Viet Nam: Central Mekong Delta Connectivity Project · detailed Income Restoration Programs (IRP)...

37
Social Monitoring Report #16 Quarterly Report (March November 2018) December 2018 Viet Nam: Central Mekong Delta Connectivity Project Prepared by DDIS for the Cuu Long Corporation for I nvestment, Development and Project M anagement of I nfrastructure (Cuu Long CIPM) and the Asian Development Bank.

Transcript of Viet Nam: Central Mekong Delta Connectivity Project · detailed Income Restoration Programs (IRP)...

Social Monitoring Report

#16 Quarterly Report (March – November 2018)

December 2018

Viet Nam: Central Mekong Delta Connectivity

Project

Prepared by DDIS for the Cuu Long Corporation for Investment, Development and Project

Management of Infrastructure (Cuu Long CIPM) and the Asian Development Bank.

CMDCP Resettlement & Social – Quarterly Report No. 16

i

CURRENCY EQUIVALENTS (as of 10 October 2018)

For this report, the rate of $1 USD: VND 23,310 has been used.

ABBREVIATIONS

ADB - Asian Development Bank

AP - Affected Person

CIPM - Corporation for Investment, Development and Project

Management of Infrastructure

CLFD - Center for Land Fund Development (Can Tho City)

CHLFD - Center for Housing & Land Fund Development (Dong Thap

Province)

CMDCP - Central Mekong Delta Connectivity Project

CY - Construction Yard

DDIS - Detailed Design and Implementation Support

DMS - Detailed Measurement Survey

DNA - Detailed Needs Assessment

DOLISA - Department of Labor, Invalids and Social Assistance

FU - Farmers’ Union

GOV - Government of Vietnam

HH - Households

IRP - Income Restoration Program

LUF - Land Use Fee

MOT - Ministry of Transport

MOU - Memorandum of Understanding

PAC - Provincial AIDS Center

ROW - Right-of-way

RP - Resettlement Plan

SAP - Social Action Plan

SES - Socio-economic survey

USD - United States Dollar

VND - Vietnamese dong

WU - Women’s Union

CMDCP Resettlement & Social – Quarterly Report No. 16

ii

NOTES

This Internal Social Safeguards Monitoring Report is a document of the borrower. The

views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the

Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

CMDCP Resettlement & Social – Quarterly Report No. 16

3

TABLE OF CONTENT

1. INTRODUCTION ............................................................................................................................ 5

2. OBJECTIVES OF INTERNAL MONITORING REPORT (IMR) ............................................................. 5

3. STATUS OF LAND ACQUISITION AND RESETTLEMENT ACTIVITIES............................................... 5

3.1 Civil Works Packages .................................................................................................................... 5

3.2 Status of Resettlement Activities ................................................................................................. 6

3.2.1 Status of Handover and Compensation ......................................................................... 6

3.2.2 Residual Resettlement ................................................................................................... 7

3.3 Relocated Households................................................................................................................ 11

3.4 Status of Payment of Compensation ......................................................................................... 12

4. OUTSTANDING RESETTLEMENT ISSUES ..................................................................................... 12

4.1 Land Assets in the 4 Interchanges.............................................................................................. 13

4.1.1 Interchange with NH 30 (CW1A) .................................................................................. 13

4.1.2 Three other Interchanges............................................................................................. 13

4.3 Physical Demarcation of the Safety Corridor for Stage 1 CMDCP ............................................. 14

5. GRIEVANCE PROCESS ................................................................................................................. 14

6. INCOME RESTORATION PROGRAM............................................................................................ 16

6.1 IRP Completion Report ............................................................................................................... 16

6.2 Disbursement ............................................................................................................................. 17

6.3 Liquidation of Funds ................................................................................................................... 17

7. SOCIAL ACTION PLAN ................................................................................................................. 17

7.1 Employment of Female Workers by Contractor ........................................................................ 17

7.2 Income Restoration Program for Shopkeepers at Ferry Sites ................................................... 18

7.3 Name on LURC............................................................................................................................ 18

8. HIV/AIDS AND HUMAN TRAFFICKING PREVENTION PROGRAM................................................ 19

9. MONITORING INDICATORS ........................................................................................................ 19

9.1 Land Acquisition and Resettlement ........................................................................................... 19

9.2 Income Restoration Plan ............................................................................................................ 21

9.3 HIV/AIDS and Human Trafficking Prevention program.............................................................. 22

Annex 1: List of pending grievances ................................................................................................ 23

Annex 2: Obstacles on the ROW ...................................................................................................... 25

Annex 3: Letter of Dong Thap PPC to allocate plot to Mr.Vo Trung Hue ........................................ 26

Annex 4: Status of Implementation of the Social Action Plan ......................................................... 27

Annex 5: Planning of Resettlement and Social Activities from October to Decembe r 2018 .......... 35

Annex 6: Disbursement to HH affected by the ferries in Dong Thap province ............................... 36

LIST OF TABLES

Table 1: Construction Status for each Package................................................................................... 6

CMDCP Resettlement & Social – Quarterly Report No. 16

4

Table 2: Updated Number of Affected Households ............................................................................ 6

Table 3: Dong Thap Province: Progress of Payment and Handover of Land to Contractors .............. 7

Table 4: Can Tho City: Progress of Payment and Handover of Land to Contractors .......................... 7

Table 5: Summary of Outstanding Resettlement Cases..................................................................... 9

Table 6: Households who Need to be Relocated .............................................................................. 11

Table 7: Households who Received a Plot in a RS............................................................................. 12

Table 8: Summary of Compensation Payments ................................................................................ 12

Table 9: Summary of Grievances for Land Acquisition ..................................................................... 14

Table 10: Summary of Results of the Land Survey ............................................................................ 16

Table 11: Costs estimate for MP ....................................................................................................... 16

Table 12: Staff Employed by Contractors by Gender ........................................................................ 17

Table 13: Status of Disbursement ..................................................................................................... 18

Table 14: Name on LURC in Plot Allocated in Resettlement Sites in Dong Thap Province ............... 19

Table 21: Indicators for Land Acquisition and Resettlement ............................................................ 19

Table 22: Indicators for Income Restoration Plan ............................................................................ 21

LIST OF FIGURES Figure 1: Division of the Project into Packages ................................................................................... 6

LIST OF ANNEXES

Annex 1: List of pending grievances.................................................................................................. 23

Annex 2: Obstacles on the ROW ....................................................................................................... 25

Annex 3: Letter of Dong Thap PPC to allocate plot to Mr.Vo Trung Hue ......................................... 26

Annex 4: Status of Implementation of the Social Action Plan .......................................................... 27

Annex 5: Planning of Resettlement and Social Activities from October to December 2018 ........... 35

CMDCP Resettlement & Social – Quarterly Report No. 16

5

INTRODUCTION

1. The Central Mekong Delta Connectivity Project (CMDCP) will improve connectivity in the Mekong Delta Region and provide efficient access from Ho Chi Minh City to the Southern Coastal Region through construction of two cable stayed bridges across the Mekong River and associated roads: Component 1: Cao Lanh Bridge (2.4 km) and approach roads (5.4 km); Component 2: Interconnecting Road (15.7 km); and Component 3: Vam Cong Bridge (2.97 km) and approach roads (4.08 km).

2. Resettlement Plans (RP) have been approved, for Dong Thap Province & Can Tho, City by ADB

on 5 April 2013. A RP Addendum for a new access road in Tinh Thoi commune (Dong Thap Province) was approved on 24 November 2014. A RP Addendum for the loops within the interchange with NH 30 and for the relocation of a 220 kV TL was also prepared in January 2018. ADB also approved detailed Income Restoration Programs (IRP) for Dong Thap Province and Can Tho City on 17 March 2015.

3. A Social Action Plan (SAP) has also been prepared and approved by ADB on 7 May 2013 and MoT on 4 July 2013. Finally, the HIV/AIDS and Human Trafficking Prevention Program has been

approved by ADB in June 2013 and by MOT on 26th August 2013.

