VOLUME II - Regional SanSO-2 Laguna Blvd. to Franklin Blvd. $21,360,000 SO-3 Franklin Blvd. to East...

177

Transcript of VOLUME II - Regional SanSO-2 Laguna Blvd. to Franklin Blvd. $21,360,000 SO-3 Franklin Blvd. to East...

  • VOLUME IIChapter 9- Recommended Capital Improvement Program............................................... 9-19.1 Recommended Capital Expenditures ............................................................... 9-19.2 Schedule of Improvements ............................................................................... 9-19.2.1 Project Prioritization......................................................................................... 9-19.3 Comparison to Previous Master Planned Expenditures ................................... 9-39.4 Guidelines for Implementation......................................................................... 9-59.4.1 Project Verification .......................................................................................... 9-5

    List of Figures PageFigure 9-1 .......................................................................................... Following Page 9-1Figure 9-2 .......................................................................................... Following Page 9-1Figure 9-3 .......................................................................................... Following Page 9-1Figure 9-4 .......................................................................................... Following Page 9-1Figure 9-5 .......................................................................................... Following Page 9-1Figure 9-6 .......................................................................................... Following Page 9-1Figure 9-7 .......................................................................................... Following Page 9-1Figure 9-8 .......................................................................................... Following Page 9-1Figure 9-9 .......................................................................................... Following Page 9-3Figure 9-10 .......................................................................................... Following Page 9-4

    List of Tables PageTable 9-1 .......................................................................................... Following Page 9-1Table 9-2 ......................................................................................................On Page 9-2Table 9-3 ......................................................................................................On Page 9-3Table 9-4 .......................................................................................... Following Page 9-5

  • SRCSD Interceptor System Master Plan 2000

    S:\MP 2000\Draft MP2000\Chapter 9\Chapter 9.doc 9-1

    Chapter 9

    Recommended Capital Improvement Program

    9.1 Recommended Capital ExpendituresThe recommended SRCSD Interceptor System Master Plan Capital Improvement Programcontains 52 projects required to convey wastewater flows from existing and planneddevelopment to the Sacramento Regional Wastewater Treatment Plant. The facilities arescheduled to be constructed over the next 35 years, and when operational, will providecapacity for all planned development within the Urban Services Boundary and WestSacramento. The total capital cost of the master planned facilities is $950,100,000. Thiscost is in year 2000 dollars and does not include inflation or interest adjustments for any ofthe identified projects. The capital cost of each project is shown in Table 9-1. The capitalexpenditure per year is shown on Figure 9-1.

    9.2 Schedule of ImprovementsThe improvements identified in MP 2000 have been assigned start and completion datesbased on the anticipated need for each facility to be operational. The start and completiondates for each project are contained in the project schedule, Figure 9-2. A large format,more detailed project schedule may be found in the appendix of this report. A visualrepresentation of the recommended project implementation over time is shown in Figures9-3 through 9-8.

    9.2.1 Project PrioritizationThe recommended interceptor projects were developed to address existing and futurecapacity deficiencies in the existing interceptor system, and to extend conveyance facilitiesto planned development within the SRCSD service area. Each project was categorized intoone of three types of project justifications:

    Category A: Required to relieve existing capacity deficiency

    Category B: Required to relieve future capacity deficiency

    Category C: Required to provide conveyance of wastewater generated fromfuture planned development beyond the reaches of the existinginterceptor system

  • TABLE 9-1ESTIMATED CAPITAL COST OF RECOMMENDED INTERCEPTOR PROJECTS

    Project ID Project LocationEstimated Capital

    CostBR-1 SRWTP to Franklin Blvd. $14,180,000

    BR-6A South of Gerber Rd. to Bradshaw Rd. $16,620,000BR-6B South of Elder Creek to Mayhew and Jackson $19,600,000BR-7 Jackson Hwy. to International Dr. $31,890,000BR-8 International Dr. to Folsom Blvd. $29,890,000SR-1 Folsom Blvd. to South of American River $10,820,000SR-2 South of American River to Pennsylvania Ave. $9,300,000

    FE-1B East of Sunrise Blvd. to Folsom South Canal $10,890,000FE-3 Iron Point Road $11,790,000

    FE-3PS South of Iron Point Road $4,660,000LE-1 SRWTP to Franklin Blvd. at Dwight Rd. $9,000,000NN-1 Del Paso Rd. to end of pipe $3,400,000ARPS Arden Pump Station Site to south of American River $20,000,000RCPS Cordova Pump Station Site $9,350,000

    UNW-1 Natomas PS to Del Paso Blvd. $29,200,000UNW-2 Del Paso Blvd. to Elkhorn Blvd. $26,280,000UNW-3 Elkhorn Blvd. to Natomas East Main Drain $8,660,000UNW-4 Natomas East Main Drain to Cherry Lane $14,460,000UNW-5 Cherry Lane to East of Watt Ave. $22,260,000UNW-6 East of Watt Ave. to West of SPRR $8,290,000DRR-1 28th St. and Elkhorn Blvd. to Scotland Dr. $7,080,000UNW-7 West of SPRR to Van Maren PS $12,620,000UNW-8 Van Maren Pump Station $13,920,000UNW-9 Van Maren PS to Fair Oaks Blvd. $14,210,000LNW-1 SRWTP to West of Sacramento River $27,500,000SRPS Southport Regional Pump Station (Phase 1 - 3) $33,050,000

    LNW-2 West of Sacramento River to South of Linden Rd. $84,010,000WSCSM West Sacramento Treatment Plant $2,000,000LNW-3 South of Linden Rd. to Natomas Pump Station $75,070,000NNPS Natomas Pump Station Site (Phase 1 - 4) $21,090,000SO-1 SRWTP to Laguna Blvd. $8,660,000SO-2 Laguna Blvd. to Franklin Blvd. $21,360,000SO-3 Franklin Blvd. to East of Bruceville Rd. $18,270,000LC-1 SRWTP to Bruceville Rd. $24,840,000LC-2 Bruceville Rd. to Waterman Rd. $44,700,000LC-3 Waterman Rd. to Excelsior Rd. $36,040,000LC-4 Excelsior Rd. to Sunrise Blvd. $20,500,000LC-5 Sunrise Blvd. to end of pipe $5,430,000DC-1 Waterman Rd. North of Bond Rd. to Deer Creek $25,430,000DC-2 Deer Creek to Folsom South Canal $18,210,000DC-3 Folsom South Canal to end of pipe $16,080,000DC-4 South of Crevis Creek to end of pipe $3,320,000MA-1 Happy Lane to East of Folsom South Canal $37,020,000AJ-1 Sunrise and Douglas to West of Jaeger Rd. $5,080,000AJ-2 Sunrise and Douglas to White Rock Rd. $17,400,000

    AJ-2S Sunrise and Douglas to North of Morrison Creek $7,490,000AJ-3 White Rock Rd. to South of Hwy 50 $7,680,000

    AJ-3S White Rock Rd. to Old White Rock Rd. $3,930,000AJ-4 Sunrise and Douglas to end of LC-5 $21,940,000RL-1 Elkhorn Blvd. to Elverta Rd. East of Rio Linda Blvd. $10,800,000

    BR-6BS Bradshaw Rd. to South of Elder Creek Rd. $2,990,000FS-1 South of Hwy. 50 to Iron Point Rd. $8,440,000

    Total $966,700,000

  • Black & Veatch 1/4/2001

    Figure 9-1SRCSD Master Plan 2000 - Estimated Capital Expenditures

    $0

    $20

    $40

    $60

    $80

    $100

    $120

    $140

    $160

    $180

    $20020

    00

    2002

    2004

    2006

    2008

    2010

    2012

    2014

    2016

    2018

    2020

    2022

    2024

    2026

    2028

    2030

    2032

    2034

    Year

    ly E

    xpen

    ditu

    res

    ($ M

    illio

    ns)

    $0

    $200

    $400

    $600

    $800

    $1,000

    $1,200

    Cum

    ulat

    ive

    Expe

    nditu

    res

    ($ M

    illio

    ns)

    Yearly ExpendituesCummulative Expenditures

  • Project Start FinishSRCSD Interceptor Master Plan 2000 1/3/00 2/16/01Upper NWI Design Report 7/3/00 5/11/01Lower NWI Design Report 6/8/00 12/5/01Interceptor Design Manual 1/3/01 11/13/01Bradshaw Interceptor Section 1 & 2 1/3/00 10/6/00Bradshaw Interceptor Section 6A 1/3/00 7/11/03Bradshaw Interceptor Section 6B 1/3/00 4/16/04Bradshaw Interceptor Section 7 1/2/01 11/29/04Bradshaw Interceptor Section 8 1/8/01 1/14/05Sunrise Interceptor Section 1 12/9/02 12/15/06Sunrise Interceptor Section 2 12/9/02 12/15/06Folsom East Interceptor Section 1B 6/5/00 12/13/02Folsom East Section 3 & Pump Station 1/3/00 11/29/02Laguna Interceptor Extension 2/19/01 8/29/03North Natomas Interceptor 1/3/02 7/14/04Arden Pump Station / Force Main 1/3/00 4/19/02Rancho Cordova Pump Station (Phase 1) 11/1/00 7/23/02Rancho Cordova Pump Station (Phase 2) 2/15/18 8/26/20Upper Northwest Interceptor Section 1 1/3/03 1/11/07Upper Northwest Interceptor Section 2 & 3 12/3/04 6/11/09Upper Northwest Interceptor Section 4 4/2/07 10/9/09Upper Northwest Interceptor Section 5 & 6 2/19/01 1/14/05Dry Creek Relief 7/8/02 1/14/05Upper Northwest Interceptor Section 7 & 8 6/4/01 4/29/05Upper Northwest Interceptor Section 9 1/3/07 7/14/09Lower Northwest Interceptor Section 1 4/3/02 2/28/06Southport Regional Pump Station (Phase 1) 4/7/03 7/7/06Southport Regional Pump Station (Phase 2) 1/4/16 4/5/19Southport Regional Pump Station (Phase 3) 1/7/30 4/8/33Lower Northwest Interceptor Section 2 7/8/02 6/2/06West Sac Collection System Modifications 7/7/03 1/13/06Lower Northwest Interceptor Section 3 10/7/02 1/19/07Natomas Pump Station (Phase 1) 10/5/00 1/7/04Natomas Pump Station (Phase 2) 1/2/06 4/3/09Natomas Pump Station (Phase 3) 1/4/12 4/7/15Natomas Pump Station (Phase 4) 1/6/20 4/7/23South Interceptor Section 1 5/7/07 11/13/09South Interceptor Section 2 & Pump Station 10/8/07 10/14/11South Interceptor Section 3 6/14/10 12/21/12Laguna Creek Interceptor Section 1 9/7/09 3/16/12Laguna Creek Interceptor Section 2 3/19/12 2/12/16Laguna Creek Interceptor Section 3 2/15/16 1/10/20Laguna Creek Interceptor Section 4 1/13/20 12/8/23Laguna Creek Interceptor Section 5 1/3/22 7/12/24Deer Creek Interceptor Section 1 1/13/20 7/21/23Deer Creek Interceptor Section 2 7/24/23 1/29/27Deer Creek Interceptor Section 3 2/1/27 8/9/30Deer Creek Interceptor Section 4 8/12/30 2/18/33Mather Interceptor Section 1 7/5/11 1/12/15Aerojet Interceptor Section 1 7/8/13 1/15/16Aerojet Interceptor Section 2 1/18/16 7/27/18Aerojet Interceptor Section 2S 1/18/16 7/27/18Aerojet Interceptor Section 3 9/25/20 4/6/23Aerojet Interceptor Section 3S 4/7/23 10/16/25Aerojet Interceptor Section 4 7/16/29 6/10/33Rio Linda Interceptor Section 1 2/6/23 8/15/25Bradshaw Interceptor Section 6BS 1/4/21 7/14/23Folsom South Pump Station and Force Main 1/3/20 7/14/22

    2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033

    Figure 9-2SRCSD Interceptor Master Plan 2000 Project Schedule

    1/3/01

  • SRCSD Interceptor System Master Plan 2000

    S:\MP 2000\Draft MP2000\Chapter 9\Chapter 9.doc 9-2

    Those projects assigned to Category A were scheduled to begin as soon as possible.Projects in Category B and C were scheduled based on the need for sewerage facilities asprojected by anticipated development plans.

