Wambo - DA 305-7-2003 MOD 17 Briefing · Micheal Alexander – Dir. Projects & Portfolio Management...
Transcript of Wambo - DA 305-7-2003 MOD 17 Briefing · Micheal Alexander – Dir. Projects & Portfolio Management...
Wambo - DA 305-7-2003 MOD 17 Briefing 6 December 2017
Albert Scheepers – General Manager Micheal Alexander – Dir. Projects & Portfolio Management NSW Steven Peart – Manager Environment & Community
1. Overview of MOD 17.
2. Subsidence effects and impacts.
3. Groundwater and surface water conclusions.
4. Proposed conditions.
5. Justification of Modification.
2
Agenda
• Continued use of South Bates Underground coal handling
infrastructure located within the Bates South pit.
• Two additional ventilation shafts within existing approved
disturbance area.
• Gas drainage boreholes would be restricted to grassland.
• Delay in the commencement of South Wambo Underground
to allow for access to this coal.
• Extends the life of the operations by 7 years.
3
Overview of MOD 17
Modification Components
4
Overview of MOD 17
• 18 Mt of ROM coal from
the Whybrow Seam.
• Whybrow Seam
extensively mined at
Wambo.
• Wholly Wambo-owned
land.
• Adjacent to existing open
cut and underground
mining areas.
• No changes to the open
cut operations.
• No change to maximum
production rates or coal
handling operations.
5
Subsidence Effects and Impacts
Extent of Conventional
Subsidence
Wollemi Escarpment
• Extensive working knowledge of the Whybrow Seam and
high degree of confidence in prediction modelling.
• Subsidence impacts would continue to be managed in
accordance with:
• Subsidence impact performance measures in the
consent.
• Extraction Plan process – detailed management and
monitoring.
6
Subsidence Effects and Impacts
Management of Subsidence Impacts
• No additional impacts on surrounding water supply.
• Incremental impacts are generally confined to the extent of the
Modification longwalls.
• Numerical model developed by Dr Noel Merrick.
• Calibrated against 11 years of continuous monitoring data
(2003 – 2014).
• Peer reviewed by Dr Frans Kalf.
7
Groundwater and Surface Water Conclusions
Groundwater Assessment Conclusions
• North Wambo Creek has been diverted around the approved
Wambo open cut operations.
• North Wambo Creek is ephemeral.
• The catchment area of North Wambo Creek is approximately
2% of the catchment area of Wollombi Brook at Warkworth.
8
Groundwater and Surface Water Conclusions
North Wambo Creek
Water Supply
• No water used for domestic or stock along the complete length of North Wambo Creek.
• Classified as “less productive” by CLWD (formerly DPI Water).
• No privately-owned land along North Wambo Creek.
Ecological Values
• No permanent pools in the section of North Wambo Creek that would be undermined by Longwalls 23 to 25.
• 1 km of the length above LW 23 and 24 has been historically cleared for agriculture.
• Remaining vegetation is fragmented and affected by previous grazing activities.
9
Groundwater and Surface Water Conclusions
Values of North Wambo Creek
• Anticipated to be similar to impacts elsewhere on North Wambo
Creek and the Diversion where subsidence has already occurred at
similar mine geometries:
• Creation of semi-permanent or permanent pools.
• Surface soil cracking and changes in grade that may require local
scour protection works or remediation.
• Direct hydraulic connection has not been observed:
• Extraction of South Bates Underground LWs 11 to 13 (2016 – 2017)
beneath North Wambo Creek Diversion.
• Extraction of North Wambo Underground LWs 1 to 8a (2008 – 2015)
beneath North Wambo Creek (downstream of the Modification
area).
10
Groundwater and Surface Water Conclusions
Potential Impacts on North Wambo Creek
11
Groundwater and Surface Water Conclusions
• Hunter Lowland Redgum Forest.
• Not considered by Dr Colin Bower to be groundwater dependent.
• Recent drilling in the area showed the depth to groundwater is 4.8 to 13.8 m.
• Groundwater table is generally in consolidated bedrock below colluvium (generally not suitable for rooting).
• Significant monitoring programs have been undertaken at Wambo in areas of undermined vegetation. No observable effects to vegetation health due to reduced access to groundwater have been recorded at Wambo.
• Conditions require Wambo to meet subsidence impact performance
measure:
• Limited to - minor cracking and ponding of the land surface or other impact.
• Negligible environmental consequences.
• Failure to meet these measures is a non-compliance and also
requires an offset of the impact.
• The Extraction Plan provides further detail and confidence about
meeting these measures and how performance will be assessed.
• Wambo will conduct further studies into the potential groundwater
dependence of the riparian vegetation along North Wambo Creek.
• 4 years of mining prior to Longwall 25.
12
Proposed Conditions
Riparian Vegetation
• Underground mining and subsidence within WCPL owned land.
• Enables continued use of Wambo infrastructure and workforce.
• Economic recovery of coal resource that would otherwise not be
recovered.
• Facilitate continuity of underground operations (230 personnel).
• Additional royalties in the order of $66 M (NPV).
• Economic and social benefits in the Wambo region associated with
ongoing employment opportunities and expenditure.
13
Justification for Modification
Highlights