VOLUME II - Regional SanSO-2 Laguna Blvd. to Franklin Blvd. $21,360,000 SO-3 Franklin Blvd. to East...
Transcript of VOLUME II - Regional SanSO-2 Laguna Blvd. to Franklin Blvd. $21,360,000 SO-3 Franklin Blvd. to East...
-
VOLUME IIChapter 9- Recommended Capital Improvement Program............................................... 9-19.1 Recommended Capital Expenditures ............................................................... 9-19.2 Schedule of Improvements ............................................................................... 9-19.2.1 Project Prioritization......................................................................................... 9-19.3 Comparison to Previous Master Planned Expenditures ................................... 9-39.4 Guidelines for Implementation......................................................................... 9-59.4.1 Project Verification .......................................................................................... 9-5
List of Figures PageFigure 9-1 .......................................................................................... Following Page 9-1Figure 9-2 .......................................................................................... Following Page 9-1Figure 9-3 .......................................................................................... Following Page 9-1Figure 9-4 .......................................................................................... Following Page 9-1Figure 9-5 .......................................................................................... Following Page 9-1Figure 9-6 .......................................................................................... Following Page 9-1Figure 9-7 .......................................................................................... Following Page 9-1Figure 9-8 .......................................................................................... Following Page 9-1Figure 9-9 .......................................................................................... Following Page 9-3Figure 9-10 .......................................................................................... Following Page 9-4
List of Tables PageTable 9-1 .......................................................................................... Following Page 9-1Table 9-2 ......................................................................................................On Page 9-2Table 9-3 ......................................................................................................On Page 9-3Table 9-4 .......................................................................................... Following Page 9-5
-
SRCSD Interceptor System Master Plan 2000
S:\MP 2000\Draft MP2000\Chapter 9\Chapter 9.doc 9-1
Chapter 9
Recommended Capital Improvement Program
9.1 Recommended Capital ExpendituresThe recommended SRCSD Interceptor System Master Plan Capital Improvement Programcontains 52 projects required to convey wastewater flows from existing and planneddevelopment to the Sacramento Regional Wastewater Treatment Plant. The facilities arescheduled to be constructed over the next 35 years, and when operational, will providecapacity for all planned development within the Urban Services Boundary and WestSacramento. The total capital cost of the master planned facilities is $950,100,000. Thiscost is in year 2000 dollars and does not include inflation or interest adjustments for any ofthe identified projects. The capital cost of each project is shown in Table 9-1. The capitalexpenditure per year is shown on Figure 9-1.
9.2 Schedule of ImprovementsThe improvements identified in MP 2000 have been assigned start and completion datesbased on the anticipated need for each facility to be operational. The start and completiondates for each project are contained in the project schedule, Figure 9-2. A large format,more detailed project schedule may be found in the appendix of this report. A visualrepresentation of the recommended project implementation over time is shown in Figures9-3 through 9-8.
9.2.1 Project PrioritizationThe recommended interceptor projects were developed to address existing and futurecapacity deficiencies in the existing interceptor system, and to extend conveyance facilitiesto planned development within the SRCSD service area. Each project was categorized intoone of three types of project justifications:
Category A: Required to relieve existing capacity deficiency
Category B: Required to relieve future capacity deficiency
Category C: Required to provide conveyance of wastewater generated fromfuture planned development beyond the reaches of the existinginterceptor system
-
TABLE 9-1ESTIMATED CAPITAL COST OF RECOMMENDED INTERCEPTOR PROJECTS
Project ID Project LocationEstimated Capital
CostBR-1 SRWTP to Franklin Blvd. $14,180,000
BR-6A South of Gerber Rd. to Bradshaw Rd. $16,620,000BR-6B South of Elder Creek to Mayhew and Jackson $19,600,000BR-7 Jackson Hwy. to International Dr. $31,890,000BR-8 International Dr. to Folsom Blvd. $29,890,000SR-1 Folsom Blvd. to South of American River $10,820,000SR-2 South of American River to Pennsylvania Ave. $9,300,000
FE-1B East of Sunrise Blvd. to Folsom South Canal $10,890,000FE-3 Iron Point Road $11,790,000
FE-3PS South of Iron Point Road $4,660,000LE-1 SRWTP to Franklin Blvd. at Dwight Rd. $9,000,000NN-1 Del Paso Rd. to end of pipe $3,400,000ARPS Arden Pump Station Site to south of American River $20,000,000RCPS Cordova Pump Station Site $9,350,000
UNW-1 Natomas PS to Del Paso Blvd. $29,200,000UNW-2 Del Paso Blvd. to Elkhorn Blvd. $26,280,000UNW-3 Elkhorn Blvd. to Natomas East Main Drain $8,660,000UNW-4 Natomas East Main Drain to Cherry Lane $14,460,000UNW-5 Cherry Lane to East of Watt Ave. $22,260,000UNW-6 East of Watt Ave. to West of SPRR $8,290,000DRR-1 28th St. and Elkhorn Blvd. to Scotland Dr. $7,080,000UNW-7 West of SPRR to Van Maren PS $12,620,000UNW-8 Van Maren Pump Station $13,920,000UNW-9 Van Maren PS to Fair Oaks Blvd. $14,210,000LNW-1 SRWTP to West of Sacramento River $27,500,000SRPS Southport Regional Pump Station (Phase 1 - 3) $33,050,000
LNW-2 West of Sacramento River to South of Linden Rd. $84,010,000WSCSM West Sacramento Treatment Plant $2,000,000LNW-3 South of Linden Rd. to Natomas Pump Station $75,070,000NNPS Natomas Pump Station Site (Phase 1 - 4) $21,090,000SO-1 SRWTP to Laguna Blvd. $8,660,000SO-2 Laguna Blvd. to Franklin Blvd. $21,360,000SO-3 Franklin Blvd. to East of Bruceville Rd. $18,270,000LC-1 SRWTP to Bruceville Rd. $24,840,000LC-2 Bruceville Rd. to Waterman Rd. $44,700,000LC-3 Waterman Rd. to Excelsior Rd. $36,040,000LC-4 Excelsior Rd. to Sunrise Blvd. $20,500,000LC-5 Sunrise Blvd. to end of pipe $5,430,000DC-1 Waterman Rd. North of Bond Rd. to Deer Creek $25,430,000DC-2 Deer Creek to Folsom South Canal $18,210,000DC-3 Folsom South Canal to end of pipe $16,080,000DC-4 South of Crevis Creek to end of pipe $3,320,000MA-1 Happy Lane to East of Folsom South Canal $37,020,000AJ-1 Sunrise and Douglas to West of Jaeger Rd. $5,080,000AJ-2 Sunrise and Douglas to White Rock Rd. $17,400,000
AJ-2S Sunrise and Douglas to North of Morrison Creek $7,490,000AJ-3 White Rock Rd. to South of Hwy 50 $7,680,000
AJ-3S White Rock Rd. to Old White Rock Rd. $3,930,000AJ-4 Sunrise and Douglas to end of LC-5 $21,940,000RL-1 Elkhorn Blvd. to Elverta Rd. East of Rio Linda Blvd. $10,800,000
BR-6BS Bradshaw Rd. to South of Elder Creek Rd. $2,990,000FS-1 South of Hwy. 50 to Iron Point Rd. $8,440,000
Total $966,700,000
-
Black & Veatch 1/4/2001
Figure 9-1SRCSD Master Plan 2000 - Estimated Capital Expenditures
$0
$20
$40
$60
$80
$100
$120
$140
$160
$180
$20020
00
2002
2004
2006
2008
2010
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
2034
Year
ly E
xpen
ditu
res
($ M
illio
ns)
$0
$200
$400
$600
$800
$1,000
$1,200
Cum
ulat
ive
Expe
nditu
res
($ M
illio
ns)
Yearly ExpendituesCummulative Expenditures
-
Project Start FinishSRCSD Interceptor Master Plan 2000 1/3/00 2/16/01Upper NWI Design Report 7/3/00 5/11/01Lower NWI Design Report 6/8/00 12/5/01Interceptor Design Manual 1/3/01 11/13/01Bradshaw Interceptor Section 1 & 2 1/3/00 10/6/00Bradshaw Interceptor Section 6A 1/3/00 7/11/03Bradshaw Interceptor Section 6B 1/3/00 4/16/04Bradshaw Interceptor Section 7 1/2/01 11/29/04Bradshaw Interceptor Section 8 1/8/01 1/14/05Sunrise Interceptor Section 1 12/9/02 12/15/06Sunrise Interceptor Section 2 12/9/02 12/15/06Folsom East Interceptor Section 1B 6/5/00 12/13/02Folsom East Section 3 & Pump Station 1/3/00 11/29/02Laguna Interceptor Extension 2/19/01 8/29/03North Natomas Interceptor 1/3/02 7/14/04Arden Pump Station / Force Main 1/3/00 4/19/02Rancho Cordova Pump Station (Phase 1) 11/1/00 7/23/02Rancho Cordova Pump Station (Phase 2) 2/15/18 8/26/20Upper Northwest Interceptor Section 1 1/3/03 1/11/07Upper Northwest Interceptor Section 2 & 3 12/3/04 6/11/09Upper Northwest Interceptor Section 4 4/2/07 10/9/09Upper Northwest Interceptor Section 5 & 6 2/19/01 1/14/05Dry Creek Relief 7/8/02 1/14/05Upper Northwest Interceptor Section 7 & 8 6/4/01 4/29/05Upper Northwest Interceptor Section 9 1/3/07 7/14/09Lower Northwest Interceptor Section 1 4/3/02 2/28/06Southport Regional Pump Station (Phase 1) 4/7/03 7/7/06Southport Regional Pump Station (Phase 2) 1/4/16 4/5/19Southport Regional Pump Station (Phase 3) 1/7/30 4/8/33Lower Northwest Interceptor Section 2 7/8/02 6/2/06West Sac Collection System Modifications 7/7/03 1/13/06Lower Northwest Interceptor Section 3 10/7/02 1/19/07Natomas Pump Station (Phase 1) 10/5/00 1/7/04Natomas Pump Station (Phase 2) 1/2/06 4/3/09Natomas Pump Station (Phase 3) 1/4/12 4/7/15Natomas Pump Station (Phase 4) 1/6/20 4/7/23South Interceptor Section 1 5/7/07 11/13/09South Interceptor Section 2 & Pump Station 10/8/07 10/14/11South Interceptor Section 3 6/14/10 12/21/12Laguna Creek Interceptor Section 1 9/7/09 3/16/12Laguna Creek Interceptor Section 2 3/19/12 2/12/16Laguna Creek Interceptor Section 3 2/15/16 1/10/20Laguna Creek Interceptor Section 4 1/13/20 12/8/23Laguna Creek Interceptor Section 5 1/3/22 7/12/24Deer Creek Interceptor Section 1 1/13/20 7/21/23Deer Creek Interceptor Section 2 7/24/23 1/29/27Deer Creek Interceptor Section 3 2/1/27 8/9/30Deer Creek Interceptor Section 4 8/12/30 2/18/33Mather Interceptor Section 1 7/5/11 1/12/15Aerojet Interceptor Section 1 7/8/13 1/15/16Aerojet Interceptor Section 2 1/18/16 7/27/18Aerojet Interceptor Section 2S 1/18/16 7/27/18Aerojet Interceptor Section 3 9/25/20 4/6/23Aerojet Interceptor Section 3S 4/7/23 10/16/25Aerojet Interceptor Section 4 7/16/29 6/10/33Rio Linda Interceptor Section 1 2/6/23 8/15/25Bradshaw Interceptor Section 6BS 1/4/21 7/14/23Folsom South Pump Station and Force Main 1/3/20 7/14/22
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033
Figure 9-2SRCSD Interceptor Master Plan 2000 Project Schedule
1/3/01
-
SRCSD Interceptor System Master Plan 2000
S:\MP 2000\Draft MP2000\Chapter 9\Chapter 9.doc 9-2
Those projects assigned to Category A were scheduled to begin as soon as possible.Projects in Category B and C were scheduled based on the need for sewerage facilities asprojected by anticipated development plans.