    The projects contained in each category are listed in Table 9-2.

    TABLE 9-2 – PROJECTS LISTED BY CATEGORY

    Category A Category B Category CBR-1 RCPS FE-3

    BR-6A UNW-9 FE-3PSBR-6B LNW-1 NN-1BR-7 SRPS UNW-1BR-8 LNW-2 UNW-2SR-1 LNW-3 UNW-3SR-2 NNPS UNW-4

    FE-1B WSCSMLE-1 SO-1ARPS SO-2

    UNW-5 SO-3UNW-6 LC-1DRR-1 LC-2UNW-7 LC-3UNW-8 LC-4RCPS LC-5

    DC-1DC-2DC-3DC-4MA-1AJ-1AJ-2

    AJ-2SAJ-3

    AJ-3SAJ-4RL-1

    BR-6BSFS-1

  • SRCSD Interceptor System Master Plan 2000

    S:\MP 2000\Draft MP2000\Chapter 9\Chapter 9.doc 9-3

    As shown in Figure 9-1 there is a spike in project expenditures between the years 2002 and2006. This period of high expenditures is primarily caused by the construction of threemajor interceptor projects: Bradshaw/Folsom, Upper Northwest, and Lower Northwest.The yearly expenditures for these projects are shown in Figure 9-9. The Bradshaw/Folsomand Upper Northwest Interceptors are required to relieve existing capacity deficiencies inthe SRCSD interceptor system and CSD-1 trunk system. Although the project segments ofthe Lower Northwest Interceptor are classified as Category B projects, they are required toprovide relief to the Natomas and Arden Pumping stations. Each of these pumping stationsare being upgraded to increase capacity, however, this is intended to only be a stop-gapmeasure to allow a reasonable timeframe for the design and construction of the LowerNorthwest Interceptor.

    9.3 Comparison to Previous Master PlannedExpenditures

    The 1994 update to the Sacramento Sewerage Expansion Study (SSES) estimated the totalcapital cost of the recommended interceptor projects to be $595,100,000 (1993 dollars).The current MP 2000 estimate is $966,700,000. The major increases in project costsaccounting for the $371,600,000 increase are itemized in Table 9-3, below. The differencebetween the $385 million total increase and $372 million difference from the previousmaster plan is due to a net cost savings on other projects contained in the MP 2000.

    TABLE 9-3 – PROJECTS CONTRIBUTING TO INCREASED PROGRAM COSTS

    Item: Increase:Inflation (ENR CCI) $93 millionLower Northwest Interceptor $148 millionUpper Northwest Interceptor $61 millionNewly Identified Projects $82 millionTotal: $385 million

    A description of each of these items is presented below.

    Inflation - The Sacramento Sewerage Expansion Study - 1994 Update used anENR Construction Cost Index (CCI) of 5,600 which represented the mid-pointbetween the 20-cities index and the San Francisco index at the time the estimatewas being generated. The January 2000 value of this index is 6474. Thisrepresents a 15.6% increase due to inflation of the seven-year period and results inan $93 million increase in program costs.

    Lower Northwest Interceptor – The SSES estimated the cost of the LowerNorthwest Interceptor to be $95 million (2000 dollars). The MP 2000 estimate forthese facilities is $243 million. The MP 2000 assumes a West Sacramento route forthe Lower Northwest Interceptor and increases the size of the interceptor facilities

  • Figure 9-9Major Near Term Interceptor Projects

    $0

    $20

    $40

    $60

    $80

    $100

    $120

    2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010

    Cap

    ital C

    ost (

    $ M

    illio

    ns)

    Bradshaw/Folsom Interceptor

    Upper Northwest Interceptor

    Lower Northwest Interceptor

  • SRCSD Interceptor System Master Plan 2000

    S:\MP 2000\Draft MP2000\Chapter 9\Chapter 9.doc 9-4

    to provide conveyance capacity for West Sacramento. A cursory review of theoriginal estimate revealed some additional reasons for the large discrepancy.Approximately half of the base pipeline cost from the SSES was based on a unitcost for 72-inch force main of $320 per foot. This unit price appears to be low forthe type of area the pipeline is routed through. Additionally, the $5 million basecost of expanding the Natomas Pump Station to 73 mgd appears to be low.

    Upper Northwest Interceptor – The Upper Northwest Interceptor was estimatedat $89 million (2000 dollars) in the SSES. The estimate from the Upper NorthwestInterceptor Design Report is approximately $138 million, and the MP 2000estimate is $150 million. The increase is primarily attributable to the increasedcapacity of the facilities identified in the design report to divert additional flowsfrom impacted trunk facilities in the northeast system. Additional costs are alsoexpected to be incurred due to the combination of poor soil and accelerateddevelopment in the North Natomas Area. The increase from the Design Reportestimate to the MP 2000 estimate was related to the need to increase the size of theinterceptor to convey higher flows based on modeling results, and costs associatedwith deepening the pipeline to provide gravity service to a larger portion of theservice area.

    Newly Identified Projects – The Interceptor System Master Plan 2000 hasidentified additional projects beyond those identified in the SSES that will berequired to provide conveyance capacity to serve ultimate development within theUrban Services Boundary. These projects include the ARPS (Arden Pump StationModifications), FS-1 (Folsom South Pump Station and Force Main), and AJ-1through AJ-4 (AeroJet Interceptor). Modifications to the Arden Pump Station areneeded to bring its capacity up to the value assumed in the SSES (approximately105-mgd). The Folsom South Pump Station was required due to the realignment ofFolsom East Interceptor Section 3 to Iron Point Road. The AeroJet Interceptor isrequired to provide service to the Mather/AeroJet Area. This area was originallyidentified as not requiring sewer service. However, due to changes in land useplanning since the SSES, this area has been assigned an average developmentdensity of 6 ESD per acre.

    A comparison of expenditures in relation to time between the SSES and the MP 2000 isshown in Figure 9-10. To estimate expenditure over time for the SSES the capital cost foreach phase was divided evenly by the number of years per phase. The costs associatedwith interceptor projects completed to date are indicated in red. The total costs to date forthe previously construction interceptors have been added to the cumulative MP 2000 costsin order to compare with the previous estimates of the entire program.

    As indicated in Figure 9-10, total expenditures since 1993 have been less than projected inthe 93/94 SSES. This indicates that not all improvements identified in Phase 1 of the93/94 SSES were completed on schedule. The delay in the construction of these facilitieshas contributed to the expenditure spike projected between the years 2002 and 2006.

  • Black & Veatch Final CIP Expend.xls

    Figure 9-10SRCSD Interceptor Actual and Recommended Expenditures

    $0

    $20

    $40

    $60

    $80

    $100

    $12019

    9319

    9419

    9519

    9619

    9719

    9819

    9920

    0020

    0120

    0220

    0320

    0420

    0520

    0620

    0720

    0820

    0920

    1020

    1120

    1220

    1320

    1420

    1520

    1620

    1720

    1820

    1920

    2020

    2120

    2220

    2320

    2420

    2520

    2620

    2720

    2820

    2920

    3020

    3120

    3220

    3320

    3420

    35

    Cap

    ital E

    xpen

    ditu

    re p

    er Y

    ear (

    $ M

    illio

    ns)

    $0

    $200

    $400

    $600

    $800

    $1,000

    $1,200

    Cum

    ulat

    ive

    Expe

    nditu

    res

    ($ M

    illio

    ns)

    1993/94 SSES (1993 dollars)

    1993/94 SSES (2000 dollars)

    MP 2000

    Actual Expenditures

    Cumulative Values

  • SRCSD Interceptor System Master Plan 2000

    S:\MP 2000\Draft MP2000\Chapter 9\Chapter 9.doc 9-5

    9.4 Guidelines for ImplementationThe MP 2000 provides a detailed plan of the interceptor facilities and right of waynecessary to provide sewage conveyance within the Sacramento County USB and citylimits of West Sacramento. Timing of interceptor projects identified for constructionwithin the next 20 years is based on the operational condition of the existing regionalfacilities and/or SACOG growth projections within the study area. Projects identified forconstruction after the year 2020 are based on buildout densities within the USB that are notassociated with a particular timeframe. Projects scheduled after 2020 are intendedprimarily to identify facilities required to provide service under a developed USB scenario.As the case with previous master planning efforts, the MP 2000 should be consider a“working document” and subject to review at least every year and updated every fiveyears.

    Table 9-4 summarized the recommended interceptor projects, describes project “drivers”and timing considerations, and assigns a priority level to the project.

    9.4.1 Project VerificationThe modeling results of the expanded interceptor system during a 10-year design periodstorm at buildout of the USB predict two interceptors with significant surcharging causedby limited pipe capacity. These facilities are the McClellan Interceptor and the LagunaInterceptor. The predicted surcharging may be caused by inaccurate flow monitoringinformation. It is recommended that additional flow monitor analysis be performed inthese areas and the hydraulic model be recalibrated before identifying future relief projects.

    If major land use changes have occurred since the completion of this MP 2000, designflows should be updated and the hydraulic model re-run to determine the impacts the landuse changes have on the interceptor system.

    Finally, the SRCSD should continue metering flow at strategic locations along theinterceptor system. This data should be used to verify and update regional inflowcoefficient (Kp) values throughout the service area. By periodically updating the hydraulicmodel with this information, the SRCSD may accelerate or delay recommended projectsbased on the most recent system response information.

  • Improvement Project Category Driver Priority Timing Considerations Start Finish Start Finish

    Bradshaw Interceptor Section 1&2 ARequired for relief of Central and Northeast Interceptors. Needed to bring Bradshaw Sections 3, 4, 5A, and 5B into service.

