VIRGINIA Class, OHIO Replacement Submarines & Ford … · VIRGINIA Class, OHIO Replacement...
Transcript of VIRGINIA Class, OHIO Replacement Submarines & Ford … · VIRGINIA Class, OHIO Replacement...
VIRGINIA Class, OHIO Replacement Submarines & Ford Class Carriers Supplier Conference
#2532 06-14-16 Pg 2
Agenda
1. Introduction, Welcome & Purpose
2. Introduction/Discussion of Shipbuilding Plan
3.Discussion of SUBS Team Efforts
4.Submarine Industrial Base Council Overview
5.VCS, OR and CVN Contract Timelines
6.Shipbuilder Lessons Learned
7.Proposal Content
8.Shipbuilder-Supplier Session
#2532 06-14-16 Pg 3
1. Introduction, Welcome & Purpose
Blair Decker, EB
Rob Hogan, NNS
RADM Jabaley, PEO SUBS
Click to edit Master title style
4
Opportunity and Challenge
Exponential Increase in Demand for Material
Single VIRGINIA SSN 7,800 LT
2 VIRGINIA SSN per year 15,600 LT
2 VIRGINIA SSN per year w/ VPM and AS 20,400 LT
CY 2010–2021
2 VIRGINIA SSN per year w/ VPM & AS +OHIO Replacement SSBN 41,200 LT
Su
bm
ari
ne
Bu
ild
Rate
#2532 06-14-16 Pg 5
2. Introduction/Discussion of
Shipbuilding Plan
CAPT Oglesby, CVN Program
CAPT Stevens, VIRGINIA Class Program
CAPT Goggins, OR Program
#2532 06-14-16 Pg 6
CVN Program
CAPT Oglesby
6/21/2016 CVN 79/80 Program Office 7 For Official Use Only
Aircraft Carrier Programs
CAPT Doug Oglesby
CVN 79/80 Program Manager, PMS 379
For Official Use Only
Supplier’s Conference
14 June 2016
NAVSEA: Statement A: Approved for Release. Distribution is unlimited.
6/21/2016 CVN 79/80 Program Office 8 For Official Use Only
Mission:
Deliver Aircraft Carriers
on time, ready for tasking,
at an affordable cost
New
Construction
RCOH
Maintenance &
Modernization
Inactivation
PEO Aircraft Carriers
PEO Carriers Portfolio
NAVSEA: Statement A: Approved for Release. Distribution is unlimited.
6/21/2016 CVN 79/80 Program Office 9 For Official Use Only
GERALD R. FORD Class Focused Investment
GERALD R. FORD Class Ushers in the
Next Generation of Capability, including:
Increased Capability
33% increase in Sortie
Generation Rates
Increased space for flight deck
operations and aircraft
maintenance
Increased Flexibility
Nearly 3 times the electric plant
capacity
Restored weight and stability
service life allowances
Increased Affordability
Reduced manning and 20%
reduction in maintenance costs
Designed for 43-month
maintenance cycle and 12-year
docking intervals
NAVSEA: Statement A: Approved for Release. Distribution is unlimited.
6/21/2016 CVN 79/80 Program Office 10 For Official Use Only
Significant Events
Feb 2011 – CVN 79 Steel Cutting Ceremony
Jun 2015 – DD&C Contract Awarded
Aug 2015 – Keel Laying Ceremony
Jun 2017 – 50% Erected
Apr 2018 – 75% Erected
May 2019 – Island Loaded
Feb 2020 – Launch
Jun 2022 – Delivery
JOHN F. KENNEDY (CVN 79) Status
(Clockwise from top left):
CVN 79 Steel Cutting Ceremony, 25 Feb 2011.
CVN 79 Keel Laying, 22 Aug 2015. Joseph P. Kennedy III signs the keel unit before
the ceremony.
CVN 79’s Aft Pump Room Being Set in Place – 60,000 More Hours of Pre-Outfitting
than CVN 78.
965 Ton Aft Pump Room Superlift Being Moved to Dry-Dock. (Photos courtesy of HII-NNS)
NAVSEA: Statement A: Approved for Release. Distribution is unlimited.
6/21/2016 CVN 79/80 Program Office 11 For Official Use Only
ENTERPRISE (CVN 80) Status
Background: CVN 80 replaces CVN 69 (FY2027 inactivation)
2 years of Advance Procurement (AP) funding (FY16-17)
followed by 6 years of Full Funding (FY18-23)
No advance construction planned
Intend to perform some limited long lead time fabrication
in FY 2017 as an overall cost reduction
Single phase delivery (two-phase delivery is unique to
CVN 79)
CVN 80 expected to continue downward trend in labor
hours (Engineering & Production)
Status: Design for Affordability efforts initiated
Long-Lead Time Material (LLTM) Procurement technical
assessment review in process
Significant Events 2015 – Initial funding for Affordability Initiatives
May 2016 – Advance Procurement (AP) & Long Lead Time Material (LLTM) Awarded
2016 - 2017 – Further LLTM Contract Awards
2018 – First year of Full Funding, award Detail Design and Construction (DD&C) Contract
2021 – Keel Laying
2025 – Launch
2027 – Delivery
NAVSEA: Statement A: Approved for Release. Distribution is unlimited.
6/21/2016 CVN 79/80 Program Office 12 For Official Use Only
Carrier Force Structure Sustainment PB17 Aircraft Carrier Delivery and Inactivation Plan
Steady-state production of FORD Class Carriers on 5 year centers
NIMITZ - class
FORD - class
NAVSEA: Statement A: Approved for Release. Distribution is unlimited.
6/21/2016 CVN 79/80 Program Office 13 For Official Use Only
The Challenge
Budgetary Pressures
Congress continues to apply pressure to the Navy’s budget
Navy’s 30-year shipbuilding plan:
Stresses the budget considerably and
Doesn’t fully support the 308 ship Navy
The solution is not squeezing the suppliers; nor is it reducing ship capabilities
Together we must find opportunities in the challenge to capitalize on the
higher volume of ship construction coming from all programs
Economic order quantities
More efficient production runs
Cross-programmatic thinking
Alignment of requirements
Level loading manufacturing through longer term planning
NAVSEA: Statement A: Approved for Release. Distribution is unlimited.