The projects contained in each category are listed in Table 9-2.
TABLE 9-2 – PROJECTS LISTED BY CATEGORY
Category A Category B Category CBR-1 RCPS FE-3
BR-6A UNW-9 FE-3PSBR-6B LNW-1 NN-1BR-7 SRPS UNW-1BR-8 LNW-2 UNW-2SR-1 LNW-3 UNW-3SR-2 NNPS UNW-4
FE-1B WSCSMLE-1 SO-1ARPS SO-2
UNW-5 SO-3UNW-6 LC-1DRR-1 LC-2UNW-7 LC-3UNW-8 LC-4RCPS LC-5
DC-1DC-2DC-3DC-4MA-1AJ-1AJ-2
AJ-2SAJ-3
AJ-3SAJ-4RL-1
BR-6BSFS-1
-
SRCSD Interceptor System Master Plan 2000
S:\MP 2000\Draft MP2000\Chapter 9\Chapter 9.doc 9-3
As shown in Figure 9-1 there is a spike in project expenditures between the years 2002 and2006. This period of high expenditures is primarily caused by the construction of threemajor interceptor projects: Bradshaw/Folsom, Upper Northwest, and Lower Northwest.The yearly expenditures for these projects are shown in Figure 9-9. The Bradshaw/Folsomand Upper Northwest Interceptors are required to relieve existing capacity deficiencies inthe SRCSD interceptor system and CSD-1 trunk system. Although the project segments ofthe Lower Northwest Interceptor are classified as Category B projects, they are required toprovide relief to the Natomas and Arden Pumping stations. Each of these pumping stationsare being upgraded to increase capacity, however, this is intended to only be a stop-gapmeasure to allow a reasonable timeframe for the design and construction of the LowerNorthwest Interceptor.
9.3 Comparison to Previous Master PlannedExpenditures
The 1994 update to the Sacramento Sewerage Expansion Study (SSES) estimated the totalcapital cost of the recommended interceptor projects to be $595,100,000 (1993 dollars).The current MP 2000 estimate is $966,700,000. The major increases in project costsaccounting for the $371,600,000 increase are itemized in Table 9-3, below. The differencebetween the $385 million total increase and $372 million difference from the previousmaster plan is due to a net cost savings on other projects contained in the MP 2000.
TABLE 9-3 – PROJECTS CONTRIBUTING TO INCREASED PROGRAM COSTS
Item: Increase:Inflation (ENR CCI) $93 millionLower Northwest Interceptor $148 millionUpper Northwest Interceptor $61 millionNewly Identified Projects $82 millionTotal: $385 million
A description of each of these items is presented below.
Inflation - The Sacramento Sewerage Expansion Study - 1994 Update used anENR Construction Cost Index (CCI) of 5,600 which represented the mid-pointbetween the 20-cities index and the San Francisco index at the time the estimatewas being generated. The January 2000 value of this index is 6474. Thisrepresents a 15.6% increase due to inflation of the seven-year period and results inan $93 million increase in program costs.
Lower Northwest Interceptor – The SSES estimated the cost of the LowerNorthwest Interceptor to be $95 million (2000 dollars). The MP 2000 estimate forthese facilities is $243 million. The MP 2000 assumes a West Sacramento route forthe Lower Northwest Interceptor and increases the size of the interceptor facilities
-
Figure 9-9Major Near Term Interceptor Projects
$0
$20
$40
$60
$80
$100
$120
2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010
Cap
ital C
ost (
$ M
illio
ns)
Bradshaw/Folsom Interceptor
Upper Northwest Interceptor
Lower Northwest Interceptor
-
SRCSD Interceptor System Master Plan 2000
S:\MP 2000\Draft MP2000\Chapter 9\Chapter 9.doc 9-4
to provide conveyance capacity for West Sacramento. A cursory review of theoriginal estimate revealed some additional reasons for the large discrepancy.Approximately half of the base pipeline cost from the SSES was based on a unitcost for 72-inch force main of $320 per foot. This unit price appears to be low forthe type of area the pipeline is routed through. Additionally, the $5 million basecost of expanding the Natomas Pump Station to 73 mgd appears to be low.
Upper Northwest Interceptor – The Upper Northwest Interceptor was estimatedat $89 million (2000 dollars) in the SSES. The estimate from the Upper NorthwestInterceptor Design Report is approximately $138 million, and the MP 2000estimate is $150 million. The increase is primarily attributable to the increasedcapacity of the facilities identified in the design report to divert additional flowsfrom impacted trunk facilities in the northeast system. Additional costs are alsoexpected to be incurred due to the combination of poor soil and accelerateddevelopment in the North Natomas Area. The increase from the Design Reportestimate to the MP 2000 estimate was related to the need to increase the size of theinterceptor to convey higher flows based on modeling results, and costs associatedwith deepening the pipeline to provide gravity service to a larger portion of theservice area.
Newly Identified Projects – The Interceptor System Master Plan 2000 hasidentified additional projects beyond those identified in the SSES that will berequired to provide conveyance capacity to serve ultimate development within theUrban Services Boundary. These projects include the ARPS (Arden Pump StationModifications), FS-1 (Folsom South Pump Station and Force Main), and AJ-1through AJ-4 (AeroJet Interceptor). Modifications to the Arden Pump Station areneeded to bring its capacity up to the value assumed in the SSES (approximately105-mgd). The Folsom South Pump Station was required due to the realignment ofFolsom East Interceptor Section 3 to Iron Point Road. The AeroJet Interceptor isrequired to provide service to the Mather/AeroJet Area. This area was originallyidentified as not requiring sewer service. However, due to changes in land useplanning since the SSES, this area has been assigned an average developmentdensity of 6 ESD per acre.
A comparison of expenditures in relation to time between the SSES and the MP 2000 isshown in Figure 9-10. To estimate expenditure over time for the SSES the capital cost foreach phase was divided evenly by the number of years per phase. The costs associatedwith interceptor projects completed to date are indicated in red. The total costs to date forthe previously construction interceptors have been added to the cumulative MP 2000 costsin order to compare with the previous estimates of the entire program.
As indicated in Figure 9-10, total expenditures since 1993 have been less than projected inthe 93/94 SSES. This indicates that not all improvements identified in Phase 1 of the93/94 SSES were completed on schedule. The delay in the construction of these facilitieshas contributed to the expenditure spike projected between the years 2002 and 2006.
-
Black & Veatch Final CIP Expend.xls
Figure 9-10SRCSD Interceptor Actual and Recommended Expenditures
$0
$20
$40
$60
$80
$100
$12019
9319
9419
9519
9619
9719
9819
9920
0020
0120
0220
0320
0420
0520
0620
0720
0820
0920
1020
1120
1220
1320
1420
1520
1620
1720
1820
1920
2020
2120
2220
2320
2420
2520
2620
2720
2820
2920
3020
3120
3220
3320
3420
35
Cap
ital E
xpen
ditu
re p
er Y
ear (
$ M
illio
ns)
$0
$200
$400
$600
$800
$1,000
$1,200
Cum
ulat
ive
Expe
nditu
res
($ M
illio
ns)
1993/94 SSES (1993 dollars)
1993/94 SSES (2000 dollars)
MP 2000
Actual Expenditures
Cumulative Values
-
SRCSD Interceptor System Master Plan 2000
S:\MP 2000\Draft MP2000\Chapter 9\Chapter 9.doc 9-5
9.4 Guidelines for ImplementationThe MP 2000 provides a detailed plan of the interceptor facilities and right of waynecessary to provide sewage conveyance within the Sacramento County USB and citylimits of West Sacramento. Timing of interceptor projects identified for constructionwithin the next 20 years is based on the operational condition of the existing regionalfacilities and/or SACOG growth projections within the study area. Projects identified forconstruction after the year 2020 are based on buildout densities within the USB that are notassociated with a particular timeframe. Projects scheduled after 2020 are intendedprimarily to identify facilities required to provide service under a developed USB scenario.As the case with previous master planning efforts, the MP 2000 should be consider a“working document” and subject to review at least every year and updated every fiveyears.
Table 9-4 summarized the recommended interceptor projects, describes project “drivers”and timing considerations, and assigns a priority level to the project.
9.4.1 Project VerificationThe modeling results of the expanded interceptor system during a 10-year design periodstorm at buildout of the USB predict two interceptors with significant surcharging causedby limited pipe capacity. These facilities are the McClellan Interceptor and the LagunaInterceptor. The predicted surcharging may be caused by inaccurate flow monitoringinformation. It is recommended that additional flow monitor analysis be performed inthese areas and the hydraulic model be recalibrated before identifying future relief projects.
If major land use changes have occurred since the completion of this MP 2000, designflows should be updated and the hydraulic model re-run to determine the impacts the landuse changes have on the interceptor system.
Finally, the SRCSD should continue metering flow at strategic locations along theinterceptor system. This data should be used to verify and update regional inflowcoefficient (Kp) values throughout the service area. By periodically updating the hydraulicmodel with this information, the SRCSD may accelerate or delay recommended projectsbased on the most recent system response information.
-
Improvement Project Category Driver Priority Timing Considerations Start Finish Start Finish
Bradshaw Interceptor Section 1&2 ARequired for relief of Central and Northeast Interceptors. Needed to bring Bradshaw Sections 3, 4, 5A, and 5B into service.
