VDOT Primavera P6 Scheduling Guide

178
VDOT Primavera P6 Scheduling Guide CONSTRUCTION DIVISION

Transcript of VDOT Primavera P6 Scheduling Guide

Page 1: VDOT Primavera P6 Scheduling Guide

 

 

 

 

 

VDOTPrimaveraP6SchedulingGuide

 

CONSTRUCTIONDIVISION

Page 2: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page1 

TABLE OF CONTENTS  

INTRODUCTION  ........................................................................................................................................... 6 OVERVIEW .................................................................................................................................................... 6  SECTION I: NAVIGATING AROUND IN THE VDOT SCHEDULING APPLICATION ........................................ 7 

1. Overview  ......................................................................................................................................... 8 2. Requesting Access to the VDOT Scheduling Application ................................................................. 8 3. Setting‐up the VDOT Scheduling Application .................................................................................. 9 4. Accessing the VDOT Scheduling Application ................................................................................. 14 5. Navigating Around in Primavera P6 Application ............................................................................ 17 6. Defining User Preferences ............................................................................................................. 25 7. Using the Right‐click Function ....................................................................................................... 31 8. Using the SpringBoard FileManager Application ........................................................................... 32 

   SECTION II: WORKING WITH LAYOUTS ............................................................................................... 35 

1. Overview  ....................................................................................................................................... 36 2. Working with Project Layouts in the Projects Window ................................................................. 36 

1. Layout Options Bar ........................................................................................................... 37 2. Top Layout ........................................................................................................................ 37 3. Bottom Layout .................................................................................................................. 39 

3. Opening a Project .......................................................................................................................... 40 4. Working with Activity Layouts in the Activities Window ............................................................... 41 

1. Activity Layout Options Bar .............................................................................................. 41 2. Opening an Activity Layout ............................................................................................... 42 3. Top Layout ........................................................................................................................ 43 

1. Activity Details ..................................................................................................... 43 2. Activity Gantt Chart ............................................................................................. 44 3. Activity Usage Spreadsheet ................................................................................. 44 4. Activity Network .................................................................................................. 45 

4. Bottom Layout .................................................................................................................. 45 1. Activity Details ..................................................................................................... 46 2. Activity Usage Profile ........................................................................................... 46 3. Activity Trace Logic .............................................................................................. 47 

5. Modifying an Activity Layout ......................................................................................................... 48 1. Bars ................................................................................................................................... 48 2. Bar Chart Options ............................................................................................................. 49 3. Columns ............................................................................................................................ 50 4. Timescale .......................................................................................................................... 51 5. Table Font, Color, and Row Height ................................................................................... 51 6. Filters ................................................................................................................................ 52 7. Group and Sort .................................................................................................................. 53 

6. Saving a Layout .............................................................................................................................. 55 7. Exporting a Layout ......................................................................................................................... 56 8. Importing a Layout ......................................................................................................................... 58 

  

Page 3: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page2 

SECTION III: DEVELOPING A CPM SCHEDULE ....................................................................................... 60 1. Overview ........................................................................................................................................ 61 2. Creating a New Project .................................................................................................................. 61 

1. Creating a Project Using the New Projects Wizard ........................................................... 61 2. Defining Project Properties and Settings .......................................................................... 65 

3. Creating and Assigning Calendars .................................................................................................. 69 1. Types of Calendars ............................................................................................................ 69 2. Creating Calendars ............................................................................................................ 70 3. Assigning a Calendar ......................................................................................................... 75 

4. Developing a Work Breakdown Structure (WBS) .......................................................................... 77 5. Adding Activities ............................................................................................................................ 79 6. Defining and Assigning Activity Codes ........................................................................................... 84 

1. Defining Activity Codes ..................................................................................................... 84 2. Assigning Activity Codes ................................................................................................... 86 

7. Adding Activity Relationships ........................................................................................................ 88 8. Assigning Constraints ..................................................................................................................... 90 

1. Assigning a Project Constraint .......................................................................................... 90 2. Assigning an Activity Constraint ....................................................................................... 91 3. Assigning an Activity Constraint Notebook Topic ............................................................. 93 