#2532 06-14-16 Pg 14
VIRGINIA Class Program
CAPT Stevens
Click to edit Master title style
15
• Block V (FY19-23 ships) – Planned award Oct 2018 – Up to 10 ships – Multi-Year Procurement (MYP) contract with Economic Order Quantity (EOQ)
– Includes VIRGINIA Payload Module (VPM) and Acoustic Superiority (AS)
• VPM – Increases Tomahawk strike capability – Insertion in FY19-2 and all follow-on Block V ships
– PB17 includes VPM Detail Design and Contractor Furnished Equipment (CFE) Long Lead Time Material
(LLTM)
• AS – Addresses CNO’s undersea dominance mandate – PB17 includes RDT&E funding for SOUTH DAKOTA Insertion Program (SDIP) and AS for Block V
VIRGINIA Class Submarines (VCS)
– Detail Design of Large Vertical Array & Coatings planned for completion in FY17
– PCU SOUTH DAKOTA (SSN 790) will be outfitted and tested during FY18/19 PSA
• VPM and AS represent increased design and construction workload for the industrial
base in the near-term and construction workload beginning in FY19
VIRGINIA Class Block V and Beyond
VIRGINIA Class The Right Submarine for Today with Flexibility for the Future
Design for Affordability (2 VA per year) Blocks I & II (FY98–08) – SSNs 774 – 783 Block III (FY09–13) – SSNs 784 – 791
Block IV (FY14–18) – SSNs 792 – 801 Block V (FY19–23) – SSNs 802 – and later
VPM (beginning with 19-2 ship) and AS increase undersea influence effects
Increase in platform capability
Block I & II
Bow Design
12 VLS Tubes
Block III and later
2 VIRGINIA
Payload Tubes
10 Ships Delivered 8 Ships – 2 Delivered, 6 Under Construction
10 Ships – 5 Under Construction, 5 Under Contract In Design Phase, FY19 Construction Start
RTOC enables increased Ao per hull
16
Block V Overview
• Planned award in early FY 2019 – PB18 Request for Multi-year Approval
– Up to 10 ships, FY19 – FY23
– Fixed Price Incentive contract
– 2 year AP starts in FY17
• Incorporation of VPM to increase undersea strike capacity and AS to pace the threat into
baseline VA
• Will take advantage of MYP with EOQ procurement (CFE & GFE)
• Adequate subcontractor proposals necessary to streamline contracting timeline and
improve responsiveness amongst all parties
Advance Procurement and Economic Order Quantity Funding Critical to Successfully Maintaining Two-Per Year Delivery Cadence
17
FY19 FY20 FY21 FY22 FY23
2 2 1* 2 2
Block V - PB17 Build Profile
*Evaluating a 2nd ship
Click to edit Master title style
18
Increasing Submarine Build Rate with
Increasing Complexity
• Single SSN – 7,800 LT
• Two SSNs – 15,600 LT
• Two SSNs with VPM and AS – 20,400 LT
• Two SSNs with VPM and AS and OHIO
Replacement SSBN – 41,200 LT
• Hydraulic power plant pump demand
across the submarine enterprise will
increase by approximately 43% between
2018 and 2021 to support VIRGINIA with
VPM and OR
Click to edit Master title style
19
06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45
B1 B2 B3 B4 B5 B6 B7 B8 B9 B10 B11 B12
X3 X5 X7 X9 X12 X15 X18
X1 X2 X4 X6 X8 X10 X11 X13 X14 X16 X17 X19
802 804 807 809 817 818 819 820 821
786 788 790 803 805 806 808 810 812
784 785 787 789 791 792 794 796 798 800 811 813 814 815 816
781 782 783 793 795 797 799 801
53 53 54 54 55 54 53 50 52 50 51 51 48 49 48 47 45 44 42 41 42 43 43 44 45 46 47 48 47 47 47 47 49 49 50 50
784782 783 783 785
780 781 781 782 782 784 787779 780 780 781 781 783 786 791778 779 779 780 780 782 785 790 795 797777 778 778 779 779 781 784 789 789 792 794 796 X10 X11776 777 777 778 778 780 783 788 788 791 793 795 801 X6 X8 X9 X10775 776 776 777 777 779 782 787 787 790 792 794 799 800 803 820 X5 X7 X8 X9774 775 775 776 776 778 781 786 786 789 791 793 798 799 802 805 819 819 821 X1 X2 X4 X4 X6 X7 X823 774 774 775 775 777 780 785 785 788 790 792 797 798 801 804 818 818 818 820 821 X1 X3 X3 X5 X6 X722 23 23 774 774 776 779 784 784 787 789 791 796 797 800 803 806 817 817 817 817 819 820 821 X2 X2 X4 X5 X621 22 22 23 23 775 778 783 783 786 788 790 795 796 799 802 805 808 816 816 816 816 816 818 819 820 X1 X1 X3 X4 X5773 21 21 22 22 774 777 782 782 785 787 789 794 795 798 801 804 807 814 815 815 815 815 815 815 817 818 819 821 821 X2 X3 X4772 773 773 21 21 23 776 781 781 784 786 788 793 794 797 800 803 806 810 813 813 814 814 814 814 814 814 816 817 818 820 820 X1 X2 X3771 772 772 773 773 22 775 780 780 783 785 787 792 793 796 799 802 805 809 811 812 812 813 813 813 813 813 813 815 816 817 819 819 821 X1 X2770 771 771 772 772 21 774 779 779 782 784 786 791 792 795 798 801 804 808 810 811 811 812 812 812 812 812 812 814 815 816 818 818 820 821 X1769 770 770 771 771 773 23 778 778 781 783 785 790 791 794 797 800 803 807 809 810 810 811 811 811 811 811 811 813 814 815 817 817 819 820 821768 769 769 770 770 772 22 777 777 780 782 784 789 790 793 796 799 802 806 808 809 809 810 810 810 810 810 810 812 813 814 816 816 818 819 820767 768 768 769 769 771 21 776 776 779 781 783 788 789 792 795 798 801 805 807 808 808 809 809 809 809 809 809 811 812 813 815 815 817 818 819766 767 767 768 768 770 773 775 775 778 780 782 787 788 791 794 797 800 804 806 807 807 808 808 808 808 808 808 810 811 812 814 814 816 817 818763 766 766 767 767 769 772 774 774 777 779 781 786 787 790 793 796 799 803 805 806 806 807 807 807 807 807 807 809 810 811 813 813 815 816 817765 763 763 766 766 768 771 23 23 776 778 780 785 786 789 792 795 798 802 804 805 805 806 806 806 806 806 806 808 809 810 812 812 814 815 816762 765 765 763 763 767 770 22 22 775 777 779 784 785 788 791 794 797 801 803 804 804 805 805 805 805 805 805 807 808 809 811 811 813 814 815761 762 762 765 765 766 769 21 21 774 776 778 783 784 787 790 793 796 800 802 803 803 804 804 804 804 804 804 806 807 808 810 810 812 813 814764 761 761 762 762 763 768 773 773 23 775 777 782 783 786 789 792 795 799 801 802 802 803 803 803 803 803 803 805 806 807 809 809 811 812 813760 764 764 761 761 765 767 772 772 22 774 776 781 782 785 788 791 794 798 800 801 801 802 802 802 802 802 802 804 805 806 808 808 810 811 812759 760 760 764 764 762 766 771 771 21 23 775 780 781 784 787 790 793 797 799 800 800 801 801 801 801 801 801 803 804 805 807 807 809 810 811758 759 759 760 760 761 763 770 770 773 22 774 779 780 783 786 789 792 796 798 799 799 800 800 800 800 800 800 802 803 804 806 806 808 809 810757 758 758 759 759 764 765 769 769 772 21 23 778 779 782 785 788 791 795 797 798 798 799 799 799 799 799 799 801 802 803 805 805 807 808 809756 757 757 758 758 760 762 768 768 771 773 22 777 778 781 784 787 790 794 796 797 797 798 798 798 798 798 798 800 801 802 804 804 806 807 808755 756 756 757 757 759 761 767 767 770 772 21 776 777 780 783 786 789 793 795 796 796 797 797 797 797 797 797 799 800 801 803 803 805 806 807753 755 755 756 756 758 764 766 766 769 771 773 775 776 779 782 785 788 792 794 795 795 796 796 796 796 796 796 798 799 800 802 802 804 805 806754 753 753 753 753 757 760 763 763 768 770 772 774 775 778 