3. CIPM is the representative of the executive agency (MOT) and is responsible for internal

monitoring. As per agreed RPs, CIPM has to submit monitoring report to ADB and MOT. This report constitutes the resettlement & social monitoring report covering period from March to November 2018.

1. OBJECTIVES OF INTERNAL MONITORING REPORT (IMR)

4. The objectives of the internal monitoring program are (i) to ensure that the standard of living

of AHs are restored or improved; (ii) to monitor whether the overall project and resettlement objectives are being met; (iii) to assess if rehabilitation measures and compensation are sufficient; (iv) to identify problems and risks; and (v) to identify measures to mitigate problems.

5. The range of activities and issues that need to be recorded and verified, include:

− Compensation, allowance payments and delivery of assistance measures to AHs; − Re-establishment of AH settlements and business enterprises;

− Reaction of AHs, in particular, to resettlement and compensation packages; and

− Re-establishment of income levels and living of AHHs

2. STATUS OF LAND ACQUISITION AND RESETTLEMENT ACTIVITIES

2.1 Civil Works Packages

6. Among the 8 packages, all have been awarded and received Notice to Proceed (NTP) and are under construction. These packages will be completed in the coming months except for the Vam Cong bridge (package CW3A) where completion is unknown due to technical issues.

CMDCP Resettlement & Social – Quarterly Report No. 16

6

Table 1: Construction Status for each Package

Package Award and signing NTP Planned completion

CW1A 29-Aug-14 29-Oct-14 April 2018

CW1B 15-Oct-13 25-Mar-14 March 2018

CW1C 5-Nov-14 29 Dec 2014 April 2018

CW2A 15-Dec-14 31 Dec 2014 April 2018

CW2B 15-Dec-14 31 Dec 2014 April 2018

CW2C 15-Dec-14 29 Dec 2014 May 2018

CW3A 15 Sep-13 26-Nov-2013 March 2019

CW3B 19 Mar-15 30-June-2015 April 2018

Figure 1: Division of the Project into Packages

2.2 Status of Resettlement Activities

2.2.1 Status of Handover and Compensation

7. A total of 1,891 HH (1,633 HH in Dong Thap Province and 258 in Can Tho City) are affected by

the project. Compensation is completed at 99.4 % for the whole project (94,8 % in Dong Thap and 99.6% in Can Tho). These numbers include the HH affected due to the clearance of the loops within

the interchange with NH30 (77 HH) and the relocation of the 220 kV TL (34 HH). 2 HHs isolated within the loop of the interchange with NH30 are also included (see Table 2 below).

Table 2: Updated Number of Affected Households

Affected HH Dong Thap Can Tho Total

RoW 1,520 258 1,778

2 HH isolated 2 2

NH30 Interchange Loops 77 77

Relocation of the 220 kV TL 34 34

Total 1,633 258 1,891

8. Handover of land is completed at 95,5% for the whole project (94,8 % in Dong Thap and 100%

CMDCP Resettlement & Social – Quarterly Report No. 16

7

in Can Tho). 85 HH (in Dong Thap province) have not handed over land: (i) In package CW1A, one HH (Mr Nguyen Thanh Qui) affected by both CMDCP and local project (198.2 m2) requested review of compensation rates for construction materials (wood) and assistance to move back his house on his remaining land. 7 HH affected by the 220 TL requested to increase allowance rate for land use limitation. 77 HH affected by the clearance of the loops have not yet been compensated due to CIPM has not allocated budget (under ask budget from MOT). It’s expected to allocate budget in November 2018.

9. In component 3, 1 HH (Can Tho City) has not yet compensated due mainly to dispute between heirs; however, this HH already handed over land to the project. Tables 3 and 4 present the status of

compensation and handover of land.

Table 3: Dong Thap Province: Progress of Payment and Handover of Land to Contractors

Components AHs Who Received Payment AHs Who Have Not Received

Payment Total No. of

AHs

Handed Over the Land

Have not Handed Over the Land Yet

Handed Over the Land

Have not Handed Over the Land Yet

Component 1 807 721 1 1 84 Component 2 619 619 0 0 0

Component 3 207 207 0 0 0 Total 1633 1548 85

Percentage 100 % 94.8% 5.2%

Table 4: Can Tho City: Progress of Payment and Handover of Land to Contractors

Components AHs Who Received Payment AHs Who Have Not Received Payment Total No. of

AHs

Handed Over the Land

Have not Handed Over the Land Yet

Handed Over the Land

Have not Handed Over the Land Yet

Component 3A 110 110 0 0 0 Component 3B 148 147 0 1 0

258 257 1 Percentage 100 % 99.6 % 0.4 %

2.2.2 Residual Resettlement

10. In QR15, there are 3 HH in package CW1A (Mr. Nguyen Thanh Qui, Vo Trung Hieu and Vo Trung Hue) who didn’t handover their land. However, now there is only 1 HH (Nguyen Thanh Qui HH) who has not handed over land.

11. Vo Trung Hue and Vo Trung Hieu HHs handed over land in June 2018. Mr.Hieu moved to My Tho RS and built new house (he was allowed to pay the plot in 5 years). Mr.Hue1: On 13 June, 2018, Dong Thap PPC issued the letter No.229/UBND-KTN and agreed to allocate the plot in Dong Rach Mieu Residential. These HH are very happy with solving of Dong Thap PPC.

12. Regarding Mr. Qui, on 18 May 2017, DONRE submitted compensation plan to Dong Thap PPC; it is proposed to compensate for wood at 100% of replacement costs in the acquired land; due to the

1 Mr. Hue is living with his son in Binh Duong province

CMDCP Resettlement & Social – Quarterly Report No. 16

8

high costs of the wood, HH will not be authorized to re-use the wood compensated; local authorities will collect the wood. On 18 September 2017, PPC approved the compensation plan. On 18 October, 2017, CDHLF invited this HH to receive compensation payment but this HH did not receive because they disagreed with compensation rate for wood. Under direction of Dong Thap PPC, DONRE held the meeting on 21 September 2018 to discuss about compensating for wood and acquiring remaining land (local authorities proposed to acquire remaining land and compensate fully for wood). This HH will response after discussing with their family.

CMDCP Resettlement & Social – Quarterly Report No. 16

9

Table 5: Summary of Outstanding Resettlement Cases

Name of HH

Commune /Ward

Received payment but didn’t

hand over land

yet

Didn’t receive

payment but

handed over land

Didn’t receive

payment and didn’t hand over

land

Package Reason for non-payment or non-hand-over

DONG THAP PROVINCE

1

Nguyễn Thanh Quí

An Binh

x

CW1A

- Affected by both local project and CMDCP; the HH requested review of compensation rate for construction material (wood); HH is partially affected;

- On 18 May 2017, DONRE submitted compensation plan to Dong Thap PPC; it was proposed to compensate for wood at 100% of replacement costs in the acquired land; due to the high costs of the wood, HH will not be authorized to re-use the wood compensated; local authorities will collect the wood.

- On 18 September 2017, PPC approved the compensation plan and HH disagreed with this plan.

- DONRE held the meeting on 21 September 2018 to discuss about compensating for wood and acquiring remaining land (local authorities proposed to acquire remaining land and compensate fully for wood). This HH will response after discussing with their family.

2 Lê Thị Nở An Binh x 220 TL

- Requested to be increased allowance rate for land use limitation 3

Trần Hoàng Thủy Tiên An Binh

x

220 TL

4 Lâm Thị Lệ Nga An Binh

x 220 TL

5 Nguyễn Thị Thảo An Binh

x 220 TL

6 Lý Khắc An Binh x 220 TL

CMDCP Resettlement & Social – Quarterly Report No. 16

10

Name of HH

Commune /Ward

Received payment but didn’t

hand over land

yet

Didn’t receive

payment but

handed over land

Didn’t receive

payment and didn’t hand over

land

Package Reason for non-payment or non-hand-over

Thiện

7 Bùi Văn Tèo An Binh

x 220 TL

8 Quách Thị Phu An Binh

x 220 TL

9 Võ Ngọc Thanh An Binh

x

220 TL - Small money

10 77 HHs An Binh

x Loop of NH30 IC

- Budget has not been yet allocated for payment. It’s expected to allocate budget in November 2018 and will pay for all HH in November 2018.

