-265.0YMP-92-266.0YMP-92-267.0YMP-92-268.0YMP-92-269.0YMP-92-270.0YMP-92-271.0YMP-92-272.0YMP-92-273.0YMP-92-274.0YMP-92-275.0YMP-92-276.0YMP-92-277.0YMP-92-278.0YMP-92-279.0YMP-92-280.0YMP-92-281.0YMP-92-282.0YMP-92-283.0YMP-92-284.0YMP-92-285.0YMP-92-286.0YMP-92-287.0YMP-92-289.0YMP-92-290.0YMP-92-291.0YMP-92-292.0YMP-92-301.0YMP-92-306.1YMP-93-001.0YMP-93-002.0YMP-93-003.0YMP-93-004.0YMP-93-005.0YMP-93-006.0

McKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGS

2/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/93

PagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePage

111111I1111111111111111111111111111111111111

24

YMP-93-007.1YMP-93-008.0YMP-93-009.0YMP-93-012.0YMP-93-012.1YMP-93-013.0YMP-93-013.1YMP-93-018.1YMP-93-019.0YMP-93-020.0YMP-93-022.0YMP-93-023.0YMP-93-027.0YMP-93-027.1YMP-93-027.2YMP-93-028.0YMP-93-029.0YMP-93-030.1YMP-93-037.0

McKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGSMcKinley/USGS

2/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/932/18/93

2/19/93

2/19/93

2/19/93

2/19/93

PagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePagePage

YMP-92-289.0 ProposedSeismic Reflection LineLocations & Proposed DeepSeismic Shothole LocationsNE Area

YMP-92-290.0 ProposedSeismic Reflection LineLocations & Proposed DeepSeismic Shothole LocationsSE Area

YMP-92-291.0 ProposedSeismic Reflection LineLocations & Proposed DeepSeismic Shothole LocationsSW Area

YMP-92-292.0 ProposedSeismic Reflection LineLocations & Proposed DeepSeismic Shothole LocationsNW Area

Savino/SAIC

Savino/SAIC

Savino/SAIC

Savino/SAIC

Full l

Full 1

Full 1

Full 1

25

YMP-92-184.0 ExistingDrillholes with SubsurfaceAccess Drifts

YMP-92-185.0 ProposedDrillholes with SubsurfaceAccess Drifts

YMP-93-018.0 Testand Waste IsolationEvaluation Zone

YMP-93-001.1 ReclamationSites

YMP-93-027.3 Near TermBoreholes

YMP-93-027.4 UpcomingIntermediate Boreholes

YMP-93-029.1 PlannedTrenches and Test Pits inRegional Investigations(Planned Locations)

YMP-93-030.1 PlannedTrenches in the Site Area(Proposed Locations)

YMP-93-048.0 ProposedSeismic Reflection ProfilingLines

YMP-93-049.0 Fran RidgePit and Pavement Areas

YMP-91-008.2 OrthophotoSheet Index

YMP-92-266.0 FieldVerification Map Sheet 9

Biggar/M&O

Biggar/M&O

Biggar/M&O

Green/EG&G/EM

Gauthier/M&O

Gauthier/M&O

Gauthier/M&O

Gauthier/M&O

Gauthier/M&O

Gauthier/M&O

Savino/SAIC

Savino/SAIC

2/19/93

2/19/93

2/19/93

2/19/93

2/22/93

2/22/93

2/22/93

2/22/93

2/22/93

2/22/93

2/23/93

2/23/93

Full 1

Full 1

Page 1

Page 4

Page 1

Page 1

Page 1

Page 1

Page 1

Page 1

Full 1

Full 1

26

YMP-92-267.0 FieldVerification Map Sheet 10

YMP-92-268.0 FieldVerification Map Sheet 11

YMP-92-269.0 FieldVerification Map Sheet 12

YMP-92-272.0 FieldVerification Map Sheet 15

YMP-92-273.0 FieldVerification Map Sheet 16

YMP-92-274.0 FieldVerification Map Sheet 17

YMP-92-275.0 FieldVerification Map Sheet 18

YMP-92-278.0 FieldVerification Map Sheet 21

YMP-92-279.0 FieldVerification Map Sheet 22

YMP-92-280.0 FieldVerification Map Sheet 23

YMP-92-281.0 FieldVerification Map Sheet 24

YMP-92-093.3 YMSCP,Existing Boreholes

YMP-92-094.4 YMSCP,Proposed Boreholes

YMP-92-224.0 Existing& Proposed Test Pits

YMP-92-225.0 Existing& Proposed Trenches

Savino/SAIC

Savino/SAIC

Savino/SAIC

Savino/SAIC

Savino/SAIC

Savino/SAIC

Savino/SAIC

Savino/SAIC

Savino/SAIC

Savino/SAIC

Savino/SAIC

Lobo/SAIC

Lobo/SAIC

Menges/USGS

Menges/USGS

2/23/93

2/23/93

2/23/93

2/23/93

2/23/93

2/23/93

2/23/93

2/23/93

2/23/93

2/23/93

2/23/93

2/23/93

2/23/93

2/23/93

2/23/93

Full

Full

Full

Full

Full

Full

Full

Full

Full

Full

Full

Full

Full

Full

Full

1

1

1

1

1

1

I

1

1

1

1

1

1

1

1

27

YMP-91-060.1 Environ-mental Sampling Locationswith 200 meter Buffer andProposed Activities