- Under Construction - - - 10/6/2000
Bradshaw Interceptor Section 6A A Required for relief of Central and Northeast Interceptors. 1 Requires completion of Bradshaw 1 & 2, project under design1/3/2000 5/4/2001 5/7/2001 7/11/2003
Bradshaw Interceptor Section 6B A Required for relief of Central and Northeast Interceptors. 1 Requires completion of Bradshaw 1 & 2, project under design1/3/2000 2/8/2002 2/11/2002 4/16/2004
Bradshaw Interceptor Section 7 A Required for relief of Northeast area and Folsom Interceptor. 2 Required to abandon portion of Folsom Interceptor prior to extension of Light Rail1/2/2001 9/23/2002 9/24/2002 11/29/2004
Bradshaw Interceptor Section 8 A Required for relief of Northeast area and Folsom Interceptor. 2 Required to abandon portion of Folsom Interceptor prior to extension of Light Rail1/8/2001 2/14/2003 2/17/2003 1/14/2005
Sunrise Interceptor Section 1 A Required for relief of capacity deficient trunks in Northeast area. 2 Coordinate with extension of Light Rail12/9/2002 1/14/2005 1/17/2005 12/15/2006
Sunrise Interceptor Section 2 A Required for relief of capacity deficient trunks in Northeast area. 212/9/2002 1/14/2005 1/17/2005 12/15/2006
Folsom East Interceptor Section 1B A Existing Folsom Interceptor at capacity during PWWF. Required to provide capacity for new development in Folsom. 2 Folsom Blvd road improvements6/5/2000 10/5/2001 10/8/2001 12/13/2002
Folsom East Section 3 C Required to provide service to new development in Folsom East area. 2
Requires peak shaving in Folsom East Interceptor prior to completion of Bradshaw and Folsom East 1B. This project has been combined with Folsom East 3 Pump Station to form a single construction project.
1/3/2000 9/22/2000 9/25/2000 11/29/2002
Folsom East 3 Pump Station C Required to provide service to new development in Folsom East area. 2
Requires peak shaving in Folsom East Interceptor prior to completion of Bradshaw and Folsom East 1B. This project has been combined with Folsom East Section 3 to form a single construction project.
1/3/2000 9/22/2000 9/25/2000 11/29/2002
Laguna Interceptor Extension A Required to bring Laguna Interceptor into service and relieve existing deficiencies in Elk Grove trunk system. 1 Requires completion of MP20002/19/2001 6/21/2002 6/24/2002 8/29/2003
North Natomas Interceptor C Required for new development in North Natomas and Metro Air Park areas. 31/3/2002 5/7/2003 5/8/2003 7/14/2004
Arden Pump Station / Force Main A Existing PWWF exceeds firm capacity of pump station. 1 Requires completion of MP2000 and Arden Capacity Study1/3/2000 10/6/2000 10/9/2000 4/19/2002
Rancho Cordova Pump Station (Phase 1) A
Pump station does not have firm capacity for Peak Wet Weather Flows 1 Currently under design
11/1/2000 10/16/2001 10/17/2001 7/23/2002
Rancho Cordova Pump Station (Phase 2) B
Pump station does not have sufficient capacity for ultimate development of the area. 3
Dependant upon actual flows as monitored at the pump station
2/5/2018 6/7/2019 6/10/2019 8/14/2020
Upper Northwest Interceptor Section 1 C
Required for new development in North Natomas and Rio Linda and relief of Northeast area. 2
Available capacity of Dry Creek Interceptor, Natomas and Arden Pump Stations
1/3/2003 2/10/2005 2/11/2005 1/11/2007
Upper Northwest Interceptor Section 2 C
Required for new development in North Natomas and Rio Linda and relief of Northeast area. 2
Available capacity of Dry Creek Interceptor, Natomas and Arden Pump Stations. This project has been combined with Upper Northwest Interceptor Section 3 to form a single construction project.
12/3/2004 1/11/2007 1/12/2007 6/11/2009
TABLE 9-4
ConstructionDesignSCHEDULING AND PRIORITY LIST
Black & Veatch 1/4/2001
-
Improvement Project Category Driver Priority Timing Considerations Start Finish Start Finish
Upper Northwest Interceptor Section 3 C
Required for new development in North Natomas and Rio Linda and relief of Northeast area. 2
Available capacity of Dry Creek Interceptor, Natomas and Arden Pump Stations. This project has been combined with Upper Northwest Interceptor Section 2 to form a single construction project.
12/3/2004 1/11/2007 1/12/2007 6/11/2009
Upper Northwest Interceptor Section 5 A
Required for relief of capacity deficient trunks in Northeast area including Mission Trunk. 1
Requires completion of MP2000. This project has been combined with Upper Northwest Interceptor Section 6 to form a single construction project.
2/19/2001 11/8/2002 11/11/2002 1/14/2005
Upper Northwest Interceptor Section 6 A
Required for relief of capacity deficient trunks in Northeast area including Mission Trunk. 1
Requires completion of MP2000. This project has been combined with Upper Northwest Interceptor Section 5 to form a single construction project.
2/19/2001 11/8/2002 11/11/2002 1/14/2005
Dry Creek Relief A Required for relief of Dry Creek Interceptor. 1 Requires completion of Upper Northwest Section 5 & 6 7/8/2002 11/7/2003 11/10/2003 1/14/2005
Upper Northwest Interceptor Section 7 A
Required for relief of capacity deficient trunks in Northeast area including Mission Trunk. 1
Requires completion of Upper Northwest 5 & 6. This project has been combined with Upper Northwest Interceptor Section 8 to form a single construction project.
6/4/2001 2/21/2003 2/24/2003 4/29/2005
Upper Northwest Interceptor Section 8 A
Required for relief of capacity deficient trunks in Northeast area including Mission Trunk. 1
Requires completion of Upper Northwest 5 & 6. This project has been combined with Upper Northwest Interceptor Section 7 to form a single construction project.
6/4/2001 2/21/2003 2/24/2003 4/29/2005
Upper Northwest Interceptor Section 9 B
Required for relief of future capacity deficiency in Northeast area. 3 Depends on impact of development on trunk capacity
1/3/2007 5/6/2008 5/7/2008 7/14/2009
Lower Northwest Interceptor Section 1 B
Required for relief of Northeast area and for new development in North Natomas. 1
Available capacity of Arden Pump Station, Natomas Interceptor, and Mission Trunk. Requires completion of Lower Northwest Design Report
4/3/2002 12/23/2003 12/24/2003 2/28/2006
Southport Regional Pump Station B Required for relief of Northeast area and for new development in North Natomas and West Sacramento. 1Project to be constructed in multiple stages to provide flexibility in the facility's ultimate capacity. Requires completion of Lower Northwest Design Report
4/7/2003 8/6/2004 8/9/2004 7/7/2006
Lower Northwest Interceptor Section 2 B
Required for relief of Northeast area and for new development in North Natomas. 1
Available capacity of Arden Pump Station, Natomas Interceptor, and Mission Trunk. Requires completion of Lower Northwest Design Report
7/8/2002 3/26/2004 3/29/2004 6/2/2006
West Sacramento Collection System Modifications C Capacity considerations at West Sacramento Treatment Plant. 1 Requires completion of Lower Northwest Interceptor
7/7/2003 11/5/2004 11/8/2004 1/13/2006
Lower Northwest Interceptor Section 3 B
Required for relief of Northeast area and for new development in North Natomas. 1
Available capacity of Arden Pump Station, Natomas Interceptor, and Mission Trunk. Requires completion of Lower Northwest Design Report
10/7/2002 11/12/2004 11/15/2004 1/19/2007
Natomas Pump Station B Required for relief of Northeast area and for new development in North Natomas. 1Limited capacity of existing Natomas Pump Station. Project to be constructed in multiple stages to provide flexibility in the facility's ultimate capacity
10/5/2000 2/6/2002 2/7/2002 1/7/2004
South Interceptor Section 1 C Required for future development in East Franklin area. 2 Requires construction of Laguna Interceptor Extension 5/7/2007 9/5/2008 9/8/2008 11/13/2009
South Interceptor Section 2 C Required for future development in East Franklin area. 2 10/8/2007 11/13/2009 11/16/2009 10/14/2011
South Interceptor Section 3 C Required for future development in East Franklin area. 2 6/14/2010 10/14/2011 10/17/2011 12/21/2012
TABLE 9-4 - CONTINUEDSCHEDULING AND PRIORITY LIST
Design Construction
Black & Veatch 1/4/2001
-
Improvement Project Category Driver Priority Timing Considerations Start Finish Start FinishLaguna Creek Interceptor Section 1 C Required for future development in Southeast county. 3 Available capacity in Bradshaw 9/7/2009 1/7/2011 1/10/2011 3/16/2012
Laguna Creek Interceptor Section 2 C Required for future development in Southeast county. 3 Available capacity in Bradshaw 3/19/2012 12/6/2013 12/9/2013 2/12/2016
Laguna Creek Interceptor Section 3 C Required for future development in Southeast county. 3 Available capacity in Bradshaw 2/15/2016 11/3/2017 11/6/2017 1/10/2020
Laguna Creek Interceptor Section 4 C Required for future development in Southeast county. 3 Available capacity in Bradshaw 1/13/2020 10/1/2021 10/4/2021 12/8/2023
Laguna Creek Interceptor Section 5 C Required for future development in Southeast county. 3 Available capacity in Bradshaw 1/3/2022 5/5/2023 5/8/2023 7/12/2024
Deer Creek Interceptor Section 1 C Required for future development in Deer Creek basin. 3 1/13/2020 5/14/2021 5/17/2021 7/21/2023
Deer Creek Interceptor Section 2 C Required for future development in Deer Creek basin. 3 7/24/2023 11/22/2024 11/25/2024 1/29/2027
Deer Creek Interceptor Section 3 C Required for future development in Deer Creek basin. 3 2/1/2027 6/2/2028 6/5/2028 8/9/2030
Deer Creek Interceptor Section 4 C Required for future development in Deer Creek basin. 3 8/12/2030 12/12/2031 12/15/2031 2/18/2033
Mather Interceptor Section 1 C Required for new development in Sunrise-Douglas area. 3 Requires completion of Bradshaw 7 7/5/2011 11/5/2012 11/6/2012 1/12/2015
Aerojet Interceptor Section 1 C Required for future development in Aerojet area. 3 7/8/2013 11/7/2014 11/10/2014 1/15/2016
Aerojet Interceptor Section 2 C Required for future development in Aerojet area. 3 1/18/2016 5/19/2017 5/22/2017 7/27/2018
Aerojet Interceptor Section 2S C Required for future development in Aerojet area. 3 1/18/2016 5/19/2017 5/22/2017 7/27/2018
Aerojet Interceptor Section 3 C Required for future development in Aerojet area. 3 9/25/2020 1/27/2022 1/28/2022 4/6/2023
Aerojet Interceptor Section 3S C Required for future development in Aerojet area. 3 4/7/2023 8/8/2024 8/9/2024 10/16/2025
Aerojet Interceptor Section 4 C Required for future development in Aerojet area. 3 Available capacity in Bradshaw 7/16/2029 4/4/2031 4/7/2031 6/10/2033
Rio Linda Interceptor Section 1 C Required for future development in Rio Linda. 3 2/6/2023 6/7/2024 6/10/2024 8/15/2025
Bradshaw Interceptor Section 6BS C Required for future development West of Bradshaw. 3 1/4/2021 5/6/2022 5/9/2022 7/14/2023
Folsom South PS and Force Main C Required for future development in Folsom South area. 3 1/3/2020 5/6/2021 5/7/2021 7/14/2022
SCHEDULING AND PRIORITY LISTDesign Construction
TABLE 9-4 - CONTINUED
Black & Veatch 1/4/2001
-
SRCSD Master Plan 2000Project Summary
Project Name: Bradshaw Interceptor Section 1 & 2
Project ID: BR-1 1
Location: SRWTP to Franklin Blvd
Description of Facility: 90 and 120-inch gravity pipeline
Length: 6,690 ft.
