Vibratory Caisson: A Case Study in the Southwestern Deserttsdos.org/media/presentation2019/Farahani,...
Transcript of Vibratory Caisson: A Case Study in the Southwestern Deserttsdos.org/media/presentation2019/Farahani,...
SEPTEMBER 4 - 6, 2019
Vibratory Caisson: A Case Studyin the Southwestern Desert
By Majid Farahani, P.E.Leidos Engineering, LLC
SEPTEMBER 4 - 6, 2019
INTRODUCTION• Tucson Electric Power (TEP) is a municipal utility located in Tucson, AZ
• TEP operates 46, 138, 345 and 500 kV overhead lines
• Maintenance had identified foundation of structure#30 on TEP’s 138kV Transmission Line-114 to be out of alignment
• Closer inspection showed the piles below the reinforced concrete cap to be twisted and bent
• The decision was made to replace this structure as soon as possible.
• The structure was placed on order and one of the options considered was use of a vibratory caisson. No one had tried in the Southwest at that point.
• The intent of this presentation is to share that experience with you.
SEPTEMBER 4 - 6, 2019
INTRODUCTION
What is a Vibratory Caisson?A vibratory caisson is a hollow end tubular steel shaft with typically zero taper. The cross section may be round or polygonal. A hydraulic hammer mounted on top of it allows it to be accelerate/vibrate the soil in contact with the caisson. The soil loses its axial capacity and effectively becomes liquefied. This allows the caisson to drop through the soil. Once the hammer is turned off, the soil returns to its post vibration natural state and foundation is ready for use.
SEPTEMBER 4 - 6, 2019
INTRODUCTIONThere are 3 types of common connections available between the pole and caisson:
• Base-Plated/Flanged Connection
• Drop-in Type
• Slip-Jointed Connection
SEPTEMBER 4 - 6, 2019
DESIGN CONSIDERATIONSGeotechnical Investigation• 1 boring to the depth of 86.5 ft
• No water encountered at the time of boring
• Wash protected by soil-cemented banks which rose to 10 ft above the bottom of wash at the time
• Soil was sand & gravel to gravelly sand with varying layers of cemented clay in between
• At 30 ft N=94, at 45 ft N=59 and at 50 ftN=81
SEPTEMBER 4 - 6, 2019
DESIGN CONSIDERATIONSFoundation Design• No specific guide or standard for design of vibratory caissons in transmission
lines• As of early 2018, CEATI was attempting to form a study group on Vibratory
Caisson Design• Approach: no different than other deep foundations• Impact of vibration on coefficient of friction• Soil confined on the inside of caissonGeotechnical Recommendation:
22 ft below the scour depth with 0.5 degree rotation15 ft below the scour depth with 1.5 degree rotation(both per Broms method*)
* Broms, Bengt B. (1964). “Lateral Resistance of Piles in Cohesion-less Soils.” Journal of The Soil Mechanics and Foundation Division, Proceedings of The American Society of Civil Engineers. Vol. 90, Issue 3, pp. 123–156.
SEPTEMBER 4 - 6, 2019
DESIGN CONSIDERATIONS
Structural Aspects of Design• Matching resulting
moment capacity above and below the scour depth
• Connection plates
SEPTEMBER 4 - 6, 2019
DESIGN CONSIDERATIONSOther Considerations –
Scour• 100-year flow
• Flood control use permit
• Scour depth changed from 29 ft to 22 ft with newer velocity data
• F.S. = 1.3
SEPTEMBER 4 - 6, 2019
DESIGN CONSIDERATIONSOther Considerations –
Rotational Movement of Caisson• Oversizing the holes in base plate
• Rotate the pole above its slip joint
• Drilling new holes for line post insulators
• Slotting the holes in the base plate
SEPTEMBER 4 - 6, 2019
DESIGN CONSIDERATIONSOther Considerations –
Impact by Floating Objects and Corrosion• Top 30 ft of caisson out of 7/8-in plate
• The balance was 1/2-in plate
• The caisson was hot dipped galvanized
• The caisson was coated with CorroCote II Classic, both inside and outside to a thickness of 35 mils, minimum average
SEPTEMBER 4 - 6, 2019
PUBLIC OUTREACH
• Vibration Impact: Residents adjacent to the area were placed on notice, however, the vibration could not be felt 40-50 feet away from the location
• Noise Impact: Most of the noise generated was muffled by the heavy traffic in adjacent River Avenue
SEPTEMBER 4 - 6, 2019
CONSTRUCTION SEQUENCE
• Environmental restrictions: drive over riverbed• Hammer and its supervisor rented by
contractor• Excavation of 5 ft deep hole for alignment• Boulder encountered• It took 18 minutes to drive the caisson 45 ft
deep
SEPTEMBER 4 - 6, 2019
CONSTRUCTION SEQUENCE
Cost Comparison• Vibratory Caisson $132,400 Total 1-Day Installation
• R.C. foundation $ 142,500 Total 4-Days installation and 28 days to cure
• 250 ton-ft hammer at $4,000
• 600 ton-ft hammer at $600 more!
SEPTEMBER 4 - 6, 2019
CONSTRUCTION SEQUENCE
Intended Versus Actual
• The objective was to drive the caisson 50 feet deep
• The caisson was vibrated in 45 feet before we hit a layer that we could not break through
• Design required 44 feet of burial depth
SEPTEMBER 4 - 6, 2019
LESSONS LEARNED/BENEFITS/DISADVANTAGES
Lessons Learned• Below grade coating application – special attention
• Additional soil borings to develop a better profile
• Load case combinations – don’t need worst case river flow + worst case overhead simultaneously
• Hammer size selection
• Take noise level readings before and during the installation
SEPTEMBER 4 - 6, 2019
LESSONS LEARNED/BENEFITS/DISADVANTAGES
Benefits• Quick installation: don’t need to wait for concrete to
cure; usable the moment you turn off the hammer
• Minimal disturbance: no excavation; no spills to remove; reduced environmental impact
• Helicopter lift, if access is an issue
• Cost competitive depending on proximity to hammers
SEPTEMBER 4 - 6, 2019
LESSONS LEARNED/BENEFITS/DISADVANTAGES
Disadvantages• It falls in a unique construction category, so not every
contractor has or has dealt with vibratory hammers
• Need more design guidelines – hopefully CEATIprogram will provide this
• Not sufficient guidelines on selection of hammer
• No data on any that have been installed and removed after 30 years
SEPTEMBER 4 - 6, 2019
SEPTEMBER 4 - 6, 2019
Questions and Open Discussion
Please contact:Majid Farahani, P.E.Sr. Transmission Line Engineering Manager(312) [email protected]