Subtotal Dong Thap 1 1 83 -

CAN THO CITY -

1

Nguyen Ngoc Manh x

CW3B - Mr. Nguyễn Ngọc Mạnh died; his heirs are disputing. Not yet

solved. Amount (68 M VND/3,000 USD) put at city’s treasury.

Sub-total Can Tho 0 1 TOTAL 1 2 83

CMDCP Resettlement & Social – Quarterly Report No.16

11

2.3 Relocated Households

13. A total of 603 relocated HH as their houses were totally affected and their remaining

residential lands were not viable. 350 HH (299 in Dong Thap and 51 in Can Tho) opted for self-relocation and 253 (209 in Dong Thap and 44 in Can Tho) to relocate in a serviced resettlement site.

Table 5: Households who need to be relocated

Package Commune/ward Affected HH

Household who Need Relocation

Total HH opted for Self-

Relocation HH opted to relocate

in RS

Component 1 807 116 155 271

CW1A An Binh 216 7 73 80

Ward 3 47 0 19 19

Tinh Thoi 370 93 33 126

CW1B

Tan My 1 174 16 30 46 CW1C

Component 2 619 124 50 174

Tan My 2 28 5 0 5

CW2A My An Hung B 175 6 26 32

Binh Thanh Trung

142 23 6 29

CW2B

Binh Thanh 173 72 1 73

CW2C Dinh An C2 101 18 17 35

Component 3 207 59 4 63

CW3B Dinh An C3 207 59 4 63

CW3A

Total Dong Thap 1633 299 209 508

CW3A Thoi Thuan 190 35 32 67

CW3B Vinh Trinh 68 16 12 28

Total Can Tho 258 51 44 95

TOTAL PROJECT 1891 350 253 603 Source: CHLFD/CLFD October 2018

14. At the time of the preparation of the report, only 35 HH built a house among a total of 234 HH who received a plot of land in a RS2 (see Table 6). 199 HH didn’t build a house yet even if they received compensation and handed over their land. Reasons for not building a house on the plot

allocated are the following: i) some HH kept the plots as an investment and are planning to sell the plot; ii) some AH want to keep the plot for their children; iii) some HH find plots in resettlement site too small for their family. Most of these HH already built a new house at another location.

2 15 HHs affected by the loop requested to allocate plot in Cao Lanh City and it is under review

CMDCP Resettlement & Social – Quarterly Report No.16

12

Table 6: Households who Received a Plot in a RS

Relocation Site Number of HH who

received a plot in a RS Number of plots3

Number of HH who built a house

Dong Thap Province 190 204 29 My Tho 57 59 15

Ward 3 22 28 4 Ward 6 22 24 0

Tan My 64 65 2

Dinh An 14 14 7

General Hospital 11 14 1

Can Tho City 44 55 6 Long Thanh 2 21 29 5

Thoi Thuan 23 26 1

Total 234 259 35 Source: CHLFD/CLFD October 2018

2.4 Status of Payment of Compensation

15. Compensation is almost completed for all components. The total compensation costs for Dong Thap province is VND 1054.3 billion (45.229 M USD). Compensation was made under the Government and provincial budget (part of Components 1 and 3) and under ADB OCR loan (part of Components 1 and 2). Up to now disbursement reached 992.2 billion VND (97%).

16. In Can Tho City, compensation was done under local funds. The total compensation cost is

VND 201 billion (9.0 M USD). Up to now the Government has funded VND 199.8 billion (92%).

Table 7: Summary of Compensation Payments

Component Total Nb

of HH

HH who received

compensation

Total compensation

Total disbursed Budget needed to

complete compensation

Billion VND Billion VND % Billion VND %

Component 1 807 722 463.8 407.7 88% 56.1 12%

Component 2 619 619 436.3 430.9 99% 5.4 1%

Component 3 207 207 154.2 153.6 100% 0.6 0%

Total Dong Thap

1633 1548 1054.3 992.2 94% 62.1 6%

Component 3 258 257 201 184.4 92% 16.6 8.3%

Total Can Tho 258 257 201 199.8 92% 16.6 8.3%

TOTAL PROJECT

1891 1805 1255.3 1192 95% 63.3 5%

Source: CHLFD/CLFD October 2018

3. OUTSTANDING RESETTLEMENT ISSUES

17. This section presents the outstanding issues regarding resettlement.

3 One HH can be allocated more than one plot, if extended families jointly reside on the same acquired lot and are eligible for separate HH registration books.

CMDCP Resettlement & Social – Quarterly Report No.16

13

3.1 Land Assets in the 4 Interchanges

3.1.1 Interchange with NH 30 (CW1A)

18. MOT approved clearance of the Interchange with NH 30 (CW1A) in letter No: 3259/BGTVT-

CQLXD issued on 29 March 2017 to ensure traffic safety, creating favorable condition for people to live and cultivate as proposed by Dong Thap PPC and Cuu Long CIPM.

19. The date of the public announcement by local authorities (cut-off date) is the 26 July 2017. DMS was conducted in July 2017. A qualified appraiser was hired by Dong Thap PPC to carry out a replacement cost survey (RCS) The RCS reports, which includes current market rates as proposed by

the qualified appraiser, was approved by Dong Thap PPC. In January 2018, Dong Thap PPC authorized to PC of Cao Lanh district to approve the compensation plan. It was approved on 13 March, 2018.

Budget has not been yet allocated for payment.

20. A RP for the loops of the interchange with NH30 was prepared in September 2017 based on DMS data and RCS. It was revised in October 2017 to include the land acquisition for the relocation of the 220 kV Transmission Line which is crossing the interchange. Comments from ADB were received in December 2017 and a revised version was submitted to ADB on 10 January 2018 and was approved by ADB in February 2018. A total of 77 HH area affected by the clearance of the loops and 29 HH will need to be relocated.

3.1.2 Three other Interchanges

21. On 20 August, 2018, MOT had a meeting with Dong Thap PPC and issued the notice No. 428/TB-BGTVT: Due to lack of capital, Dong Thap People's Committee agreed with MOT that land acquisition will not be implemented for three other interchanges. CIPM is assigned to study and propose technical solutions to enable people to have access to the loops and continue agricultural production, ensuring social security and traffic safety. CIPM is conducting the nest steps.

3.2 Relocation of 220 kV Electric Line in An Binh Commune

22. Two towers (No. 9 and 10) of the 220-kV transmission line Cai Lay - Cao Lanh and Cao Lanh - Thot Not, are located within the IC with NH 30 (see Figure 1-3) in package CW1A (An Binh commune). Based on MOT standards, the clearance between the existing line and the new bridge above NH30 (Dinh Chung bridge) is not sufficient. Therefore, the relocation of the line is needed. We should note that the new TL will cross one of the loop with the IC of NH 30. Four new towers will be necessary.

23. On 10/19/2015, CIPM sent a document No. 3900/ CIPM/QLDACL to Dong Thap PPC to request relocation of the 220-kV transmission line out of Dinh Chung Bridge.

24. DMS was conducted in July 2017 and a RCS was conducted in August 2017. A total of 33 will be affected, 1 HH will need to relocate. RCS was approved by PPC. In January 2018, Dong Thap PPC

authorized to PC of Cao Lanh district to approve the compensation plan. It was approved in March 2018.

25. A RP addendum for the loop of the interchange with NH30 which also includes the land acquisition/compensation for the relocation of the line has been submitted to CIPM on 11 October 2017 based on DMS and RCS. Comments from ADB were received in December 2017 and a revised version was submitted to ADB on 10 January 2018. 26/34 HH received compensation; 7 HH did not receive compensation and requested to increase allowance rate for land use limitation.