Design Capacity: 206 to 303 mgd
Project Justification: Category A: Required for relief of Northeast and Central Interceptors
Primary Construction Method: Open Cut
Special Considerations: Tunnel beneath railroad and wetlands
Base Construction Cost: $5,689,592
Special Structures: $1,765,000Traffic Control: $56,896
Environmental Mitigation: $20,000Right-of-Way: -
Special Construction/Pipe Jack: $2,778,713Contingency: $1,031,020
Total Construction Cost $11,341,221
Engineering/Admin/Legal Costs: $2,835,305
Total Capital Cost: $14,176,526
BR-1 10/13/20006:06 PM
-
Bradshaw1-2.xls 10/13/2000
Bradshaw Interceptor- Sections 1, 2
-20
-15
-10
-5
0
5
10
15
20
25
0+00 10+00 20+00 30+00 40+00 50+00 60+00
Station
Elev
atio
n
120"
Bradshaw Equalization Structure
90"
Lagu
na C
reek
Franklin Blvd. Transition Structure
Influ
ent T
rans
ition
Str
uctu
re
Exis
ting
90"
Dia
. RC
P
120"
Rai
lroad
Cro
ssin
g
-
SRCSD Master Plan 2000Project Summary
Project Name: Bradshaw Interceptor Section 6A
Project ID: BR-6A 2
Location: Elk Grove-Florin and Gerber Rds to Bradshaw Rd and Elder Creek
Description of Facility: 108-inch gravity pipeline
Length: 14,875 ft.
Design Capacity: 215 mgd
Project Justification: Category A: Required for relief of Northeast and Central Interceptors
Primary Construction Method: Open Cut
Special Considerations: Railroad crossing
Base Construction Cost: $11,244,678
Special Structures: -Traffic Control: -
Environmental Mitigation: $100,000Right-of-Way: $56,406
Special Construction/Pipe Jack: $158,510Contingency: $1,733,939
Total Construction Cost $13,293,533
Engineering/Admin/Legal Costs: $3,323,383
Total Capital Cost: $16,616,916
BR-6A 10/13/20006:09 PM
-
Bradshaw 6A.xls 10/13/2000
Bradshaw Interceptor- Section 6A
10
20
30
40
50
60
70
80
336+00 356+00 376+00 396+00 416+00 436+00 456+00 476+00
Station
Elev
atio
n
108"
Ger
ber R
oad
Flor
in R
oad
Rai
lroad
Cro
ssin
g
Bra
dsha
w/C
entr
al J
unct
ion
Stru
ctur
e
-
SRCSD Master Plan 2000Project Summary
Project Name: Bradshaw Interceptor Section 6B and Jackson Connector
Project ID: BR-6B 3
Location: Bradshaw Rd and Elder Creek Rd to Jackson Hwy
Description of Facility: 84 and 108-inch gravity pipeline
Length: 11,359 ft.
Design Capacity: 205 to 215 mgd
Project Justification: Category A: Required for relief of Northeast and Central Interceptors
Primary Construction Method: Open Cut
Special Considerations: Crossing Jackson Hwy
Base Construction Cost: $10,689,142
Special Structures: $2,399,616Traffic Control: $320,674
Environmental Mitigation: $50,000Right-of-Way: $12,501
Special Construction/Pipe Jack: $162,540Contingency: $2,045,171
Total Construction Cost $15,679,644
Engineering/Admin/Legal Costs: $3,919,911
Total Capital Cost: $19,599,555
BR-6B 10/13/20006:10 PM
-
Bradshaw 6B.xls 10/13/2000
Bradshaw Interceptor- Section 6B
0
10
20
30
40
50
60
70
80
90
484+75 494+75 504+75 514+75 524+75 534+75 544+75 554+75 564+75
Station
Elev
atio
n
Bradshaw/Jackson Junction Structure
84"
Jack
son
Hig
hway
Bradshaw Section 6A
108"
Bradshaw Road
Elde
r Cre
ek R
oad
Mor
rison
Cre
ek
-
SRCSD Master Plan 2000Project Summary
Project Name: Bradshaw Interceptor Section 7
Project ID: BR-7 4
Location: Bradshaw Rd and Jackson Hwy to International Dr
Description of Facility: 72 and 84-inch gravity pipeline
Length: 26,300 ft.
Design Capacity: 93 to 110 mgd
Project Justification: Category A: Required for relief of Northeast area and Folsom Interceptor
Primary Construction Method: Open Cut
Special Considerations: Traffic control for Bradshaw Rd and Kiefer Blvd
Base Construction Cost: $19,827,197
Special Structures: $589,782Traffic Control: $594,816
Environmental Mitigation: $100,000Right-of-Way: $991,714
Special Construction/Pipe Jack: $78,100Contingency: $3,327,241
Total Construction Cost $25,508,851
Engineering/Admin/Legal Costs: $6,377,213
Total Capital Cost: $31,886,064
BR-7 10/13/20006:11 PM
-
Bradshaw 7.xls 10/13/2000
Bradshaw Interceptor- Section 7
20
30
40
50
60
70
80
90
100
110
570+00 620+00 670+00 720+00 770+00 820+00
Station
Elev
atio
n
Happy Lane
Lower Placerville Road
84"
72"
Bradshaw Road
Bradshaw/Mather Junction Structure
Keifer Boulevard
Bra
dsha
w/J
acks
on J
unct
ion
Stru
ctur
e
Old Placerville Road
-
SRCSD Master Plan 2000Project Summary
Project Name: Bradshaw Interceptor Section 8
Project ID: BR-8 5
Location: International Dr to Folsom Blvd And Citrus Rd
Description of Facility: 48 and 72-inch gravity pipeline
Length: 17,975 ft.
Design Capacity: 85 mgd
Project Justification: Category A: Required for relief of Northeast area and Folsom Interceptor
Primary Construction Method: Open Cut
Special Considerations: Traffic control for construction in International Dr, Kilgore Dr, and Folsom Blvd, Crossing Sunrise Blvd and RT tracks
Base Construction Cost: $17,296,577
Special Structures: $531,086Traffic Control: $518,897
Environmental Mitigation: $100,000Right-of-Way: $533,532
Special Construction/Pipe Jack: $150,960Contingency: $4,782,763
Total Construction Cost $23,913,815
Engineering/Admin/Legal Costs: $5,978,454
Total Capital Cost: $29,892,269
BR-8 10/13/20006:11 PM
-
Bradshaw 8.xls 10/13/2000
Bradshaw Interceptor- Section 8
60
70
80
90
100
110
120
130
140
833+00 853+00 873+00 893+00 913+00 933+00 953+00 973+00 993+00
Station
Elev
atio
n
Folsom Boulevard
72"
Folsom/Citrus West Junction Structure
48"
Folsom/Citrus East Junction Structure
Citrus Drive
Kilgore Road
International Drive
Sunr
ise
Bou
leva
rd
Rai
lroad
Cro
ssin
g
-
SRCSD Master Plan 2000Project Summary
Project Name: Sunrise Interceptor Section 1
Project ID: SR-1 6
Location: Folsom Blvd And Citrus Rd to Sunrise Blvd Bridge
Description of Facility: 48-inch gravity pipeline
Length: 8,670 ft.
Design Capacity: 23 to 25 mgd
Project Justification: Category A: Required for relief of Northeast area trunks
Primary Construction Method: Open Cut
Special Considerations: Hwy 50 crossing, Traffic control for construction in Sunrise Blvd
Base Construction Cost: $5,667,789
Special Structures: $128,961Traffic Control: $283,389
Environmental Mitigation: $100,000Right-of-Way: $628,222
Special Construction/Pipe Jack: $117,250Contingency: $1,731,403
Total Construction Cost $8,657,014
Engineering/Admin/Legal Costs: $2,164,254
Total Capital Cost: $10,821,268
SR-1 10/13/20006:12 PM
-
sunrise1 10/13/2000
Sunrise Interceptor - Section 1
50
70
90
110
130
150
170
1012+75 1022+75 1032+75 1042+75 1052+75 1062+75 1072+75 1082+75 1092+75
Station
Elev
atio
n
48"
Vortex Drop Structure
Sunrise Boulevard
Hig
hway
50
Col
oma
Roa
d
Citrus Road
Fols
om/C
itrus
Eas
t Jun
ctio
n St
ruct
ure
-
SRCSD Master Plan 2000Project Summary
Project Name: Sunrise Interceptor Section 2
Project ID: SR-2 7
Location: Sunrise Blvd Bridge to Pennsylvania Ave and Sunset Ave
Description of Facility: 36-inch gravity pipeline, 24-inch pressure pipeline
Length: 7,871 ft.
Design Capacity: 20 to 73 mgd
Project Justification: Category A: Required for relief of Northeast area trunks
Primary Construction Method: Open Cut
Special Considerations: American River Crossing, Traffic control for construction along Sunrise Blvd
Base Construction Cost: $4,166,806
Special Structures: $94,962Traffic Control: $208,340
Environmental Mitigation: $100,000Right-of-Way: $503,920
Special Construction/Pipe Jack: $880,000Contingency: $1,488,507
Total Construction Cost $7,442,536
Engineering/Admin/Legal Costs: $1,860,634
Total Capital Cost: $9,303,170
SR-2 10/13/20006:12 PM
-
sunrise2 10/13/2000
Sunrise Interceptor - Section 2
90
110
130
150
170
190
210
1099+00 1109+00 1119+00 1129+00 1139+00 1149+00 1159+00 1169+00
Station
Elev
atio
n
Pressure Manhole
Pennsylvania Avenue
36"
36"
24"
Vort
ex D
rop
Stru
ctur
e
Am
eric
an R
iver
Microtunneling
-
SRCSD Master Plan 2000Project Summary
Project Name: Folsom East Interceptor Section 1B
Project ID: FE-1B 8
Location: Folsom Blvd And Citrus Rd to Hwy 50 and Folsom South Canal
Description of Facility: 48-inch gravity pipeline
Length: 10,500 ft.