9. Scheduling a Project ....................................................................................................................... 95 1. Schedule Calculation Settings ........................................................................................... 95 2. Scheduling a Project .......................................................................................................... 97 

 SECTION IV: COST‐LOADING AND RESOURCE‐LOADING A SCHEDULE .................................................. 98 

1. Overview ........................................................................................................................................ 99 2. Understanding Resources .............................................................................................................. 99 

1. Labor Resources ................................................................................................................ 99 2. Non‐labor Resources ....................................................................................................... 100 3. Material Resources ......................................................................................................... 100 

3. Working in the Resources Window ............................................................................................. 101 1. Resource Hierarchy ......................................................................................................... 101 2. Display Options Bar ......................................................................................................... 101 3. Command Bar ................................................................................................................. 102 4. Resource Details ............................................................................................................. 103 

4. Software Settings for Resource Assignments .............................................................................. 106 1. User Preferences Settings ............................................................................................... 106 2. Project Settings ............................................................................................................... 109 

5. Cost‐loading a Schedule ............................................................................................................... 112 1. Creating Cost Resources Using New Resource Wizard ................................................... 112 2. Creating Cost Resources from VDOT Standard Bid Item Resources ............................... 121 3. Assigning Cost Resources ................................................................................................ 137 4. Reviewing Cost Resource Assignments ........................................................................... 141 5. Defining and Assigning a 20‐80 Resource Curve (Design‐Build Only) ............................. 144 6. Defining Financial Periods ............................................................................................... 148 7. Reviewing Monthly Budgeted Units and Cost Data ........................................................ 154 

  

Page 4: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page3 

6. Resource‐loading a Schedule ....................................................................................................... 158 1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 

7. TBD ............................................................................................................................................... TBD 1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 3. TBD .................................................................................................................................. TBD 

8. TBD ............................................................................................................................................... TBD 1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 

9. TBD ............................................................................................................................................... TBD  SECTION V: MAINTAINING A SCHEDULE ........................................................................................... 139 

1. Overview ...................................................................................................................................... 141 2. TBD ............................................................................................................................................... TBD 

1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 3. TBD .................................................................................................................................. TBD 

3. TBD ............................................................................................................................................... TBD 1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 3. TBD .................................................................................................................................. TBD 4. TBD .................................................................................................................................. TBD 5. TBD .................................................................................................................................. TBD 6. TBD .................................................................................................................................. TBD 

4. TBD ............................................................................................................................................... TBD 1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 

5. TBD ............................................................................................................................................... TBD 1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 3. TBD .................................................................................................................................. TBD 4. TBD .................................................................................................................................. TBD 5. TBD .................................................................................................................................. TBD 6. TBD .................................................................................................................................. TBD 7. TBD .................................................................................................................................. TBD 

6. TBD ............................................................................................................................................... TBD 1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 

7. TBD ............................................................................................................................................... TBD 8. TBD ............................................................................................................................................... TBD 

1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 3. TBD .................................................................................................................................. TBD 

9. TBD ............................................................................................................................................... TBD 1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 

Page 5: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page4 

SECTION VI: REPORTING .................................................................................................................. TBD 1. Overview ...................................................................................................................................... TBD 2. TBD ............................................................................................................................................... TBD 

1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 3. TBD .................................................................................................................................. TBD 

3. TBD ............................................................................................................................................... TBD 1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 3. TBD .................................................................................................................................. TBD 4. TBD .................................................................................................................................. TBD 

4. TBD ............................................................................................................................................... TBD 1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 

5. TBD ............................................................................................................................................... TBD 1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 3. TBD .................................................................................................................................. TBD 4. TBD .................................................................................................................................. TBD 5. TBD .................................................................................................................................. TBD 6. TBD .................................................................................................................................. TBD 7. TBD .................................................................................................................................. TBD 

6. TBD ............................................................................................................................................... TBD 1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 

7. TBD ............................................................................................................................................... TBD 8. TBD ............................................................................................................................................... TBD 

1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 3. TBD .................................................................................................................................. TBD 

9. TBD ............................................................................................................................................... TBD 1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 