CMDCP Resettlement & Social – Quarterly Report No.16

14

26. Relocation of 220 kV TL started in August, 2018 and constructed 2 towers; 2 remaining towers have not been constructed because HH have not handed over land. It’s expected to finish in December, 2018.

3.3 Physical Demarcation of the Safety Corridor for Stage 1 CMDCP

27. As per Vietnamese regulations, the investor (CIPM) has to prepare the plan for removing demarcation marks and to submit the plan to Dong Thap PPC for approval and implementation. CIPM

assigned the contractor (VNC) to prepare documents. The contractor prepared documents and CIPM submitted them to PPC.

28. On 15 February, CIPM in letter No.: 385/CIPM-QLDACL requested Dong Thap PPC to get the legal basis for completing the design alternative of marks for the safety corridor as per the instruction of MOT by the letter No-. 13807/BGTVT-CQLXD dated 22 November, 2016.

29. On 17/08/2017, CIPM sent letter No.2273/CIPM-QLDACL to DOC. In this letter, CIPM indicated that Cao Lanh City PC only provided the boundary lines of some roads in Cao Lanh City (it is not the

boundary line for the CMDRCP). CIPM requested PC of Cao Lanh City to provide the boundary line in order to install the demarcation markers. Until now, PC of Cao Lanh City didn’t answer.

30. CIPM is directing the contractor (VND) to revise the design documents according to MOT’s comments.

3.3.1 Rental Allowance

31. Rental allowance was not paid to all HH in Can Tho City. Of the remaining 12 HHs (8 HHs in Vinh Trinh and 4 HHs in Thoi Thuan), 10 received these allowances. 2 HHs have not received rental

allowances: 1 HH went to oversee (Tran Van Dung: 10,200,000 VND), 1 HH cannot be contacted (Nguyen Phuoc Hai: 1,200,000 VND).

4. GRIEVANCE PROCESS

4.1 Resettlement and Land Acquisition Grievances

32. Dong Thap Province established a task force to manage the Project grievance redress process.

3 grievances remain in the Province.

33. Table 9 presents a summary of the reasons of grievances. The reasons for the eight grievances are the compensation rates for material, allowance rate for land use limitation. Annex 1 presents the details of each grievance with a time frame.

Table 8: Summary of Grievances for Land Acquisition

No Commune Total HH with Grievances

Increase material

construction rates

Increase allowance rate for

land use limitation Total

A COMPONENT 1 1 7 8

I An Binh 1 7 8

4.2 Environmental Complaints

34. Environmental complains cover complaints or claims for damages of houses or fields that

CMDCP Resettlement & Social – Quarterly Report No.16

15

occasionally come to force in connection with the ongoing construction activities. Among 542 complaints, 324 complaints caused by construction activities were solved, 218 complaints by land subsidence have not been solved.

4.3 Land Subsidence

35. According to Lap Vo district’s letter No.03/UBND-NN&PTNT dated 23 January, 2018, the total area affected by land subsidence is 61.19 ha with 218 affected households. The 3 affected communes

are: (i) Binh Thanh commune (5.72 ha/22HH); (ii) Binh Thanh Trung (29.083 ha/95 HH); (iii) My An Hung B commune (26.4/101 ha).

36. An Inception Report regarding impacts on livelihood due to land subsidence was prepared by

DDIS and submitted to ADB/DFAT on 3 October 2017. The inception report was approved by ADB/DFAT in October, 2017.

37. MOT in letter 12079/BGTVT-CQLXD dated 26 October, 2017 approved in principle the implementation of survey and assessment of land subsidence at CMDCP to determine compensation

for the affected households as requested by ADB/DFAT at Cuu Long CIPM. Bas ed on the above approval, Cuu Long CIPM is assigned appraisal and approval for the TOR and cost estimate for survey and assessment of land subsidence in the project.

38. Cuu Long CIPM approved the TOR, cost estimate for survey and evaluation work of the land subsidence in Decision 3625/QD-CIPM dated 8 December, 2017. On December 2017, CIPM sent letter

3643/CIPM-QLDACL to Lap Vo district PC to inform of the land survey and to ask Lap Vo district to put the necessary resources to support the implementation of the land survey.

39. The land survey was undertaken by the N&N Construction Investment Consultant JSC. The survey started on 6 February 2018 and was completed on 31 March 2018. The objectives of the survey were to identify areas affected by land subsidence and the severity of impacts (difference of ground level between pre-construction period and current situation) along sections where VCM was

used (i.e. 6 km).

40. The land survey was conducted in collaboration with local authorities and affected farmers.

Representatives of local authorities join the meeting. Each affected farmer was also present at the time of the measurement. Each affected farmer had to present an identity card, or the family registration book and proof of ownership (i.e. Land Use Right Certificate or other documents).

41. Results of the survey were submitted to farmers during the workshops conducted on 21 May 2018 in Binh Thanh commune, on 24 May 2018 in Binh Thanh Trung commune, and on 25 May 2018

in My An Hung B commune. During these workshops, each HH received an individual form with the following information: i) map of the plot of land with identification of the area affected by land

subsidence; ii) area affected by land subsidence; iii) average depth of land subsidence; and iv) volume of topsoil needed to restore land. 42. A total of 383 plots4 (247 HHs) have been recorded as affected by land subsidence and the

area affected is 66.78 ha. This area considers the adjustments of measurement following complaint

from farmers.

4 The data from the land survey measurement are by plot. Compensation will be done by plot

CMDCP Resettlement & Social – Quarterly Report No.16

16

Table 9: Summary of Results of the Land Survey

Land Survey

(February -March 2018)

Affected Area by Land Subsidence

(m2)

Affected plots5

Affected HHs

Binh Thanh 58,059 33 21

Binh Thanh Trung 292,026 166 102

My An Hung B 317,753 184 124

Total 667,838 383 247

43. The cost estimates to address the impacts linked to land subsidence are presented are: 49,154,504,391 VND equivalent to 2,158,266 USD (including 10% contingencies).

44. The compensation for crops corresponds to the remaining amount not paid by the Insurance Companies (3,965,923,977 VND). This amount must be recovered by CIPM in order to pay back the various agencies and to pay the remaining compensation for crops to farmers. Compensation for land corresponds to the amount to cover long term impacts.

Table 10: Costs estimate for MP

Amount

VND USD

1 COMPENSATION FOR CROPS (Temporary Impacts) 3,965,923,977 174,135

1.1 Remaining Payment Summer Autumn, Autumn Winter 2017 747,143,048 32,805

1.2 Payment for Winter Spring and Summer Autumn 2018 3,218,780,929 141,330

2 COMPENSATION FOR LAND (Permanent Impacts) 40,719,989,106 1,787,925

3 TOTAL BUDGET FOR CROPS AND LAND (1+2) 44,685,913,083 2,136,195

4 CONTINGENCIES (10%) 4,468,591,308 213,620

5 GRAND-TOTAL (3+4) 49,154,504,391 2,158,266

45. It is proposed that the compensation under the MP will be under the project loan (land acquisition and resettlement cost category) subject to approval by MOT and PM.

46. The report of assessment of impact of land subsidence on livelihood loss & management plan

to restore livelihoods was prepared by DDIS and submitted to ADB/DFAT in August, 2018. It’s watiting to response.

5. INCOME RESTORATION PROGRAM

5.1 IRP Completion Report

47. Final evaluation workshops were organized on 28 April in Can Tho and on 6 and 7 June 2017 in Dong Thap. An IRP Completion Report was prepared and submitted to ADB/DFAT in September 2017

5 One farmer can have several plots affected.

CMDCP Resettlement & Social – Quarterly Report No.16

17

for review and uploading on ADB website. This activity is now completed.

5.2 Disbursement

48. Can Tho City has disbursed 88.3% of the IRP budget and Dong Thap Province 99%. We should

note that, all expenses/fees for staff have to be justified. The non-used fund will be not disbursed by CHLFD without justification.