Design Capacity: 46 mgd
Project Justification: Category A: Existing Folsom Int at capacity during PWWF andrequired to provide capacity for new devel. in Folsom
Primary Construction Method: Open Cut
Special Considerations: Traffic control for construction in Folsom Blvd
Base Construction Cost: $6,151,582
Special Structures: $397,655Traffic Control: $307,579
Environmental Mitigation: $50,000Right-of-Way: $79,358
Special Construction/Pipe Jack: $39,700Contingency: $1,053,881
Total Construction Cost $8,079,756
Engineering/Admin/Legal Costs: $2,019,939
Total Capital Cost: $10,099,695
FE-1B 10/13/20006:12 PM
-
folsomeast1B 10/13/2000
Folsom East Interceptor- Sections 1B
70
80
90
100
110
120
130
140
150
0+00 20+00 40+00 60+00 80+00 100+00
Station
Elev
atio
n
48"
Folsom/Citrus EastJunction Structure
48"
Vortex Drop Structure
48"
Folsom Boulevard
-
SRCSD Master Plan 2000Project Summary
Project Name: Folsom East Interceptor Section 3
Project ID: FE-3 9
Location: Folsom Blvd and Iron Point Rd to Iron Point Rd and Oak Ave Pkwy
Description of Facility: 36 and 42-inch gravity pipeline, 16 and 24-inch force main
Length: 15,154 ft.
Design Capacity: 23 to 80 mgd
Project Justification: Category C: Required to provide service to new development in Folsom East area
Primary Construction Method: Open Cut
Special Considerations: Traffic Control for construction in Iron Point Rd
Base Construction Cost: $7,675,676
Special Structures: $203,114Traffic Control: $230,270
Environmental Mitigation: $10,000Right-of-Way: -
Special Construction/Pipe Jack: $81,840Contingency: $1,230,135
Total Construction Cost $9,431,035
Engineering/Admin/Legal Costs: $2,357,759
Total Capital Cost: $11,788,793
FE-3 10/13/20006:12 PM
-
folsomeast3 10/13/2000
Folsom East Interceptor- Section 3
150
200
250
300
350
400
0+00 20+00 40+00 60+00 80+00 100+00 120+00 140+00
Station
Elev
atio
n
42"
16" and 24" FM
36"
36"
Iron Point Road
Prai
rie C
ity R
oad
Fols
om B
oule
vard
FE
3 In
terc
epto
r Jun
ctio
n St
ruct
ure
-
SRCSD Master Plan 2000Project Summary
Project Name: Folsom East Interceptor Section 3 Pump Station
Project ID: FE-3PS 10
Location: Iron Point Rd North of Hwy 50
Description of Facility: New pump station
Length: N/A
Design Capacity: 10 mgd
Project Justification: Category C: Required to provide service to new development in Folsom East area
Primary Construction Method: Open Cut
Special Considerations:
Base Construction Cost: $3,019,782
Special Structures: -Traffic Control: $0
Environmental Mitigation: $10,000Right-of-Way: $213,542
Special Construction/Pipe Jack: -Contingency: $486,499
Total Construction Cost $3,729,822
Engineering/Admin/Legal Costs: $932,456
Total Capital Cost: $4,662,278
FE-3PS 10/13/20006:13 PM
-
SRCSD Master Plan 2000Project Summary
Project Name: Laguna Extension Interceptor Section 1
Project ID: LE-1 11
Location: SRWTP to Franklin Blvd and Dwight Rd
Description of Facility: 60 and 108-inch gravity pipeline
Length: 7,900 ft.
Design Capacity: 40 to 400 mgd
Project Justification: Category A: Required for relief of trunk sewer in Big Horn Blvd andto bring Laguna Interceptor into service
Primary Construction Method: Open Cut
Special Considerations: Tunneling under wetlands
Base Construction Cost: $4,148,222
Special Structures: $1,510,653Traffic Control: $0
Environmental Mitigation: $100,000Right-of-Way: -
Special Construction/Pipe Jack: -Contingency: $1,439,719
Total Construction Cost $7,198,594
Engineering/Admin/Legal Costs: $1,799,648
Total Capital Cost: $8,998,242
LE-1 10/13/20006:13 PM
-
Lei-1 10/13/2000
Laguna Extension Interceptor- Section 1
-20
-15
-10
-5
0
5
10
15
20
25
-5+00 5+00 15+00 25+00 35+00 45+00 55+00 65+00 75+00
Station
Elev
atio
n
60"
Con
nect
to E
xist
ing
Bra
dsha
wEq
ualiz
atio
n St
ruct
ure
Con
nect
to E
xist
ing
60"
in F
rank
lin B
lvd
at M
H 1
19-0
13-0
10
108"
54" South Interceptor
102" Laguna Creek Interceptor
Tunnel
Laguna Extension Junction Structure
-
SRCSD Master Plan 2000Project Summary
Project Name: North Natomas Interceptor Section 1
Project ID: NN-1 12
Location: Del Paso Rd at Arco Arena to South of Elkhorn Blvd
Description of Facility: 36 and 42-inch gravity pipeline
Length: 6,700 ft.
Design Capacity: 13 to 22 mgd
Project Justification: Category C: Required for new development in North Natomas andMetro Air Park areas
Primary Construction Method: Open Cut
Special Considerations:
Base Construction Cost: $2,366,692
Special Structures: -Traffic Control: -
Environmental Mitigation: -Right-of-Way: -
Special Construction/Pipe Jack: -Contingency: $355,004
Total Construction Cost $2,721,696
Engineering/Admin/Legal Costs: $680,424
Total Capital Cost: $3,402,120
NN-1 10/13/20006:13 PM
-
Nni-1 10/13/2000
North Natomas Interceptor- Section 1
-15
-10
-5
0
5
10
15
20
25
0+00 10+00 20+00 30+00 40+00 50+00 60+00
Station
Elev
atio
n
42"
36"
Tunnel Construction
-
SRCSD Master Plan 2000Project Summary
Project Name: Arden Pump Station Improvements
Project ID: ARPS 13
Location: Arden Pump Station Site, Howe Ave and Enterprise Dr
Description of Facility: Upgrade of existing Arden Pump Station
Length: N/A
Design Capacity: 100 mgd +/- to be determined
Project Justification: Category A: Existing PWWF exceeds firm capacity of pump station
Primary Construction Method:
Special Considerations: Specific improvements to be determined, $5,000,000is a budgetary placeholder.
Base Construction Cost: $5,000,000
Special Structures: -Traffic Control: -
Environmental Mitigation: -Right-of-Way: -
Special Construction/Pipe Jack: -Contingency: $750,000
Total Construction Cost $5,750,000
Engineering/Admin/Legal Costs: $1,437,500
Total Capital Cost: $7,187,500
ARPS 10/13/20006:14 PM
-
SRCSD Master Plan 2000Project Summary
Project Name: Rancho Cordova Pump Station Improvements
Project ID: RCPS 14
Location: Cordova Pump Station Site, Chase Dr
Description of Facility: Upgrade of existing pump station / construct new PS in future
Length: N/A
Design Capacity: 15 mgd
Project Justification: Category A/B: Pump station does not have sufficient firm capacityfor existing flows nor ultimate development of the area
Primary Construction Method:
Special Considerations: Project contains Phase 1 (pump station upgrade) andPhase 2 (construction of new pump station in future)
Base Construction Cost: $5,985,091
Special Structures: -Traffic Control: -
Environmental Mitigation: -Right-of-Way: -
Special Construction/Pipe Jack: -Contingency: $1,496,273
Total Construction Cost $7,481,364
Engineering/Admin/Legal Costs: $1,870,341
Total Capital Cost: $9,351,705
RCPS 1/4/200110:34 AM
-
SRCSD Master Plan 2000Project Summary
Project Name: Upper Northwest Interceptor Section 1
Project ID: UNW-1 15
Location: Natomas Pump Station to Del Paso Blvd
Description of Facility: 84 and 96-inch gravity pipeline
Length: 10,400 ft.
Design Capacity: 133 to 150 mgd
Project Justification: Category C: Required for future devel. in North Natomas and Rio Linda and relief of Northeast trunks and Dry Creek Int
Primary Construction Method: Tunneled
Special Considerations: Poor soil conditions and high ground water
Base Construction Cost: $20,232,000
Special Structures: -Traffic Control: $0
Environmental Mitigation: $50,000Right-of-Way: $31,003
Special Construction/Pipe Jack: -Contingency: $3,046,950
Total Construction Cost $23,359,953
Engineering/Admin/Legal Costs: $5,839,988
Total Capital Cost: $29,199,941
UNW-1 10/13/20006:14 PM
-
Unwi-1 10/13/2000
Upper Northwest Interceptor- Section 1
-35
-25
-15
-5
5
15
25
10+00 30+00 50+00 70+00 90+00 110+00
Station
Elev
atio
n
84"
96"
East Drainage Canal
Nat
omas
Pum
p St
atio
n
C1
Can
al
Del
Pas
o B
oule
vard
Tunnel Construction
-
SRCSD Master Plan 2000Project Summary
Project Name: Upper Northwest Interceptor Section 2
Project ID: UNW-2 16
Location: Del Paso Blvd To Elkhorn Blvd
Description of Facility: 84-inch gravity pipeline
Length: 10,652 ft.
Design Capacity: 133 mgd
Project Justification: Category C: Required for future devel. in North Natomas and Rio Linda and relief of Northeast trunks and Dry Creek Int
Primary Construction Method: Tunneled
Special Considerations: Poor soil conditions and high ground water
Base Construction Cost: $18,203,242
Special Structures: -Traffic Control: -
Environmental Mitigation: $50,000Right-of-Way: $25,565
Special Construction/Pipe Jack: -Contingency: $2,741,821
Total Construction Cost $21,020,628
Engineering/Admin/Legal Costs: $5,255,157
Total Capital Cost: $26,275,785
UNW-2 10/13/20006:15 PM
-
Unwi-2 10/13/2000
Upper Northwest Interceptor- Section 2
-35
-25
-15
-5
5
15
25
114+00 134+00 154+00 174+00 194+00 214+00
Station
Elev
atio
n
84"
84"
East Drainage Canal
Elkh
orn
Bou
leva
rd
Tunnel Construction
-
SRCSD Master Plan 2000Project Summary
Project Name: Upper Northwest Interceptor Section 3
Project ID: UNW-3 17
Location: Elkhorn Blvd to Natomas East Main Drain
Description of Facility: 84-inch gravity pipeline
Length: 6,129 ft.