781 784 787 791 793 794 794 795 795 795 795 795 795 797 798 799 801 801 803 804 805752 754 754 754 754 756 759 765 765 767 769 771 23 774 777 780 783 786 790 792 793 793 794 794 794 794 794 794 796 797 798 800 800 802 803 804750 752 752 752 752 753 758 762 762 766 768 770 22 23 776 779 782 785 789 791 792 792 793 793 793 793 793 793 795 796 797 799 799 801 802 803751 750 750 750 750 754 757 761 761 763 767 769 21 22 775 778 781 784 788 790 791 791 792 792 792 792 792 792 794 795 796 798 798 800 801 802723 751 751 751 751 752 756 764 764 765 766 768 773 21 774 777 780 783 787 789 790 790 791 791 791 791 791 791 793 794 795 797 797 799 800 801725 723 723 723 723 750 753 760 760 762 763 767 772 773 23 776 779 782 786 788 789 789 790 790 790 790 790 790 792 793 794 796 796 798 799 800724 725 725 725 725 751 754 759 759 761 765 766 771 772 22 775 778 781 785 787 788 788 789 789 789 789 789 789 791 792 793 795 795 797 798 799722 724 724 724 724 723 752 758 758 764 762 763 770 771 21 774 777 780 784 786 787 787 788 788 788 788 788 788 790 791 792 794 794 796 797 798721 722 722 722 722 725 750 757 757 760 761 765 769 770 773 23 776 779 783 785 786 786 787 787 787 787 787 787 789 790 791 793 793 795 796 797720 721 721 721 721 724 751 756 756 759 764 762 768 769 772 22 775 778 782 784 785 785 786 786 786 786 786 786 788 789 790 792 792 794 795 796719 720 720 720 720 722 723 753 753 758 760 761 767 768 771 21 774 777 781 783 784 784 785 785 785 785 785 785 787 788 789 791 791 793 794 795717 719 719 719 719 721 725 754 754 757 759 764 766 767 770 773 23 776 780 782 783 783 784 784 784 784 784 784 786 787 788 790 790 792 793 794711 717 717 717 717 720 724 752 752 756 758 760 763 766 769 772 22 775 779 781 782 782 783 783 783 783 783 783 785 786 787 789 789 791 792 793715 711 711 711 711 719 722 750 750 753 757 759 765 763 768 771 21 774 778 780 781 781 782 782 782 782 782 782 784 785 786 788 788 790 791 792705 715 715 715 715 717 721 751 751 754 756 758 762 765 767 770 773 23 777 779 780 780 781 781 781 781 781 781 783 784 785 787 787 789 790 791706 705 705 705 705 711 720 723 723 752 753 757 761 762 766 769 772 22 776 778 779 779 780 780 780 780 780 780 782 783 784 786 786 788 789 790714 706 706 706 706 715 719 725 725 750 754 756 764 761 763 768 771 21 775 777 778 778 779 779 779 779 779 779 781 782 783 785 785 787 788 789713 714 714 714 714 705 717 724 724 751 752 753 760 764 765 767 770 773 774 776 777 777 778 778 778 778 778 778 780 781 782 784 784 786 787 788701 713 713 713 713 706 711 722 722 723 750 754 759 760 762 766 769 772 23 775 776 776 777 777 777 777 777 777 779 780 781 783 783 785 786 787700 701 701 701 701 713 715 721 721 725 751 752 758 759 761 763 768 771 22 774 775 775 776 776 776 776 776 776 778 779 780 782 782 784 785 786699 700 700 700 700 700 700 720 720 722 723 750 757 758 764 765 767 770 21 23 774 774 775 775 775 775 775 775 777 778 779 781 781 783 784 785698 699 699 699 699 699 699 719 719 721 722 722 756 757 760 762 766 769 773 22 23 23 774 774 774 774 774 774 776 777 778 780 780 782 783 784691 698 698 698 698 698 698 717 717 717 721 721 753 756 759 761 763 768 772 21 22 22 23 23 23 23 23 23 775 776 777 779 779 781 782 783
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45
729 729 729 729 729 729 729 729 729 729 729 729 729 729 729 729728 728 728 728 728 728 728 728 728 728 728 728 728 728 728 728727 727 727 727 727 727 727 727 727 727 727 727 727 727 727 727 729726 726 726 726 726 726 726 726 726 726 726 726 726 726 726 726 727 729
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45FY (XX)
FY (XX)
Pla
tfo
rm S
tra
teg
y(P
rocu
rem
en
t S
che
du
le)
Total SSNs in Comm
FY (XX)
New SSN
VA Class(Block 7)
VA Class(Block 6)
VA Class(Block 5)
VA Class(Block 4)
VA Class(Block 3)
VA Class(Blocks 1-2)
SEAWOLFClass
LA Class(VLS)
LA Class(non-VLS)
SSGNs
(18)
(28)
(37)
(12)
VA Block 3
VA Block 4
VA Block 5
VA Block 4 Detailed Design
VA Block 3 Detailed Design
VA Block 5 Detailed Design
New SSN
OHIO Replacement SSBN
OR SSBN Requirements Definition
OR SSBN Detailed DesignOR SSBN R&D
New SSN Requirements Definition
New SSN Detailed Design
New SSN R&D
(10)
(19)
(43)VA Block 6VA Block 6 Detailed Design
(48)VA Block 7
VA Block 7 Detailed Design
SSN Force Structure
Note: Based on PB16 SPB
Click to edit Master title style
20
Summary
• Shipbuilding program presents significant opportunity for
increased industrial base workload – Inclusion of VPM and AS
• Affordability is paramount in fiscally constrained
environment – Navy and Industry need to have mutual goal of best value pricing to
maintain and grow our shipbuilding numbers
• OR success tied to VIRGINIA performance – Sustain VIRGINIA cost and schedule performance, while retaining
flexibility for capability enhancement
Click to edit Master title style
21
Questions?
#2532 06-14-16 Pg 22
OHIO Replacement Program
CAPT Goggins
23 Supplier Conference June 2016
OHIO Replacement Program Key Messages
Ship Design & Systems Developments
Progressing to Achieve 83% Design Completion Target
Prototyping Missile Tube Module
Reduce Risk to Construction
Test Facilities
Progressing on Schedule to Support Lead Ship
Affordability
Efforts Progressing at Pace to Achieve Cost Objectives
Pursuing Innovative Acquisition Authorities
Improve Cost and Reduce Schedule Risk
24 Supplier Conference June 2016
OHIO Replacement Program Schedule
25 Supplier Conference June 2016
ACCOMPLISHED
Integrated Power System (IPS) Compatibility Test
Facility (CTF) MILCON placed (May 2015)
U.S./UK E Fixture Construction Contract Awarded
(May 2015)
Ship Control Concept of Operations Exercise
(COOPEX) Phase 2 (Jul 2015)
JROC Validated CDD (Aug 2015)
Construction Group Established
Gate 4 Technical Baseline Configuration Control
(Nov 2015)
In Process Review / Defense Acquisition Board with
USD(AT&L) (Dec 2015)
Released Design Contract RFP (Jan 2016)
OSD AT&L signed OR Acquisition Strategy (Jan 2016)
ON-GOING & UPCOMING (FY16)
Gate 5 (Jul 2016)
Milestone B (Aug 2016)
Generation 1 Propulsor Testing
Construction of the OR Quad Pack Manufacturing
Facility in Quonset, RI
Manufacturing of U.S. and UK Missile Tubes
Preparation for First Article Quad Pack Missile
Compartment construction
HM&E component prototyping (Diesel Generator,
Air Conditioning Plant, Reverse Osmosis Unit, Light
Emitting Diode (LED) Lighting, Advanced CO2
Removal Unit)
Manufacturing Fixtures OR Quad Pack
Manufacturing Facility
First Article
Quad Pack (FAQP)
OHIO Replacement Accomplishments
26 Supplier Conference June 2016
Goal: Achieve best value for the Navy in delivering quality, affordable OHIO Replacement (OR), including the Common Missile Compartment for the UK, and VIRGINIA-class submarines (VCS), including VIRGINIA Payload Module (VPM), and CVN common material on time, to specifications, in the necessary quantities, with acceptable risk.