    - Under Construction - - - 10/6/2000

    Bradshaw Interceptor Section 6A A Required for relief of Central and Northeast Interceptors. 1 Requires completion of Bradshaw 1 & 2, project under design1/3/2000 5/4/2001 5/7/2001 7/11/2003

    Bradshaw Interceptor Section 6B A Required for relief of Central and Northeast Interceptors. 1 Requires completion of Bradshaw 1 & 2, project under design1/3/2000 2/8/2002 2/11/2002 4/16/2004

    Bradshaw Interceptor Section 7 A Required for relief of Northeast area and Folsom Interceptor. 2 Required to abandon portion of Folsom Interceptor prior to extension of Light Rail1/2/2001 9/23/2002 9/24/2002 11/29/2004

    Bradshaw Interceptor Section 8 A Required for relief of Northeast area and Folsom Interceptor. 2 Required to abandon portion of Folsom Interceptor prior to extension of Light Rail1/8/2001 2/14/2003 2/17/2003 1/14/2005

    Sunrise Interceptor Section 1 A Required for relief of capacity deficient trunks in Northeast area. 2 Coordinate with extension of Light Rail12/9/2002 1/14/2005 1/17/2005 12/15/2006

    Sunrise Interceptor Section 2 A Required for relief of capacity deficient trunks in Northeast area. 212/9/2002 1/14/2005 1/17/2005 12/15/2006

    Folsom East Interceptor Section 1B A Existing Folsom Interceptor at capacity during PWWF. Required to provide capacity for new development in Folsom. 2 Folsom Blvd road improvements6/5/2000 10/5/2001 10/8/2001 12/13/2002

    Folsom East Section 3 C Required to provide service to new development in Folsom East area. 2

    Requires peak shaving in Folsom East Interceptor prior to completion of Bradshaw and Folsom East 1B. This project has been combined with Folsom East 3 Pump Station to form a single construction project.

    1/3/2000 9/22/2000 9/25/2000 11/29/2002

    Folsom East 3 Pump Station C Required to provide service to new development in Folsom East area. 2

    Requires peak shaving in Folsom East Interceptor prior to completion of Bradshaw and Folsom East 1B. This project has been combined with Folsom East Section 3 to form a single construction project.

    1/3/2000 9/22/2000 9/25/2000 11/29/2002

    Laguna Interceptor Extension A Required to bring Laguna Interceptor into service and relieve existing deficiencies in Elk Grove trunk system. 1 Requires completion of MP20002/19/2001 6/21/2002 6/24/2002 8/29/2003

    North Natomas Interceptor C Required for new development in North Natomas and Metro Air Park areas. 31/3/2002 5/7/2003 5/8/2003 7/14/2004

    Arden Pump Station / Force Main A Existing PWWF exceeds firm capacity of pump station. 1 Requires completion of MP2000 and Arden Capacity Study1/3/2000 10/6/2000 10/9/2000 4/19/2002

    Rancho Cordova Pump Station (Phase 1) A

    Pump station does not have firm capacity for Peak Wet Weather Flows 1 Currently under design

    11/1/2000 10/16/2001 10/17/2001 7/23/2002

    Rancho Cordova Pump Station (Phase 2) B

    Pump station does not have sufficient capacity for ultimate development of the area. 3

    Dependant upon actual flows as monitored at the pump station

    2/5/2018 6/7/2019 6/10/2019 8/14/2020

    Upper Northwest Interceptor Section 1 C

    Required for new development in North Natomas and Rio Linda and relief of Northeast area. 2

    Available capacity of Dry Creek Interceptor, Natomas and Arden Pump Stations

    1/3/2003 2/10/2005 2/11/2005 1/11/2007

    Upper Northwest Interceptor Section 2 C

    Required for new development in North Natomas and Rio Linda and relief of Northeast area. 2

    Available capacity of Dry Creek Interceptor, Natomas and Arden Pump Stations. This project has been combined with Upper Northwest Interceptor Section 3 to form a single construction project.

    12/3/2004 1/11/2007 1/12/2007 6/11/2009

    TABLE 9-4

    ConstructionDesignSCHEDULING AND PRIORITY LIST

    Black & Veatch 1/4/2001

  • Improvement Project Category Driver Priority Timing Considerations Start Finish Start Finish

    Upper Northwest Interceptor Section 3 C

    Required for new development in North Natomas and Rio Linda and relief of Northeast area. 2

    Available capacity of Dry Creek Interceptor, Natomas and Arden Pump Stations. This project has been combined with Upper Northwest Interceptor Section 2 to form a single construction project.

    12/3/2004 1/11/2007 1/12/2007 6/11/2009

    Upper Northwest Interceptor Section 5 A

    Required for relief of capacity deficient trunks in Northeast area including Mission Trunk. 1

    Requires completion of MP2000. This project has been combined with Upper Northwest Interceptor Section 6 to form a single construction project.

    2/19/2001 11/8/2002 11/11/2002 1/14/2005

    Upper Northwest Interceptor Section 6 A

    Required for relief of capacity deficient trunks in Northeast area including Mission Trunk. 1

    Requires completion of MP2000. This project has been combined with Upper Northwest Interceptor Section 5 to form a single construction project.

    2/19/2001 11/8/2002 11/11/2002 1/14/2005

    Dry Creek Relief A Required for relief of Dry Creek Interceptor. 1 Requires completion of Upper Northwest Section 5 & 6 7/8/2002 11/7/2003 11/10/2003 1/14/2005

    Upper Northwest Interceptor Section 7 A

    Required for relief of capacity deficient trunks in Northeast area including Mission Trunk. 1

    Requires completion of Upper Northwest 5 & 6. This project has been combined with Upper Northwest Interceptor Section 8 to form a single construction project.

    6/4/2001 2/21/2003 2/24/2003 4/29/2005

    Upper Northwest Interceptor Section 8 A

    Required for relief of capacity deficient trunks in Northeast area including Mission Trunk. 1

    Requires completion of Upper Northwest 5 & 6. This project has been combined with Upper Northwest Interceptor Section 7 to form a single construction project.

    6/4/2001 2/21/2003 2/24/2003 4/29/2005

    Upper Northwest Interceptor Section 9 B

    Required for relief of future capacity deficiency in Northeast area. 3 Depends on impact of development on trunk capacity

    1/3/2007 5/6/2008 5/7/2008 7/14/2009

    Lower Northwest Interceptor Section 1 B

    Required for relief of Northeast area and for new development in North Natomas. 1

    Available capacity of Arden Pump Station, Natomas Interceptor, and Mission Trunk. Requires completion of Lower Northwest Design Report

    4/3/2002 12/23/2003 12/24/2003 2/28/2006

    Southport Regional Pump Station B Required for relief of Northeast area and for new development in North Natomas and West Sacramento. 1Project to be constructed in multiple stages to provide flexibility in the facility's ultimate capacity. Requires completion of Lower Northwest Design Report

    4/7/2003 8/6/2004 8/9/2004 7/7/2006

    Lower Northwest Interceptor Section 2 B

    Required for relief of Northeast area and for new development in North Natomas. 1

    Available capacity of Arden Pump Station, Natomas Interceptor, and Mission Trunk. Requires completion of Lower Northwest Design Report

    7/8/2002 3/26/2004 3/29/2004 6/2/2006

    West Sacramento Collection System Modifications C Capacity considerations at West Sacramento Treatment Plant. 1 Requires completion of Lower Northwest Interceptor

    7/7/2003 11/5/2004 11/8/2004 1/13/2006

    Lower Northwest Interceptor Section 3 B

    Required for relief of Northeast area and for new development in North Natomas. 1

    Available capacity of Arden Pump Station, Natomas Interceptor, and Mission Trunk. Requires completion of Lower Northwest Design Report

    10/7/2002 11/12/2004 11/15/2004 1/19/2007

    Natomas Pump Station B Required for relief of Northeast area and for new development in North Natomas. 1Limited capacity of existing Natomas Pump Station. Project to be constructed in multiple stages to provide flexibility in the facility's ultimate capacity

    10/5/2000 2/6/2002 2/7/2002 1/7/2004

    South Interceptor Section 1 C Required for future development in East Franklin area. 2 Requires construction of Laguna Interceptor Extension 5/7/2007 9/5/2008 9/8/2008 11/13/2009

    South Interceptor Section 2 C Required for future development in East Franklin area. 2 10/8/2007 11/13/2009 11/16/2009 10/14/2011

    South Interceptor Section 3 C Required for future development in East Franklin area. 2 6/14/2010 10/14/2011 10/17/2011 12/21/2012

    TABLE 9-4 - CONTINUEDSCHEDULING AND PRIORITY LIST

    Design Construction

    Black & Veatch 1/4/2001

  • Improvement Project Category Driver Priority Timing Considerations Start Finish Start FinishLaguna Creek Interceptor Section 1 C Required for future development in Southeast county. 3 Available capacity in Bradshaw 9/7/2009 1/7/2011 1/10/2011 3/16/2012

    Laguna Creek Interceptor Section 2 C Required for future development in Southeast county. 3 Available capacity in Bradshaw 3/19/2012 12/6/2013 12/9/2013 2/12/2016

    Laguna Creek Interceptor Section 3 C Required for future development in Southeast county. 3 Available capacity in Bradshaw 2/15/2016 11/3/2017 11/6/2017 1/10/2020

    Laguna Creek Interceptor Section 4 C Required for future development in Southeast county. 3 Available capacity in Bradshaw 1/13/2020 10/1/2021 10/4/2021 12/8/2023

    Laguna Creek Interceptor Section 5 C Required for future development in Southeast county. 3 Available capacity in Bradshaw 1/3/2022 5/5/2023 5/8/2023 7/12/2024

    Deer Creek Interceptor Section 1 C Required for future development in Deer Creek basin. 3 1/13/2020 5/14/2021 5/17/2021 7/21/2023

    Deer Creek Interceptor Section 2 C Required for future development in Deer Creek basin. 3 7/24/2023 11/22/2024 11/25/2024 1/29/2027

    Deer Creek Interceptor Section 3 C Required for future development in Deer Creek basin. 3 2/1/2027 6/2/2028 6/5/2028 8/9/2030

    Deer Creek Interceptor Section 4 C Required for future development in Deer Creek basin. 3 8/12/2030 12/12/2031 12/15/2031 2/18/2033

    Mather Interceptor Section 1 C Required for new development in Sunrise-Douglas area. 3 Requires completion of Bradshaw 7 7/5/2011 11/5/2012 11/6/2012 1/12/2015

    Aerojet Interceptor Section 1 C Required for future development in Aerojet area. 3 7/8/2013 11/7/2014 11/10/2014 1/15/2016

    Aerojet Interceptor Section 2 C Required for future development in Aerojet area. 3 1/18/2016 5/19/2017 5/22/2017 7/27/2018

    Aerojet Interceptor Section 2S C Required for future development in Aerojet area. 3 1/18/2016 5/19/2017 5/22/2017 7/27/2018

    Aerojet Interceptor Section 3 C Required for future development in Aerojet area. 3 9/25/2020 1/27/2022 1/28/2022 4/6/2023

    Aerojet Interceptor Section 3S C Required for future development in Aerojet area. 3 4/7/2023 8/8/2024 8/9/2024 10/16/2025

    Aerojet Interceptor Section 4 C Required for future development in Aerojet area. 3 Available capacity in Bradshaw 7/16/2029 4/4/2031 4/7/2031 6/10/2033

    Rio Linda Interceptor Section 1 C Required for future development in Rio Linda. 3 2/6/2023 6/7/2024 6/10/2024 8/15/2025

    Bradshaw Interceptor Section 6BS C Required for future development West of Bradshaw. 3 1/4/2021 5/6/2022 5/9/2022 7/14/2023

    Folsom South PS and Force Main C Required for future development in Folsom South area. 3 1/3/2020 5/6/2021 5/7/2021 7/14/2022

    SCHEDULING AND PRIORITY LISTDesign Construction

    TABLE 9-4 - CONTINUED

    Black & Veatch 1/4/2001

  • SRCSD Master Plan 2000Project Summary

    Project Name: Bradshaw Interceptor Section 1 & 2

    Project ID: BR-1 1

    Location: SRWTP to Franklin Blvd

    Description of Facility: 90 and 120-inch gravity pipeline

    Length: 6,690 ft.