Design Capacity: 133 mgd
Project Justification: Category C: Required for future devel. in North Natomas and Rio Linda and relief of Northeast trunks and Dry Creek Int
Primary Construction Method: Open Cut
Special Considerations:
Base Construction Cost: $5,211,230
Special Structures: $758,292Traffic Control: $52,112
Environmental Mitigation: -Right-of-Way: $2,648
Special Construction/Pipe Jack: -Contingency: $903,642
Total Construction Cost $6,927,924
Engineering/Admin/Legal Costs: $1,731,981
Total Capital Cost: $8,659,905
UNW-3 10/13/20006:15 PM
-
Unwi-3 10/13/2000
Upper Northwest Interceptor- Section 3
-15
-5
5
15
25
35
45
220+50 230+50 240+50 250+50 260+50 270+50 280+50
Station
Elev
atio
n
84"84"
Elkhorn Boulevard
-
SRCSD Master Plan 2000Project Summary
Project Name: Upper Northwest Interceptor Section 4
Project ID: UNW-4 18
Location: Elkhorn Blvd and NEMDC to Elkhorn Blvd and Cherry Ln
Description of Facility: 66 and 84-inch gravity pipeline
Length: 11,084 ft.
Design Capacity: 98 to 133 mgd
Project Justification: Category C: Required for future devel. in North Natomas and Rio Linda and relief of Northeast trunks and Dry Creek Int
Primary Construction Method: Open Cut
Special Considerations: Railroad crossing and traffic control along Elkhorn Blvd
Base Construction Cost: $8,326,717
Special Structures: $572,158Traffic Control: $249,802
Environmental Mitigation: $50,000Right-of-Way: $554,622
Special Construction/Pipe Jack: $304,780Contingency: $1,508,712
Total Construction Cost $11,566,790
Engineering/Admin/Legal Costs: $2,891,697
Total Capital Cost: $14,458,487
UNW-4 10/13/20006:15 PM
-
Unwi-4 10/13/2000
Upper Northwest Interceptor- Section 4
-10
0
10
20
30
40
50
60
70
281+80 301+80 321+80 341+80 361+80 381+80
Station
Elev
atio
n
66"
Dry CreekJunction Structure
Elkhorn Boulevard
Dry
Cre
ek
Nat
omas
Eas
t Mai
n D
rain
age
Can
al
84"
54" Rio Linda Interceptor
27" Dry Creek Interceptor
Rio
Lin
da B
oule
vard
Rai
lroad
Cro
ssin
g
Junction Structure
-
SRCSD Master Plan 2000Project Summary
Project Name: Upper Northwest Interceptor Section 5
Project ID: UNW-5 19
Location: Elkhorn Blvd and Cherry Ln to Elkhorn Blvd and Watt Ave
Description of Facility: 54 and 66-inch gravity pipeline
Length: 19,385 ft.
Design Capacity: 69 to 81 mgd
Project Justification: Category A: Required for relief of Northeast area
Primary Construction Method: Open Cut
Special Considerations: Traffic control along Elkhorn Blvd, Watt Ave crossing
Base Construction Cost: $13,610,919
Special Structures: $770,299Traffic Control: $680,546
Environmental Mitigation: -Right-of-Way: $160,272
Special Construction/Pipe Jack: $260,480Contingency: $2,322,377
Total Construction Cost $17,804,893
Engineering/Admin/Legal Costs: $4,451,223
Total Capital Cost: $22,256,116
UNW-5 10/13/20006:15 PM
-
Unwi-5 10/13/2000
Upper Northwest Interceptor- Section 5
10
20
30
40
50
60
70
80
90
100
390+00 410+00 430+00 450+00 470+00 490+00 510+00 530+00 550+00 570+00
Station
Elev
atio
n
66"
Dry Creek ReliefJunction Structure
Elkhorn Boulevard
28th
Str
eet
Dry
Cre
ek
Junction Structure
54"
Junction Structure
Wat
t Ave
nue
Dry
Cre
ek R
oad
42" Dry Creek Relief
-
SRCSD Master Plan 2000Project Summary
Project Name: Upper Northwest Section 6
Project ID: UNW-6 20
Location: Elkhorn Blvd and Watt Ave to Elkhorn Blvd and Don Julio Blvd
Description of Facility: 48-inch gravity pipeline
Length: 9,370 ft.
Design Capacity: 59 to 62 mgd
Project Justification: Category A: Required for relief of Northeast area
Primary Construction Method: Open Cut
Special Considerations: Traffic control along Elkhorn Blvd, Don Julio Blvd crossing,
Base Construction Cost: $5,071,110
Special Structures: $399,780Traffic Control: $253,556
Environmental Mitigation: -Right-of-Way: -
Special Construction/Pipe Jack: $42,840Contingency: $865,093
Total Construction Cost $6,632,378
Engineering/Admin/Legal Costs: $1,658,095
Total Capital Cost: $8,290,473
UNW-6 10/13/20006:16 PM
-
Unwi-6 10/13/2000
Upper Northwest Interceptor- Section 6
50
70
90
110
130
150
586+50 596+50 606+50 616+50 626+50 636+50 646+50 656+50 666+50 676+50
Station
Elev
atio
n
48"
Vortex Drop Structure
Elkhorn Boulevard
Wal
erga
Roa
d
48"
Don
Jul
io
Ave
nue
Don Julio TransitionStructure
-
SRCSD Master Plan 2000Project Summary
Project Name: Dry Creek Relief
Project ID: DRR-1 21
Location: 28th St and Elkhorn Blvd to 28th St and Scotland Dr
Description of Facility: 42-inch gravity pipeline
Length: 8,703 ft.
Design Capacity: 24 to 28 mgd
Project Justification: Category A: Required for relief of Dry Creek Interceptor
Primary Construction Method: Open Cut
Special Considerations:
Base Construction Cost: $4,210,244
Special Structures: $197,472Traffic Control: $126,307
Environmental Mitigation: -Right-of-Way: -
Special Construction/Pipe Jack: -Contingency: $1,133,506
Total Construction Cost $5,667,529
Engineering/Admin/Legal Costs: $1,416,882
Total Capital Cost: $7,084,412
DRR-1 10/13/20006:16 PM
-
DRR.xls 10/13/2000
Dry Creek Relief
40
50
60
70
80
90
100
110
0+00 10+00 20+00 30+00 40+00 50+00 60+00 70+00 80+00
Station
Elev
atio
n
42"
28th Street
Dry Creek Relief Junction Structure
42"
Dry
Cre
ek M
H 2
0300
918
-
SRCSD Master Plan 2000Project Summary
Project Name: Upper Northwest Section 7
Project ID: UNW-7 22
Location: Elkhorn Blvd and Don Julio Blvd to Van Maren Pump Station
Description of Facility: 36-inch force main
Length: 16,040 ft.
Design Capacity: 45 mgd
Project Justification: Category A: Required for relief of Northeast area
Primary Construction Method: Open Cut
Special Considerations: Probable dual force main, Crossing Railroad, Roseville Rd, and I-80Traffic control along Elkhorn Blvd, Greenback Ln, and Auburn Blvd
Base Construction Cost: $6,440,714
Special Structures: $139,278Traffic Control: $322,036
Environmental Mitigation: $20,000Right-of-Way: $1,368,330
Special Construction/Pipe Jack: $488,070Contingency: $1,316,764
Total Construction Cost $10,095,191
Engineering/Admin/Legal Costs: $2,523,798
Total Capital Cost: $12,618,989
UNW-7 10/13/20006:16 PM
-
Unwi-71 10/13/2000
Upper Northwest Interceptor- Section 7
110
120
130
140
150
160
170
680+20 682+20 684+20 686+20 688+20 690+20 692+20 694+20 696+20 698+20
Station
Elev
atio
n
36" FM
Elkhorn Boulevard
Ros
evill
e R
oad
36" FM
Hill
sdal
e B
oule
vard
Bore & JackR
ailro
ad C
ross
ing
Don
Jul
io T
rans
ition
Str
uctu
re
-
Unwi-72 10/13/2000
Upper Northwest Interceptor- Section 7
110
120
130
140
150
160
170
700+00 702+00 704+00 706+00 708+00 710+00 712+00 714+00
Station
Elev
atio
n
36" FM
Elkhorn Boulevard
36" FM
And
rea
Bou
leva
rd
Util
ity C
ross
ings
-
Unwi-73 10/13/2000
Upper Northwest Interceptor- Section 7
80
90
100
110
120
130
140
150
160
715+00 717+00 719+00 721+00 723+00 725+00 727+00 729+00
Station
Elev
atio
n
36" FM
Elkhorn Boulevard
36" FM
Diablo Drive
OlympicWay
Util
ity C
ross
ings
-
Unwi-74 10/13/2000
Upper Northwest Interceptor- Section 7
80
90
100
110
120
130
140
150
160
730+00 732+00 734+00 736+00 738+00 740+00 742+00 744+00
Station
Elev
atio
n
36" FM
36" FM
I-80 FreewayOlympicWayVerner Avenue
Bore & Jack
-
Unwi-75 10/13/2000
Upper Northwest Interceptor- Section 7
80
90
100
110
120
130
140
150
745+00 747+00 749+00 751+00 753+00 755+00 757+00 759+00
Station
Elev
atio
n
36" FM
36" FM
Greenback LaneVerner Avenue
Low
ered
for
Util
ity C
ross
ings
-
Unwi-76 10/13/2000
Upper Northwest Interceptor- Section 7
70
80
90
100
110
120
130
140
760+00 762+00 764+00 766+00 768+00 770+00 772+00 774+00
Station
Elev
atio
n
36" FM
36" FM
Greenback Lane
3- 2
0'x1
2' B
ox C
ulve
rts
-
Unwi-77 10/13/2000
Upper Northwest Interceptor- Section 7
80
90
100
110
120
130
140
775+50 780+50 785+50 790+50 795+50 800+50
Station
Elev
atio
n
36" FM
36" FM
Greenback Lane Auburn Boulevard
-
Unwi-78 10/13/2000
Upper Northwest Interceptor- Section 7
80
90
100
110
120
130
140
805+00 807+00 809+00 811+00 813+00 815+00 817+00 819+00 821+00 823+00 825+00
Station
Elev
atio
n
36" FM
36" FM
Auburn Boulevard Halifax Street
Box
Cul
vert
Stre
am C
ross
ing
-
Unwi-79 10/13/2000
Upper Northwest Interceptor- Section 7
90
100
110
120
130
140
825+00 827+00 829+00 831+00 833+00 835+00 837+00 839+00
Station
Elev
atio
n
36" FM
36" FM
Halifax Street Westbrook Drive
FM lowered to avoid conflicts
-
SRCSD Master Plan 2000Project Summary
Project Name: Van Maren Pump Station
Project ID: UNW-8 23
Location: West of Van Maren Dr and Auburn Blvd
Description of Facility: New pump station
Length: N/A
Design Capacity: 45 mgd
Project Justification: Category A: Required for relief of Northeast area
Primary Construction Method: Open Cut
Special Considerations:
Base Construction Cost: $9,291,636
Special Structures: -Traffic Control: -
Environmental Mitigation: $20,000Right-of-Way: $374,400
Special Construction/Pipe Jack: -Contingency: $1,452,905
Total Construction Cost $11,138,942
Engineering/Admin/Legal Costs: $2,784,735
Total Capital Cost: $13,923,677
UNW-8 10/13/20006:17 PM
-
SRCSD Master Plan 2000Project Summary
Project Name: Upper Northwest Interceptor Section 9
Project ID: UNW-9 24
Location: Van Maren Pump Station to Old Auburn Rd and Fair Oaks Blvd
Description of Facility: 36-inch gravity pipeline
Length: 13,185 ft.