SUBS: A strategy coordinating OR, VCS and CVN programs to achieve the Goal and: Prioritize OR program execution – OR and SUCCESSOR must deliver on time
Prioritize SSN force structure – VCS must deliver on time
Ensure executability and enable affordability during the planned ramp-up in submarine production
Sustain VCS cost and schedule performance, while retaining flexibility for capability enhancement
Retain two shipyards and the supplier base capable of delivering nuclear-powered submarines
Meet decision timing necessary to support RFPs for OR and VCS
Be well informed by FORD Class CVN
SUBS addressed how best to:
Distribute shipbuilder submarine construction work-load share • Accommodate capacity, capability and fragility constraints identified by industry
Employ existing and potential new funding and contracting authorities
Enhance OR/VCS alignment as needed to reduce risk to schedule and cost goals
Leverage volume, stability and maturity of VCS to drive down cost
Incorporate lessons learned from CVN 78 (first in class) delivery
Aggressively pursue cost reduction opportunities to minimize impact on other national priorities
Submarine Unified Build Strategy (SUBS)
Navy Is Transitioning To SUBS-Execution
27 Supplier Conference June 2016
Procurement Authority Expansion Impact to Industrial Base
Over the next two decades, there will be a significant increase in demand on the nuclear shipbuilding industrial base
The OHIO Replacement (OR) Program, in coordination with VCS and CVN, is working with Congress to expand acquisition authorities
Expanded Authorities Would: Enable innovative funding strategies to gain efficiencies on OR
Support the industrial base with stable EOQ benefits for suppliers across the nuclear enterprise
Reduce schedule risk on ship deliveries and lower enterprise costs
28 Supplier Conference June 2016
Maintaining Schedule Design ready for construction start (83%) Construction start in 2021 Deploy on schedule (2031 IOC)
Transition from Design to Shipbuilding
Collaboration of builders, maintainers, operators, in the design process Achieve 83% design complete at construction start, enables Manufacturing
Assembly Plan (MAP) detailed planning Utilizing proven technologies and test facilities to mitigate lead ship risk Established Integrated Master Schedule (IMS); execution performance
consistently evaluated Experienced Government and Contractor technical and programmatic
leadership in key positions
Achieving Affordability
Aggressive actions to achieve all cost targets Continuous measurement of progress Challenge industrial base
Milestone B – Aug 2016
Program Focus Areas
#2532 06-14-16 Pg 29
3. Discussion of SUBS Team Efforts
Sara Ainey, PEO SUBS
Cindy Blanchette, EB
Bryan Caccavale, NNS
Jennifer Navarro, GD Corporate
#2532 06-14-16 Pg 30
Submarine Unified Build Strategy (SUBS) Construct and Objective
Coordinated Navy / EB / NNS effort to develop integrated plan for the Nuclear shipbuilding enterprise over the next twenty years
Participation
– Joint effort supported by PEO Subs, PEO Carriers, Naval Reactors, EB, and NNS
– Priority effort for shipbuilders and Navy staffed with critical personnel across key value stream elements (“Lines of Effort”)
1) Design
2) Construction
3) Material and Supply Base
4) GFE / RDT&E
5) Acquisition
#2532 06-14-16 Pg 31
Huge Challenge for Industrial Base - Achieve Generational Ship Construction and Delivery Requirements
31
= 20,000 tons delivered
= VA-Class SSN tonnage
= OR SSBN tonnage
= VPM tonnage
= CVN tonnage
15 Years
(1987 – 2001)
15 Years
(2002 – 2016)
15 Years
(2017 – 2031)
Deliveries: 4 CVNs, 31 SSNs, 10 SSBNs Total Tonnage: 792,000 Tons
Deliveries: 3 CVNs, 14 SSNs, 0 SSBNs Total Tonnage: 408,000 Tons
Deliveries: 3 CVNs, 28 SSNs, 12 VPMs, 2 SSBNs Total Tonnage: 589,000 Tons
#2532 06-14-16 Pg 32
Submarine Unified Build Strategy (SUBS) Focal Points
● Developing a plan to support enhanced congressional acquisition authorities and funding profiles
● Elements of the plan
– Design readiness
– Optimal build strategies
– Shipbuilder facility preparation
– Resource readiness and sustainability
– Industrial base capacity and planning
Add stability and increase predictability across the Navy’s nuclear portfolio and entire industrial base
#2532 06-14-16 Pg 33
Continuous Production Reduce schedule risk and lower enterprise costs
Calendar Year
*Assumes use of National Sea Based Deterrence Fund and incremental funding for the continuous production plan for missile tubes RELEASABLE TO UK IN SUPPORT
OF THE POLARIS SALES AGREEMENT
Program of Record
Pro forma C/P
#2532 06-14-16 Pg 34
Capitol Hill Environment ● DoD Base Budget: $523.9 billion (+$2.2B from FY16 enacted)
– Complies with Bipartisan Budget Act of 2015
– Protects the department from the threat of sequestration
● Some consensus to get through the budget process quickly
– But, would still bet on a CR – how long?
– Presidential election year
– Passing of Supreme Court Justice Scalia may have effect on the budget
process
● World Environment Instability Increases – Russian aggression
– Terrorism
– China’s island building
– North Korea’s nuclear program
– International financial instability
#2532 06-14-16 Pg 35
Congressional Landscape for Shipbuilding
● Shipbuilding Programs are Strongly Supported
by Congress
– Demonstrated through maintaining or adding to President’s
Budget request for submarine programs
● OHIO Replacement is the #1 Priority for the Navy,
Congressional support has followed
– National Sea-based Deterrence Fund shows desire from
Congress to keep funding protected
● Congressional support for adding additional SSNs into
the Shipbuilding Plan, specifically by adding an
additional SSN in FY21
#2532 06-14-16 Pg 36
Defense Bills in Congress
National Defense
Authorization Act (NDAA)
Defense Appropriations
Act or Omnibus
Senate Armed
Services
Committee
(SASC)
House Armed
Services
Committee
(HASC)
Senate
Appropriations
Committee (SAC)
House
Appropriations
Committee (HAC)
Conference Conference
PB17 PB17
House Armed
Services Seapower &
Projection Forces
Subcommittee
Senate Appropriations
Committee Defense
Subcommittee (SAC-D)
House Appropriations
Committee Defense
Subcommittee (HAC-D)
Senate Armed
Services Seapower
Subcommittee
Date
TBD
Date
TBD
#2532 06-14-16 Pg 37
Bill Language Supporting SUBS Initiatives Continuous Production Authority
● The House Armed Services Committee (HASC) included language
in its draft of the NDAA that states:
– Authority for multiyear procurement of critical components to support
continuous production—(1) To implement the continuous production of
critical components, the Secretary of the Navy may use funds deposited
in the Fund, in conjunction with funds appropriated for the procurement
of other nuclear-powered vessels, to enter into one of more multiyear
contracts (including economic ordering quantity contracts), for the
procurement of critical contractor-furnished and Government-furnished
components for national sea-based deterrence vessels. The authority
under this subsection extends to the procurement of equivalent critical
parts, components, systems and subsystems common with and required
for other nuclear powered vessels.