10. TBD ............................................................................................................................................... TBD  SECTION VII: MANAGING CONTRACTOR SCHEDULES ........................................................................ TBD 

1. Overview ...................................................................................................................................... TBD 2. TBD ............................................................................................................................................... TBD 

1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 3. TBD .................................................................................................................................. TBD 

3. TBD ............................................................................................................................................... TBD 1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 3. TBD .................................................................................................................................. TBD 4. TBD .................................................................................................................................. TBD 

4. TBD ............................................................................................................................................... TBD 

Page 6: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page5 

1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 

5. TBD ............................................................................................................................................... TBD 1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 3. TBD .................................................................................................................................. TBD 4. TBD .................................................................................................................................. TBD 5. TBD .................................................................................................................................. TBD 6. TBD .................................................................................................................................. TBD 7. TBD .................................................................................................................................. TBD 

6. TBD ............................................................................................................................................... TBD 1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 

7. TBD ............................................................................................................................................... TBD 8. TBD ............................................................................................................................................... TBD 

1. TBD .................................................................................................................................. TBD 2. TBD .................................................................................................................................. TBD 3. TBD .................................................................................................................................. TBD 

9. TBD ............................................................................................................................................... TBD 4. TBD .................................................................................................................................. TBD 5. TBD .................................................................................................................................. TBD 

10. TBD ............................................................................................................................................... TBD   

                    

   

Page 7: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page6 

INTRODUCTION  To  establish  standard  and  consistent  scheduling  practices  and  to  facilitate  scheduling  software deployment, administration, and training, VDOT has established Primavera P6 (currently version 7.0) as the  standard  state‐wide  scheduling  software  application  for  administering  its  projects  during  the construction  phase.  VDOT  uses  Primavera  P6  for  preparing  Contract  Time  Determination  (CTD) schedules and managing contractor project schedules. VDOT also uses Primavera P6  for planning and managing its resources during the construction phase.   To minimize software administration requirements and streamline access for both internal and external users, VDOT utilizes a web‐based hosting service for software access (Loadspring). The VDOT scheduling software application is accessible anywhere and at any time via the internet. Users are assigned named user accounts with limited access privileges based on their roles and responsibilities. Users can only view or edit projects to which they have been granted access.   

OVERVIEW  This  guide  is  intended  to  complement  the  VDOT  Post‐award  Scheduling  Guide,  to  provide  specific guidelines  on  using  Primavera  P6  to  develop  and  maintain  schedules  to  comply  with  the  VDOT scheduling specifications. This guide is not intended to address every aspect of Primavera P6, but does provide sufficient guidelines for developing and maintaining a project schedule to comply with the VDOT scheduling specifications. Users may refer to the Primavera P6 User Manual or other available Primavera training  or  reference materials  for  topics  not  covered  in  this  guide.  The  guide  is  organized  in  the following major sections:   Section  I – Navigating around  in the VDOT Scheduling Application: This section provides guidelines 

for setting‐up, accessing, and navigating around in Primavera P6.  

Section  II – Working with Layouts: This section provides guidelines for creating, editing, and saving user‐defined layouts in Primavera P6.  

Section  III  –  Developing  a  Schedule:  This  section  provides  guidelines  for  developing  a  baseline schedule in Primavera P6 according to the VDOT CPM scheduling specifications.  

Section IV – Cost‐loading and Resource‐loading a Schedule: This section provides guidelines for cost‐loading and resource‐loading a schedule in Primavera P6 according to the VDOT specifications. (TBD)  

Section V – Maintaining a Schedule: This section provides guidelines for updating and maintaining a schedule in Primavera P6 according to the VDOT specifications. (TBD)  

Section VI – Reporting: This section provides guidelines for creating reports in Primavera P6. (TBD)  

Section VII  – Managing  Contractor  Schedules:  This  section  provides  guidelines  for managing  and analyzing contractor schedules in Primavera P6. (TBD) 