5.3 Liquidation of Funds

49. Regarding liquidation of funds used for the IRP, CLFD Can Tho prepared Interim Payment Certificate (IPC) in December 2015 (1,971,847,991 VND) and July 2016 (1,599,668,267 VND), and January 2018 (434,783,709 VND) and submitted to CIPM. CHLFD Dong Thap submitted the first IPC in August 2016 (8,477,199,081 VN), the second IPC in July 2017 (13,301,662,373 VND) and the third IPC in January 2018 (514,200,255 VND).

6. SOCIAL ACTION PLAN

50. Annex 4 presents the status of implementation of the Social Action Plan (SAP). The national

gender and social development specialist resigned by the end of December 2017; she will not be replaced.

51. A gender social completion report is planned to be prepared by the end of November 2018.

6.1 Employment of Female Workers by Contractor

52. Up to the end of October 2018, women represented 3.7% of all staff (11.2 % of management and office staff and 1.3% of workers). We should note that most of the civil works are now close to completion and a large number of staff have been demobilized. As per former reports, the number of women is more important among management and office staff (i.e. secretary, accountant, interpreter etc.) the workers. To explain why few women are employed as workers, contractors gave gender

stereotype reasons such as women do not like hard work and working outside under hot weather.

Table 11: Staff Employed by Contractors by Gender

Management & Office Staff Workers Total M. & Office staff &Workers

Men Women

Total %

Women

Men Women Total %

Women Men Women Total

% Women

CW 1A 4 0 4 0% 0 0 0 0% 4 0 4 0%

CW1B 8 4 12 33% 5 1 6 20% 13 5 18 28%

CW1C 2 1 3 33% 0 0 0 0% 2 1 3 33%

CW2A/2B 7 3 10 30% 4 1 5 25% 11 4 15 27%

CW2C 3 1 4 25% 0 0 0 0% 3 1 4 25%

CW3A NA NA NA NA NA NA NA NA NA NA NA NA

CW3B NA NA NA NA NA NA NA NA NA NA NA NA

Total 24 9 33 27% 9 2 11 18% 33 11 44 25%

Source: contractors October 2018

CMDCP Resettlement & Social – Quarterly Report No.16

18

6.2 Income Restoration Program for Shopkeepers at Ferry Sites

53. A revised IRP was submitted to ADB/DFAT in August 2017. ADB sent non-objection letter for

the implementation of the IRP on 12 October 2017.

54. MOT authorized CIPM to approve and implement the IRP on 7 November 2017 (letter 12530/BGTVT-CQLXD). CIPM approved the ToR and costs estimates for the IRP (115,833 USD) on 15 January 2018 (letter 128/QD-CIPM).

55. Kick-off meeting with Women’s Union of Dong Thap province and Long Xuyen City were organized respectively on 31st January and 1st February 2018. The purpose of the meetings were to

explain to WU, their tasks, the budget and the schedule.

56. In March 2018, WU of Dong Thap province and Long Xuyen City surveyed again to finalize the list of eligible HH in IRP.

57. CDM signed the contract No.01 dated 15 May, 2018 with WU’s Dong Thap province for implementation of IRP. Total value of the contract is 1,364,056,000 VND, including: 1,229,040,000

VND for HH and 135,016,000 VND for administrative cost. CDM transferred 1,310,049,600 VND (96%) to WU. WU’s Dong Thap province disbursed 996,465,000 VND (73.1%) - started from September 2018. Disbursement for HH will be finished by January, 2019. In October 2018, WU of Dong Thap province also provided the existing programs to HH (i.e. credit program, recruitment information of some enterprises,..).

58. For Long Xuyen, CDM signed the contract on 8 October 2018 with WU’s Long Xuyen City, value contract is 1,213,965,000 VND, including: 1,150,800,000 VND for HH and 63,165,000 VND for administrative cost. CDM has not transferred money to WU’s Long Xuyen City because waiting the guarantee certificates provided by WU. It’s expected to disburse to HH in November, 2018.

59. Table 13 presents the details of the disbursement.

Table 12: Status of Disbursement

Item

Contract Transfer by CDM Disbursement %Disbursement

Dong Thap Long Xuyen Dong Thap Long

Xuyen Dong Thap Long

Xuyen Dong Thap

Long Xuyen

Fixed business 444,960,000 246,240,000 444,960,000 0 419,040,000 0 94.2% 0%

Vendor 190,080,000 682,560,000 190,080,000 0 168,480,000 0 88.6% 0% Motorbike driver 594,000,000 222,000,000 594,000,000 0 353,250,000 0 59.5% 0%

Administrative cost for WU 135,016,000 63,165,000 81,009,600 0 55,715,000 0 41.3% 0%

Total 1,364,056,000 1,213,965,000 1,310,049,600 0 996,485,000 0 73.1% 0%

6.3 Name on LURC

60. Table 14 shows that still few LURC have been issued in both name of husband and wife. For the 127 HH who received a LURC (mainly in RS) in Dong Thap Province, only 11 HH have both name on

LURC while 65 are under husband’s name and 51 under the wife’s name.

61. As per Vietnamese Law, new LURC has to be issued in both name of husband and wife. However, by customs, new LURC follows the provisions of the former LURC (i.e. if only the husband

CMDCP Resettlement & Social – Quarterly Report No.16

19

name was on the former LURC, the new LURC will also be under the husband’s name). The explanation given is because the land came from inheritance from the husband or the wife’s family and they want to keep ownership. DDIS is working with WU to issue new LURC in both name.

Table 13: Name on LURC in Plot Allocated in Resettlement Sites in Dong Thap Province

No Resettlement Site Name on LURC Total

Wife Husband Both

1 Dinh An RS 0 0 0 0

2 Tan My RS 10 16 10 36

3 Ward 3 RS 13 8 0 21

4 Ward 6 RS 7 12 0 19

5 General Hospital 4 3 1 8

6 My Tho RS 17 26 0 43

Total 51 65 11 127 Source CHLFD October 2018

7. HIV/AIDS AND HUMAN TRAFFICKING PREVENTION PROGRAM

62. Updated HAPP/HTPP data unavailable due to resignation of the National HAPP/HTPP

Specialist. Final data will be provided following mobilization of the International HAPP/HTPP Specialist.

8. MONITORING INDICATORS

63. This section includes the progress against monitoring indicators.

8.1 Land Acquisition and Resettlement

64. Regarding indicators for land acquisition and resettlement, Table 26 summarizes the main

results.

Table 14: Indicators for Land Acquisition and Resettlement

Indicator Units Resettlement Plan Implementation Remarks

Land acquisition

HH

- Dong Thap: 1,336 - Can Tho: 219 - Total: 1,555

- Dong Thap: 1,633 - Can Tho: 258 - Total: 1,891

- Changes are due to: i) adjustment of number of HHs in Construction Yard; ii) some HH with several families were first considered as one AH and were then separated in 2 or more AHs; and iii) a number of HH, affected by loss of grave only were first not included among the AHs (Can Tho city); (iv) new access road in Tinh Thoi commune; (v) 10 new HH affected by both CMDCP and local project; (vi) 5 HH excluded in Tan My commune due to change in design; (vii) acquire land in the loop of

CMDCP Resettlement & Social – Quarterly Report No.16

20

Indicator Units Resettlement Plan Implementation Remarks

IC NH30 and 220 kV TL;

Ha - Dong Thap: 199.7 - Can Tho: 54.8 - Total: 254.5

- Dong Thap: 196 - Can Tho: 28.5 - Total: 224.5

- Changes are due to: i) reduced area for construction yards; and ii) toll plaza removed;

Disbursement of compensation & allowances

Billion VND Total

- Dong Thap: 44.5 M USD

- Can Tho: 6.09 M USD

- Total: 50.57 M USD

- Dong Thap: 45.2 M USD

- Can Tho: 8.6 - Total: 53.8 M

USD

- Compensation is now almost completed (95%)

Disbursement of compensation & allowances within agreed time limit

% Total

- Dong Thap: 94% - Can Tho: 99% - Total: 95% -

Compensation plans agreed jointly by husband and spouse

% eligible cases

N/A

- Husband: 75% - Spouse: 25% - Both: 0%

- Based on EM Report, none of the compensation plans (CPs) of AHs in Can Tho and Dong Thap had been signed jointly by husband and wife; either the husband or the wife signed the CPs, depending under whom the land use rights certificate (LURC) of the affected properties was named.

