  • EMC VPLEX Hardware Installation Guide

    IntroductionThis document describes the basic hardware setup tasks for a factory-racked EMC VPLEX cluster at a customer site. Steps are included for both VS1 and VS2 VPLEX hardware.

    Prerequisites1. Verify that you have the following documents:

    EMC Best Practices Guide for AC Power Connections in Two-PDP Bays - Power requirements, including redundant power feeds on separate circuits (included in Open First box)

    EMC AC Power Configuration Worksheet - Power zone identification (included in Open First box)

    EMC 40U-C Cabinet Unpacking and Setup Guide - Instructions to unpack and secure the hardware in the data center (attached to cabinet)

    2. Note the approximate time that you moved the equipment into the data center. The equipment requires the time shown in the following table before you apply power, to prevent condensation on VPLEX components.

    3. Confirm that the following customer-supplied cables are available:

    Enough fiber-optic cables to make all necessary I/O connections, each cable with enough additional length to allow for component serviceability and a minimum two-inch bend radius

    Ethernet cable, to connect the VPLEX management server to the network

    Two AC power cables from separate site power sources

    4. Review the following information, available on EMC Powerlink:

    EMC VPLEX Site Preparation Guide, for electrical, mechanical, and cooling requirements

    EMC Simple Support Matrix, for support information on VPLEX integration into the customers storage environment

    Implementation and Planning Best Practices for EMC VPLEX Technical Notes

    EMC VPLEX with GeoSynchrony (version) Configuration Worksheet - Download for use during VPLEX setup

    Procedure1. Remove the cable holder kit from the Open First box, and place it into the

    pouch on the inside of the cabinets rear door.

    2. VS1 hardware only:

    a. At the front of the cabinet, remove each engines bezel, and confirm that the components shown in the following figure are secure:

    b. At the rear of the cabinet, push in on each director and the I/O module (IOM) carrier. If a component is not fully seated, loosen the orange screws, push the component firmly in, and retighten the screws. Verify that each IOMs latch button is in:

    3. VS2 hardware only :

    a. At the front of the cabinet, remove the 2U (3.5 inch) front panel approximately nine inches below the VPLEX nameplate, to expose the laptop service tray. Then remove and discard the two Phillips screws (used only for shipping) that secure the tray to the NEMA rails, and snap the front panel back into place.

    b. Remove each engines front panel. Then check the latches on all power supplies, and directors, and confirm that the components are secure. When finished, replace the front panel(s).

    c. At the rear, check the latches on all modules, and confirm that the components are secure. Verify that each modules latch button is in:

    4. VS1 and VS2 - Pull gently on each SFP on the I/O modules and (if present) Fibre Channel switches, to confirm that the SFPs are secure.

    5. Verify each cable connection by pressing the cable connector into its port or receptacle. Check the AC power cable connections closely, and confirm that any wire cable bales are positioned as shown in the following figure.

    13. Verify the LED status on each SPS:

    NOTE: The On-Battery LED stays on while the SPS units fully charge (which could be a few minutes or a few hours).

    From transit/storage environment Time required To nominal computer room environment

    Above 75oF (24oC) 4 hours

    68oF to 72oF (20oC to 22oC)

    68oF to 72oF (20oC to 22oC) None

    40oF to 65oF (4oC to 18oC) 4 hours

    Below 40oF (4oC) 8 hours

    Damp/high humidity 16 hours Air conditioned, low humidity

    VPLX-000345

    !

    !

    Power suppliesFan modules

    AA

    BB

    C D

    SSD enclosure

    VS1 engine, rear view

    VPLX-000304

    Director n B

    Director n A

    IOM carrier

    Latchbutton

    VPLX-000364

    VS2 engine, front view Power supply latches

    Director latches

    VPLX-000342

    Latchbutton

    VS2 engine, rear view

    VPLX-000344

    If an SFP is loose: a. Release the spring latch.b. Push the SFP fully in.c. Close the spring latch.

    a cb

    SPS or UPSThe wire cable bail is inserted into

    the middle of the plugs plastic molding.

    Fibre Channel switchThe wire cable bail is against

    the end of the plugs plastic molding.

    SYM-002500z

    VPLX-000309

    ON

    I

    OFF

    O

    ON

    I

    OFF

    O

    ON

    I

    OFF

    O

    ONI

    OFFO

    7. Switch OFF both PDP power switches. 8. Switch ON all 12 PDU circuit breakers. 9. Switch ON all SPS circuit breakers.

    10. Connect customer-supplied AC power cables from the PDPs to site power as described in the EMC Best Practices Guide for AC Power Connections in Two-PDP Bays.

    11. Switch ON both PDP power switches.

    ON

    I

    OFF

    O

    ON

    I

    OFF

    O

    ON

    I

    OFF

    O

    ONI

    OFFO

    PDPs

    PDUs

    To 30 A220 VAC

    12. Complete the EMC AC Power Configuration Worksheet. Then fold it in half and place it into the pouch on cabinets rear door.