YMP-92-025.0 AreaDesignator Map

YMP-92-093.3 ExistingDrillholes

YMP-92-094.4 ProposedDrillholes

YMP-92-255.0 ExistingDrillholes & SelectedGeologic Features

YMP-92-258.0 PotentiallyUseable Areas with Topsoiland Rack Storage Areas

Simmons/YMPO

Simmons/YMPO

Simmons/YMPO

Simmons/YMPO

Simmons/YMPO

Simmons/YMPO

2/23/93 Full I

2/23/93

2/23/93

2/23/93

2/23/93

2/23/93

Full 1

Full 1

Full 1

Full 1

Full 1

YMP-93-050.0Boreholes withAccess Drifts

YMP-93-051.0Boreholes withAccess Drifts

ExistingSubsurface

ProposedSubsurface

Simmons/YMPO

Simmons/YMPO

2/23/93

2/23/93

Full 1

Full 1

YMP-92-014.0 OCRWMTour map

YMP-92-132.0 ProposedActivities

SA1-4.0 ExploratoryStudies Facilities andSubsurface Access Drifts

SA6-1.0 StructuralFeatures and Bedrock/Alluvium Contacts

Bradford/SAIC

Bradford/SAIC

Bradford/SAIC

Bradford/SAIC

2/24/93

2/24/93

2/24/93

2/24/93

-Full 1

Full 1

Full 1

Full 3

28

YMP-92-252.0 FloodProne Area

YMP-92-261.0 FieldVerification Map Sheet 3

YMP-92-262.0 FieldVerification Map Sheet 4

YMP-92-270.0 FieldVerification Map Sheet 13

YMP-92-271.0 FieldVerification Map Sheet 14

YMP-92-276.0 FieldVerification Map Sheet 19

YMP-92-277.0 FieldVerification Map Sheet 20

YMP-92-282.0 FieldVerification Map Sheet 25

YMP-92-283.0 FieldVerification Map Sheet 26

Hill/RSN

Savino/SAIC

Savino/SAIC

Savino/SAIC

Savino/SAIC

Savino/SAIC

Savino/SAIC

Savino/SAIC

Savino/SAIC

2/25/93

2/26/93

2/26/93

2/26/93

2/26/93

2/26/93

2/26/93

2/26/93

2/26/93

Full

Full

Full

Full

Full

Full

Full

Full

Full

Total Maps 347

Total New Maps 44

29

ENERGY MEASUREMENTSwBs: 1.2.5.3.6

QA: NA

TRACKING DESIGNATOR: ,41R �_3 6 -3,/f) 0 /

TRANSMITTAL

RSL YMP Support OfficeEG&G Energy Measurements, Inc.P.O. Box 1912, M/S: V-02Las Vegas, Nevada 89125Telephone: 702-794-7852 FAX: 702-794-7469

Date Sent:

NAME: Carl Gertz TELEPHONE: 794-7920

ORGANIZATION: U.S. DOE

ADDRESS: BOA. 101 Convention Center Drive. Las Veaas, NV 89109

Fed-X Certified Company Mail Hand Carry- Pick Up by Customer

-Ne page size copy of:

'YIMP-92-293.0 YMP-93-021.0 YMP-93-045.0YMP-92-294.0 YMP-93-021.1 YMP-93-046.0YMP-92-295.0 YMP-93-022.1 YMP-93-047.0YMP-92-296.0 YMP-93-027.3 YMP-93-047.1YMP-93-001.1 YMP-93-027.4 YMP-93-048.0YMP-93-010.0 YMP-93-029.1 YMP-93-049.0YMP-93-010.1 YMP-93-030.1 YMP-93-050.0YMP-93-01 1.0 YMP-93-031.0 YMP-93-051.0YMP-93-01 1.1 YMP-93-032.0YMP-93-014.0 YMP-93-033.0YMP-93-015.0 YMP-93-034.0YMP-93-016.0 YMP-93-035.0YMP-93-017.0 YMP-93-036.0YMP-93-019.1 YMP-93-038.0YMP-93-019.2 YMP-93-039.0YMP-93-020.1 YMP-93-040.0YMP-93-020.2 YMP-93-043.0YMP-93-020.3 YMP-93-044.0

IVROVED BY: . M DATE:

RecordL)

YMPSO Copy MRSD Copy Customer Copy

WBS: 1.2.5.3.6

ENERGYMEASUREMENTS OA: NA

TRACKING DESIGNATOR:

WORK REQUEST

RSL YMP Support Office Today's Date:EG&G Energy Measurements, Inc.P.O. Box 1912, M/S: V-02Las Vegas, Nevada 89125Telephone: 702-794-7852 FAX: 702-794-7469

TO BE COMPLETED BY THE REQUESTOR: YMP Participant YIN): Y

NAME: Carl Gertz SIGNATURE:

ORGANIZATION: U.S. D ! YMPn TELEPHONE: 7Q4-7Q:)n

ADDRESS: BOA, 101 Convention Center Drive, Las Vegas, NV 89109

PURPOSE OF PRODUCT: Monthly Progress Report

WILL THE PRODUCT BE USED IN QUALITY AFFECTING WORK?_N0 DATE NEEDED: _2 ____

PRODUCT FORMAT Hardcopy: ). Number of Copies: | Map Size or Scale: j

Digital: ,4 OS: A/A File Format: 1A' Media: IWORK DESCRIPTION:

Is one page size copy of each of the following new map products generated during the month of February 1993:

-1 .YMP-92-293.0 YMP-93-021.0 YMP-93-045.0YMP-92-294.0 YMP-93-021.1 YMP-93-046.0YMP-92.295.0 YMP-93-022.1 YMP-93-047.0YMP-92-296.0 YMP-93-027.3 YMP-93-047.1YMP-93-001.1 YMP-93-027.4 YMP.93-048.0YMP-93-010.0 YMP-93-029.1 YMP-93-049.0YMP-93-010.1 YMP-93-030.1 YMP-93-050.0YMP-93-01 1.0 YMP-93-031.0 YMP-93-051.0YMP-93-01 1.1 YMP-93-032.0YMP-93-014.0 YMP-93-033.0YMP-93-015.0 YMP-93-034.0YMP-93-016.0 YMP-93-035.0YMP-93-017.0 YMP-93-036.0YMP-93-019.1 YMP-93-038.0YMP-93-019.2 YMP-93-039.0YMP-93-020.1 YMP-93-040.0YMP-93-020.2 YMP-93-043.0YMP-93-020.3 YMP-93-044.0

TO BE COMPLETED BY GENISES DATABASE PERSONNEL Job No: 3 //O y

Cost Estimate IY/NI:, Processing Plan IY/NI: Due Date: 3 /? 5

[Map) | Dat a Photo |Graphic Image 0G Analv I DGI: Photo Data|lProcess Acq. Submkt

[ ~ VED BY: D DATE: C

APPROVED BY: - DATE: 3 WHITE: Record I-TELLOW: YMPSO Copy PINK: MRSD CopyY3002 IDac 92) Pe 1 Of

---- :

SN6000NI E5600001t

ij!Ii

E_ _

;1~

a

-

UE-25c 1-;z UE-25c 3 %4

UE-25c 2-a

,A mt TIR-134l7

YUCCA MOUNTAIN SITECHAIACTlIZATION P1ONICT

7 1531I01 ESB666011 V 40000m \ E"' - $ A ooo

_ u~i-anS I

an

7,30, tic 00YUCCA MUNIAIN 11'22'30'

NIL 'S ' ' SITE CRARACTIRIZATION PROECTB~tlS PROPOSED LOCATIONS OF SEISMIC REFLECTION PROFILES, 1993

t t~~~~IILOMITIIS

Con e ol011t AVBzG Yumum.Centen IwinnI IN It �BgG TV? 11111.1

WHOM001 !5bDOODIt 1564000[t 1568000ft

~-usW UZ*14

- I~~~~~~~~~~~~~~~~~~~~~~~~~~L2 RG

K ~~~~~~~~~USW NRG-6- NR-3'