Provision of consultation counselling

Activity comple-tion

- - Dong Thap: 100% - Can Tho: 100%

- Activity completed by Women’s Union;

Households self-relocated

Total HH

- Dong Thap: 23 - Can Tho: N/A

- Dong Thap: 299 - Can Tho: 51

- More HH opted for self-relocation during implementation; possible reasons: i) cash grant allowance for self-relocation; ii) distance of RS from affected area;

- Most of the relocated HH who received a plot in RS didn’t yet relocate (only 35 AH built house in RS)

Households relocated to service resettlement site

HH built a house/ Total HH

- Dong Thap: 415 - Can Tho: N/A

- Dong Thap: 29/177

- Can Tho: 6/44

LURC/asset titles issued jointly in husband and spouse names

% Total eligible

- - Dong Thap - Husband: 65HH - Wife: 51 HH - Both: 11 HH

- Can Tho - No LURC issued

yet in RS

- Data on LURC for HH who relocated in RS only recorded by CHLFD/CLFD;

- Few LURC (127) issued up to now (none in Can Tho): HH have 5 years to pay for land use fee; they will receive LURC when fees will be paid

Resettlement completed within agreed time limit

% Total % Vul. HH

- - - Major delay for resettlement & compensation for component 2 due to delay in loan effectiveness;

Beneficiaries satisfied with

- - 100% satisfied - Activities completed based on WU

monitoring reports;

CMDCP Resettlement & Social – Quarterly Report No.16

21

Indicator Units Resettlement Plan Implementation Remarks

compensation counselling Outstanding cases of grievance with compensation rates for land

- - Dong Thap: 7 - Can Tho City: 0

- 7 HH requested to increase allowance rate for land use limitation;

Beneficiary satisfaction with resettlement site

- - Dong Thap: 100% - Can Tho City:

100%

- 29 HH relocated up to now in RS in Dong Thap and 6 in Can Tho;

- Up to now all satisfied due to better living conditions based on interviews; some HH however indicated that due to the few number of HH relocated, there is few business opportunities;

Outstanding cases of grievance with resettlement process

- Dong Thap: 8 - Can Tho City: 0

- 1 case of grievances regarding compensation rates for construction material, 7 cases regarding allowance rate for land use limitation.

8.2 Income Restoration Plan

65. The IRP activities for affected households are now completed.

Table 15: Indicators for Income Restoration Plan

Indicator Units Income Restoration Plan Implementation

Dong Thap Can Tho

Training • Agriculture (Agr.)

• Vocational Training (VT)

• Small business (SB)

Nb of HH trained

- Agr. Training

168/790 HHs 139 M 29 F

- VT: 14/14

10 M - 4 F

- SB 156/346 - 91 M 65 F

- Agr. Training

49/55 42 M - 7 F

- VT: 28/28

21 M - 7 F

- SB 37/50 12 M - 25 F

– Agriculture training completed in CT; in DT, due to change of activities new training will be needed; training for pigs ongoing;

– Vocational training completed in DT & CT; 45 HH changed of activity

– Training for small business is completed in both DT & CT;

– A large number of HH didn’t follow training (no time, have already experience)

Input delivered

• Agriculture • Vocational Training

• Small business

HH who received inputs

- Agr. 790/790 - VT: 13/13 - SB: 346/346

- Agr. 58/58 - VT: 26/26 - SB: 57/57

– Inputs were delivered completely

Overall expenditure of IRP against plan

Disbursed/ Total VND

– 21,541,765,850 VND disbursed /23.088,189,200 VND (93.3%)

– 2,722,080,465 VND disbursed /3,081,996,612 VND (88.3%)

CMDCP Resettlement & Social – Quarterly Report No.16

22

8.3 HIV/AIDS and Human Trafficking Prevention program

66. Updated HAPP/HTPP data unavailable due to resignation of the National HAPP/HTPP Specialist. Final data will be provided following mobilization of the International HAPP/HTPP

Specialist.

CMDCP Resettlement & Social – Quarterly Report No.16

23

Annex 1: List of pending grievances

Names Contract

Compensation Paid

Handover of Land

Date of first

grievance filed/

request made

Nature of Grievance/Request

Status Full Parts

Not yet

Handed over

Not yet

1/ CW1A

Nguyễn Thanh Quí X X 2015 CASE: GRIEVANCE

- The HH has not yet allowed project authorities to dismantle the frontage of its house-cum-shop that is marginally affected by the access ramp of An Binh Interchange. He is asking for an additional VND1.8 billion for the expensive wood paneling used on the wall of his structure.

Affecting Construction Works: YES 191 m2

(construction of the West Access ramp) - Affected by both local project and CMDCP;

Request review of compensation rate for construction material (wood) and to move back his house; HH is partially affected;

- On 18 May 2017, DONRE submitted compensation

plan to Dong Thap PPC; it is proposed to

compensate for wood at 100% of replacement

costs in the acquired land; due to the high costs of

the wood, HH will not be authorized to re-use the

wood compensated; local authorities will collect

the wood. On 18 September 2017, PPC approved

the compensation plan. On 18 October, 2017,

CDHLF invited this HH to receive compensation

payment but this HH did not receive because they

disagreed with compensation rate for wood.

- Under direction of Dong Thap PPC, DONRE held

the meeting on 21 September 2018 to discuss

about compensating for wood and acquiring

CMDCP Resettlement & Social – Quarterly Report No.16

24

Names Contract

Compensation Paid

Handover of Land

Date of first

grievance filed/

request made

Nature of Grievance/Request

Status Full Parts

Not yet

Handed over

Not yet

remaining land (local authorities proposed to

acquire remaining land and compensate fully for

wood). This HH will response after discussing with

their family.

7 HH: Lê Thị Nở Trần Hoàng Thủy Tiên Nguyễn Thị Thảo Lý Khắc Thiện Bùi Văn tèo Quách Thị Phu Lâm Thị Lệ Nga

x x 2018 CASE: GRIEVANCE

- These HH requested to increase allowance rate for land use limitation

- PC of Cao Lanh district received their complaints

and they are checking documents and will

response soon.

CMDCP Resettlement & Social – Quarterly Report No.16

25

Annex 2: Obstacles on the ROW

No Commune Type of

infrastructure Location Owner of infrastructure Status of relocation

– 220 kV – 0 km to 0 km + 300 – Electricity of Vietnam

- 2 towers was constructed, 2 remaining towers have not been constructed because of obstacles. It’s expected to complete in December 2018.

CMDCP Resettlement & Social – Quarterly Report No.16

26

Annex 3: Letter of Dong Thap PPC to allocate plot to Mr.Vo Trung Hue

CMDCP Resettlement & Social – Quarterly Report No.16

27

Annex 4: Status of Implementation of the Social Action Plan

Issues Actions Required in

FS & Timing

Actions Taken During

Detailed Design Status of implementation as of 31 October 2018 Issues/challenges

i. Land

Acquisition and Resettlement

- Resettlement Plans

prepared for Components 1 to 3

and agreed on by ADB and the Government of Vietnam

- (From 2011 -

- Based on draft Resettlement

Plans (RPs) prepared by TA consultants during FS,

finalized draft RPs based on detailed design and in accordance with ADB Safeguard Policy Statement.

- As part of the RPs, income restoration programs (IRPs) were prepared and funded

under DDIS Contract.

- RP implementation is almost completed. See separate

Annex for details;

- Draft RP Addendum for the loops in the interchange

with NH 30 prepared on 13 September 2015;

- IRP was implemented from April 2015 to May 2017

among 1,190 households (1,249 in Dong Thap Province and 141 in Can Tho City).

- Final evaluation workshops were conducted in April

2017 in can Tho and in June 2017 in Dong Thap. IRP completion report was prepared in June 2017;

- Due to lack of capital, Dong Thap People's

Committee agreed with MOT that land acquisition will not be implemented for three

other interchanges. CIPM is assigned to study and propose technical solutions to enable people to have access to the loops and continue agricultural production, ensuring

social security and traffic safety.