Language Still Needs to be Reconciled in Conference with SASC,
Funding Required from Appropriators to be Effective
#2532 06-14-16 Pg 38
Summary
Acquisition initiatives require Congressional support in
order to take shape—both in the NDAA and
Appropriations bills
Authority for Continuous Production is a possibility in the
FY17 NDAA, but will need funding from Appropriators in
order to be impactful
Engagement with Congress on acquisition authorities
will continue for FY18 budget cycle
#2532 06-14-16 Pg 39
4. Submarine Industrial Base
Council Overview
Robert Dunn, EB
• Advocacy group of over 1,200 members from
over 600 companies – created 25 years ago
• Mission is to educate policymakers and the
public on the need to preserve the strength of
the U.S. submarine force and promote the value
of the submarine industrial base as a vital part of
our national security.
Submarine Industrial Base Council (SIBC)
• Annual 2-day Supplier Days conference in
Washington D.C. held in March
• Over 300 suppliers get updates from Navy and
Shipbuilders on submarine programs and then
engage members of congress on Capitol Hill
• Periodic alerts to engage Congressional
members as needed during the year to address
key SIBC legislative issues
SIBC Activity
• Anyone supporting the submarine industrial
base can and should join
• No cost to join or remain a member
• Sign up via the SIBC website
(www.submarinesuppliers.org)
• SIBC website is a good informational resource
for suppliers on submarine programs and
legislative priorities
SIBC Membership
#2532 06-14-16 Pg 44
5. VCS, OR and CVN Contract
Timelines
Jim Cassidy, EB
Alma Fallon, NNS
#2532 06-14-16 Pg 45
VCS, OR, CVN Contracting Timelines
Topics:
● Supplier Contracting - Goals / Approach / Assumptions
● VCS Block V Timeline
● OR Block I Timeline
● CVN80 Timeline
● Integrated View with Opportunities
● Key Takeaways
#2532 06-14-16 Pg 46
Contracting with Suppliers - VCS, OR, CVN Goals / Approach / Assumptions
● Goals – Expand and Stabilize Industrial Base
– Reduce Material Delivery Risk
– Reduce Overall Program Cost
● Approach – Clearly communicate opportunities (volume / timing)
Supports supplier planning (capital investment / hiring)
– Level supplier and sub-tier workload where possible De-conflict supplier schedules between programs to reduce peak demands
Optimize capital investment and other business decisions with growth
Stabilize workforce to reduce risk (quality / delivery)
Efficiency benefits of continuous production
– Early identification of obsolescence risks and other risks
– Ensure that Multi-Program workload is appropriately reflected in proposals
● Assumptions – FY 17 Shipbuilding plan of record with up to two VA Class authorizations
in FY 21
– Maintain Shipbuilder procurement responsibilities / worksplit
#2532 06-14-16 Pg 47
Notional VCS Contracting Timeline VCS Block V
Handshake
June-2018
Request for Proposal
March-2017
Contract Award
Oct-2018
Full
Proposal due
Sept-2017
Technical
Baseline
Feb-2017
Prime Contract
Supplier Proposals
Request for
Proposals
Dec- 2016
Estimate AP2
Requirements
Sept-2016
Estimate AP1
Requirements
Sept-2017
Receive
Proposals
March-2017
AP1(FY19-1/2)
Funding Available
Jan-2018
AP2 (FY19-1/2)
Funding Available
Jan-2017
Complete cost analysis
for proposals >$13.5M
July-2017
Fact Finding/Audits
FF (FY19-1/2)
Funding Available
Jan-2019
Place AP2
Purchase Orders
Feb-2017
Place AP1
Purchase Orders
Feb-2018
Place FF
Purchase Orders
Feb-2019
Funding &
Purchase
Orders
Cost analysis
provided to Gov.
Jul-2017
#2532 06-14-16 Pg 48
Notional OR Contracting Timeline OR Block I
Contract
Award
Oct-2020
Handshake
July-2020
Full Proposal
due
Sept-2019
OR IPPD
Award
Sept-2016
Prime Contract
Supplier Proposals
Request for
Proposal
Dec-2018
Estimate AP2
Requirements
Dec-2018
Estimate AP-1
Requirements
Dec-2019
Receive
Proposals
March-2019
AP1 Funding
Available
Jan-2020
AP-2 Funding
Available
Jan-2019
Complete cost
analysis for proposals
July-2019
Fact Finding/Audits
Funding &
Purchase
Orders
Place AP2
Purchase Orders
Feb-2019
Place AP1
Purchase Orders
Feb-2020
FF Funding
Available
Jan-2021
Place FF
Purchase Orders
Feb-2021
#2532 06-14-16 Pg 49
Notional CVN 80 Contracting Schedule Detail Design & Construction
DD&C Award
1QCY18
DD&C RFP Amendment
Issued 4QCY16
NNS Start DD&C
Proposal Prep 3QCY16
Supplier Proposals
Prime Contract
RFPs to Suppliers 4QCY16
Supplier Proposals Received 1QCY17
Anticipated Contract Award
1QCY18
#2532 06-14-16 Pg 50
Contracting Timeline – Integrated View Key Supplier Milestones
Supplier Proposals
Funding Availability
VCS Block V
AP2 (FY19-1/2)
1/31/17
FF (FY19-1/2)
AP1, AP2, & EOQ
1/31/19
1/31/20
Next
Increment
AP1 (FY19-1/2)
AP2 (FY20-1/2)
1/31/18
Dec-2016 March-2017
CVN80
OR Block I
Dec- 2018 March- 2019
1/31/21
Next
Increment
VCS Block V
4QCY16 1QCY17
AP-2 Funding
Available
1/31/19
OR Block I
AP1 Funding
Available
1/31/20
FF Funding
Available
1/31/21
Detail Design &
Construction Award
1QCY18
CVN80
Advanced Procurement
In Process
Opportunities:
1. EB include OR Options in VCS Block V RFPs
2. NNS include OR Options in CVN80/VCS RFPs
Challenges:
1. OR requirements maturity for late CY16 RFPs
2. Without MY-MP obligation authority, suppliers will
have to hold OR option pricing for 2 to 4 years
3. CVN80 AP procurements are already in process
#2532 06-14-16 Pg 51
VCS, OR, CVN Contracting Timelines - Key Takeaways
● EB/HII-NNS/Gov’t will conduct VCS, OR, and CVN procurement
activities to:
– Expand and Stabilize Industrial Base
– Reduce Material Delivery Risk
– Reduce Overall Program Cost
● Current Shipbuilder procurement responsibilities / worksplit will
be maintained
– EB/HII-NNS procurement worksplit for VCS is not affected
– HII-NNS will procure all CVN material
– HII-NNS will procure some OR major components consistent with
current VCS procurement responsibilities
For new design items, EB will procure some major components for lead
ship only
● Changes to Shipbuilding Plan of Record could affect procurement
timeline milestones
#2532 06-14-16 Pg 52
6. Shipbuilder Lessons Learned
Jim Cassidy, EB
Alma Fallon, NNS
#2532 06-14-16 Pg 53
Block IV Process Improvement Event Overview & Purpose Purpose: Document the process and timeline for starting a new VCS
Construction Contract Block using Block IV lessons learned
Joint Shipbuilder team pursued this initiative in order to address
recognized problems with the Block IV Start-up
Contracts, Cost Engineering, Engineering, IT, Planning, Material Planning, Material
Procurement, Operations, and Facilities
Deliverables: Block Startup Timeline and formal POA&M
− Less dependency on the “tribal knowledge”; repeatable process
− Clear “road map” of required actions; higher level of preparedness
− Continuous improvement by incorporating lessons learned
Timely Execution & Management of Block Start-up Activities is Critical to Maintain the
Required 2 per year Delivery Cadence and Ensure Success of Program
#2532 06-14-16 Pg 54
Block IV Process Improvement Event Focus Areas 1. Development of Technical Baseline