    Design Capacity: 206 to 303 mgd

    Project Justification: Category A: Required for relief of Northeast and Central Interceptors

    Primary Construction Method: Open Cut

    Special Considerations: Tunnel beneath railroad and wetlands

    Base Construction Cost: $5,689,592

    Special Structures: $1,765,000Traffic Control: $56,896

    Environmental Mitigation: $20,000Right-of-Way: -

    Special Construction/Pipe Jack: $2,778,713Contingency: $1,031,020

    Total Construction Cost $11,341,221

    Engineering/Admin/Legal Costs: $2,835,305

    Total Capital Cost: $14,176,526

    BR-1 10/13/20006:06 PM

  • Bradshaw1-2.xls 10/13/2000

    Bradshaw Interceptor- Sections 1, 2

    -20

    -15

    -10

    -5

    0

    5

    10

    15

    20

    25

    0+00 10+00 20+00 30+00 40+00 50+00 60+00

    Station

    Elev

    atio

    n

    120"

    Bradshaw Equalization Structure

    90"

    Lagu

    na C

    reek

    Franklin Blvd. Transition Structure

    Influ

    ent T

    rans

    ition

    Str

    uctu

    re

    Exis

    ting

    90"

    Dia

    . RC

    P

    120"

    Rai

    lroad

    Cro

    ssin

    g

  • SRCSD Master Plan 2000Project Summary

    Project Name: Bradshaw Interceptor Section 6A

    Project ID: BR-6A 2

    Location: Elk Grove-Florin and Gerber Rds to Bradshaw Rd and Elder Creek

    Description of Facility: 108-inch gravity pipeline

    Length: 14,875 ft.

    Design Capacity: 215 mgd

    Project Justification: Category A: Required for relief of Northeast and Central Interceptors

    Primary Construction Method: Open Cut

    Special Considerations: Railroad crossing

    Base Construction Cost: $11,244,678

    Special Structures: -Traffic Control: -

    Environmental Mitigation: $100,000Right-of-Way: $56,406

    Special Construction/Pipe Jack: $158,510Contingency: $1,733,939

    Total Construction Cost $13,293,533

    Engineering/Admin/Legal Costs: $3,323,383

    Total Capital Cost: $16,616,916

    BR-6A 10/13/20006:09 PM

  • Bradshaw 6A.xls 10/13/2000

    Bradshaw Interceptor- Section 6A

    10

    20

    30

    40

    50

    60

    70

    80

    336+00 356+00 376+00 396+00 416+00 436+00 456+00 476+00

    Station

    Elev

    atio

    n

    108"

    Ger

    ber R

    oad

    Flor

    in R

    oad

    Rai

    lroad

    Cro

    ssin

    g

    Bra

    dsha

    w/C

    entr

    al J

    unct

    ion

    Stru

    ctur

    e

  • SRCSD Master Plan 2000Project Summary

    Project Name: Bradshaw Interceptor Section 6B and Jackson Connector

    Project ID: BR-6B 3

    Location: Bradshaw Rd and Elder Creek Rd to Jackson Hwy

    Description of Facility: 84 and 108-inch gravity pipeline

    Length: 11,359 ft.

    Design Capacity: 205 to 215 mgd

    Project Justification: Category A: Required for relief of Northeast and Central Interceptors

    Primary Construction Method: Open Cut

    Special Considerations: Crossing Jackson Hwy

    Base Construction Cost: $10,689,142

    Special Structures: $2,399,616Traffic Control: $320,674

    Environmental Mitigation: $50,000Right-of-Way: $12,501

    Special Construction/Pipe Jack: $162,540Contingency: $2,045,171

    Total Construction Cost $15,679,644

    Engineering/Admin/Legal Costs: $3,919,911

    Total Capital Cost: $19,599,555

    BR-6B 10/13/20006:10 PM

  • Bradshaw 6B.xls 10/13/2000

    Bradshaw Interceptor- Section 6B

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    484+75 494+75 504+75 514+75 524+75 534+75 544+75 554+75 564+75

    Station

    Elev

    atio

    n

    Bradshaw/Jackson Junction Structure

    84"

    Jack

    son

    Hig

    hway

    Bradshaw Section 6A

    108"

    Bradshaw Road

    Elde

    r Cre

    ek R

    oad

    Mor

    rison

    Cre

    ek

  • SRCSD Master Plan 2000Project Summary

    Project Name: Bradshaw Interceptor Section 7

    Project ID: BR-7 4

    Location: Bradshaw Rd and Jackson Hwy to International Dr

    Description of Facility: 72 and 84-inch gravity pipeline

    Length: 26,300 ft.

    Design Capacity: 93 to 110 mgd

    Project Justification: Category A: Required for relief of Northeast area and Folsom Interceptor

    Primary Construction Method: Open Cut

    Special Considerations: Traffic control for Bradshaw Rd and Kiefer Blvd

    Base Construction Cost: $19,827,197

    Special Structures: $589,782Traffic Control: $594,816

    Environmental Mitigation: $100,000Right-of-Way: $991,714

    Special Construction/Pipe Jack: $78,100Contingency: $3,327,241

    Total Construction Cost $25,508,851

    Engineering/Admin/Legal Costs: $6,377,213

    Total Capital Cost: $31,886,064

    BR-7 10/13/20006:11 PM

  • Bradshaw 7.xls 10/13/2000

    Bradshaw Interceptor- Section 7

    20

    30

    40

    50

    60

    70

    80

    90

    100

    110

    570+00 620+00 670+00 720+00 770+00 820+00

    Station

    Elev

    atio

    n

    Happy Lane

    Lower Placerville Road

    84"

    72"

    Bradshaw Road

    Bradshaw/Mather Junction Structure

    Keifer Boulevard

    Bra

    dsha

    w/J

    acks

    on J

    unct

    ion

    Stru

    ctur

    e

    Old Placerville Road

  • SRCSD Master Plan 2000Project Summary

    Project Name: Bradshaw Interceptor Section 8

    Project ID: BR-8 5

    Location: International Dr to Folsom Blvd And Citrus Rd

    Description of Facility: 48 and 72-inch gravity pipeline

    Length: 17,975 ft.

    Design Capacity: 85 mgd

    Project Justification: Category A: Required for relief of Northeast area and Folsom Interceptor

    Primary Construction Method: Open Cut

    Special Considerations: Traffic control for construction in International Dr, Kilgore Dr, and Folsom Blvd, Crossing Sunrise Blvd and RT tracks

    Base Construction Cost: $17,296,577

    Special Structures: $531,086Traffic Control: $518,897

    Environmental Mitigation: $100,000Right-of-Way: $533,532

    Special Construction/Pipe Jack: $150,960Contingency: $4,782,763

    Total Construction Cost $23,913,815

    Engineering/Admin/Legal Costs: $5,978,454

    Total Capital Cost: $29,892,269

    BR-8 10/13/20006:11 PM

  • Bradshaw 8.xls 10/13/2000

    Bradshaw Interceptor- Section 8

    60

    70

    80

    90

    100

    110

    120

    130

    140

    833+00 853+00 873+00 893+00 913+00 933+00 953+00 973+00 993+00

    Station

    Elev

    atio

    n

    Folsom Boulevard

    72"

    Folsom/Citrus West Junction Structure

    48"

    Folsom/Citrus East Junction Structure

    Citrus Drive

    Kilgore Road

    International Drive

    Sunr

    ise

    Bou

    leva

    rd

    Rai

    lroad

    Cro

    ssin

    g

  • SRCSD Master Plan 2000Project Summary

    Project Name: Sunrise Interceptor Section 1

    Project ID: SR-1 6

    Location: Folsom Blvd And Citrus Rd to Sunrise Blvd Bridge

    Description of Facility: 48-inch gravity pipeline

    Length: 8,670 ft.

    Design Capacity: 23 to 25 mgd

    Project Justification: Category A: Required for relief of Northeast area trunks

    Primary Construction Method: Open Cut

    Special Considerations: Hwy 50 crossing, Traffic control for construction in Sunrise Blvd

    Base Construction Cost: $5,667,789

    Special Structures: $128,961Traffic Control: $283,389

    Environmental Mitigation: $100,000Right-of-Way: $628,222

    Special Construction/Pipe Jack: $117,250Contingency: $1,731,403

    Total Construction Cost $8,657,014

    Engineering/Admin/Legal Costs: $2,164,254

    Total Capital Cost: $10,821,268

    SR-1 10/13/20006:12 PM

  • sunrise1 10/13/2000

    Sunrise Interceptor - Section 1

    50

    70

    90

    110

    130

    150

    170

    1012+75 1022+75 1032+75 1042+75 1052+75 1062+75 1072+75 1082+75 1092+75

    Station

    Elev

    atio

    n

    48"

    Vortex Drop Structure

    Sunrise Boulevard

    Hig

    hway

    50

    Col

    oma

    Roa

    d

    Citrus Road

    Fols

    om/C

    itrus

    Eas

    t Jun

    ctio

    n St

    ruct

    ure

  • SRCSD Master Plan 2000Project Summary

    Project Name: Sunrise Interceptor Section 2

    Project ID: SR-2 7

    Location: Sunrise Blvd Bridge to Pennsylvania Ave and Sunset Ave

    Description of Facility: 36-inch gravity pipeline, 24-inch pressure pipeline

    Length: 7,871 ft.

    Design Capacity: 20 to 73 mgd

    Project Justification: Category A: Required for relief of Northeast area trunks

    Primary Construction Method: Open Cut

    Special Considerations: American River Crossing, Traffic control for construction along Sunrise Blvd

    Base Construction Cost: $4,166,806

    Special Structures: $94,962Traffic Control: $208,340

    Environmental Mitigation: $100,000Right-of-Way: $503,920

    Special Construction/Pipe Jack: $880,000Contingency: $1,488,507

    Total Construction Cost $7,442,536

    Engineering/Admin/Legal Costs: $1,860,634

    Total Capital Cost: $9,303,170

    SR-2 10/13/20006:12 PM

  • sunrise2 10/13/2000

    Sunrise Interceptor - Section 2

    90

    110

    130

    150

    170

    190

    210

    1099+00 1109+00 1119+00 1129+00 1139+00 1149+00 1159+00 1169+00

    Station

    Elev

    atio

    n

    Pressure Manhole

    Pennsylvania Avenue

    36"

    36"

    24"

    Vort

    ex D

    rop

    Stru

    ctur

    e

    Am

    eric

    an R

    iver

    Microtunneling

  • SRCSD Master Plan 2000Project Summary

    Project Name: Folsom East Interceptor Section 1B

    Project ID: FE-1B 8

    Location: Folsom Blvd And Citrus Rd to Hwy 50 and Folsom South Canal

    Description of Facility: 48-inch gravity pipeline

    Length: 10,500 ft.