- Implementation of the IRP was found satisfactory. With the help of the IRP most of

the participants could stabilize their l ivelihood. Most of the participants are satisfied with the program and the activity chosen generate income which is usually a

secondary income for the family

- Several small businesses sold their inputs or stopped their small business due to i) lack of customers due to unsuitable shop location;

some HH prefer to sell directly in nearby market i i) not enough profit; i i i) i l lness of wife/husband.

- HH who chose raising cows and pigs were affected by the decrease of the price of meat

and some didn’t reinvest in the activity after 2 years.

ii. Livelihoods

Associated

with Ferry Traffic and Changed Traffic Flow

- Income restoration

strategy for affected

persons and businesses.

- (2014-

- Ferry service will be

maintained for Cao Lanh by

the DOT of Dong Thap Province (see MOU review mission 25-29 April 2016).

- At PCC meeting #3 (August

2012) it was agreed that the future of ferry services at

- Preparation of IRP started in October 2016 (planning of

survey, discussion with local authorities) with support of

the DDIS gender national consultant.

- Workshops have been conducted at the end of November 2016 to assess need of shopkeepers/hawkers/ motorbike drivers.

- The revised IRP was submitted to ADB in August 2017.

- Identification of appropriate alternative

l ivelihood for the affected shopkeepers/

hawkers is a challenge.

CMDCP Resettlement & Social – Quarterly Report No.16

28

Issues Actions Required in

FS & Timing

Actions Taken During

Detailed Design

Status of implementation as of 31 October 2018 Issues/challenges

Vam Cong bridge would be

subject to the results of a demand study.

- Maintaining these ferry

services is a requirement set out in the project’s loan agreement

The IRP includes the following measures: i) support in

cash or in petrol bonds during the transition period; and ii) facilitation to existing programs for income restoration.

- WU of Dong Thap and An Giang provinces will be involved in the implementation of this IRP. Kick off meetings with Wus were conducted on 31 January, 2018 and 1 February, 2018.

- CDM signed contracts with WU of Dong Thap province in May 2018 and WU of Long Xuyen City in October 2018.

- CDM transfer 1.3 bil l ion VND to WU of Dong Thap

province. WU of Dong Thap province disbursed with amount of 996 mill ion VND.

- CDM will transfer money to WU of Long Xuyen City when having guarantee certificate from them. It’s

expected to disburse to HH in November 2018.

iii. Access and

Mobility

- Improvement of local

road networks in the project area and inclusion of crossings

(bridges/underpasses) during the DD phase of the project. The

design of local road systems and crossings is based on detailed needs assessment of

local communities.

- (2012 -)

- A survey on the needs

assessment of local communities related to the design of local road systems

and crossings was prepared in December 2010.

- Reviewed technical

drawings.

- Report part of 2011 FS

- DDIS monitored closely and have so far ensured Technical drawing include of existing access through bridges/underpasses.

- At Km 6+44 an access planned the design under the new road was not included in the construction drawings; two alternatives were proposed one under the road as

planned or a detour of 1 km to an existing bridge (South approach to Cao Lang bridge). Following discussion with community and regarding technical and cost issues, a detour was agreed and built to ensure connection.

-

iv. Affordability

- Toll fees not to be

higher than ferry user fees

- (2016 -)

- The Government has issued

a circular (MOF Circular No.197/2012/TT-BTC

dated 15/11/2012 on Collection of Road

- No further action is required given the abolishment of

tolls on national highways; -

CMDCP Resettlement & Social – Quarterly Report No.16

29

Issues Actions Required in

FS & Timing

Actions Taken During

Detailed Design

Status of implementation as of 31 October 2018 Issues/challenges

Maintenance and Fee

abolishing tolls on national highways

v. Road Safety - Road safety audit to

be undertaken

during detailed design.

- (2016)

- DDIS undertook road safety

audit in October 2012.

- Detailed design has incorporated the following measures: (i) the right-of-way (ROW) will be fenced for

safety reasons and to secure the corridor only after the second phase (6 lanes); and (i i) all crossings will be done

under bridges or through underpasses in the embankment

- Since no horizontal crossing will be allowed, community road safety awareness is no longer necessary

- Road safety report prepared (2013);

- Pre-Opening Road Safety Audit will be conducted 6 months before traffic is allowed on the road based on government of Vietnam requirements.

-

- As per MOU following the September 2016

ADB/DFAT mission, it was agreed that CIPM

will advise ADB how it intends to undertake the required road safety audit.

- DDIS will follow up preparation of such audits. No safety audit prepared up to now.

vi. Risk of

HIV/AIDS & Human Trafficking

- A HIV/AIDS and

Human Trafficking Awareness and Prevention Program will be prepared and

implemented.

- Undertook detailed planning

in consultation with various stakeholders such as Provincial AIDS centers, Women’ Union from April to

September 2012

- HIV/AIDS and Human Trafficking HIV/AIDS and Human

Trafficking Prevention Program has been approved by ADB in June 2013 and by MOT on 26th August 2013

- The program has recruited and gave skill training on HA and HT awareness raising skills to 36 outreach Educators

(OEs) (18 women, 18 men) and 14 peer’s educators (PEs) (12 women, 2 men)

- OEs and PEs have reached 141.474 turns of participants of

community people (71.211 female among them); 14.094 turns female sex workers and 1224 IDUs, delivered 135.074 condoms and 123.007 leaflets, conveying messages with focus on the HAPP and HTPP.

- IEC campaign: 6 times/communes in Can Tho and 6 times/commune in Dong Thap reached 2110 men, 2187

- The program provides additional training on

human trafficking prevention to grassroots women’s union members in each location

CMDCP Resettlement & Social – Quarterly Report No.16

30

Issues Actions Required in

FS & Timing

Actions Taken During

Detailed Design

Status of implementation as of 31 October 2018 Issues/challenges

women, distributed 6151 IEC materials and 6907

condoms

- The program supported HIV/STI testing to 3.388 people. The testing result were informed to concerned individuals

and information on availability of care and treatment is also provided to them.

- HIV/AIDS awareness

and prevention measures to be

included in the contractors’ contracts.

- - HIV/AIDS prevention measures included in the

contractors’ contracts (item Section 1.1 Social Provisions in Contract Documents);

- All 8 packages (CW1A, CW1B, CW1C, CW2A, CW2B, CW2C, CW3A, CW3B) have HIV/AIDS awareness raising sessions going on with workers. Service providers have conducted 77 HIV/AIDS education sessions for 2,533

construction workers6, distributed 69,607condoms and 7065 IEC materials; HIV and STIs examined and tested for 1377 workers. Nobody had HIV positive.

- IEC materials in Chinese is well appreciated by Chinese related contractors and staff.

- Delays receiving activity data from service

providers for CW Package 3A and 3B

- Service providers will ensure “Female-Only

Education Sessions” on STI/HIV/reproduce-tive health are provided by female health professional at all CW packages or carry out separate Q&A with female workers if separate

sessions are not practical to arrange

- Service providers wi ll ensure confidential HIV-testing process at the construction sites

- Service providers will ensure that HIV/AIDS sessions are held for 20-30 participants only to ensure effective communication

- Service providers will update the workers on

HIV/AIDS prevalence situation at the CW site’s localities on a regular basis.

vii. Women - Gender concerns are

to be main-streamed in all project

components, as part of the RPs, HIV/AIDS and Human

Trafficking Awareness and

- Considered partnership with

Women’s Union (WU). Undertook extensive

consultations with Women’s union at all levels to assess WU’s capacity, commitment,

and available resources from 2013to 2017.

- CIPM, through DDIS consultant entered a partnership

with Women’s Union for the following activities: (i) resettlement plan including income restoration program;

and (i i) HAPP and HTPP. Estimated cost: 68,363 USD (excluding IRP and HAPP & HTPP).