Page 8: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page7 

SECTION I  NAVIGATING AROUND IN THE VDOT SCHEDULING APPLICATION                 

1. Overview  2. Requesting Access to the VDOT Scheduling Application  3. Setting Up the VDOT Scheduling Application  4. Accessing the VDOT Scheduling Application  5. Navigating Around in Primavera P6 Application  6. Defining User Preferences in Primavera P6  7. Using the Right‐click Function in Primavera P6 

 

8. Using the SpringBoard FileManager Application  

    

 

 

Page 9: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page8 

SECTION 

I   

 

1. OVERVIEW  

The VDOT scheduling software application (Primavera P6)  is available via the  internet (LoadSpring) for use by VDOT personnel,  its  representatives,  and Contractors working on VDOT projects.  This section  of  the  guide  is  intended  to  provide  guidelines  for  setting‐up,  accessing,  and  navigating around in the Primavera P6 scheduling application via the LoadSpring website.    

2. REQUESTING ACCESS TO THE VDOT SCHEDULING APPLICATION  

A written  request  for access must be  submitted and approved before access can be granted. The request must be completed as follows:   

1. Internal Users – Access for VDOT personnel and representatives with VDOT network accounts will be granted as follows: 

 

1. Consult with District or State Scheduler to determine need and level of access.  

2. Submit a System Access Request Application (SARA ITD‐35) online using the link below:  

http://sara/  

3. In the SARA webpage, click on New Request to open the New Request dialog box.  

4. Specify Myself to indicate who the request is for.  

5. Specify New Request to indicate the request type.  

6. From the Select Application drop down menu, select Primavera Project Management.  

7. From the Select Module drop down menu, select P6 Client.  

8. From the Role/Access Level drop down list, select the user’s role.  

9. Specify proposed start date.  

Page 10: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page9 

10. Click the Add To List button, and then click on the Submit button.  

11. Upon approval by the VDOT Scheduling Environment Administrator, a user account will be created and EPS nodes will be added  in  the appropriate VDOT database  for  the user and project.  

12. The user will then be provided user access information, including username, password, and name of the database and EPS nodes to which access has been granted. 

 2. External  Users  –  Access  for  Contractors  and  VDOT  representatives  without  VDOT  network 

accounts will be granted as follows:  

1. Submit a written  request  for access  to  the VDOT Engineer  responsible  for  the project on which the Contractor is working.  

2. Provide names and contact information of the proposed users; as well as information about the projects to which access will be granted. Number of users per Contractor is limited to 2 provided  the  Contractor  is working  on  a VDOT  project. Additional  user  accounts may  be granted per project for additional VDOT projects on which the Contractor is working.  

3. The Engineer will then forward the request to the District or State Scheduler, who will then forward the request to the VDOT Scheduling Environment Administrator.  

4. Upon approval by the VDOT Scheduling Environment Administrator, a user account will be created and EPS nodes will be added  in  the appropriate VDOT database  for  the user and project.  

5. The  user  will  then  be  provided  user  access  information,  including  username,  generic password, and name of the database and EPS nodes to which access has been granted. 

  

3. SETTING UP THE VDOT SCHEDULING APPLICATION  

Before  using  the  VDOT  scheduling  application  for  the  first  time  on  any  computer,  users will  be required to download and  install Citrix Online Web Plug‐in software upon  launching an application in  LoadSpring  for  the  first  time,  if  a  Citrix  Receiver  application  is  not  currently  installed.  The following are guidelines for setting up the VDOT scheduling application:   1. Use  the  following  link  or  address  to  launch  the  internet  and  to  land  on  the  LoadSpring 

SpringBoard Portal Login window:  https://ws2‐60.myloadspring.com/Public/Logon.aspx      

Page 11: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page10 

2. Upon  accessing  the  internet,  click  on  Tools,  then  Pop‐up  Blocker,  and  then  Turn Off  Pop‐up Blocker to turn off the Pop‐up Blocker.  

   

3. Citrix software is required to access applications in LoadSpring. When login on to an application in SpringBoard  for  the  first  time, Citrix will be automatically  installed  if  the user has sufficient permissions on  their computer. To manually download and  install Citrix software, click on  the Downloads  link  in  the  SpringBoard Portal  Login window  to open  the  SpringBoard Downloads Archive page. 

