VISHVVEER 44766

download VISHVVEER 44766

of 30

Transcript of VISHVVEER 44766

  • 8/17/2019 VISHVVEER 44766

    1/30

    GaGanttntt PERPER

    TT

    &

  • 8/17/2019 VISHVVEER 44766

    2/30

    TT WHAT ISSCHEDULING ?

    Scheduling refers to-

    1.Determination of rate at which the work shallbe performed in order to its priority.

    2.Determination of proper times when work willbe released to the plant

    3.Determination of proper sequence

    2

  • 8/17/2019 VISHVVEER 44766

    3/30

    TECHNIQUES FORSCHEDULING

     GRA!"#A$ %&'!(D

     A$G&)RA"# %&'!(D

      %(D" %&'!(D

     $"*&AR R(GRA%%"*G

    3

  • 8/17/2019 VISHVVEER 44766

    4/30

    WHAT ARE THE?

     'hese are tools to+

    mana,e the tasks inoled in bi, and

    comple pro/ects let pro/ect mana,ers or,anise time0

    people0 equipment and money

    ensure the ri,ht people and equipment arein the ri,ht place and the ri,ht time

    allow mana,ers to monitor the pro,ress ofa pro/ect

    4

  • 8/17/2019 VISHVVEER 44766

    5/30

    5

    Henry Laurence Gantt (1861-1919) 

    Gantt

    Charts

  • 8/17/2019 VISHVVEER 44766

    6/30

    !"'(RDesi,ned by !"# HENR LGANTT in 990 to meet therequirements of army for

    an improed method of

    lannin, 4 #ontrollin, theproduction of ordnance

    factories.6

  • 8/17/2019 VISHVVEER 44766

    7/30

    "*'R(D#'"(*Displays the schedule as wellas makes a comparision

    between actual performance4 ori,inal schedule.

    7

  • 8/17/2019 VISHVVEER 44766

    8/30

    %A5"*G

    AGA*''#!AR'

    8

  • 8/17/2019 VISHVVEER 44766

    9/30

    tep 1 6 $ist the tasks in the pro/ect

    9

  • 8/17/2019 VISHVVEER 44766

    10/30

    tep 2 6 Add task durations

    10

  • 8/17/2019 VISHVVEER 44766

    11/30

    tep 3 6 Add dependencies 7which taskscannot start before another task 8nishes9

    11

  • 8/17/2019 VISHVVEER 44766

    12/30

    "%(R'A*' ("*'

    12

    •The arrows indicate dependencies.

    •Tas 1 is a predecessor  o! tas 2 " i.e. tas 2 cannot start #e!ore tas 1 ends.

    •Tas 3 is dependent on tas 2. Tas 7 is de$endent on two other tass

    •%&ectrics' $&#in* and &andsca$in* are concurrent tass and can ha$$en at

    the sae tie' so the+ o,er&a$ on the chart. && 3 can start a!ter tas 4 ends.

    •aintin* st wait !or #oth e&ectrics and $&#in* to #e !inished.

    •Tas 9 has /ero dration' and is a milestone

  • 8/17/2019 VISHVVEER 44766

    13/30

    tep : 6 ;ind the c"itical $ath

    13

    The critica& $ath is the seence o! tass !ro #e*innin* to end that taes

    the longest time to co$&ete.

    t is a&so the shortest possible time that the $roect can #e !inished in.

     n+ tas on the critica& $ath is ca&&ed a critical task.

    o critica& tas can ha,e its dration chan*ed withot a!!ectin* the end

    date o! the $roect.

  • 8/17/2019 VISHVVEER 44766

    14/30

     'he len,th of the critical path is the sum of

    the len,ths of all critical tasks 7the red tasks102030:03>1>1.2>1 ?1@.< days.

    "n other words0 the minimum amount oftime required to ,et all tasks completed is1@.< days

     'he other tasks 70B9 can each run oer-time

    before aCectin, the end date of the pro/ect 14

  • 8/17/2019 VISHVVEER 44766

    15/30

     'he amount of time a task can be etendedbefore it aCects other tasks is called slack  7orfoat 9.

     'ask can take an etra day and a half

    before it aCects the pro/ects end date0 soeach has %#& da'() )lac* .

    #ritical tasks0 by de8nition0 can hae *(slack.