I - ~~~UE 25 NRG3

4 [JE~~~~~Ul25 NRG-

Ul-25 UZ-16~~

3m ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~~~~~-

SW SIG-5~

uz-N59~~~~~~~~~~~~

-. 5 .5 x~~~~~~~~~~~~~~~~~~~~~~~~~-

- YUCCA MOUNTAIN SIH~~~~~

* Upcoiia~ t~edu loreboles -.5MILES CICA MOUTIN IJTE

Upcoming Intermediate Boreholes

I

14033001t WHO00M 1331460h11300IOOm ESS00h IOCOm

k- el~~~~~~~~~~~~~~~~~~~~~~~~

~~~~~~~~~~~~~~~~~~~It

01 11 I ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~

b~~~~~~~~~~~~~~~~~~~~~S SS

114 4510G 011 30W III 051' I 01V0p! l* 1*-139YUCCA MOUNIN SITE

how%, e l . CIAACTERIZATION PROJECT

( I I 7 .!

4" 1

1t~ I

* .. 'tiiiiu tuXs1 ° y

Z wE

-I

4. .

1' ;

. _

. ..

r--

I ' I a,.I

"' I_ | . . wv fF; -r-- -

*1I

* § - _ - Iw * - _

i-E,

7~, ii,

' 1,I II...

40 -

I I

7' ___t__

0''~I -' ;-

fI1-7

. i

. IIV

- ' --- 1

I. i. _ __

4 .... i--

I .

. 'It

I I

I -_- 1

,h Ar #e Am'^1. .

%"h W p

| I

I -

!. . . . . E

..1

154mg.

j . .

I

1.- _..

15-;n-

i

-

II I

I3.

_01 .?

_ _ I I- _

liIIiIII

AI

IBII I ~U iI I I

I , I ff " IP I!

II II"

U P

I I -a

II

, * | '-' 1. t ._ _ , * . |

tw | #, | | . ^ | . , _4z_

I. /r e-,.

I .,. ,1II

fJ#54

S

'

2 =

=S M

: m

:a0 Co

Co2

O =

- ttC!.; c t

:2

am"w

2 P"

Cpl-

:I. _ :_ z.:.

_ M m

O92 ~

I- � �5SFI, MILf VA�I�

r

a

4 .�- .-

I �

'

ii

- . I.. .... I

I ,

I 1' ..

_ . L I_-- .. _

IW-,

1. ,.... .I'_n -

I-- ,-

S- ' 1- .

II I

..- I :

I1 . 1

II t

i,

I" .*

4.

.. .. mI .. ;.

-

4

UII'I I ;

h l..

.

r,

1.

lI .. _

i _ i _ __ _ | . _, . : . .. ... . .

.. ._ s _ -

'mggqm

t

I Ltuh 1mltee:

s; J - -1 L---. . N. utn' :I tbtumfm.c§ _", " r-1 I i... - ? , ,,

I P i1"I. A.**;If 0- . 5

"t n --wA... --- - bin~~~l. ~ *- ~.-- 'I I"s

. Ii

1TZi#~

t 8! t - !-\ h

1~~ K. ~" --- 1:W7P$,:r)-tteu

I ' \| .. j.Ai *j-|" //

.~*****~* I .' ~ .-

1 t i: ' j ,,mr 4 1Xl

................ , . ..-

-. -__ t1IC.,I1.2.'-' _ _ ._ , I _ _ _ _ _

11-- 1 1 :0--'.2 1 £31 -Il 1

_ _I , -- 1 t t 1 . w -t EI I

. _ ____z 'li~ _____ * ___'t;1 ' ' tl

____ ____ |___ ____ 'L- .< *..* 4Efat szs".l , , , tmml~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~ .I

I. - ,

Ul:DID/V U1m Nq h b .O id. Eazdhdx/V kkptln d *W i i0md klim"I bai a i a %eeln kfhft g Oafft

- 4ktati k

{s' 'hpd kmt wo he a 1w ffaf

a won~ k, fk-

* .., k brI. w h letkk Mg~ h

J~wuiI~mz

LnU

f~rI Iffff LOW

____ffffff W.=u&

bfffwowffif WAfffff

YUCCA MOUNTAIN iSITE CHllACIERIZATION PfOJECT

11010SD SSVIC IERICT10K UNE 1OCATIONS iWAD OOlSLD DEEI SEiSUIC SEOTHOE LocATIONS i

SOUMEAST AU1A I

Afao ww 'a W Iu I

f_=bfVf _ff"f orftf'a-va'"'f fffffr._

.fff~fffffff-M _

I

IvISUn

rI ; i

I ! b. i ;

e ii11 !_..... - i.*..

Vi_ w " _ ',__

I tV IM hht haL I dlh II I1=~~~~~~~~~~

v', bqmi teL am .cud kdat

.--.- hA kithw X in ha Di U^' hpSo=kLft ho ibli* hqkgf

* hapeelkqhlh

c

onnu

m n mu n s

_ F- , Nt. _ .

4_o _ or_ ^ , _".~.

YUCCA MOUNTAINSITE CRA1ACTRIIZATION ?1OI!CT

?1OOSID SUSUIC IIELECTION LINE LOCATIONSAND 11OOS1D DE SEISC SHOTIOL LOCATIONS

-. SOVTLITl MU

Aeao Nx I

(

I

l

I

II

Ia

drys I ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ '

~~ ~ ~ I I, I CNEIR N I

.i 6 i

di. ~~~~~~~~~~~~~.~T'~~~~~~~~~~~ .r~~~~~~~~~~~~~~~~~~i I- A

I'~~~~~ieo(.b ~~~~~~ wi

~ ~~~ ~~~~~~ ~~~~~~

|§ms§ip .... le

a..,... ~~~~~All-.

1•' *'~~ '-ii'' ~h#4 .

17Aj I/

vt I , .F- ~~~~ ,~~~ /1_

-,K ~ A*" I (A / \

. I.. _Ns I

Cz o

Ir,

I

....... I so.-`Ii v;ads ....... a .... ev",

I

'a;

S.

-/ .-

0

I 9 I 0 0 0 a 9 I I I a a 0 1 5 4 es 9 0 a I 4 I a a a I I of a 0 fill#*& I I 6 I 0 0 0 1986998 919111188 I I 0 0 6 9 8 0 0 a 0 9 usages 5 0 8 0 9 0 9 6615569 9 0 1 9 0.

~~b~~mtmh~~ .- --5~

- - -. _ _ ". ss~~~(j

. D.&

. bl�bmbwd

. &.� ft�: =16hskft�

Gol"boft

YUCCA MOUNTAINSITE CHARACTERIZATION PROJECTAREA OVERVIEW, NORTH

as~ ~..... --_-__~ £---

I

1 - 0 EcTsR

I-J

ERG Gvi 93-500.I

.WggE!e I II I6 leri'Ur U,..... altele, .. .,g a I . a. ( 7tjeres I,,, I ,, a& 1064 ....... a.......a ....... ".'.vi 0.SE e 9g

I

I

..*-I 37ese

+ + 4

-fW 11:11

In-1 T-$

As-o .e-#seE-,, ge -,

.ew so-, e . . PIN VA.

I

.09-,2 *wl

.3w 1-f

.ME. 111060 2s-.

C.fe *S*I

,nw w-,1

MIe.% .gE- . .4,.. .. e.. .... 6004'ro,i';ti I " ... l . XS2f8

4

...-. pool

a.

.s.. .iC.

...t g. ..

-.+

A.

.... ~~~~~~~~~~~- - -..... ..__ .. . . . . . . . .. . . . . . . . . . .. .-.. .- n. . . . ; . . . . ....... .. , g g g . . . . . . . 1 1 . . * s s * e . . . . . * W ..... . . .... .... ....

1 I I -=I

7 ~ ~ ~ 2 L .t o

,I....... ...... ...... Tigi a

10

YUCCA MOUNTAIN ISITE CHARACTERIZATION PROJECT

AREA OVERVIEW, NORTH"oqv... tom WV 9-91-009

%ffmawnw w #I 11

- IIg Ia I

*I .j

b- iu , I l _ -S a' ~i I

Iw \<t :<:

I4 I

- -

.. . (pivilV dues. Estes* 9***'*g ....... § iX~ ... VW;* I* *llgo 92 ~is 8,sse -s n a.....- - ---- I

. W

I

e

+ y.

.../-

+ .

------ . - - - -

1~~~~~~~~~~~~~~ 'I~~~~~~~~~~~~~~~~~~4

