© Facility Engineering Associates 2010
VSP Vision CareVSP Vision CareHQ1, AT A GLANCE:
• 152,000 SF
• 9,700SF Data Center
• Fully automated
• Rancho Cordova, CA
• Constructed in 1992
• Began certification effort in 2007
• Internal Team – 5 people
• External Team –
FEA and Commissioning Agent
© Facility Engineering Associates 2010
IMPLEMENTATION RESULTS……….
Energy Saving Energy Saving Started with an Energy Star rating of 29!29! Implemented:
◦ Optimized lighting and HVAC controls◦ Sub-metered electricity◦ Scheduled Janitorial daytime cleaning◦ Developed training for employees
Received ENERGY STAR Label in 20092009
$ 123,254 Implementation Costs $ 64,030 Annual Savings 14% Annual Energy Savings 2 years Payback Energy Star rating of 93!93!
© Facility Engineering Associates 2010
IMPLEMENTATION RESULTS………
Waste ReductionWaste Reduction Initial Diversion Rate of 40%40% Implemented:
◦ Performed Waste Audit (Baseline)◦ Increased Number of Recycling Bins◦ Improved Staff Education◦ Reduced Size of General Waste◦ Sustainable Purchasing
Achieved 82%82% Waste Diversion (September 2008)
$ 42,828 Implementation Costs $ 21,888 Annual Savings 14% Annual Energy Savings 2 years Payback
© Facility Engineering Associates 2010
IMPLEMENTATION RESULTS……….
Water Projects - Savings Beyond EnergyWater Projects - Savings Beyond Energy
• Implemented:o Installed of low flow plumbing fixtureso Installed of aerators on faucets and dual flush valves on water
closetso Installed Light-Powered touch-free faucetso Installed Sub-meters on process systems (café’ and cooling tower)o Replaced irrigation water use by:
– Replacing scrubs with decomposed granite– Replacing spray irrigation with bubbles– Replacing existing plants with more water efficient plantings
$ 39,597 Implementation Costs $ 5,111 Annual Savings 50% Annual Water Savings 7.5 years Payback
© Facility Engineering Associates 2010
IMPLEMENTATION RESULTS……….
Indoor Environmental QualityIndoor Environmental Quality
• Implemented:o Meet ASHREA 62.1-2004 Standardo Relocated Smoking Sheltero Installed CO2 and Humidity Sensorso Installed MVR13 Filters
$ 82,546 Implementation Costs
© Facility Engineering Associates 2010
LEED by the NumbersLEED by the Numbers
The difference is $ 425,845.
Consulting Fees $84,050
USGBC Certification Fees
$5,002
Total Soft Costs $89,052
Energy Reduction Implementation Costs
$123,254
Water Reduction Implementation Costs
$39,597
Waste Reduction Implementation Costs
$42,828
IEQ
Implementation Costs
$82,546
INNO - Dolphin System $42,897
Total Hard Costs $331,122
Internal Staff $96,000
Total Others $96,000
Total Costs: $516,174Estimated Baseline Savings
$90,329
© Facility Engineering Associates 2010
Innovation – Raising the BarInnovation – Raising the Bar
Exemplary Performance
• Recycling 82% - September 2008
• Water Efficiency 36% below the water use Baseline
Innovative Operation
Chemical-free cooling water treatment.
Solar battery recharging station – decreased the amount of battery purchased as well as the recycling cost
© Facility Engineering Associates 2010
Sustainable Sites 7 points
Water Efficiency 3 points
Energy & Atmosphere 20 points
Materials & Resources 16 points
Indoor Environmental Quality 14 points
Innovation 5 points
Total 65 points
VSP Vision CareVSP Vision Care
ACHIEVED PLATINUM CERTIFICATION UNDER LEED – EB VERSION 2.0 - AUGUST 2008
Certified 32-39, Silver 40-47, Gold 48-63, Platinum 64-85
© Facility Engineering Associates 2010
Achievements: VSPAchievements: VSP
• Over 2,200 VSP team hours
1600VSP hours + 600 FEA hours = 2,200 team hours
• Achieved Platinum – August 2008
• Achieving Operational Excellence
14% annual energy savings
50% annual water savings
82% high, waste recycled (Sept ’08)
• Received 5% reduction on insurance premium