Design Capacity: 12 to 34 mgd
Project Justification: Category A: Required to relieve future capacity deficincies inNortheast trunk system
Primary Construction Method: Open Cut
Special Considerations: Traffic control along Auburn Blvd, Sunrise Blvd crossing
Base Construction Cost: $8,682,128
Special Structures: -Traffic Control: $434,106
Environmental Mitigation: $50,000Right-of-Way: $691,417
Special Construction/Pipe Jack: $24,640Contingency: $1,482,344
Total Construction Cost $11,364,635
Engineering/Admin/Legal Costs: $2,841,159
Total Capital Cost: $14,205,793
UNW-9 10/13/20006:17 PM
-
Unwi-9 10/13/2000
Upper Northwest Interceptor- Section 9
90
110
130
150
170
190
210
840+61 860+61 880+61 900+61 920+61 940+61 960+61 980+61 1000+61
Station
Elev
atio
n
36"
Auburn Boulevard
Aub
urn
Bou
leva
rd
Van
Mar
en L
ane
36"
Old Auburn Road
36"
-
SRCSD Master Plan 2000Project Summary
Project Name: Lower Northwest Interceptor Section 1
Project ID: LNW-1 25
Location: SRWTP to West of Sacramento River
Description of Facility: 96-inch force main
Length: 17,917 ft.
Design Capacity: 275 mgd
Project Justification: Category B: Required for relief of Northeast area and futureNorth Natomas and West Sacramento development
Primary Construction Method: Open Cut
Special Considerations: Crossing Interstate 5, Highway 160, Southern Pacific Railroad,and Sacramento River
Base Construction Cost: $15,443,727
Special Structures: -Traffic Control: -
Environmental Mitigation: $200,000Right-of-Way: $481,517
Special Construction/Pipe Jack: $1,472,580Contingency: $4,399,456
Total Construction Cost $21,997,279
Engineering/Admin/Legal Costs: $5,499,320
Total Capital Cost: $27,496,599
LNW-1 10/13/20006:17 PM
-
Lnwi-1 10/13/2000
Lower Northwest Interceptor- Section 1
-40
-30
-20
-10
0
10
20
30
40
0+00 20+00 40+00 60+00 80+00 100+00 120+00 140+00 160+00
Station
Elev
atio
n
96" FM
Mor
rison
Cre
ek
2-72" FM
Southport Regional Pump Station
SRWTP Influent Junction Structure
96" FM
Sacr
amen
to R
iver
Lagu
na C
reek
96"FM
Hw
y 16
0
Inte
rsta
te 5
Rai
lroad
Cro
ssin
g
-
SRCSD Master Plan 2000Project Summary
Project Name: Southport Regional Pump Station
Project ID: SRPS 26
Location: West of Sacramento River, Northwest of SRWTP
Description of Facility: New pump station
Length: N/A
Design Capacity: 250 mgd
Project Justification: Category B: Required for relief of Northeast area and futureNorth Natomas and West Sacramento development
Primary Construction Method:
Special Considerations: Facility is anticipated to be constructed in phasesPhase 1: 100 mgd Phases 2 & 3: additional 75 mgd each
Base Construction Cost: $21,000,000
Special Structures: -Traffic Control: -
Environmental Mitigation: -Right-of-Way: $150,000
Special Construction/Pipe Jack: -Contingency: $5,287,500
Total Construction Cost $26,437,500
Engineering/Admin/Legal Costs: $6,609,375
Total Capital Cost: $33,046,875
SRPS 10/13/20006:17 PM
-
SRCSD Master Plan 2000Project Summary
Project Name: Lower Northwest Interceptor Section 2
Project ID: LNW-2 27
Location: West of Sacramento River to South of Linden Rd
Description of Facility: 120-inch gravity pipeline
Length: 41,602 ft.
Design Capacity: 262 mgd
Project Justification: Category B: Required for relief of Northeast area and futureNorth Natomas and West Sacramento development
Primary Construction Method: Open Cut
Special Considerations: Crossing Willow Point Babel Slough
Base Construction Cost: $48,189,778
Special Structures: $1,354,092Traffic Control: $481,898
Environmental Mitigation: $150,000Right-of-Way: $2,235,807
Special Construction/Pipe Jack: $1,357,650Contingency: $13,442,306
Total Construction Cost $67,211,531
Engineering/Admin/Legal Costs: $16,802,883
Total Capital Cost: $84,014,414
LNW-2 10/13/20006:18 PM
-
Lnwi-2 10/13/2000
Lower Northwest Interceptor- Section 2
-40
-30
-20
-10
0
10
20
30
40
225+00 275+00 325+00 375+00 425+00 475+00 525+00 575+00Station
Elev
atio
n
120"
Riv
er R
oad
120"
Will
ow P
oint
Bab
el S
loug
h
Transition Structure
Sout
hpor
t Reg
iona
l Pum
p St
atio
n
-
SRCSD Master Plan 2000Project Summary
Project Name: West Sacramento Collection System Modifications
Project ID: WSCSM 28
Location: Throughout West Sacramento Collection System
Description of Facility: Necessary modifications of collection system to connect to LNWI
Length: Varies
Design Capacity: Varies
Project Justification: Category C: Needed to serve West Sacramento
Primary Construction Method: Varies
Special Considerations: Cost estimate to be refined by Lower Northwest Design Report
Base Construction Cost: $1,282,746
Special Structures: -Traffic Control: -
Environmental Mitigation: -Right-of-Way: -
Special Construction/Pipe Jack: -Contingency: $320,687
Total Construction Cost $1,603,433
Engineering/Admin/Legal Costs: $400,858
Total Capital Cost: $2,004,291
WSCSM 10/13/20006:18 PM
-
SRCSD Master Plan 2000Project Summary
Project Name: Lower Northwest Interceptor Section 3
Project ID: LNW-3 29
Location: South of Linden Rd to Natomas Pump Station
Description of Facility: 60 and 84-inch force main
Length: 43,467 ft.
Design Capacity: 200 mgd
Project Justification: Category B: Required for relief of Northeast area and futureNorth Natomas development
Primary Construction Method: Open Cut
Special Considerations: Crossing of Sacramento River, I-80, Business 80, Hwy 84, Garden Highway, and West Capitol Ave
Base Construction Cost: $37,650,335
Special Structures: -Traffic Control: $1,129,510
Environmental Mitigation: $200,000Right-of-Way: $5,290,713
Special Construction/Pipe Jack: $3,773,930Contingency: $12,011,122
Total Construction Cost $60,055,610
Engineering/Admin/Legal Costs: $15,013,902
Total Capital Cost: $75,069,512
LNW-3 10/13/20006:18 PM
-
LNWI-3a 10/13/2000
Lower Northwest Interceptor- Section 3a
-30
-20
-10
0
10
20
30
40
595+19 645+19 695+19 745+19 795+19Station
Elev
atio
n
84" FM
Lind
en R
oad
84" FM
Jeffe
rson
Bou
leva
rd
Bar
ge C
anal H
ighw
ay 8
4
Bus
ines
s 80
Wes
t Cap
itol A
venu
e
-
LNWI-3b 10/13/2000
Lower Northwest Interceptor- Section 3b
-30
-20
-10
0
10
20
30
40
814+94 864+94 914+94 964+94 1014+94Station
Elev
atio
n
84" FM
Nat
omas
Pum
p St
atio
n
84" FM
Sacr
amen
to R
iver
Wes
t Dra
inag
e C
anal
2-60" FM
Inte
rsta
te 8
0
Gar
den
Hig
hway
-
SRCSD Master Plan 2000Project Summary
Project Name: Natomas Pump Station Expansion
Project ID: NNPS 30
Location: Natomas Pump Station Site
Description of Facility: 175 mgd Pump Station
Length: N/A
Design Capacity: 175 mgd
Project Justification: Category B: Required for relief of Northeast area and futureNorth Natomas development
Primary Construction Method:
Special Considerations: Facility is anticipated to be constructed in phasesPhase 1: 100 mgd Phase 2: additional 75 mgd
Base Construction Cost: $13,500,000
Special Structures: -Traffic Control: -
Environmental Mitigation: -Right-of-Way: -
Special Construction/Pipe Jack: -Contingency: $3,375,000
Total Construction Cost $16,875,000
Engineering/Admin/Legal Costs: $4,218,750
Total Capital Cost: $21,093,750
NNPS 10/13/20006:21 PM
-
SRCSD Master Plan 2000Project Summary
Project Name: South Interceptor Section 1
Project ID: SO-1 31
Location: SRWTP to Laguna Blvd
Description of Facility: 54-inch gravity pipeline
Length: 8,886 ft.
Design Capacity: 43 mgd
Project Justification: Category C: Capacity required to serve new development in the south area
Primary Construction Method: Open Cut
Special Considerations: Crossing Laguna Blvd and Railroad
Base Construction Cost: $3,670,898
Special Structures: -Traffic Control: -
Environmental Mitigation: $200,000Right-of-Way: $1,602,374
Special Construction/Pipe Jack: $69,800Contingency: $1,385,768
Total Construction Cost $6,928,840
Engineering/Admin/Legal Costs: $1,732,210
Total Capital Cost: $8,661,050
SO-1 10/13/20006:21 PM
-
sintusb1.xls 10/13/2000
South Interceptor- Section 1
-20
-10
0
10
20
30
40
0+00 10+00 20+00 30+00 40+00 50+00 60+00 70+00 80+00
Station
Elev
atio
n
54"
Southern Pacific Railroad
Lagu
na B
lvd
Lagu
na E
xten
sion
Junc
tion
Stru
ctur
e
-
SRCSD Master Plan 2000Project Summary
Project Name: South Interceptor Section 2 and South Interceptor Pump Station
Project ID: SO-2 32
Location: Laguna Blvd to Franklin Blvd South of Elk Grove Blvd
Description of Facility: 54-inch gravity pipeline, 36-inch force main
Length: 8,032 ft.