 

  

Page 12: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page11 

1. Click on the Download Citrix Online Web Plug‐in link for the latest version (currently 12.0) to download  and  install  Citrix  application.  (Note:  Administrative  level  security  privileges  are required on a user’s computer to install Citrix successfully. If you do not have administrative level privileges, contact your local IT staff for assistance).  

   

2. Click on the Run button to proceed with Citrix download.  

   

3. Click on OK.  

 

Page 13: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page12 

4. Each  user  is  provided  a  username  and  a  generic  password.  In  the  SpringBoard  Portal  Login window, enter username and generic password provided, and then click on the Login button.  

   

5. When login on to LoadSpring for the first time, users are required to reset their password. In the Password  Reset  window,  enter  the  generic  password  provided  as  Current  Password,  then enter/confirm a new user‐defined password, and  then  click on  the Change Password button. (Note: The user‐defined password must be a minimum of 8 characters, and comprise of at least 1 uppercase,  lowercase,  number,  and  special  character,  for  example:  Guest$User1.  Passwords must not include a user’s first or last name).  

 

Page 14: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page13 

6. Read the LoadSpring SpringBoard User Agreement, and then click on the I Agree button.  

   

7. When  login  on  to  LoadSpring  for  the  first  time,  users  are  required  to  define  secret questions/answers  for  use  in  validating  the  user when  a  password  reset  is  needed.  Select  a secret question from the drop down menu, then provide an answer for each question, and then click on the Save button.  

 

Page 15: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page14 

4. ACCESSING THE VDOT SCHEDULING APPLICATION  

The following are guidelines for accessing the VDOT scheduling application (Primavera P6):   1. In the SpringBoard Portal Login window, enter your username and user‐defined password, and 

then click on the Login button.  

   

2. In the left pane of the SpringBoard Portal (My Applications) are links to the applications to which the  user  has  been  granted  access.  FileManager  is  used  to  transfer  files  between  the  user’s computer and LoadSpring server. Use of FileManager will be covered later in this guide. Click on the Project Management v7 SP3 link to launch the Primavera P6 application.  

 

Page 16: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page15 

3. If the “Do you want to open or save SpringBoard_App.ica file from ws2‐60.myloadspring.com?” question comes up, click on the Open button.  

   

4. Wait for the Citrix Online Plug‐in application to finish running and starting Primavera P6.  

   

5. When the Citrix Online Plug‐in application requests permission to access files on your computer, mark the “Do not ask me again for this site” box and then click on the Yes button. (Note: Do not mark the Read files only box).  

    

Page 17: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page16 

6. In the Login to Primavera P6 dialog box, enter your username and user‐defined password, and 

then click on the Database browse button   to open the Edit Database Connections dialog box from which to select a database.  

   

7. In  the Edit Database Connections dialog box,  click on  the database  to which access has been granted, and then click on the Select button to select the database.  

   

8. In the Login to Primavera P6 dialog box, click on the OK button to login to the selected database.  

 

Page 18: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page17 

5. NAVIGATING AROUND IN PRIMAVERA P6 APPLICATION  

Primavera P6 uses various windows to display global, project, or activity data. To view, add, or edit global, project, or activity data, the appropriate window must be open. The following are guidelines for navigating around in the Primavera P6 (v7.0) scheduling application:   1. Toolbars –  In each window  in Primavera P6 are  toolbars  that can be used  to perform various 

functions. To display/hide toolbars, click on View, then Toolbars, and then click on the toolbar you want to display/hide. A checkmark in front of the toolbar name indicates that it is currently displayed.   

   

The following are descriptions of the Primavera P6 scheduling application tool bars:  1. Menu Bar: The Menu bar provides various menu items that can be used to perform a variety 

of  functions  including  viewing,  creating,  and managing  global, projects,  and  activity data. Each  item  on  the  Menu  bar  provides  a  drop  down  list  of  options.  Menu  items  vary depending on the open window.  