    Design Capacity: 46 mgd

    Project Justification: Category A: Existing Folsom Int at capacity during PWWF andrequired to provide capacity for new devel. in Folsom

    Primary Construction Method: Open Cut

    Special Considerations: Traffic control for construction in Folsom Blvd

    Base Construction Cost: $6,151,582

    Special Structures: $397,655Traffic Control: $307,579

    Environmental Mitigation: $50,000Right-of-Way: $79,358

    Special Construction/Pipe Jack: $39,700Contingency: $1,053,881

    Total Construction Cost $8,079,756

    Engineering/Admin/Legal Costs: $2,019,939

    Total Capital Cost: $10,099,695

    FE-1B 10/13/20006:12 PM

  • folsomeast1B 10/13/2000

    Folsom East Interceptor- Sections 1B

    70

    80

    90

    100

    110

    120

    130

    140

    150

    0+00 20+00 40+00 60+00 80+00 100+00

    Station

    Elev

    atio

    n

    48"

    Folsom/Citrus EastJunction Structure

    48"

    Vortex Drop Structure

    48"

    Folsom Boulevard

  • SRCSD Master Plan 2000Project Summary

    Project Name: Folsom East Interceptor Section 3

    Project ID: FE-3 9

    Location: Folsom Blvd and Iron Point Rd to Iron Point Rd and Oak Ave Pkwy

    Description of Facility: 36 and 42-inch gravity pipeline, 16 and 24-inch force main

    Length: 15,154 ft.

    Design Capacity: 23 to 80 mgd

    Project Justification: Category C: Required to provide service to new development in Folsom East area

    Primary Construction Method: Open Cut

    Special Considerations: Traffic Control for construction in Iron Point Rd

    Base Construction Cost: $7,675,676

    Special Structures: $203,114Traffic Control: $230,270

    Environmental Mitigation: $10,000Right-of-Way: -

    Special Construction/Pipe Jack: $81,840Contingency: $1,230,135

    Total Construction Cost $9,431,035

    Engineering/Admin/Legal Costs: $2,357,759

    Total Capital Cost: $11,788,793

    FE-3 10/13/20006:12 PM

  • folsomeast3 10/13/2000

    Folsom East Interceptor- Section 3

    150

    200

    250

    300

    350

    400

    0+00 20+00 40+00 60+00 80+00 100+00 120+00 140+00

    Station

    Elev

    atio

    n

    42"

    16" and 24" FM

    36"

    36"

    Iron Point Road

    Prai

    rie C

    ity R

    oad

    Fols

    om B

    oule

    vard

    FE

    3 In

    terc

    epto

    r Jun

    ctio

    n St

    ruct

    ure

  • SRCSD Master Plan 2000Project Summary

    Project Name: Folsom East Interceptor Section 3 Pump Station

    Project ID: FE-3PS 10

    Location: Iron Point Rd North of Hwy 50

    Description of Facility: New pump station

    Length: N/A

    Design Capacity: 10 mgd

    Project Justification: Category C: Required to provide service to new development in Folsom East area

    Primary Construction Method: Open Cut

    Special Considerations:

    Base Construction Cost: $3,019,782

    Special Structures: -Traffic Control: $0

    Environmental Mitigation: $10,000Right-of-Way: $213,542

    Special Construction/Pipe Jack: -Contingency: $486,499

    Total Construction Cost $3,729,822

    Engineering/Admin/Legal Costs: $932,456

    Total Capital Cost: $4,662,278

    FE-3PS 10/13/20006:13 PM

  • SRCSD Master Plan 2000Project Summary

    Project Name: Laguna Extension Interceptor Section 1

    Project ID: LE-1 11

    Location: SRWTP to Franklin Blvd and Dwight Rd

    Description of Facility: 60 and 108-inch gravity pipeline

    Length: 7,900 ft.

    Design Capacity: 40 to 400 mgd

    Project Justification: Category A: Required for relief of trunk sewer in Big Horn Blvd andto bring Laguna Interceptor into service

    Primary Construction Method: Open Cut

    Special Considerations: Tunneling under wetlands

    Base Construction Cost: $4,148,222

    Special Structures: $1,510,653Traffic Control: $0

    Environmental Mitigation: $100,000Right-of-Way: -

    Special Construction/Pipe Jack: -Contingency: $1,439,719

    Total Construction Cost $7,198,594

    Engineering/Admin/Legal Costs: $1,799,648

    Total Capital Cost: $8,998,242

    LE-1 10/13/20006:13 PM

  • Lei-1 10/13/2000

    Laguna Extension Interceptor- Section 1

    -20

    -15

    -10

    -5

    0

    5

    10

    15

    20

    25

    -5+00 5+00 15+00 25+00 35+00 45+00 55+00 65+00 75+00

    Station

    Elev

    atio

    n

    60"

    Con

    nect

    to E

    xist

    ing

    Bra

    dsha

    wEq

    ualiz

    atio

    n St

    ruct

    ure

    Con

    nect

    to E

    xist

    ing

    60"

    in F

    rank

    lin B

    lvd

    at M

    H 1

    19-0

    13-0

    10

    108"

    54" South Interceptor

    102" Laguna Creek Interceptor

    Tunnel

    Laguna Extension Junction Structure

  • SRCSD Master Plan 2000Project Summary

    Project Name: North Natomas Interceptor Section 1

    Project ID: NN-1 12

    Location: Del Paso Rd at Arco Arena to South of Elkhorn Blvd

    Description of Facility: 36 and 42-inch gravity pipeline

    Length: 6,700 ft.

    Design Capacity: 13 to 22 mgd

    Project Justification: Category C: Required for new development in North Natomas andMetro Air Park areas

    Primary Construction Method: Open Cut

    Special Considerations:

    Base Construction Cost: $2,366,692

    Special Structures: -Traffic Control: -

    Environmental Mitigation: -Right-of-Way: -

    Special Construction/Pipe Jack: -Contingency: $355,004

    Total Construction Cost $2,721,696

    Engineering/Admin/Legal Costs: $680,424

    Total Capital Cost: $3,402,120

    NN-1 10/13/20006:13 PM

  • Nni-1 10/13/2000

    North Natomas Interceptor- Section 1

    -15

    -10

    -5

    0

    5

    10

    15

    20

    25

    0+00 10+00 20+00 30+00 40+00 50+00 60+00

    Station

    Elev

    atio

    n

    42"

    36"

    Tunnel Construction

  • SRCSD Master Plan 2000Project Summary

    Project Name: Arden Pump Station Improvements

    Project ID: ARPS 13

    Location: Arden Pump Station Site, Howe Ave and Enterprise Dr

    Description of Facility: Upgrade of existing Arden Pump Station

    Length: N/A

    Design Capacity: 100 mgd +/- to be determined

    Project Justification: Category A: Existing PWWF exceeds firm capacity of pump station

    Primary Construction Method:

    Special Considerations: Specific improvements to be determined, $5,000,000is a budgetary placeholder.

    Base Construction Cost: $5,000,000

    Special Structures: -Traffic Control: -

    Environmental Mitigation: -Right-of-Way: -

    Special Construction/Pipe Jack: -Contingency: $750,000

    Total Construction Cost $5,750,000

    Engineering/Admin/Legal Costs: $1,437,500

    Total Capital Cost: $7,187,500

    ARPS 10/13/20006:14 PM

  • SRCSD Master Plan 2000Project Summary

    Project Name: Rancho Cordova Pump Station Improvements

    Project ID: RCPS 14

    Location: Cordova Pump Station Site, Chase Dr

    Description of Facility: Upgrade of existing pump station / construct new PS in future

    Length: N/A

    Design Capacity: 15 mgd

    Project Justification: Category A/B: Pump station does not have sufficient firm capacityfor existing flows nor ultimate development of the area

    Primary Construction Method:

    Special Considerations: Project contains Phase 1 (pump station upgrade) andPhase 2 (construction of new pump station in future)

    Base Construction Cost: $5,985,091

    Special Structures: -Traffic Control: -

    Environmental Mitigation: -Right-of-Way: -

    Special Construction/Pipe Jack: -Contingency: $1,496,273

    Total Construction Cost $7,481,364

    Engineering/Admin/Legal Costs: $1,870,341

    Total Capital Cost: $9,351,705

    RCPS 1/4/200110:34 AM

  • SRCSD Master Plan 2000Project Summary

    Project Name: Upper Northwest Interceptor Section 1

    Project ID: UNW-1 15

    Location: Natomas Pump Station to Del Paso Blvd

    Description of Facility: 84 and 96-inch gravity pipeline

    Length: 10,400 ft.

    Design Capacity: 133 to 150 mgd

    Project Justification: Category C: Required for future devel. in North Natomas and Rio Linda and relief of Northeast trunks and Dry Creek Int

    Primary Construction Method: Tunneled

    Special Considerations: Poor soil conditions and high ground water

    Base Construction Cost: $20,232,000

    Special Structures: -Traffic Control: $0

    Environmental Mitigation: $50,000Right-of-Way: $31,003

    Special Construction/Pipe Jack: -Contingency: $3,046,950

    Total Construction Cost $23,359,953

    Engineering/Admin/Legal Costs: $5,839,988

    Total Capital Cost: $29,199,941

    UNW-1 10/13/20006:14 PM

  • Unwi-1 10/13/2000

    Upper Northwest Interceptor- Section 1

    -35

    -25

    -15

    -5

    5

    15

    25

    10+00 30+00 50+00 70+00 90+00 110+00

    Station

    Elev

    atio

    n

    84"

    96"

    East Drainage Canal

    Nat

    omas

    Pum

    p St

    atio

    n

    C1

    Can

    al

    Del

    Pas

    o B

    oule

    vard

    Tunnel Construction

  • SRCSD Master Plan 2000Project Summary

    Project Name: Upper Northwest Interceptor Section 2

    Project ID: UNW-2 16

    Location: Del Paso Blvd To Elkhorn Blvd

    Description of Facility: 84-inch gravity pipeline

    Length: 10,652 ft.

    Design Capacity: 133 mgd

    Project Justification: Category C: Required for future devel. in North Natomas and Rio Linda and relief of Northeast trunks and Dry Creek Int

    Primary Construction Method: Tunneled

    Special Considerations: Poor soil conditions and high ground water

    Base Construction Cost: $18,203,242

    Special Structures: -Traffic Control: -

    Environmental Mitigation: $50,000Right-of-Way: $25,565

    Special Construction/Pipe Jack: -Contingency: $2,741,821

    Total Construction Cost $21,020,628

    Engineering/Admin/Legal Costs: $5,255,157

    Total Capital Cost: $26,275,785

    UNW-2 10/13/20006:15 PM

  • Unwi-2 10/13/2000

    Upper Northwest Interceptor- Section 2

    -35

    -25

    -15

    -5

    5

    15

    25

    114+00 134+00 154+00 174+00 194+00 214+00

    Station

    Elev

    atio

    n

    84"

    84"

    East Drainage Canal

    Elkh

    orn

    Bou

    leva

    rd

    Tunnel Construction

  • SRCSD Master Plan 2000Project Summary

    Project Name: Upper Northwest Interceptor Section 3

    Project ID: UNW-3 17

    Location: Elkhorn Blvd to Natomas East Main Drain

    Description of Facility: 84-inch gravity pipeline

    Length: 6,129 ft.