Design Capacity: 43 mgd
Project Justification: Category C: Capacity required to serve new development in the south area
Primary Construction Method: Open Cut
Special Considerations: Crossing Elk Grove Blvd and Railroad
Base Construction Cost: $10,445,371
Special Structures: -Traffic Control: -
Environmental Mitigation: $50,000Right-of-Way: $3,066,489
Special Construction/Pipe Jack: $108,400Contingency: $3,417,565
Total Construction Cost $17,087,825
Engineering/Admin/Legal Costs: $4,271,956
Total Capital Cost: $21,359,781
SO-2 10/13/20006:22 PM
-
sintusb2 10/13/2000
South Interceptor- Section 2
-10
-5
0
5
10
15
20
25
30
35
40
88+90 98+90 108+90 118+90 128+90 138+90 148+90 158+90 168+90
Station
Elev
atio
n
36" FM54"
Elk G
rove
Bou
leva
rd
Southern Pacific Railroad
-
SRCSD Master Plan 2000Project Summary
Project Name: South Interceptor Section 3
Project ID: SO-3 33
Location: Bruceville Rd to Franklin Blvd South of Elk Grove Blvd
Description of Facility: 36, 48, and 54-inch gravity pipeline
Length: 20,168 ft.
Design Capacity: 13 to 31 mgd
Project Justification: Category C: Capacity required to serve new development in the south area
Primary Construction Method: Open Cut
Special Considerations: Traffic control for construction in Franklin BlvdCrossing Bruceville Rd
Base Construction Cost: $8,984,360
Special Structures: -Traffic Control: $89,844
Environmental Mitigation: -Right-of-Way: $2,621,576
Special Construction/Pipe Jack: -Contingency: $2,923,945
Total Construction Cost $14,619,725
Engineering/Admin/Legal Costs: $3,654,931
Total Capital Cost: $18,274,656
SO-3 10/13/20006:22 PM
-
sintusb3 10/13/2000
South Interceptor- Section 3
-20
-10
0
10
20
30
40
169+00 219+00 269+00 319+00 369+00
Station
Elev
atio
n
54"
39"
48"
Bru
cevi
lle R
oad
Franklin Blvd
-
SRCSD Master Plan 2000Project Summary
Project Name: Laguna Creek Interceptor Section 1
Project ID: LC-1 34
Location: SRWTP to Big Horn Blvd
Description of Facility: 102-inch gravity pipeline
Length: 13,297 ft.
Design Capacity: 183 mgd
Project Justification: Category C: Required for future service to east county area
Primary Construction Method: Open Cut
Special Considerations: Wetlands mitigation for construction in Laguna Creek, CrossingFranklin Blvd and Bruceville Rd, Tunnel under wetlands at SRWTP
Base Construction Cost: $12,086,807
Special Structures: $533,636Traffic Control: $120,868
Environmental Mitigation: $400,000Right-of-Way: $2,108,732
Special Construction/Pipe Jack: $647,900Contingency: $3,974,485
Total Construction Cost $19,872,427
Engineering/Admin/Legal Costs: $4,968,107
Total Capital Cost: $24,840,534
LC-1 10/13/20006:22 PM
-
Lci-1 10/13/2000
Laguna Creek Interceptor- Section 1
-30
-20
-10
0
10
20
30
40
50
0+00 20+00 40+00 60+00 80+00 100+00 120+00
Station
Elev
atio
n
102"
102"
Lagu
na E
xten
sion
Jun
ctio
n St
ruct
ure
Fran
klin
Bou
leva
rd
Bru
cevi
lle R
oad
42" Elk Grove Trunk
Elk Grove Trunk Bypass
-
SRCSD Master Plan 2000Project Summary
Project Name: Laguna Creek Interceptor Section 2
Project ID: LC-2 35
Location: Bruceville Rd North of Big Horn Blvd to Waterman Rd North of Bond Rd
Description of Facility: 96 and 106-inch gravity pipeline
Length: 20,092 ft.
Design Capacity: 170 to 183 mgd
Project Justification: Category C: Required for future service to east county area
Primary Construction Method: Open Cut
Special Considerations: Wetlands mitigation for construction in Laguna Creek, Tunneling underWaterman Ridge, Crossing Hwy 99, Elk Grove Florin Rd, Railroad
Base Construction Cost: $20,131,699
Special Structures: $1,225,522Traffic Control: $201,317
Environmental Mitigation: $400,000Right-of-Way: $4,411,690
Special Construction/Pipe Jack: $2,236,000Contingency: $7,151,557
Total Construction Cost $35,757,785
Engineering/Admin/Legal Costs: $8,939,446
Total Capital Cost: $44,697,232
LC-2 10/13/20006:23 PM
-
Lci-2 10/13/2000
Laguna Creek Interceptor- Section 2
-10
0
10
20
30
40
50
60
70
132+97 182+97 232+97 282+97 332+97
Station
Elev
atio
n
102"
96"H
ighw
ay 9
9
Stoc
kton
Bou
leva
rd
Elk
Gro
ve- F
lorin
Roa
d
Waterman Ridge
Wat
erm
an R
oad
Rai
lroad
Cro
ssin
g
Dee
r Cre
ek J
unct
ion
Stru
ctur
e
-
SRCSD Master Plan 2000Project Summary
Project Name: Laguna Creek Interceptor Section 3
Project ID: LC-3 36
Location: Waterman Rd North of Bond Rd to Excelsior Rd South of Gerber Rd
Description of Facility: 72, 78, and 84-inch gravity pipeline
Length: 26,421 ft.
Design Capacity: 131 to 149 mgd
Project Justification: Category C: Required for future sevice to east county area
Primary Construction Method: Open Cut
Special Considerations: Wetlands mitigation for construction in Laguna Creek, RR Crossing,Traffic control for construction in Bradshaw Rd and Excelsior Rd
Base Construction Cost: $18,310,104
Special Structures: -Traffic Control: $183,101
Environmental Mitigation: $200,000Right-of-Way: $4,234,762
Special Construction/Pipe Jack: $140,250Contingency: $5,767,054
Total Construction Cost $28,835,271
Engineering/Admin/Legal Costs: $7,208,818
Total Capital Cost: $36,044,089
LC-3 10/13/20006:23 PM
-
Lci-3 10/13/2000
Laguna Creek Interceptor- Section 3
0
10
20
30
40
50
60
70
80
90
333+89 383+89 433+89 483+89 533+89 583+89
Station
Elev
atio
n
72"
84"
Shel
don
Roa
d
Cal
vine
Roa
d
Bra
dsha
w R
oad
Exce
lsio
r Roa
d
78"
15" TrunkInv=33.81
Rai
lroad
Cro
ssin
g
Dee
r Cre
ek J
unct
ion
Stru
ctur
e
-
SRCSD Master Plan 2000Project Summary
Project Name: Laguna Creek Interceptor Section 4
Project ID: LC-4 37
Location: Excelsior Rd South of Gerber Rd to Sunrise Blvd South of Jackson Hwy
Description of Facility: 66, 72, 78-inch gravity pipeline
Length: 22,297 ft.
Design Capacity: 97 to 143 mgd
Project Justification: Category C: Required for future service to east county area
Primary Construction Method: Open Cut
Special Considerations: Wetlands mitigation for construction in Laguna CreekCrossing Folsom South Canal and Florin Rd
Base Construction Cost: $12,941,595
Special Structures: -Traffic Control: -
Environmental Mitigation: $100,000Right-of-Way: $77,538
Special Construction/Pipe Jack: -Contingency: $3,279,783
Total Construction Cost $16,398,916
Engineering/Admin/Legal Costs: $4,099,729
Total Capital Cost: $20,498,645
LC-4 10/13/20006:23 PM
-
Lci-4 10/13/2000
Laguna Creek Interceptor- Section 4
40
50
60
70
80
90
100
110
120
130
140
598+09 648+09 698+09 748+09 798+09Station
Elev
atio
n
78"
72"
Fols
om S
outh
Can
al
66"
Eagl
e's
Nes
t R
oad
Flor
in R
oad
66"
-
SRCSD Master Plan 2000Project Summary
Project Name: Laguna Creek Interceptor Section 5
Project ID: LC-5 38
Location: Sunrise Blvd South of Jackson Hwy to end of pipe East of Sunrise Blvd
Description of Facility: 66-inch gravity pipeline
Length: 6,208 ft.
Design Capacity: 97 to 102 mgd
Project Justification: Category C: Required for future service to east county area
Primary Construction Method: Open Cut
Special Considerations: Wetlands mitigation for constuction in Laguna CreekCrossing Jackson Hwy and Sunrise Blvd
Base Construction Cost: $2,847,151
Special Structures: -Traffic Control: -
Environmental Mitigation: $100,000Right-of-Way: $18,605
Special Construction/Pipe Jack: $510,600Contingency: $869,089
Total Construction Cost $4,345,444
Engineering/Admin/Legal Costs: $1,086,361
Total Capital Cost: $5,431,805
LC-5 10/13/20006:23 PM
-
Lci-5 10/13/2000
Laguna Creek Interceptor- Section 5
80
90
100
110
120
130
140
821+06 831+06 841+06 851+06 861+06 871+06 881+06
Station
Elev
atio
n
Lagu
na C
reek
66"
Hw
y 16
Sunr
ise
Bou
leva
rd
Aer
ojet
Inte
rcep
tor S
ectio
n 4
(Dro
p St
ruct
ure)
-
SRCSD Master Plan 2000Project Summary
Project Name: Deer Creek Interceptor Section 1
Project ID: DC-1 39
Location: Waterman Rd North of Bond Rd to Wilton Rd and Deer Creek
Description of Facility: 60-inch gravity pipeline
Length: 23,167 ft.
Design Capacity: 43 to 48 mgd
Project Justification: Category C: Required for future service to southeast county
Primary Construction Method: Open Cut
Special Considerations: Traffic control for construction in Bond Rd, Grant Line Rd, andWilton Rd
Base Construction Cost: $15,100,484
Special Structures: -Traffic Control: $453,015
Environmental Mitigation: $50,000Right-of-Way: $674,135
Special Construction/Pipe Jack: -Contingency: $4,069,408
Total Construction Cost $20,347,041
Engineering/Admin/Legal Costs: $5,086,760
Total Capital Cost: $25,433,802
DC-1 10/13/20006:24 PM
-
Dci-1