    6. Verify that the equipment is fully acclimated to the data center environment, as described in Prerequisites step 2.

    VPLX-000313

    On-line enabled (if steady green) or Charging (if blinking green)

    On-Battery (if steady amber)

  • EMC VPLEX Hardware Installation Guide

    14. Connect customer-supplied fiber-optic cables from the front-end and back-end SANs to the appropriate VPLEX I/O ports. Do not touch the ends of any fiber-optic cable, to avoid damage or contamination.

    Use redundant physical Fibre Channel links to connect each host to the VPLEX directors, as well as each VPLEX director to the back-end storage. To prevent data unavailability, ensure that each host in a storage view has paths to at least two directors in a cluster, and that multipathing is configured to distribute the paths evenly between directors A and B in each engine:

    15. Route the cables to the sides of the cabinet as shown in the following figure, to prevent blocking components. Maintain a minimum radius of two inches for any bend in a Fibre Channel cable. (In a VS2 cabinet, route the cables along the cable management trays.)

    Route the cables up or down the sides of the cabinet through the plastic cable holders, and out the top or bottom of the cabinet.

    16. Connect the management server to the customer IP network:

    17. VPLEX Metro or VPLEX Geo only - Connect the intercluster cables as shown in the figure that applies to your WAN COM connection. Ensure that each director has two independendent paths to each director in the other cluster. (The connections are the same for each engine in a cluster.)

    VS1 directors with WAN connections over Fibre Channel:

    VS1 directors with WAN connections over IP:

    VS2 directors with WAN connections over Fibre Channel:

    VS2 directors with WAN connections over IP:

    Next steps1. Download and install the VPLEX Procedure Generator from Powerlink to

    access additional service, maintenance, and troubleshooting information.

    2. Work with the customer to complete the EMC VPLEX with GeoSynchrony (version) Configuration Worksheet, and give it to the customer.

    3. Follow the procedures in the EMC VPLEX with GeoSynchrony (version) Configuration Guide to configure the cluster for operation in the customer environment.

    Copyright 2011 EMC Corporation. All rights reserved.Published June 2011EMC believes the information in this publication is accurate as of its publication date. However, the information is subject to change without notice.

    THE INFORMATION IN THIS PUBLICATION IS PROVIDED AS IS. EMC CORPORATION MAKES NO REPRESENTATIONS OR WARRANTIES OF ANY KIND WITH RESPECT TO THE INFORMATION IN THIS PUBLICATION, AND SPECIFICALLY DISCLAIMS IMPLIED WARRANTIES OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE.

    Use, copying, and distribution of any EMC software described in this publication require an applicable software license.

    For the most up-to-date regulatory document for your product line, go to the Technical Documentation and Advisories section on EMC Powerlink.

    For the most up-to-date listing of EMC product names, see EMC Corporation Trademarks on EMC.com.

    All other trademarks used herein are the property of their respective owners. P/N 300-012-308 Rev A01

    = Fabric A

    = Fabric B

    Legend:IOM = I/O moduleFE = Front-end SAN portBE = Back-end SAN portPort colors:

    Director BIOM B0 - FE00 01 02 03

    IOM B1 - FE00 01 02 03

    IOM B2 - BE00 01 02 03

    IOM B3 - BE00 01 02 03

    Director AIOM A0 - FE00 01 02 03

    IOM A1 - FE00 01 02 03

    IOM A2 - BE00 01 02 03

    IOM A3 - BE00 01 02 03

    IOM carrierIOM B4 IOM B5 IOM A4 IOM A5

    VS1 engine, rear view

    VS2 engine, rear view

    00010203

    00010203

    Director AIOM A0 - FE IOM A1 - BE

    Director BIOM B0 - FE

    IOM

    B2

    WAN

    CO

    M

    IOM

    B3

    Loca

    l CO

    M

    IOM

    B4

    rese

    rve

    d

    IOM B1 - BE

    00010203

    00010203

    IOM

    A2

    WAN

    CO

    M

    IOM

    A3

    Loca

    l CO

    M

    IOM

    A4

    rese

    rve

    d

    VPLX-000306

    Front-e

    nd c

    able

    s

    Back

    -end

    cab

    les

    Front-e

    nd c

    able

    s

    Back

    -end

    cab

    les

    VPLX-000314VS1 VS2

    VPLX-000307

    1 Gb/s public Ethernet port

    Customer-providedEthernet cable

    CustomerIP network

    VPLX-000356

    A4-FC03B4-FC03A4-FC02

    B4-FC02

    InterclusterCOM SAN A

    InterclusterCOM SAN B

    VPLX-000357

    A5-GE01B5-GE01A5-GE00

    B5-GE00

    IP subnet A

    IP subnet B

    VPLX-000358

    B2-FC01

    B2-FC00

    A2-FC01

    A2-FC00

    InterclusterCOM SAN A

    InterclusterCOM SAN B

    VPLX-000359

    B2-XG01

    B2-XG00

    A2-XG01

    A2-XG00

    IP subnet A

    IP subnet B