Bunker Lease 35,000$ One-time payment
Ground Lease 1,000$ Annual payment
36,000$
Labor Rate: 20.00$
Construction Materials Only Labor Hours Labor Total
Concrete Floor Prep/Level 300$ 16 320$
Concrete Block Engine Room 400$ 32 640$
Steel Engine Room Door 1 250$ 4 80$
Paint Entire Dome/Door/Numbers 500$ 20 400$
Floor Covering 2,700$ 12 240$
Racking System 6,000$ 24 480$
Attic Sheathing 26 780$ 16 320$
Paint Rack Ceilings 200$ 5 100$
Doors & Hardware 12 2,000$ 24 480$
Electrical Assort 800$ 40 800$
Plumbing Assort 800$ 40 800$
Showers & Valves 1,000$ 12 240$
Wall Paneling 74 2,220$ 40 800$
Cut Arch Paneling (bulk) 6 120$
Vanity w/Sink & Faucet 2 800$ 3 60$
Kitchen Cabinets & Counter 4,000$ 60 1,200$
Kitchen Sink & Faucet 300$ 2 40$
Lighting 1,000$ 24 480$
Hardware (bolts/nuts/screws) 600$
Shipping 2,000$ 10 200$
Misc 2,000$ 100 2,000$
28,650$ 490$ 9,800$
Mechanical & Equipment Materials Only Labor Hours Labor Total
Water Connection To Vivos Well 1 3,000$ -$
Diesel Generator 6.5kW 1 6,000$ 6 120$
Diesel Fuel 55 Gal Drums 18 1,980$ 3 60$ Plus Fuel
Drum Fuel Line Kit 1 180$ 1 20$
Batteries AGM (1200 AMPs) 6 3,300$ 3 60$
Charger/Inverter 3000w 1 1,100$ 3 60$
Chimney Vents & Plates 1 300$ 4 80$
Blast Door Seal, Lock Bars, Jack, Escape Plate 1 400$ 8 160$
Hot Water Heater 1 300$ 2 40$
Water Pressure Pump 1 250$ 2 40$
Water Filter / Osmosis 1 200$ 2 40$
Water Holding Tank (100 gal) 1 300$ 2 40$
Compost Toilet 2 2,800$ 4 80$
Grey Water Filtration System 1 800$ 4 80$
NBC System w/ Blast Valves 1 3,000$ 8 160$
Geothermal Heating and Cooling 1 6,000$ 24 480$ Plus Vertical Drilling
Misc 2,000$ 50 1,000$
31,910$ 126 2,520$
Total Construction and Outfitting 60,560$ 12,320$
72,880$