- Reaching agreement on capabilities/technologies for the Block
- Timing of key decisions and approvals
2. Contract & Funding Processes
- Identification of funding requirements
- Timeliness of negotiation process and contract award
3. Planning & Material
- Adequacy and timing of contract award & funding to support material acquisition
- Establishing component/commodity/casting schedules
- Understanding downstream effects driven by late material
4. Construction Readiness
- Integrating Program plans into build sequence
- Identifying required Resources/Facilities/Footprint to support construction schedules
- Advanced manufacturing efforts (timing)
Developing this Comprehensive Block Start-up Process/Timeline Demonstrated the
Interdependencies of These Focus Areas
#2532 06-14-16 Pg 55
Inadequate Block IV Start-up Activities Impacted Performance and Target Ship Delivery Schedules
In June 2015, the Shipbuilders performed a evaluation of Block IV
production delinquencies
− Due to Block IV Delinquencies, Ship Target Deliveries were adjusted for
the SSN792-SSN795
− SSN796-SSN801 schedules will be continuously reviewed; Shipbuilders’
goal is to be back to baseline schedule by SSN801
− Reduced margin between target and contract delivery dates increases
program execution risk
Timely/Adequate Execution of Block Start-up Activities is Critical to Success of Block
#2532 06-14-16 Pg 56
Late Block IV Material Lessons Learned
Supplier Improvements for Proposal Adequacy and On-Time Delivery are Required
to Support Block V Schedules and 2 Per Year Cadence
Critical/Complex Procurement Process
– New supplier oversight process for build-to-print items
– Additional pre-award activity delayed supplier manufacturing start
Late Design Changes
– Changes associated with obsolescence issues, technical requirement
clarifications, block re-design efforts, and new component qualifications
AP2 Funding Issues
– Delayed supplier manufacturing start due to the availability, allocation,
and Shipbuilder usage of AP2 funding
Supplier Performance (including sub-tiers)
Protracted Negotiations / Proposal Quality
– Supplier proposal quality and Shipbuilder/Supplier negotiation efforts
delayed manufacturing start for some major components
#2532 06-14-16 Pg 57
Block V Technical Baseline Status and Risks
● Tech Baseline establishes the technical requirements for the block of ships and is a key input for cost and schedule
● Status
− Block V Tech Baseline includes multiple changes from Block IV:
VIRGINIA Payload Module
VIRGINIA Payload Module Host Ship Changes
South Dakota Insertion Technology
Obsolescence Changes
OR Commonality and Fleet Upgrade Commonality
● Risks
− Took 4 years to complete TBL for Blocks III and IV; Block V span is 1.5 years
− Early or incomplete TBL will create churn for procurement and manufacturing
− RFPs released to suppliers before final Block V TBL approval
Close Shipbuilder/Supplier alignment is critical for TBL change items
#2532 06-14-16 Pg 58
Shipbuilder Lessons Learned from VIRGINIA Class 2 Per Year Ramp Up
● Electric Boat and HII-NNS performed detailed studies to plan and
execute the ramp up to 2 VIRGINIA Class ships per year
– Even with detailed planning, some challenges affected performance
● Next industrial base ramp up is combined VA/OR/CVN volume
– In addition, Shipbuilders may outsource fabrication / machining work that
has been performed in-house to date
● Consider the following areas based on Shipbuilder lessons learned
– Facility planning
– Workflow / spatial analysis
– Trade workforce recruiting / training
– Knowledge management and knowledge transfer
– Capturing best practices for a less experienced workforce
Shipbuilders using detailed manufacturing/assembly plans
Detailed planning is essential for success with substantial volume increase
#2532 06-14-16 Pg 59
Partnering with the Supply Base to Improve Delivery and Quality Performance ● Capacity Analysis and Development of Delivery Dates
● Collaborating with Prime Suppliers in Support of Managing Sub-Tier
Performance
● Leverage Shipbuilders’:
– Supplier Training Programs
– Risk Management Programs
– Supplier Development and Continuous Improvement Tools
– Technical, Supplier Quality, and Project Management Resources
– NAVWELD – Weld Procedure Development Tool
● Early Engagement during Pre-Award Phase to Ensure Readiness
● Kick-Off Meetings and Program Reviews During Production
● Early Identification of Obsolescence Issues
● Request Shipbuilder Support to Resolve Technical or Manufacturing
Producibility Issues
#2532 06-14-16 Pg 60
Key Takeaways
Shipbuilders developed a comprehensive, integrated block start-up execution plan
Need Supplier Improvements to Ensure Block V Success and Maintain the VIRGINIA Class 2 Per Year Cadence
– Proposal Adequacy / Timely Negotiations
– On-Time Delivery
Close Shipbuilder/Supplier Alignment is Needed for Technical Baseline Change Items to Support Proposal Development
Suppliers should leverage available Shipbuilder resources
– Training, Risk Management, Continuous Improvement, NAVWELD, and Engineering Engagement in Issue Resolution
Consider Shipbuilder lessons learned from 2 per year ramp
– Facilities, Workflow, Workforce, Knowledge Management
#2532 06-14-16 Pg 61
7. Proposal Content
Jeff Robinson, NAVSEA02
Pete Stefanski, EB
Alma Fallon, NNS
#2532 06-14-16 Pg 62
Agenda
Section 1: View of
Adequacy/Quality of Proposals
Section 2: Ground
rules/assumptions
Section 3: FAR Part 15
Overview
Section 4: Audit/Evaluation
Process Expectations
Section 5: Q&A on Proposal
Content
Jeff Robinson, NAVSEA 02
Alma Fallon, Newport News
Pete Stefanski, Electric Boat
Pete Stefanski, Electric Boat
Suppliers
#2532 06-14-16 Pg 63
View of Adequacy / Quality of Proposals
#2532 06-14-16 Pg 64
View of Adequacy / Quality of Proposals
1) Nuclear shipbuilding demand is growing
2) Align resources to the risks
3) Develop more accurate cost estimates/proposals so
that workload is better predicted and executable
4) To begin a more collaborative approach to procurement
where proposal expectations are understood
#2532 06-14-16 Pg 65
NAVSEA Proposal Review Focus
Prior to 2012
NAVSEA primary focus on
Shipbuilder Labor Hours
Prime Contractor Rates and
Material (Subcontracts)
evaluated using historical
decrement approach primarily
supported by DCAA audits
FAR/DFAR requirements
– FAR 15.408, Table 15-2
2012 and Beyond
Focus on all cost elements for
all prime and all subcontract
tiers
Review of Actual Cost Data for
all contract types
FAR/DFAR requirements
– FAR 15.408, Table 15-2
– DFAR 252.215-7009 Proposal
Adequacy Checklist
#2532 06-14-16 Pg 66
DFAR 252.215-7009 Proposal Adequacy Checklist
Background: DoD published a proposed rule in the Federal
Register at 76 FR 75512 on December 2, 2011, to
incorporate the requirement for a proposal adequacy
checklist into DFARS 215.408, and an associated
solicitation provision at 252.215-7009, to ensure offerors
take responsibility for submitting thorough, accurate, and
complete proposals.