* ~~~~ *~~~~ (I . . I ~ ~ ~ ~ ~ ~ M

IVADA~~~~~~

I I

tAI"

.,\ .: , 1.I . ..N. - .

8

II

i

-

I

, . . .

. I I

.. ;, I I

I

I- 'l -

,I ,I _I_ I I -,, '. .Y_ -- 1-....-. -'- __J. ..|...I..

~~f~~7LT71~~~~~7~~~ 'v~'LA -Y El A I-A IP'----- 1 -----

S.-

...... . ..... ------- - ----- -- '-- --'-:

311~~~~~~~~~~~ f,,,,,

t *-*- - -. _ ._ ._

I ¶ 4 I

II I

I1I .,

, ~~~ I

I ,. . I i

I I I I,

J _ _ _ _. .. . .. .. .. . . . .. .. .. .. . .. .. _. ._.. . . . .. .. . . . .. . .. .. . .. . .. --- ..- ----- ------- ---- ------- ~~~~....... ....... ...... ............. .........

I . . I . . .. . I .. .. . . I I. . . I .... ~~~..

- I ~I-4- ) I . - - r r -

_ _ .ICtF .F0. M deg_~~Ibh~u - _ _- .

YUCCA MOUNTA I NSITE CHARACTERIZATION PROJECT

AREA OVERVIEW, SOUTH

A a E, h U _ , . 9 I

I . K~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~.

a......0 .. forst --- @@ 1161909 6174 I" $66 0sle |@@

- ffiviti a|I||||@ *|| .at Igloo$* I......... .... ..I..9 "lillvole.

_ .

Is. 9 ,,.&* S* 0 il'

a'

.5-15 020011

.09-is a,..4

+

-

+

a'#I- * $

0 ,. .

ais.,j4.. iiTsiiii.- 5*i6i;;;S eiiii"

YUCCA MOUNTAIN ISI7E CHARACTERIZATION PROJECT

AREA OVERVIEW, SOUTH |

....... -------.. ------- ....... . .------- ....... ------- -------.... ....... .... ...... ....----.... ....------- .... .......-....-----.. ....

- I Imk�

I .0 0 .1

I I ' .9 '�""i :99

iI

.... ... - .....

. 4_4

I �"na, to%" _ - 0si-

06emae

( InHifnIS*hW WiNNMM5

.� I A.

9.9..,

� � 9

I .9 (9

I.

V

99

99'k �, F 9

* .9 9.

9 91..?

I � ,.-

I 1,.'

9' 9\I- 9j Nj9 I

¶ �. 99

I. I -I

'1

- ' 1% �1 . 91

YUCCA MOUNTAINSITI CHARACTIUIZATION PROIICT

H1fSTING AND 1lOOS MMNNI

inoymnl'

A MMWC T A Him

A f 1 0 1 0 5 0 U E C I

Ad' Ii loltl, am 1. W hdmf

A. N~c" uuhw kmh howu"

Cce~ Co~o4h4 Am budu"

Sq hi wh t kr I

ib f

9 I

TIP44111Arme

1Irs4 Ww

3isr

I_ Ws~

Im I

IL �.,.

5'.

N - -$

II

--'p I

-� - - '..

,'-� :�:..

* '%c-.� '--

5.,-

�.1 � -

� 'd� - -�-

ruNg I�9 - � u .A�,, '�. �-* -

� 4 -J

IiX

qnhDNINU Snns'.Wi

Ur-

I it ~~~~~ IL ~ ~ ~ ~ ~ ~ ~ ~ ~ ~

t

rr

I!I..