2. Navigation Bar: The Navigation bar displays the name of the current window (view) and  is used to navigate back and forth between previously opened views, display the Home view; as well as display/hide the Directory bar or Help menu. The Navigation bar can be displayed or hidden by clicking on View, then Toolbars, and then Navigation.  

3. Activity Toolbar: The Activity Toolbar displays  toolbar buttons  that  can be used  to access frequently used commands quickly. 

Menu 

Bar 

Directory 

Bar 

Navigation 

Bar

Activity 

Toolbar

Command 

Bar

Status 

Bar 

Layout 

Options 

Bar

Page 19: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page18 

4. Layout Options Bar: The Layout Options bar provides a menu of items with which to perform a variety of functions including, opening, modifying, and saving a layout.  

5. Directory Bar: The Directory bar provides 12 quick launch buttons with which to access the various windows. The Directory bar  can be displayed or hidden by  clicking on View,  then Toolbars, and then Directory or simply by clicking on “Dir.” in the Navigation bar.  

 

 6. Command  Bar:  The  Command  bar  displays  on  the  right  side  of  the  window,  available 

command buttons that can be used to perform a variety of tasks within the open window such as add, delete, copy/cut/paste, or move data. For example:  

 

     

7. Status Bar: The Status bar  is a message bar at  the bottom of  the window  that displays a description of the selected menu command, the name of the current  layout and filter, and other messages. 

1. In the Projects window, command buttons can be used to add, 

delete, or copy/cut/paste projects.  

2. In the WBS window, the command buttons can be used to add, 

delete, copy/cut/paste, or move WBS elements.  

3. In the Activities window, command buttons can be used to add, 

delete, copy/cut/paste activities; or add resources, roles, 

activity codes, relationships, etc.

 

 Global    

Data 

Project    

Data 

(Click on  the  top 4 buttons  to open a window  to  view, add, delete, or edit global data for the selected object) 

(Click on the bottom 8 buttons to open a window to view, add, delete,  or  edit  project  data  for  the  selected  object  for  the open project. Note: The buttons are grayed‐out if no project is open) 

Page 20: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page19 

2. Home Window – The Home window is the initial landing page of the application, depending on user setting. The Home window provides quick access to enterprise (global) and project data. To display the Home window from other windows, click the Home button on the Navigation bar, or click on View in the Menu bar, then Home.  

   

3. Projects Window  –  The  Projects window  is  used  to  display/maintain  project‐level  data.  The Projects window  can  be  used  to  set  up  the  Enterprise  Project  Structure  (EPS) with which  to view/manage project data or organize projects. Click on the Projects button in the Directory bar to open the Projects window to view, add, delete, or edit projects.  

 

Page 21: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page20 

4. Resources Window – The Resources window is used to display/maintain the Resource hierarchy and  individual  resources.  Click  on  the  Resources  button  in  the  Directory  bar  to  open  the Resources  window  to  view,  add,  delete,  edit,  or  move  resources  around  in  the  Resource hierarchy.   

   

5. Reports Window  –  The  Reports window  is  used  to  display  the  reports menu.  Click  on  the Reports button  in  the Directory bar  to open  the Reports window to create, delete, modify, or run reports.   

   

Page 22: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page21 

6. Tracking Window – The Tracking window is used to display tracking layouts that can be used to track summary performance at the EPS, project, or WBS level. Click on the Tracking button in the Directory bar to open the Tracking window to display, create, import/export, delete, modify, or save tracking layouts.   

   

7. WBS Window – The WBS window  is used  to display/maintain project WBS hierarchy. Click on the WBS button in the Directory bar to open the WBS window to display the Project WBS to add, delete, edit, or move a WBS element around in the WBS hierarchy for the open project.  

 

Page 23: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page22 

8. Activities Window – The Activities window  is used display/maintain project activity data. Click on the Activities button in the Directory bar to open the Activities window to view, add, delete, or edit activities for the open project.   

   

9. Assignments Window – The Assignments window  is used to display/maintain project resource assignment data. Click on the Assignments button to open the Resource Assignments window to view, add, delete, or edit resource assignments for the open project.  