    Design Capacity: 133 mgd

    Project Justification: Category C: Required for future devel. in North Natomas and Rio Linda and relief of Northeast trunks and Dry Creek Int

    Primary Construction Method: Open Cut

    Special Considerations:

    Base Construction Cost: $5,211,230

    Special Structures: $758,292Traffic Control: $52,112

    Environmental Mitigation: -Right-of-Way: $2,648

    Special Construction/Pipe Jack: -Contingency: $903,642

    Total Construction Cost $6,927,924

    Engineering/Admin/Legal Costs: $1,731,981

    Total Capital Cost: $8,659,905

    UNW-3 10/13/20006:15 PM

  • Unwi-3 10/13/2000

    Upper Northwest Interceptor- Section 3

    -15

    -5

    5

    15

    25

    35

    45

    220+50 230+50 240+50 250+50 260+50 270+50 280+50

    Station

    Elev

    atio

    n

    84"84"

    Elkhorn Boulevard

  • SRCSD Master Plan 2000Project Summary

    Project Name: Upper Northwest Interceptor Section 4

    Project ID: UNW-4 18

    Location: Elkhorn Blvd and NEMDC to Elkhorn Blvd and Cherry Ln

    Description of Facility: 66 and 84-inch gravity pipeline

    Length: 11,084 ft.

    Design Capacity: 98 to 133 mgd

    Project Justification: Category C: Required for future devel. in North Natomas and Rio Linda and relief of Northeast trunks and Dry Creek Int

    Primary Construction Method: Open Cut

    Special Considerations: Railroad crossing and traffic control along Elkhorn Blvd

    Base Construction Cost: $8,326,717

    Special Structures: $572,158Traffic Control: $249,802

    Environmental Mitigation: $50,000Right-of-Way: $554,622

    Special Construction/Pipe Jack: $304,780Contingency: $1,508,712

    Total Construction Cost $11,566,790

    Engineering/Admin/Legal Costs: $2,891,697

    Total Capital Cost: $14,458,487

    UNW-4 10/13/20006:15 PM

  • Unwi-4 10/13/2000

    Upper Northwest Interceptor- Section 4

    -10

    0

    10

    20

    30

    40

    50

    60

    70

    281+80 301+80 321+80 341+80 361+80 381+80

    Station

    Elev

    atio

    n

    66"

    Dry CreekJunction Structure

    Elkhorn Boulevard

    Dry

    Cre

    ek

    Nat

    omas

    Eas

    t Mai

    n D

    rain

    age

    Can

    al

    84"

    54" Rio Linda Interceptor

    27" Dry Creek Interceptor

    Rio

    Lin

    da B

    oule

    vard

    Rai

    lroad

    Cro

    ssin

    g

    Junction Structure

  • SRCSD Master Plan 2000Project Summary

    Project Name: Upper Northwest Interceptor Section 5

    Project ID: UNW-5 19

    Location: Elkhorn Blvd and Cherry Ln to Elkhorn Blvd and Watt Ave

    Description of Facility: 54 and 66-inch gravity pipeline

    Length: 19,385 ft.

    Design Capacity: 69 to 81 mgd

    Project Justification: Category A: Required for relief of Northeast area

    Primary Construction Method: Open Cut

    Special Considerations: Traffic control along Elkhorn Blvd, Watt Ave crossing

    Base Construction Cost: $13,610,919

    Special Structures: $770,299Traffic Control: $680,546

    Environmental Mitigation: -Right-of-Way: $160,272

    Special Construction/Pipe Jack: $260,480Contingency: $2,322,377

    Total Construction Cost $17,804,893

    Engineering/Admin/Legal Costs: $4,451,223

    Total Capital Cost: $22,256,116

    UNW-5 10/13/20006:15 PM

  • Unwi-5 10/13/2000

    Upper Northwest Interceptor- Section 5

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    390+00 410+00 430+00 450+00 470+00 490+00 510+00 530+00 550+00 570+00

    Station

    Elev

    atio

    n

    66"

    Dry Creek ReliefJunction Structure

    Elkhorn Boulevard

    28th

    Str

    eet

    Dry

    Cre

    ek

    Junction Structure

    54"

    Junction Structure

    Wat

    t Ave

    nue

    Dry

    Cre

    ek R

    oad

    42" Dry Creek Relief

  • SRCSD Master Plan 2000Project Summary

    Project Name: Upper Northwest Section 6

    Project ID: UNW-6 20

    Location: Elkhorn Blvd and Watt Ave to Elkhorn Blvd and Don Julio Blvd

    Description of Facility: 48-inch gravity pipeline

    Length: 9,370 ft.

    Design Capacity: 59 to 62 mgd

    Project Justification: Category A: Required for relief of Northeast area

    Primary Construction Method: Open Cut

    Special Considerations: Traffic control along Elkhorn Blvd, Don Julio Blvd crossing,

    Base Construction Cost: $5,071,110

    Special Structures: $399,780Traffic Control: $253,556

    Environmental Mitigation: -Right-of-Way: -

    Special Construction/Pipe Jack: $42,840Contingency: $865,093

    Total Construction Cost $6,632,378

    Engineering/Admin/Legal Costs: $1,658,095

    Total Capital Cost: $8,290,473

    UNW-6 10/13/20006:16 PM

  • Unwi-6 10/13/2000

    Upper Northwest Interceptor- Section 6

    50

    70

    90

    110

    130

    150

    586+50 596+50 606+50 616+50 626+50 636+50 646+50 656+50 666+50 676+50

    Station

    Elev

    atio

    n

    48"

    Vortex Drop Structure

    Elkhorn Boulevard

    Wal

    erga

    Roa

    d

    48"

    Don

    Jul

    io

    Ave

    nue

    Don Julio TransitionStructure

  • SRCSD Master Plan 2000Project Summary

    Project Name: Dry Creek Relief

    Project ID: DRR-1 21

    Location: 28th St and Elkhorn Blvd to 28th St and Scotland Dr

    Description of Facility: 42-inch gravity pipeline

    Length: 8,703 ft.

    Design Capacity: 24 to 28 mgd

    Project Justification: Category A: Required for relief of Dry Creek Interceptor

    Primary Construction Method: Open Cut

    Special Considerations:

    Base Construction Cost: $4,210,244

    Special Structures: $197,472Traffic Control: $126,307

    Environmental Mitigation: -Right-of-Way: -

    Special Construction/Pipe Jack: -Contingency: $1,133,506

    Total Construction Cost $5,667,529

    Engineering/Admin/Legal Costs: $1,416,882

    Total Capital Cost: $7,084,412

    DRR-1 10/13/20006:16 PM

  • DRR.xls 10/13/2000

    Dry Creek Relief

    40

    50

    60

    70

    80

    90

    100

    110

    0+00 10+00 20+00 30+00 40+00 50+00 60+00 70+00 80+00

    Station

    Elev

    atio

    n

    42"

    28th Street

    Dry Creek Relief Junction Structure

    42"

    Dry

    Cre

    ek M

    H 2

    0300

    918

  • SRCSD Master Plan 2000Project Summary

    Project Name: Upper Northwest Section 7

    Project ID: UNW-7 22

    Location: Elkhorn Blvd and Don Julio Blvd to Van Maren Pump Station

    Description of Facility: 36-inch force main

    Length: 16,040 ft.

    Design Capacity: 45 mgd

    Project Justification: Category A: Required for relief of Northeast area

    Primary Construction Method: Open Cut

    Special Considerations: Probable dual force main, Crossing Railroad, Roseville Rd, and I-80Traffic control along Elkhorn Blvd, Greenback Ln, and Auburn Blvd

    Base Construction Cost: $6,440,714

    Special Structures: $139,278Traffic Control: $322,036

    Environmental Mitigation: $20,000Right-of-Way: $1,368,330

    Special Construction/Pipe Jack: $488,070Contingency: $1,316,764

    Total Construction Cost $10,095,191

    Engineering/Admin/Legal Costs: $2,523,798

    Total Capital Cost: $12,618,989

    UNW-7 10/13/20006:16 PM

  • Unwi-71 10/13/2000

    Upper Northwest Interceptor- Section 7

    110

    120

    130

    140

    150

    160

    170

    680+20 682+20 684+20 686+20 688+20 690+20 692+20 694+20 696+20 698+20

    Station

    Elev

    atio

    n

    36" FM

    Elkhorn Boulevard

    Ros

    evill

    e R

    oad

    36" FM

    Hill

    sdal

    e B

    oule

    vard

    Bore & JackR

    ailro

    ad C

    ross

    ing

    Don

    Jul

    io T

    rans

    ition

    Str

    uctu

    re

  • Unwi-72 10/13/2000

    Upper Northwest Interceptor- Section 7

    110

    120

    130

    140

    150

    160

    170

    700+00 702+00 704+00 706+00 708+00 710+00 712+00 714+00

    Station

    Elev

    atio

    n

    36" FM

    Elkhorn Boulevard

    36" FM

    And

    rea

    Bou

    leva

    rd

    Util

    ity C

    ross

    ings

  • Unwi-73 10/13/2000

    Upper Northwest Interceptor- Section 7

    80

    90

    100

    110

    120

    130

    140

    150

    160

    715+00 717+00 719+00 721+00 723+00 725+00 727+00 729+00

    Station

    Elev

    atio

    n

    36" FM

    Elkhorn Boulevard

    36" FM

    Diablo Drive

    OlympicWay

    Util

    ity C

    ross

    ings

  • Unwi-74 10/13/2000

    Upper Northwest Interceptor- Section 7

    80

    90

    100

    110

    120

    130

    140

    150

    160

    730+00 732+00 734+00 736+00 738+00 740+00 742+00 744+00

    Station

    Elev

    atio

    n

    36" FM

    36" FM

    I-80 FreewayOlympicWayVerner Avenue

    Bore & Jack

  • Unwi-75 10/13/2000

    Upper Northwest Interceptor- Section 7

    80

    90

    100

    110

    120

    130

    140

    150

    745+00 747+00 749+00 751+00 753+00 755+00 757+00 759+00

    Station

    Elev

    atio

    n

    36" FM

    36" FM

    Greenback LaneVerner Avenue

    Low

    ered

    for

    Util

    ity C

    ross

    ings

  • Unwi-76 10/13/2000

    Upper Northwest Interceptor- Section 7

    70

    80

    90

    100

    110

    120

    130

    140

    760+00 762+00 764+00 766+00 768+00 770+00 772+00 774+00

    Station

    Elev

    atio

    n

    36" FM

    36" FM

    Greenback Lane

    3- 2

    0'x1

    2' B

    ox C

    ulve

    rts

  • Unwi-77 10/13/2000

    Upper Northwest Interceptor- Section 7

    80

    90

    100

    110

    120

    130

    140

    775+50 780+50 785+50 790+50 795+50 800+50

    Station

    Elev

    atio

    n

    36" FM

    36" FM

    Greenback Lane Auburn Boulevard

  • Unwi-78 10/13/2000

    Upper Northwest Interceptor- Section 7

    80

    90

    100

    110

    120

    130

    140

    805+00 807+00 809+00 811+00 813+00 815+00 817+00 819+00 821+00 823+00 825+00

    Station

    Elev

    atio

    n

    36" FM

    36" FM

    Auburn Boulevard Halifax Street

    Box

    Cul

    vert

    Stre

    am C

    ross

    ing

  • Unwi-79 10/13/2000

    Upper Northwest Interceptor- Section 7

    90

    100

    110

    120

    130

    140

    825+00 827+00 829+00 831+00 833+00 835+00 837+00 839+00

    Station

    Elev

    atio

    n

    36" FM

    36" FM

    Halifax Street Westbrook Drive

    FM lowered to avoid conflicts

  • SRCSD Master Plan 2000Project Summary

    Project Name: Van Maren Pump Station

    Project ID: UNW-8 23

    Location: West of Van Maren Dr and Auburn Blvd

    Description of Facility: New pump station

    Length: N/A

    Design Capacity: 45 mgd

    Project Justification: Category A: Required for relief of Northeast area

    Primary Construction Method: Open Cut

    Special Considerations:

    Base Construction Cost: $9,291,636

    Special Structures: -Traffic Control: -

    Environmental Mitigation: $20,000Right-of-Way: $374,400

    Special Construction/Pipe Jack: -Contingency: $1,452,905

    Total Construction Cost $11,138,942

    Engineering/Admin/Legal Costs: $2,784,735

    Total Capital Cost: $13,923,677

    UNW-8 10/13/20006:17 PM

  • SRCSD Master Plan 2000Project Summary

    Project Name: Upper Northwest Interceptor Section 9

    Project ID: UNW-9 24

    Location: Van Maren Pump Station to Old Auburn Rd and Fair Oaks Blvd

    Description of Facility: 36-inch gravity pipeline

    Length: 13,185 ft.