-4amw

-S=

- 5 -

1

YUCCA MOUNTAIN(I: j?..~ K SIH CH IATIZsm IOPRO JEClu.~~~~~~~~~~i

PlTTNTIAIIY SA WAS

~~~ \t 1' Nil,'~~~~~~~~~~~Ni

el, NJ ~~~~ 11f~LOgWNn~e

A j; Me~~lbI~~11A Ck4

If, ~ ~ ~ ~ ) ACu ulI1kb

I ~,1 l NWifed k btt

/v m4Cbm i hku rM m fr~~~~~~~tI~~~~~~~'~o Act w p

JII

VIA~~~~~~~~~~~~

'F~~~~~~~~~~~~~~~~~~~~~~~~~~~~~"6f

.11

"V ~~~~~~~~~~~~~~~YUCCA MOUNTAINSITE CHAIACTERIZATION FROJICI

IIISTING AND lPIOSO IST MIT

mii

IILOUITIB

>. ~~~~~~~~~~~~~~~~~~~\ I ~ ~ ~ ~ ~ ~ L0 M1.O 11WSf

A. tmqW h 1ff hnu

& I~ Cuerdt An*iw

~~' k/ urn,~~~mkf

ot %also~~~/'1''~~u~ a bwaqub.W

I 2 ~~~~~~~~~~~~~~~~~~~~~~~~ ~64%MWdqu.* P011.0 .I I, / M~~~~~~ b~~dahmis

b-huoombg

i

I

.. I

A tWEW hum~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

~~~~1 r . S. - c*9'.-~~~~~~~~~~~~~~I........ -<

.4" . ~ ~ ~ ~ r. .......o1 r -, pI

W ' * .. -. ¾ * ½ .;~~~~~~~~~~~~~~~~~~ r .' .f l 4 .. .... .. .. .

IC -c 0 - ....I

-~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~L

- - .;>t- --cr~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~tr

-~~~~~~~~~~~~ ' 0"WA,

ITTMIll lUg 4 * ''q 'r1'f

to~ ~~ ~ ~~~~~~~~~~~~~. .4-.

4.......*v* .

.4

-.

.4

(.b.tvL)q -

C ;- -�

WE flung CAWtah

'4

� L.\ Nit

- 4

/ .. .,xtt

.4 .Ž .A'.'.4'.4..;5S;Y

t \i

IIIPSIIIN

umumu

USfOLON

'"OIL"

I

I - - ISnImitliImpeG

I3"wlt25M212

hz

I

2

Ccltour Interval 20 Feett I 1 2

il lu

YUCCA MOUNTAIN SITECHAIACTRIIZATION POlE0CT

A 0wt Yu-019.2

las2 1 6 I 2

IILOMTIZS

lr 4SW Ilk 3W 1

-. - to I . I* i

% 1 _ 5~~I *' s ISVoLcu

TUCCA MOUNTAIN SITECHAIACTERIZATION PlIOIECT

Awoca TW-93 021.1

I

13eh 15745hLseeo 133510

xi-: - ' s~t~n,!N. .-. 0

nu2

~~~~~......q5...b~4ANC ..EK I

*V*.*A.*.*. flVA~k Tt$\ siti

'. .3' ''' t>A~

,- N

* n j) *-> '-I-

... : WJ. X 4.t

*r l

N ~~~~HITIAI;N . .. -- 1a

..0-.34 . . 3

^ EeG *1342.

v I I

v S I SKUOlam

14333flft

I

l'S lhaKsmoo

iI

n'- 1

fN s I S v

ILHMY

YUCCA MOUNTAIN SITECRAIACTEIZATION PEOECT

A ence Ti-1u342.2

.I to .6 sio

am Coawmiusm WCTlltIM

* 61*91 .. .S.* e...d at &.m.

tsa8r - "I"F_ - i.-_ *i.I

I A, W, '- YUCCA MOUNTA I NSITE CHARACTERIZATION PROJECT

EXISTING AND PROPOSED IDREHOLESWITHIN 2 A OF UZ-1U

*WE,,,Is;A; -.=Z- Us I ,Uc-

40mac 9.alAU

S ..,,

.- ,.....mP....

I

f

J

I -- - M Book&

1'N

o I

lm um

-34

UW~ .4 urON u=nslow a m

my an

4 �

N ...

GUI 34

a &a e

lolls 169"a f YUCCA MKN-7V f SITE CHARACTERIZ

SITE C,04MRASZ. ACTIvIII116 EXISTING AND ROMI* bS..i~~~~~~e S...~~~~.s. ~~WITHIN 2 I

LM * O.n.. B1111 T...

1UNTA I NATION PROJECT

DSED FOREHOMEOF UZ-16

. i

t

z

U.0.

Co

ao

.0

-3.

Z;

U.

.5 o .5N ELLS.5 e .5

ILOIETI1S

Coutour Interal 100 feet

116 25'00'

HOME RANGE OF QUAIL 9March 1992 to January 1993

* Quail locationMinimum Convex Polygon

_ _ Aron WY13431.0

I

II

I

i

UI,)I

011I

WWF-T1I.-

s a S

mllS

N S o s__ --- _° YUCCA MOUNTAIN SITE[IOMJTEIS CHAIACTERIZATION

FROJECT

Pinted Trenches i the Site Area (Proposed locations)

36' 47'30' 36'50'008

-. - / -7

as 0 ~ ~ ~ fs 5 <" t

,..~~~~~", ;~ ~ ~~......

-~~~~~~~~. .. . . ...-' ..;.

.. ......... 1

(S d' -~~~~~~~~~~~~~~~~~~~~V. . ....... ...- r C5 ,.

-. -~~~~~~~~~~~ . ....