 

Page 24: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page23 

10. WPs &  Docs Window  –  The WPs &  Docs window  is  used  to  display/maintain  project work products  and documents  register. Click on  the WPs & Docs button  to open  the WPs & Docs window  to  view,  add, delete, or maintain work products  and documents  information  for  the open project.  

   

11. Expenses Window – The Expenses window  is used  to display/maintain project expenses data. Click on the Expenses button to open the Project Expenses window to view, add, delete, or edit expenses  for  the  open  project.  (Note:  Expenses  are  one‐time  expenditures  incurred  on  the project).   

 

Page 25: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page24 

12. Thresholds Window  –  The Thresholds window  is used  to display/maintain project  thresholds data.  Click  on  the  Thresholds  button  to  open  the  Project  Thresholds window  to  view,  add, delete, edit, or monitor thresholds for the open project.  

   

13. Issues Window – The Issues window is used to display/maintain project issues data. Click on the Issues  button  to  open  the  Issues window  to  view,  add,  delete,  edit, monitor,  or  send  email notifications on issues on the open project.  

  

Page 26: VDOT Primavera P6 Scheduling Guide

 

VDOTPri 

14. Rofosc 

  

6. DEFI 

In Pridispladate, acces 

imaveraP6S

isks Windown the Risks bor  the  open chedule, cost

INING USE

mavera P6 a ayed or calculor currency is the User Pr

Virg

SchedulingG

w – The Projecutton to opeproject;  or  ts, and duratio

ER PREFERE

user can spelated using thinformation; eferences dia

ginia DepartConstr

uide(12‐22‐

ct Risks windon the Projectto  calculate  aons. 

ENCES IN P

ecify user sethe User Prefeor specify staalog box, click

 

ment of Traruction Divisio

‐15:UnderC

ow is used to t Risks windoa  project  risk

PRIMAVER

ttings and prrences dialogartup optionsk on Edit in th

nsportationon 

onstruction)

display/mainow to view, ak's  exposure 

RA P6 

eferences to g box. Users cs, send e‐maihe Menu bar, 

)

ntain project dd, delete, ovalues  and 

 

determine hcan specify hol, or change tthen User Pr

Pa

risks registerr edit projectits  impact  o

how  informatow to display their passworeferences. 

age25

. Click t risks n  the 

tion  is  time, rd. To 

Page 27: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page26 

The following are guidelines for defining user settings and preferences:  1. Time  Units  –  Click  on  the  Time  Units  tab  to  define  the  timescale  and  format  to  use when 

displaying  time units.  Time Units  formats  affect  how  tracking  layouts,  activity durations,  and resource units, availability, and work efforts are displayed.  

   Define time units as follows:  1. Units Format: Select Day to specify the time unit for displaying work efforts, and resource 

units  and  availability  in  terms  of  days  for  resource‐loaded  schedules.  Select  2  to  display 

resource units to two (2) decimal places. Mark the Show Unit label checkbox to display the 

time unit abbreviation with the resource unit’s value (e.g. 10.00d).  

2. Durations Format: Select Day to specify the time unit used to display activity duration values 

in  terms of days. Un‐mark  the Show Duration  label checkbox  to avoid displaying  the  time 

unit abbreviation with the duration value.   

3. Units/Time  Format:  Specify  Show  as units/duration  (4h/d)  to display  resource usage  rate 

(units/time) as units per duration. 

     

Page 28: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page27 

2. Dates – Click on the Dates tab to specify how dates are displayed.  

   For  consistency  and  conformance with  the  scheduling  specifications,  dates  format  should  be defined as follows:  1. Date Format: Specify Month, Day, Year to display dates in the MM‐DD‐YY format (e.g. 08‐05‐

13).  

2. Date Format Options: Mark the Leading zeroes checkbox to display all months and days as 2‐

digit numbers. Select hyphen sign (‐) as the character used to separate a date's day, month, 

and year.   

3. Time Format: Specify Do not show time to avoid showing time of day with the dates, unless 

deemed necessary. 

      

     

Page 29: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page28 

3. Currency – Click on the Currency tab to specify how monetary values are displayed. Click on the button and select Dollar, then mark the Show currency symbol and Show decimal digits to show monetary values with dollar the symbol ($) and in two (2) decimal places.  