- For resettlement activities: WU followed-up implementation and assisted women and vulnerable

- 78/790 HH in Dong Thap and 17/57 HH in Can Tho stopped agriculture activity at the end of a production cycle and didn’t reinvest; the main

CMDCP Resettlement & Social – Quarterly Report No.16

31

Issues Actions Required in

FS & Timing

Actions Taken During

Detailed Design

Status of implementation as of 31 October 2018 Issues/challenges

Prevention Program,

Income Restoration Strategy, Road Safety, Labor issues,

& Communication Plan.

- (2011 – 2017)

groups; WU conducted focus groups discussions with

women and vulnerable groups; WU were present during consultation and encouraged women to participate; WU also followed-up relocation of HH;

- For Income Restoration Program (IRP): IRP includes 3 components (Agriculture farming, vocational training and small business training) and inputs (cow, pig, groceries supplies, etc.) to start up new livelihoods.

- In Agriculture program 790 HH in Dong Thap and 57 HH in Can Tho received animals (cows and pigs) and attended training.

- For small business program, 346 HH in Dong Thap and 53 HH in Can Tho received inputs (equipment) and attended training.

- For vocational training, 13 persons in Dong Thap & 23 HH

in Can Tho followed training. All could find a job.

- The small business training has been led by women union and intended to target women in AHs. IRP was completed in April 2017.

- Participation of women in IRP (who still implement activity by April 2017) in Dong Thap Province

- Agriculture

- Total 790 pers.: M: 441 (56%); W: 101 (13%) Both M & W: 248 (31%)

- Vocational Training - Total 13 pers.: M: 10 (77%); W: 3 (23 %)

- Small Business - Total 333 pers.: M: 84 (25%); W: 158 (48%) both: 91 (27%)

- Participation of women in IRP (who still implement

activity by April 2017) in Can Tho City

- Agriculture - Total 57 pers.: M: 51 (89%); W: 6 (11%)

both: 0 (0%)

reason is the decrease of the price of meat

(i.e. for pig and cow) and HH didn’t find profitable to re-invest in such activity.

- Dead animals have been replaced in Dong

Thap (6 HH: 7 pigs, 4 cows) province in December 2016 and in Can Tho City (for 5 HH: 6 pigs and 100 chicken) in May 2017;

- 13/346 HH in Dong Thap and 23/53 HH in Can Tho stopped small business activity before the end of the IRP implementation period (2

years); the main reasons i) lack of customers due to unsuitable shop location; i i) some HH prefer to sell directly in nearby market i i i) not enough profit; i i i) illness of wife/husband.

- For small business, there is a majority of women in charge of the activity;

- For agriculture activity, it is more considered

as a family activity and 31% of both men and women were involved in the activity;

- For vocational training, a large majority of

men were trained;

CMDCP Resettlement & Social – Quarterly Report No.16

32

Issues Actions Required in

FS & Timing

Actions Taken During

Detailed Design

Status of implementation as of 31 October 2018 Issues/challenges

- Vocational Training

- Total 26 pers.: M: 22 (84%); W: 4 (16 %) - Small Business

- Total 30 pers.: M: 16 (53%); W: 14 (47%)

- For HAPP and HTPP, WU are also involved in the

implementation of the HAPP & HTPP for community. The details of implementation results are presented above in

section vi.

- Capacity building: Six rounds of capacity building for gender mainstreaming were conducted in Dong Thap

province and Can Tho City respectively in September 2014, May 2015, September-October 2015, May 2016, November 2016 and July-August 2017;

- A total of 818 persons (65% of women) were trained in

these 6 rounds. Training were about time management, HRM, financial management, problem solving skills in small business and gender analysis tools, communication skil ls training.

- Case studies regarding women involved in IRP have been prepared and included in the quarterly reports #11-12 and in the IRP completion report.

- Women Union’s representatives express the

wish to be trained on conflict management so they can monitor and support small

business program more effectively. Training on conflict management was given during the fifth round of capacity building on 15-16

November 2016;

- Results of the Social Action Plan implementation to be accumulatively

reported in routine reports to donors; especially document success stories/case studies.

viii. Labour - Contractors’

contracts to include conditions to ensure occupational health and safety; do not

differentiate payment between women and men, and those who

- Contractors’ contract has

been reviewed to ensure that clauses related to OH&S and gender equity issued are included

-

- The contractors’ contracts include Clauses related to: i)

Occupational Health & Safety; i i) promotion of gender equity and prevention of gender-based discrimination; and ii i) prevention of use of child labour have been included in contractors’ contracts (Clauses: 6.1, 6.7 and

6.21)

Female workers are paid equally as male workers for the same work7.

- DDIS consultant on occupational health and safety

-

CMDCP Resettlement & Social – Quarterly Report No.16

33

Issues Actions Required in

FS & Timing

Actions Taken During

Detailed Design

Status of implementation as of 31 October 2018 Issues/challenges

belong to local

ethnic Khmer groups, for work of equal value; prevent

use of child labor; and comply with the government’s labor laws and related

international treaty obligations

monitored the contract compliance regularly (visiting the

CW packages and remind the contractors of the compliance requirements. Recent civil work site accidents (CW1A and CW1B) were an alarm for a requirement of

stricter compliance on this.

- In general compliance with occupational health and safety is paid sufficiently attention too by contractors by giving training to workers, providing protective

equipment (clothes, boots, helmets, gloves), monthly meeting was conducted to emphasize important of the compliance8.

- DOLISA inspected the site of CW1A and CW1B on 20 October 2016.

- There are few female workers in the CW packages. Up to the end of July 2017, women represented 3.7% (48/1,308)

of all staff (11.2% (35/303) of management and office staff and 1.3% (13/970) of workers) contractors report that they often don’t intend to recruit women for hard work and women apparently have other choices (small

business, wage labors, etc.)

- No child labor is observed in the work s ites.

- DOLISA to conduct more regular health and

labor safety inspection at contractor sites to

strengthen the effort of safety in the sites

ix. Indigenous

Peoples

- No action required;

already included

under labour issue

- DDIS carried out its own

assessment. Ethnic

minorities have not been identified as an issue in the proposed project. No ethnic Khmer is affected.

- Specific to labour issues, reviewed the contractor’s contract.

- Clauses related to prevention of personal characteristics

based on discrimination have been included in contract

documents; (clause 6.4 on labour laws)

-

CMDCP Resettlement & Social – Quarterly Report No.16

34

Issues Actions Required in

FS & Timing

Actions Taken During

Detailed Design

Status of implementation as of 31 October 2018 Issues/challenges

x. Poor

Communi-cation/ Information

Dissemination

- A communication

plan will be prepared.

- (2011- 2016)

- - Communication strategies are included in the following

documents: (i) Resettlement Plans; (i i) HAPP and HTPP; (i i i) Ferry operations; and (iv) Gender Strategy report.

- CIPM/DFAT prepare quarterly reports on social and

resettlement, covering how communication and information dissemination is implemented.

- Stakeholders interviewed have accessed to information on the project (knowing when the project is going to be

completed)

-

xi. Consistent

application of safeguards

- Adoption of

common ADB safeguard policies and requirements

for all project components

- (2011- 2016)

- DDIS worked with Local

authorities in charge of resettlement implementation

- The Final Resettlement Plans prepared cover KEXIM

section. The Resettlement Plans were prepared in accordance with ADB Safeguard Policy Statement.

-

CMDCP Resettlement & Social – Quarterly Report No.16

35

Annex 5: Planning of Resettlement and Social Activities from October to December 2018

OCTOBER NOVEMBER DECEMBER

RESETTLEMENT

- Supervision activities - Continuous - Continuous - Continuous

SOCIAL ACTION PLAN

- Income restoration for livelihoods

affected at ferry sites

- Implementation of IRP

- Implementation of IRP

- Implementation of IRP

COMPLETION REPORT

- - Preparation of the

completion report

CMDCP Resettlement & Social – Quarterly Report No.16

36

Annex 6: Disbursement to HH affected by the ferries in Dong Thap province