~~~ ~FORTYW4LE

Am. MOCO~~~~~~~~~~~~~~~1 0SLOM 009O

I

z.b

Ba%

z

.q."

EW"

.s a .5

C tt MIl1 Fe

Contour Interval 101 eet

116 25'00'

HOME RANGE OF QUAIL #5March 1992 to September 1992

* Quail Location. Minimum Convei Folygon

A m-Eg YMF.93.033._

I

E550000m Z

MUIDWY -

%~~~- V ALLH lCE

d ..#.tF\ - . /-

> I, t*;., ;e. V - - :;

* IIDCX / (\ / ' A ;

a-

' ~ iZ . ._ ..,. E

~~~~~~~~~~~~~1 25'00'

N 5___e__ .s HOME RANGE OF QUAIL #25Otober 1992 to January 199tCootu1 oIteRvl 10 iee Quail locationMinimum Convei Polygon

X&VIC13 Wl143S.0

I

kIDWAYVALUYAlC

BILL.' -~ ~ ~ M

I,~~~~r

Forta-J

. ....... Rod~~~~~~~~~~~'i~:10 1l

I .'iit wiaB

rill ~. \

K110MIT~S , Quai locatio

Cootour laternal lfl Feet .. Minimum Convei olygon

:MD

NJl 6p I 9z YW'43*031.0

I

E550000M

MIDWAY -

' ' ;<> VALLEY. A11C..-- C ; ,, . ,,,,' - ,.:,.,,'/ ,

.0 ~~~~~~~~~~~~~~~~~0

:. .. .- ..... Po-rtall

S-i~~~~~~~ig,%-./. V;

$ "' glot ' '/ .';''\ .

SM ~ ~ ~ ~ C

o~~~ '' 0z'z

116 25'00,

.5 .HOME RANGE OF QUAR #37.5 0 j ~ October 1992 toJnay19

C e10M T * Quail locationCoitcu litevil N FeetMinimum Convei Polygon

< ,> 'Y Xn ; ........ ; , G t-3436.

E 540000 a6 0a0a aIa0000e.

e

= l 4/t 00 L7040\\~~~~~CtX ' 1

i - a 1 1 > _. > | /) 8sc t T l * I ^ -7|- | <14 G *T

. ' -- F- - J-E-t-s iv .,4 e v / / +T#; (>1 E G

t { 4T87 lza tT 3eyf'. o~~~~cott~f

1-0--V /ar4T//t*~~~~~~0;\dL -04T1I_, ''' \. L AST/

I -. ~~~~~~~~~~~~~~~~~~~~~~~~~~~~

e -- I L A I T I I E

I a~9540 aees gls

.~~~~~~ ,,s t-',-5-....I so u.. I

2 a 2 E Ecological Study Plot Number/AverageMILES Number of Vehicle Passes per Day

2 a 2

K ILOMETERS Am %W-.o.ss s

.1. E 7

E 5 0 00 0 ES72 000 ES 74000 ES 76000

0a

e

at

a

0

C

e

e

e

C

0

a

3

.00.00

3

U0a0,

3

0

a

a

0

0

0

IIa0 0, 1172000 1174000 E 76a0 0

* TORTOISE SIGHTING

X RSN Flag

A VAM Benchmark

ROAD FEATURES

,o0%%* o Light Duty-'N~' Unimproved

I... 0 tots WIT?r� . ILSUSTIS

AEszG YMP-93-040.0

.I.It.A

--!-I I b F A ' i LIr

4

"'

._ _ _

l

CRATERFLAT

'I II

a _

* * LOMITBI

SPOTLIGHT SURVEY ROUTES

AERzG VWMP-03-039 .0

I

I Ip am& p

TORTOISE OSERVATIONS n° Ummarked Trtoise 0_EGIG* Markgd Torgise VW-1S-4.C

I 4~~~~~~

gW e aj

Z e a i V~~66ege

4........ .

£6I4SIL4~~~~e~IW'Igee

~~~~~~~ O0 ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ oel

-4 V~~~~f1~~A/1 4,,)len $lilt'

v~~~~* ) 4 O~~~~~~~~~~P~ Dios)

*- ewe

/.

i-

_tx

'

l a IMILkS

I I 1

A. Conceptfal Itrizete DuI lovably1. Coiceptul Ctrolled Area lodatry

NC tAr lidttl 310 bit

YUCCA MOUNTAINSITE CHARACTERIZATION PROJECT

SELECTED EXISTING BOREHOLES

AEGJsU YMP-13-046.0

2Xa a * Ecological Study Plot umber/AwetageMILES Number of Vehicle Passes per Day

2 6 2

KI LoMTERS AmngU-944 _ .