    15

  • 8/17/2019 VISHVVEER 44766

    16/30

    Can task X’s duration

    be changed withoutaecting the end date

    o the project ?If it is a critical task the answeris always

    NOE

    16

  • 8/17/2019 VISHVVEER 44766

    17/30

    17

    %TCharts

  • 8/17/2019 VISHVVEER 44766

    18/30

    "*'R(D#'"(*tands for P"+g"a, E-aluati+nRe-ie. Techni/ue

    how order of actiities ordependencies between actiities

    18

  • 8/17/2019 VISHVVEER 44766

    19/30

    &R' charts

    19

    This %T chart !o&&ows the cti,it+ on rrow st+&e.

    •The tass are shown #+ arrows. Tas nae are shown #+ &etters'

    in this case.

    •The circ&es are ca&&ed nodes. The nodes indicate the start  or end  o!

    tass.

    •Tas drations are the shown #+ the n#ers.

  • 8/17/2019 VISHVVEER 44766

    20/30

    20

      %T %:

  • 8/17/2019 VISHVVEER 44766

    21/30

    1+ Fhich tasks are on the critical path2+ Fhat is the slack time for tasks #0 D and G

    3+ 'ask # is delayed by one day. Fhat impact wouldthis hae on the completion date of the pro/ectFhy

    :+ 'ask A will be delayed by 2 days because someequipment has arried late. "f the pro/ect mana,erwants to 8nish the pro/ect on time he will need toshorten the duration of one or more of the tasks.!ow can he achiee this

  • 8/17/2019 VISHVVEER 44766

    22/30

    1+ Fhich tasks are on the critical path

    22

    ANSWER A!"!#!$!%

    ossi#&e $aths; ''C'%' < 2=3=1=4=3 < 13 da+s

     ''>'?' < 2=3=3=3=3 < 14 da+s

     'G'@' < 2=2=5=3 < 12 da+s

  • 8/17/2019 VISHVVEER 44766

    23/30

    2+ Fhat is the slack time for tasks # and G

    23

    ath C'% <  da+s' ath >'? < ' da+s

    ath 'C'% < ( da+s. ath ' >' ? < ) da+s

    ath G' @ < * da+s.

    #i++erence ,slack- . / day +or tasks 0 or E

    compared to #!$

    So G or H ha1e 2 days3 slack between them4

    "!0 or E ha1e / day3s slack4

    "!#!$ ha1e no slack4

    5AS6S 07

    5AS6 G7

  • 8/17/2019 VISHVVEER 44766

    24/30

    3+ 'ask # starts one day late. Fhat impactwould this hae on the completion date of thepro/ect Fhy

    24

    No impact! because task 0 has

    one day3s slack

  • 8/17/2019 VISHVVEER 44766

    25/30

    :+ 'ask A will be delayed by 2 days because someequipment has arried late. "f the pro/ect mana,er stillwants to 8nish the pro/ect within the ori,inal time frame0he will need to shorten the time for one or more of thetasks. Fhat steps can he take to reduce the number ofdays allocated to a task

    25

    5he answer has N85H%NG to do with the

    chart9 :ust say how ;obs can be +inishedmore

  • 8/17/2019 VISHVVEER 44766

    26/30

  • 8/17/2019 VISHVVEER 44766

    27/30

    ESTI!ATION OFACTI0IT TI!E

    "n &R'0 these three estimate times are deried foreach actiity.

    OPTI!ISTIC TI!E 1to9

    "t is the shortest possible time in which an actiitycan be completed.

    !OST LI2EL TI!E 1tm9

    "t is the time in which the actiity is normally

    epected to complete under normal contin,encies.PESSI!ISTIC TI!E 1tp)

    "t is the maimum time required to complete anactiity.

    27

  • 8/17/2019 VISHVVEER 44766

    28/30

    ESTIMATED TIME

     

    te = to + (4 x tm) + tp

    6

    STANDARD DEVIATION=S

    t

    = (t

    p

    - t

    o

    )/6

    VARIANCE=

    V

    t

      = [(t

    p

    - t

    o

    )/6

    !

     = (S

    t

    )

    !

     

    28

  • 8/17/2019 VISHVVEER 44766

    29/30

    I" t

     

    = #$ t

     

    = 6 % t

    p

    = &$t'e

    *+- ) Expe,te+ T*me

    !) St+.+ De*t*o

    ) V.*,e

    29

    ANS1ER2

     te = 6

     S

    t

     = /6

     V

    t

     = /6

  • 8/17/2019 VISHVVEER 44766

    30/30

     '!A*5  (

    30