    Design Capacity: 12 to 34 mgd

    Project Justification: Category A: Required to relieve future capacity deficincies inNortheast trunk system

    Primary Construction Method: Open Cut

    Special Considerations: Traffic control along Auburn Blvd, Sunrise Blvd crossing

    Base Construction Cost: $8,682,128

    Special Structures: -Traffic Control: $434,106

    Environmental Mitigation: $50,000Right-of-Way: $691,417

    Special Construction/Pipe Jack: $24,640Contingency: $1,482,344

    Total Construction Cost $11,364,635

    Engineering/Admin/Legal Costs: $2,841,159

    Total Capital Cost: $14,205,793

    UNW-9 10/13/20006:17 PM

  • Unwi-9 10/13/2000

    Upper Northwest Interceptor- Section 9

    90

    110

    130

    150

    170

    190

    210

    840+61 860+61 880+61 900+61 920+61 940+61 960+61 980+61 1000+61

    Station

    Elev

    atio

    n

    36"

    Auburn Boulevard

    Aub

    urn

    Bou

    leva

    rd

    Van

    Mar

    en L

    ane

    36"

    Old Auburn Road

    36"

  • SRCSD Master Plan 2000Project Summary

    Project Name: Lower Northwest Interceptor Section 1

    Project ID: LNW-1 25

    Location: SRWTP to West of Sacramento River

    Description of Facility: 96-inch force main

    Length: 17,917 ft.

    Design Capacity: 275 mgd

    Project Justification: Category B: Required for relief of Northeast area and futureNorth Natomas and West Sacramento development

    Primary Construction Method: Open Cut

    Special Considerations: Crossing Interstate 5, Highway 160, Southern Pacific Railroad,and Sacramento River

    Base Construction Cost: $15,443,727

    Special Structures: -Traffic Control: -

    Environmental Mitigation: $200,000Right-of-Way: $481,517

    Special Construction/Pipe Jack: $1,472,580Contingency: $4,399,456

    Total Construction Cost $21,997,279

    Engineering/Admin/Legal Costs: $5,499,320

    Total Capital Cost: $27,496,599

    LNW-1 10/13/20006:17 PM

  • Lnwi-1 10/13/2000

    Lower Northwest Interceptor- Section 1

    -40

    -30

    -20

    -10

    0

    10

    20

    30

    40

    0+00 20+00 40+00 60+00 80+00 100+00 120+00 140+00 160+00

    Station

    Elev

    atio

    n

    96" FM

    Mor

    rison

    Cre

    ek

    2-72" FM

    Southport Regional Pump Station

    SRWTP Influent Junction Structure

    96" FM

    Sacr

    amen

    to R

    iver

    Lagu

    na C

    reek

    96"FM

    Hw

    y 16

    0

    Inte

    rsta

    te 5

    Rai

    lroad

    Cro

    ssin

    g

  • SRCSD Master Plan 2000Project Summary

    Project Name: Southport Regional Pump Station

    Project ID: SRPS 26

    Location: West of Sacramento River, Northwest of SRWTP

    Description of Facility: New pump station

    Length: N/A

    Design Capacity: 250 mgd

    Project Justification: Category B: Required for relief of Northeast area and futureNorth Natomas and West Sacramento development

    Primary Construction Method:

    Special Considerations: Facility is anticipated to be constructed in phasesPhase 1: 100 mgd Phases 2 & 3: additional 75 mgd each

    Base Construction Cost: $21,000,000

    Special Structures: -Traffic Control: -

    Environmental Mitigation: -Right-of-Way: $150,000

    Special Construction/Pipe Jack: -Contingency: $5,287,500

    Total Construction Cost $26,437,500

    Engineering/Admin/Legal Costs: $6,609,375

    Total Capital Cost: $33,046,875

    SRPS 10/13/20006:17 PM

  • SRCSD Master Plan 2000Project Summary

    Project Name: Lower Northwest Interceptor Section 2

    Project ID: LNW-2 27

    Location: West of Sacramento River to South of Linden Rd

    Description of Facility: 120-inch gravity pipeline

    Length: 41,602 ft.

    Design Capacity: 262 mgd

    Project Justification: Category B: Required for relief of Northeast area and futureNorth Natomas and West Sacramento development

    Primary Construction Method: Open Cut

    Special Considerations: Crossing Willow Point Babel Slough

    Base Construction Cost: $48,189,778

    Special Structures: $1,354,092Traffic Control: $481,898

    Environmental Mitigation: $150,000Right-of-Way: $2,235,807

    Special Construction/Pipe Jack: $1,357,650Contingency: $13,442,306

    Total Construction Cost $67,211,531

    Engineering/Admin/Legal Costs: $16,802,883

    Total Capital Cost: $84,014,414

    LNW-2 10/13/20006:18 PM

  • Lnwi-2 10/13/2000

    Lower Northwest Interceptor- Section 2

    -40

    -30

    -20

    -10

    0

    10

    20

    30

    40

    225+00 275+00 325+00 375+00 425+00 475+00 525+00 575+00Station

    Elev

    atio

    n

    120"

    Riv

    er R

    oad

    120"

    Will

    ow P

    oint

    Bab

    el S

    loug

    h

    Transition Structure

    Sout

    hpor

    t Reg

    iona

    l Pum

    p St

    atio

    n

  • SRCSD Master Plan 2000Project Summary

    Project Name: West Sacramento Collection System Modifications

    Project ID: WSCSM 28

    Location: Throughout West Sacramento Collection System

    Description of Facility: Necessary modifications of collection system to connect to LNWI

    Length: Varies

    Design Capacity: Varies

    Project Justification: Category C: Needed to serve West Sacramento

    Primary Construction Method: Varies

    Special Considerations: Cost estimate to be refined by Lower Northwest Design Report

    Base Construction Cost: $1,282,746

    Special Structures: -Traffic Control: -

    Environmental Mitigation: -Right-of-Way: -

    Special Construction/Pipe Jack: -Contingency: $320,687

    Total Construction Cost $1,603,433

    Engineering/Admin/Legal Costs: $400,858

    Total Capital Cost: $2,004,291

    WSCSM 10/13/20006:18 PM

  • SRCSD Master Plan 2000Project Summary

    Project Name: Lower Northwest Interceptor Section 3

    Project ID: LNW-3 29

    Location: South of Linden Rd to Natomas Pump Station

    Description of Facility: 60 and 84-inch force main

    Length: 43,467 ft.

    Design Capacity: 200 mgd

    Project Justification: Category B: Required for relief of Northeast area and futureNorth Natomas development

    Primary Construction Method: Open Cut

    Special Considerations: Crossing of Sacramento River, I-80, Business 80, Hwy 84, Garden Highway, and West Capitol Ave

    Base Construction Cost: $37,650,335

    Special Structures: -Traffic Control: $1,129,510

    Environmental Mitigation: $200,000Right-of-Way: $5,290,713

    Special Construction/Pipe Jack: $3,773,930Contingency: $12,011,122

    Total Construction Cost $60,055,610

    Engineering/Admin/Legal Costs: $15,013,902

    Total Capital Cost: $75,069,512

    LNW-3 10/13/20006:18 PM

  • LNWI-3a 10/13/2000

    Lower Northwest Interceptor- Section 3a

    -30

    -20

    -10

    0

    10

    20

    30

    40

    595+19 645+19 695+19 745+19 795+19Station

    Elev

    atio

    n

    84" FM

    Lind

    en R

    oad

    84" FM

    Jeffe

    rson

    Bou

    leva

    rd

    Bar

    ge C

    anal H

    ighw

    ay 8

    4

    Bus

    ines

    s 80

    Wes

    t Cap

    itol A

    venu

    e

  • LNWI-3b 10/13/2000

    Lower Northwest Interceptor- Section 3b

    -30

    -20

    -10

    0

    10

    20

    30

    40

    814+94 864+94 914+94 964+94 1014+94Station

    Elev

    atio

    n

    84" FM

    Nat

    omas

    Pum

    p St

    atio

    n

    84" FM

    Sacr

    amen

    to R

    iver

    Wes

    t Dra

    inag

    e C

    anal

    2-60" FM

    Inte

    rsta

    te 8

    0

    Gar

    den

    Hig

    hway

  • SRCSD Master Plan 2000Project Summary

    Project Name: Natomas Pump Station Expansion

    Project ID: NNPS 30

    Location: Natomas Pump Station Site

    Description of Facility: 175 mgd Pump Station

    Length: N/A

    Design Capacity: 175 mgd

    Project Justification: Category B: Required for relief of Northeast area and futureNorth Natomas development

    Primary Construction Method:

    Special Considerations: Facility is anticipated to be constructed in phasesPhase 1: 100 mgd Phase 2: additional 75 mgd

    Base Construction Cost: $13,500,000

    Special Structures: -Traffic Control: -

    Environmental Mitigation: -Right-of-Way: -

    Special Construction/Pipe Jack: -Contingency: $3,375,000

    Total Construction Cost $16,875,000

    Engineering/Admin/Legal Costs: $4,218,750

    Total Capital Cost: $21,093,750

    NNPS 10/13/20006:21 PM

  • SRCSD Master Plan 2000Project Summary

    Project Name: South Interceptor Section 1

    Project ID: SO-1 31

    Location: SRWTP to Laguna Blvd

    Description of Facility: 54-inch gravity pipeline

    Length: 8,886 ft.

    Design Capacity: 43 mgd

    Project Justification: Category C: Capacity required to serve new development in the south area

    Primary Construction Method: Open Cut

    Special Considerations: Crossing Laguna Blvd and Railroad

    Base Construction Cost: $3,670,898

    Special Structures: -Traffic Control: -

    Environmental Mitigation: $200,000Right-of-Way: $1,602,374

    Special Construction/Pipe Jack: $69,800Contingency: $1,385,768

    Total Construction Cost $6,928,840

    Engineering/Admin/Legal Costs: $1,732,210

    Total Capital Cost: $8,661,050

    SO-1 10/13/20006:21 PM

  • sintusb1.xls 10/13/2000

    South Interceptor- Section 1

    -20

    -10

    0

    10

    20

    30

    40

    0+00 10+00 20+00 30+00 40+00 50+00 60+00 70+00 80+00

    Station

    Elev

    atio

    n

    54"

    Southern Pacific Railroad

    Lagu

    na B

    lvd

    Lagu

    na E

    xten

    sion

    Junc

    tion

    Stru

    ctur

    e

  • SRCSD Master Plan 2000Project Summary

    Project Name: South Interceptor Section 2 and South Interceptor Pump Station

    Project ID: SO-2 32

    Location: Laguna Blvd to Franklin Blvd South of Elk Grove Blvd

    Description of Facility: 54-inch gravity pipeline, 36-inch force main

    Length: 8,032 ft.