.E556OODlt 15&ODODfl iiUOooit E5613D~f . .

) \ 9 4 M & ', "' "'\'<\;''s\"; _' \ 'I ''\\\9;.'\t @ \< ~ ~ CUISW194 JE-2

* "'' -- , *'N

' -.S O * "

its. ~ ~ - s\" $

\ N '-' 5' ILS * 'V lulls I

I.-IIOMN~lS ZlACEESION lIOJECE

.1 VIIS ?1 URI II

vwicz~~~~~~~~~~~~~~~~

'~~~ '. IllS UZ~~~~~~~~~~Ia34,4

74)~~~~~~~~~~~S)KILONMIS CHARACTIRIZAT~~~~~~~I 1116

Existing Boreholes aDd UZ-16 Aeva l-13 I

I.S5floot }560DODft I56000h 151 00oft

DEW ,U.

I

1A

v5w DIS UZI.| uwgz" I

,' I >%21* 'U1^45 Ws15

isw BUM -aesw -

S~~~~~~~~~~~~~~~~~~~~~~~~~" RSW*1V-sI,'W A BEW = a \ _ }, * -ZS DI

f /~ sJ1 t2z::s .2SsoI4Ae M

,' / G~~~~~~~~~~~~~~SW u4> \ u 27*"'., 'BtlU;~~

WSW E / -- . A _ / ~ ~~~~~~~~~~~~~~~ /i2 UZWU2 t \i ' "s_

: / Bsw rz-n v\v MM sS u i

Wt*SUAEAi 01.2S 9 U6 I* 2S

~~~~~~9S | W1z- 4EU $ ,

/ > ' B~~~~~ ~~~~sw gZ Z1s¢- jelUi

C~~t =XU | | 9-2S& $1 a| 1-2IF 10

, I "s I xE.251S~~~~~~~~~~~~~~~~BE ZNC.<2"

Z __v__ s DI25 UU{~~ ~~822 \s _._

Z 4/> "s 25t4@ / \v)~~~~~~~~~~~~~~~~~~~~~~' _

Ez;;g / UR UZ-N7 | _ us/1 t-5 Z230 -- 5i

1 Zt SW RCZ 8-Nn U SII uZ.i1- U25 lZN S6

fNI l z- 9249 gS;f ms uz u w z-1l A. rsw g gzv ZNSI

\ $ 124M 9 ' sV-25 Vol*

\~~~~~~~~~~~~~~~~1 / C-NU _ 1E CE-U 1

w-----tSl f #v1X+sIF UZN3 >W2l

Ml ~~ #UW UMi21 1a2tg

\ +" leTSV Win

Z

! \ > >zsw DZ7

/~ ' ~DEWUZ.31

E:

DEW iA

9sV I

N .5 0 .5.S MILES YUCCA MOUNTAIN S17I

I LIE MTS CHAUCTIIZATION lOJIECT

Eisting Boreholes and UZ-16 A 1eso K13B4J

_( ( __~M er"~~~~~~~~~~~~355NN11

- N~~~~~~~~u

C, ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ - - - - - -

C, ~ ~ ~ ~ ~ ~ ~ ~ ~ 4

C.' ~ ~ ~ ~ ~ r

Po

574000it 575000ft

I I Hf, it~~~~ Pavem~~ent ArI ,a

''~~~~~~~~~ I I'j ~~ ~------------

ii iii, I / 1 ft / I j~~~~~~~~~~~~~~~~~~~~~~~~~~~~~kI/Il ft~~~~~~~~~~~~~~~~~~~~~~~~~~~~I

300 IS0 0 15 300

FEET YUCCA MOUNTAIN SITEo CIIRAACTEIZATION

-- ?1~~~~~POJCTMETERS

Iran Ridge Pit and Paeet Airea

I

P-

i W

! cZME . l

J F

- y = 1!~~~~~~~~~~~~~1

I IiI���i-I- 'iiII I iia ���� I

a i� I i'� �11131- A U B_ a - I

I I' j1� I I� -� - ii 111111

I H �Ii' �

c

N7Uftmima

AlitUahab

-

VI

a

Al. ~ ~ ~ - >

EWA BUXAD-

VI~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

&Alt ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ : 4 SIAM

an ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~~ -&Ms

fi7Y ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~~ *~~~

KPAWN (

TUCCA MOUNISITI CHAIA TRI ZANI RIOUIT

luSTING DIIUROUS WMI SUISUIACI ACCISS DMT

IOAD IAIS

h" Ui3p.~e lead Om I.Cnni SWe

L M .it -eb h3. C CWM. km lh,

OmI idqkU ~bfwbioaI.eId m"*RMh OM11

~~Ib ~~~N~~bI~~bbov

bm fo abofh o" W eSa

bhat---wpom.ff

Aeto n"n