The rule was incorporated on 28 March 2013
#2532 06-14-16 Pg 67
Proposal Adequacy Checklist
Public Concerns
Increased Cost to Govt
Additional Requirements
Unnecessary and duplicative
Does not support Better Buying Power
Response
This provision results from a long history of
incomplete proposals resulting in rework and lost
time, and it aims to achieve cost savings by
improving initial proposal submissions
The intent is to increase uniformity across DoD,
minimize local variations, and thereby decrease
proposal preparation costs
Provides uniform tool that is applicable across
DoD to address the inconsistent interpretations of
Table 15-2.
While this initiative predates BBP, it is consistent
with the BBP's cost reduction initiatives.
#2532 06-14-16 Pg 68
Customer Perspective
Adequate Proposals lead to reduced fact-finding questions,
site-visits and negotiation timelines in support of earlier
contract award
Where inadequacies/unsupported costs exist, the reviewer
will be required to extract more information, request field audit
services, and perform additional analysis which delays
negotiations and award
Provide data upfront in electronic format (e.g., Excel) with
linked calculations; the proposal is easier to follow and
understand
Adequate proposals are more likely with upfront discussion
and expectation setting prior to RFP release
#2532 06-14-16 Pg 69
Importance of submitting a compliant proposal
Advantages:
– Compliant to FAR Part 15 to provide adequate supporting documentation
– Minimizes Supplier Support of a Customer Field Audit (less time in facility collecting data)
– Provides the level playing field for a win-win negotiation between all parties (no assumptions)
– Determining if the proposal is adequate to provide a sound basis for pricing decisions and
contract award
– Less findings and subsequent rework for all parties
– Potential to reduce cycle time for contract award and subsequent funding release
– Provides insight for opportunities to maximize supplier capacity
– Provides insight for potential technical improvements (forgings vs castings, history of material
issues, design changes, etc.)
Incomplete Proposals Lead to:
– Increased cycle time to negotiate a contract with the customer
– Inability for the supplier to forecast sales
– Negotiation with Customer resulting in a lower budget because of incomplete information – results
in less budget, and higher risk for the supplier
– Non-Compliance to FAR Part 15 (Unilateral adjustments for failure to comply (Defective Pricing))
View of Adequacy / Quality of Proposals
#2532 06-14-16 Pg 70
Ground Rules / Assumptions (Quantities, Options, Funding)
#2532 06-14-16 Pg 71
Supplier Considerations and Assumptions When Preparing Proposals
Optimization of EOQ where possible
Level loading of work in facilities through the period of performance
Development of Rates in anticipation of work across multiple
programs
Will be a negotiation point
Will minimize cycle time in process
Recommendations for Option Pricing for multiple programs
Accurate Funding Profiles
Maximize Procurement Opportunities
Procure Most Schedule Dependent Items First
Use of Termination of Liability
Ground Rules / Assumptions (Quantities, Options, Funding)
#2532 06-14-16 Pg 72
FAR Part 15 Overview
#2532 06-14-16 Pg 73
Responsibilities
Government
– Responsible for determining fair and reasonable price for
supplier costs
– Require shipbuilder and/or supplier to submit certified cost and
pricing data when applicable
Shipbuilder
– Obtain and analyze supplier certified cost or pricing data and
submit this data as part of its own cost or pricing data
– Conduct appropriate analyses to establish the reasonableness
of proposed supplier prices
– Include the results of these analyses in the prime
contractor’s proposal
#2532 06-14-16 Pg 74
Responsibilities (cont’d)
Supplier
– For proposals meeting the cost or pricing data threshold, submit
proposals in the format provided in Table 15-2 of 15.408
– Perform the prime contractor’s responsibilities with its sub-tier
suppliers
– Certify that the cost or pricing data is current, accurate and
complete
#2532 06-14-16 Pg 75
If a proposal is FAR compliant
Lead to shorter evaluation and audit time – less
expensive for both the shipbuilder and supplier
Easier to reach a negotiated settlement for a fair and
reasonable price
Quicker award of prime contract to shipbuilder and/or
purchase order to suppliers
#2532 06-14-16 Pg 76
FAR/DFARs Thresholds
As of 10/01/2015, the following thresholds may apply to the
Prime Contractor and/or its suppliers:
Description Threshold ($) FAR Reference
Certificate of Cost or
Pricing Data
$750,000 FAR 15.403-4
Submission of Certified
Cost or Pricing Data
$13.5 million, or when
required by the
Contracting Officer
FAR 15.404-3
#2532 06-14-16 Pg 77
Certified Cost or Pricing Data Requirements
The Contractor is required to submit cost or pricing data in
accordance with the FAR when the conditions of FAR
15.403-4 are satisfied
The Contractor is not required to submit certified cost or
pricing data (but may be required to submit data other than
certified cost or pricing data) when –
1. The Contracting Officer determines that the prices agreed upon are
based on adequate price competition (see FAR 15.403-1(c)(1));
2. The Contracting Officer determines that the prices are set by law or
regulation (see FAR 15.403-1(c)(2));
3. When a commercial item is being acquired (see FAR 15.403-
1(c)(3)); or,
4. When a waiver has been granted (see FAR 15.403-1(c)(4)).
#2532 06-14-16 Pg 78
Certified Cost or Pricing Data Proposal Submission
Submission should follow the instructions at FAR 15.408, TABLE 15-2
for preparing a contract pricing proposal when certified cost or pricing
data are required. Note the following:
The requirement for submission of cost or pricing data is met when
all accurate certified cost or pricing data reasonably available to the
offeror have been submitted … to the Contracting Officer or an
authorized representative
By submitting your proposal, you grant the Contracting Officer or an
authorized representative the right to examine records that formed
the basis for the pricing proposal. It may include those books,
records, documents, and other types of factual data (regardless of
form or whether the data are specifically referenced or included in
the proposal as the basis for pricing) that will permit an adequate
evaluation of the proposed price
#2532 06-14-16 Pg 79
Certified Cost or Pricing Data Proposal Format
FAR 15.408, TABLE 15-2 and the DFARs Proposal Adequacy
Checklist at DFARs 252.215-7009 detail the format and content for
proposal submittal. The following areas are addressed:
● General Instructions
● Material and Services
● Subcontracts (Purchased materials or services)
● Exceptions to Certified Cost or Pricing Data
● Inter-organizational Transfers
● Direct Labor
● Indirect Costs
● Other Costs
● Formats for Submission for Line Item Summaries
● Other
79
#2532 06-14-16 Pg 80
Proposal Adequacy Checklist
● General Instructions
– Disclose any non compliances with Cost Accounting Standards
(CAS) or established estimating and accounting practices
– Disclose known activity that could materially impact costs (e.g.