    Design Capacity: 43 mgd

    Project Justification: Category C: Capacity required to serve new development in the south area

    Primary Construction Method: Open Cut

    Special Considerations: Crossing Elk Grove Blvd and Railroad

    Base Construction Cost: $10,445,371

    Special Structures: -Traffic Control: -

    Environmental Mitigation: $50,000Right-of-Way: $3,066,489

    Special Construction/Pipe Jack: $108,400Contingency: $3,417,565

    Total Construction Cost $17,087,825

    Engineering/Admin/Legal Costs: $4,271,956

    Total Capital Cost: $21,359,781

    SO-2 10/13/20006:22 PM

  • sintusb2 10/13/2000

    South Interceptor- Section 2

    -10

    -5

    0

    5

    10

    15

    20

    25

    30

    35

    40

    88+90 98+90 108+90 118+90 128+90 138+90 148+90 158+90 168+90

    Station

    Elev

    atio

    n

    36" FM54"

    Elk G

    rove

    Bou

    leva

    rd

    Southern Pacific Railroad

  • SRCSD Master Plan 2000Project Summary

    Project Name: South Interceptor Section 3

    Project ID: SO-3 33

    Location: Bruceville Rd to Franklin Blvd South of Elk Grove Blvd

    Description of Facility: 36, 48, and 54-inch gravity pipeline

    Length: 20,168 ft.

    Design Capacity: 13 to 31 mgd

    Project Justification: Category C: Capacity required to serve new development in the south area

    Primary Construction Method: Open Cut

    Special Considerations: Traffic control for construction in Franklin BlvdCrossing Bruceville Rd

    Base Construction Cost: $8,984,360

    Special Structures: -Traffic Control: $89,844

    Environmental Mitigation: -Right-of-Way: $2,621,576

    Special Construction/Pipe Jack: -Contingency: $2,923,945

    Total Construction Cost $14,619,725

    Engineering/Admin/Legal Costs: $3,654,931

    Total Capital Cost: $18,274,656

    SO-3 10/13/20006:22 PM

  • sintusb3 10/13/2000

    South Interceptor- Section 3

    -20

    -10

    0

    10

    20

    30

    40

    169+00 219+00 269+00 319+00 369+00

    Station

    Elev

    atio

    n

    54"

    39"

    48"

    Bru

    cevi

    lle R

    oad

    Franklin Blvd

  • SRCSD Master Plan 2000Project Summary

    Project Name: Laguna Creek Interceptor Section 1

    Project ID: LC-1 34

    Location: SRWTP to Big Horn Blvd

    Description of Facility: 102-inch gravity pipeline

    Length: 13,297 ft.

    Design Capacity: 183 mgd

    Project Justification: Category C: Required for future service to east county area

    Primary Construction Method: Open Cut

    Special Considerations: Wetlands mitigation for construction in Laguna Creek, CrossingFranklin Blvd and Bruceville Rd, Tunnel under wetlands at SRWTP

    Base Construction Cost: $12,086,807

    Special Structures: $533,636Traffic Control: $120,868

    Environmental Mitigation: $400,000Right-of-Way: $2,108,732

    Special Construction/Pipe Jack: $647,900Contingency: $3,974,485

    Total Construction Cost $19,872,427

    Engineering/Admin/Legal Costs: $4,968,107

    Total Capital Cost: $24,840,534

    LC-1 10/13/20006:22 PM

  • Lci-1 10/13/2000

    Laguna Creek Interceptor- Section 1

    -30

    -20

    -10

    0

    10

    20

    30

    40

    50

    0+00 20+00 40+00 60+00 80+00 100+00 120+00

    Station

    Elev

    atio

    n

    102"

    102"

    Lagu

    na E

    xten

    sion

    Jun

    ctio

    n St

    ruct

    ure

    Fran

    klin

    Bou

    leva

    rd

    Bru

    cevi

    lle R

    oad

    42" Elk Grove Trunk

    Elk Grove Trunk Bypass

  • SRCSD Master Plan 2000Project Summary

    Project Name: Laguna Creek Interceptor Section 2

    Project ID: LC-2 35

    Location: Bruceville Rd North of Big Horn Blvd to Waterman Rd North of Bond Rd

    Description of Facility: 96 and 106-inch gravity pipeline

    Length: 20,092 ft.

    Design Capacity: 170 to 183 mgd

    Project Justification: Category C: Required for future service to east county area

    Primary Construction Method: Open Cut

    Special Considerations: Wetlands mitigation for construction in Laguna Creek, Tunneling underWaterman Ridge, Crossing Hwy 99, Elk Grove Florin Rd, Railroad

    Base Construction Cost: $20,131,699

    Special Structures: $1,225,522Traffic Control: $201,317

    Environmental Mitigation: $400,000Right-of-Way: $4,411,690

    Special Construction/Pipe Jack: $2,236,000Contingency: $7,151,557

    Total Construction Cost $35,757,785

    Engineering/Admin/Legal Costs: $8,939,446

    Total Capital Cost: $44,697,232

    LC-2 10/13/20006:23 PM

  • Lci-2 10/13/2000

    Laguna Creek Interceptor- Section 2

    -10

    0

    10

    20

    30

    40

    50

    60

    70

    132+97 182+97 232+97 282+97 332+97

    Station

    Elev

    atio

    n

    102"

    96"H

    ighw

    ay 9

    9

    Stoc

    kton

    Bou

    leva

    rd

    Elk

    Gro

    ve- F

    lorin

    Roa

    d

    Waterman Ridge

    Wat

    erm

    an R

    oad

    Rai

    lroad

    Cro

    ssin

    g

    Dee

    r Cre

    ek J

    unct

    ion

    Stru

    ctur

    e

  • SRCSD Master Plan 2000Project Summary

    Project Name: Laguna Creek Interceptor Section 3

    Project ID: LC-3 36

    Location: Waterman Rd North of Bond Rd to Excelsior Rd South of Gerber Rd

    Description of Facility: 72, 78, and 84-inch gravity pipeline

    Length: 26,421 ft.

    Design Capacity: 131 to 149 mgd

    Project Justification: Category C: Required for future sevice to east county area

    Primary Construction Method: Open Cut

    Special Considerations: Wetlands mitigation for construction in Laguna Creek, RR Crossing,Traffic control for construction in Bradshaw Rd and Excelsior Rd

    Base Construction Cost: $18,310,104

    Special Structures: -Traffic Control: $183,101

    Environmental Mitigation: $200,000Right-of-Way: $4,234,762

    Special Construction/Pipe Jack: $140,250Contingency: $5,767,054

    Total Construction Cost $28,835,271

    Engineering/Admin/Legal Costs: $7,208,818

    Total Capital Cost: $36,044,089

    LC-3 10/13/20006:23 PM

  • Lci-3 10/13/2000

    Laguna Creek Interceptor- Section 3

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    333+89 383+89 433+89 483+89 533+89 583+89

    Station

    Elev

    atio

    n

    72"

    84"

    Shel

    don

    Roa

    d

    Cal

    vine

    Roa

    d

    Bra

    dsha

    w R

    oad

    Exce

    lsio

    r Roa

    d

    78"

    15" TrunkInv=33.81

    Rai

    lroad

    Cro

    ssin

    g

    Dee

    r Cre

    ek J

    unct

    ion

    Stru

    ctur

    e

  • SRCSD Master Plan 2000Project Summary

    Project Name: Laguna Creek Interceptor Section 4

    Project ID: LC-4 37

    Location: Excelsior Rd South of Gerber Rd to Sunrise Blvd South of Jackson Hwy

    Description of Facility: 66, 72, 78-inch gravity pipeline

    Length: 22,297 ft.

    Design Capacity: 97 to 143 mgd

    Project Justification: Category C: Required for future service to east county area

    Primary Construction Method: Open Cut

    Special Considerations: Wetlands mitigation for construction in Laguna CreekCrossing Folsom South Canal and Florin Rd

    Base Construction Cost: $12,941,595

    Special Structures: -Traffic Control: -

    Environmental Mitigation: $100,000Right-of-Way: $77,538

    Special Construction/Pipe Jack: -Contingency: $3,279,783

    Total Construction Cost $16,398,916

    Engineering/Admin/Legal Costs: $4,099,729

    Total Capital Cost: $20,498,645

    LC-4 10/13/20006:23 PM

  • Lci-4 10/13/2000

    Laguna Creek Interceptor- Section 4

    40

    50

    60

    70

    80

    90

    100

    110

    120

    130

    140

    598+09 648+09 698+09 748+09 798+09Station

    Elev

    atio

    n

    78"

    72"

    Fols

    om S

    outh

    Can

    al

    66"

    Eagl

    e's

    Nes

    t R

    oad

    Flor

    in R

    oad

    66"

  • SRCSD Master Plan 2000Project Summary

    Project Name: Laguna Creek Interceptor Section 5

    Project ID: LC-5 38

    Location: Sunrise Blvd South of Jackson Hwy to end of pipe East of Sunrise Blvd

    Description of Facility: 66-inch gravity pipeline

    Length: 6,208 ft.

    Design Capacity: 97 to 102 mgd

    Project Justification: Category C: Required for future service to east county area

    Primary Construction Method: Open Cut

    Special Considerations: Wetlands mitigation for constuction in Laguna CreekCrossing Jackson Hwy and Sunrise Blvd

    Base Construction Cost: $2,847,151

    Special Structures: -Traffic Control: -

    Environmental Mitigation: $100,000Right-of-Way: $18,605

    Special Construction/Pipe Jack: $510,600Contingency: $869,089

    Total Construction Cost $4,345,444

    Engineering/Admin/Legal Costs: $1,086,361

    Total Capital Cost: $5,431,805

    LC-5 10/13/20006:23 PM

  • Lci-5 10/13/2000

    Laguna Creek Interceptor- Section 5

    80

    90

    100

    110

    120

    130

    140

    821+06 831+06 841+06 851+06 861+06 871+06 881+06

    Station

    Elev

    atio

    n

    Lagu

    na C

    reek

    66"

    Hw

    y 16

    Sunr

    ise

    Bou

    leva

    rd

    Aer

    ojet

    Inte

    rcep

    tor S

    ectio

    n 4

    (Dro

    p St

    ruct

    ure)

  • SRCSD Master Plan 2000Project Summary

    Project Name: Deer Creek Interceptor Section 1

    Project ID: DC-1 39

    Location: Waterman Rd North of Bond Rd to Wilton Rd and Deer Creek

    Description of Facility: 60-inch gravity pipeline

    Length: 23,167 ft.

    Design Capacity: 43 to 48 mgd

    Project Justification: Category C: Required for future service to southeast county

    Primary Construction Method: Open Cut

    Special Considerations: Traffic control for construction in Bond Rd, Grant Line Rd, andWilton Rd

    Base Construction Cost: $15,100,484

    Special Structures: -Traffic Control: $453,015

    Environmental Mitigation: $50,000Right-of-Way: $674,135

    Special Construction/Pipe Jack: -Contingency: $4,069,408

    Total Construction Cost $20,347,041

    Engineering/Admin/Legal Costs: $5,086,760

    Total Capital Cost: $25,433,802

    DC-1 10/13/20006:24 PM

  • Dci-1