vendor quotes, trends such as labor efficiencies, changes in
production volume)
– Provide a summary of cost by cost element (by year if
applicable)
– If no Government forward pricing agreement – provide all rates
and factors by year that are utilized in the development of the
proposal and the basis for the rates (base and pool data)
#2532 06-14-16 Pg 81
Proposal Adequacy Checklist (cont’d)
Material and Services
– Proposal to include a consolidated bill of material that includes
the basis of pricing
– The bill of material should include all material items and:
Item description
Source of pricing
Quantity
Price (unit and extended)
#2532 06-14-16 Pg 82
Proposal Adequacy Checklist (cont’d)
Subcontracts
– If the subcontract exceeds the FAR threshold for cost or pricing
data, the supplier must include a copy of the sub-tier’s certified
cost or pricing data
– Include the cost analysis establishing the reasonableness of the
sub-tier’s pricing or a date as to when the cost analysis will be
complete
– Note: This is an area of consistent inadequacy across industry
82
#2532 06-14-16 Pg 83
Proposal Adequacy Checklist (cont’d)
Exceptions to Certified Cost or Pricing Data
– Commercial item and the basis on which it meets the definition
– Competition and the basis for establishing the reasonableness
– Pricing set by law or regulation
– Waiver granted
#2532 06-14-16 Pg 84
Proposal Adequacy Checklist (cont’d)
Inter-organizational Transfers
– For transfers at cost, does the proposal include a complete cost
proposal compliant with Table 15-2
– For transfers at price, does the proposal provide an analysis that
supports exception from certified cost or pricing
#2532 06-14-16 Pg 85
Proposal Adequacy Checklist (cont’d)
Direct Labor
– Include a time phased breakdown of labor hours, rates and cost
by category or skill level
– If labor is the allocation base of indirect costs, labor must be
summarized so that the applicable overhead rate can be applied
– Basis of estimate to include:
Labor Categories
Labor hours
Task descriptions
85
#2532 06-14-16 Pg 86
Proposal Adequacy Checklist (cont’d)
Indirect Costs
– Include the basis of estimate and how they are applied
– Include breakdown of cost pools
– Trends – Historical data (three years)
– Budgetary data
#2532 06-14-16 Pg 87
Proposal Adequacy Checklist con't
Other Costs
– Travel
Number of trips
Number of people
Length of trips
Locations
Rates (airfare, per diem, hotel, car rentals, etc.)
Royalties
#2532 06-14-16 Pg 88
Proposal Adequacy Checklist (cont’d)
• Formats for Submission
– All cost element breakdowns using format in Table 15-2 (or
alternative format if specified in request for proposal)
88
#2532 06-14-16 Pg 89
Proposal Adequacy Checklist (cont’d)
Other
– Incentive contract type – include target cost, target profit, share
ratio, etc.
89
#2532 06-14-16 Pg 90
Audit / Evaluation Process Expectations
#2532 06-14-16 Pg 91
Audit / Evaluation Process Expectations
Shipbuilder's are responsible to evaluate supplier’s proposal
How is that done?
– Review of supporting data submitted with proposal
– Audit fieldwork at supplier’s facility (DCMA or Shipbuilder and their agent)
How to expedite the process?
– Provide supporting data with the proposal submittal
– Provide as much supporting data as possible in electronic format
Excel with all formulas visible
– Allow the shipbuilders to perform the audit of all cost elements
– Shipbuilders are willing to sign Non-Disclosure Agreement (NDA)
– Audit sample’s selected prior to audit fieldwork and ready at the beginning of the
site visit
– If supporting data is sufficient, site fieldwork may not be necessary
Don’t wait for site fieldwork to provide supporting documentation
#2532 06-14-16 Pg 92
Audit / Evaluation Process Expectations (cont’d)
Shipbuilder's evaluation of supplier’s proposals must
provide meaningful responses to the following questions
for each cost element:
– What is the estimate?
What is proposed and the value associated with it
– What is it based on?
What is the basis of estimate, the source data and the history of
actual cost incurred
– How is it derived
Show and describe the proposal calculations
– Why is it reasonable?
What conclusion would a prudent business person make given the
data provided and describe why
#2532 06-14-16 Pg 93
What supporting data will be reviewed
Material and Subcontracts
– Priced Bill of Material (BOM)
– Supporting data that supports BOM (e.g. quotes, purchase
history, catalog items, estimates with BOEs)
– Historical negotiation factors
– Cost analysis for sub-tiers who are over the cost or pricing
threshold that includes discussion of all cost elements
– Copy of sub-tiers certified proposal
Labor Hours
– Historical labor hours by labor category
– Support for any cost estimating relationships proposed
– Learning curves - Provide all supporting back up including source
calculations
– Provide any back up for make versus buy fluctuations
#2532 06-14-16 Pg 94
What supporting data will be reviewed
Labor and Indirect Cost
– Identify base to which overheads are applied
– Provide actual base and pool information for the last three years
by element
– Provide rationale for projected base and pool expenses by
element
– Provide a copy of the Forward Price Rate agreement if applicable
– Provide an annual company workload projection for the proposed
period of performance
– Provide a copy of any union agreement in place
– Provide basis of any escalation proposed and its derivation
#2532 06-14-16 Pg 95
What supporting data will be reviewed (cont’d)
Other Direct Cost
– Provide breakdown and support for cost included in this category
(e.g. travel, computer usage, etc.)
Profit / Fee
– Identify the basis and rationale for the proposed profit rate
– Explain why the proposed rate is reasonable
– Discuss the programmatic/technical/cost risks in performing the
work that drive the proposed apportionment of the risk
– Recommend structured approach for development (Weighted
Guidelines – DFARs 215.404-70)
#2532 06-14-16 Pg 96
Common Omissions and Findings in Proposals
1. Proposals not containing an index of certified cost or pricing data or other
information included or referenced in the proposal.
• This index should identify each separate item, identify what it pertains to, whether
or not it is actually in the proposal, and its location in the proposal or other location
at the Offeror’s facility where it can be found, as applicable. This is not the
proposal Table of Contents
2. Pricing Proposal Cover Sheet does not contain all the required information, in
particular:
• No signature
• Values do not match the Summary Cost Elemental Breakdown
• Utilized Pricing Proposal Cover Sheet (SF1411 or similar) with outdated or
otherwise incorrect certification statement
3. Bills of Material that do not contain the appropriate requested information
• Lack of material support for previous purchase price
• Sub-tier supplier cost reviews
4. Labor Hour Data Support
5. Unsupported Variances Versus Incurred Actuals
#2532 06-14-16 Pg 97
Common Omissions and Findings in Proposals (cont’d)
6. Unsupported Escalation
7. Indirect Rate Historical Documentation
8. Inter-Organizational Cost Support
9. Lack of Support for Cost of Money
10. Pricing templates are either missing or do not add to the total proposed value
11. Cost breakdowns that do not provide time-phasing of hours, rates and factors, etc. by category
12. “No” and “N/A” responses on proposal checklist without corresponding explanations
13. Lack of traceability between offeror’s proposal pricing and the related supporting information
14. Shipbuilder access to all cost/pricing data
#2532 06-14-16 Pg 98
Q&A on Proposal Content
#2532 06-14-16 Pg 99
8. Shipbuilder-Supplier Session
#2532 06-14-16 Pg 100
Blair Decker, EB Rob Hogan, NNS
Jim Cassidy, EB Gary Zimak, NNS
Pete Stefanski, EB Alma Fallon, NNS
Jim Noonan, EB Bryan Caccavale, NNS
Shipbuilder Q&A Panel