   

4. Assistance – Click on the Assistance tab to turn on/off the New Resource or New Activity wizard for assistance when adding new resources or activities based on user preference.  

 

Page 30: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page29 

5. Resource Analysis – Click on the Resource Analysis tab to specify which projects are included in resource calculations and which dates and time  interval are used to calculate time‐distributed data for resource spreadsheets and profiles.  

   

The Resource Analysis user preferences should be defined as follows:  

1. All Projects: When All Projects are shown in the Resource Usage Spreadsheet and Profile, all 

opened projects are included as well the closed projects specified below:  

1. Specify All closed projects (except what‐if projects) only when electing to  include data 

for all closed projects other than what‐if projects.   

2. Specify All closed projects with leveling a priority only when electing to include data for 

all closed projects with a specific leveling priority.  

3. Specify Opened projects only to include data for open projects only.  

2. Time‐Distributed Data: The Time‐Distributed Data settings are used to specify which dates 

and time interval are used to calculate time‐distributed data for resource spreadsheets and 

profiles.   

1. Specify  Remaining  Early  dates  to  calculate  remaining  values  based  on  remaining 

start/finish dates (recommended).  

2. Specify Day as the Interval for time‐distributed resource calculations. 

Page 31: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page30 

6. Calculation – Click on the Calculations tab to specify how remaining values are calculated when new resource assignments are added to, or removed from activities. Specify Preserve the Units, Duration,  and Units/Time  for  existing  assignments  to  ensure  that  the  formula  for  calculating remaining  units  is  set  as  (Remaining  Units  =  Remaining  Duration  *  Remaining  Units/Time), regardless of the duration type of an activity (recommended).   

   

7. Startup  Filters  –  Click on  the  Startup  Filters  tab  to  specify  the default  filters used  in  layouts when starting the application. These filters can be modified in the individual layouts.  

 

Page 32: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page31 

7. USING THE RIGHT‐CLICK FUNCTION IN PRIMAVERA P6  

Using the right‐click function is the quickest way to access available menu items used for performing various functions in Primavera P6.  .   1. The right‐click function can be used in lieu of the Menu bar to quickly display a menu with which 

to perform various  functions.  Items available  in each menu varies based on the current active window. For  instance, right‐click with your mouse  in the Projects window to display a menu of items that can be used to perform various functions within the Projects window. 

 

  

2. When  you  right‐click  with  your  mouse  inside  either  the  Navigation  bar,  Directory  bar,  or Command bar, a toolbar menu with which to hide/display a toolbar or its text is displayed. 

 

 

Page 33: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page32 

8. USING THE SPRINGBOARD FILEMANAGER APPLICATION  

The FileManager application  in  the SpringBoard portal  is available  for use  in  transferring XER  files between a user’s computer and the LoadSpring server, when exporting/importing project schedules. XER  export  files  created  from  the VDOT  Primavera  P6  databases  can  be  temporarily  stored  in  a FileManager folder and then transferred to the user’s computer for distribution. Likewise, XER files created from other databases can be transferred from the user’s computer and stored in a folder in the LoadSpring server  for  importing  into  the VDOT database.  (Note: FileManager storage space  is limited and is intended only for temporary transfer of files with your computer. It is not intended for long‐term or permanent storage). The following are guidelines for using FileManager:   1. Click on the FileManager link to launch the FileManager application. 

 

   

2. If the “Do you want to open or save SpringBoard_App.ica file from ws2‐60.myloadspring.com?” question comes up, click on the Open button.  

 

Page 34: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page33 

3. Wait for the Citrix application to finish running and starting FileManager.  

   

4. When the Citrix Online Plug‐in application requests permission to access files on your computer, mark the “Do not ask me again for this site” box and then click on the Yes button. (Note: Do not mark the Read files only box).  

   

5. FileManager provides access to all drives and folders that are available on the user’s computer. It also provides access to the public drive (Site Public on SpringBoard (X)) and the user’s private drive  (My Private on SpringBoard  (Y)) on  the LoadSpring  server. All  file  transfers between  the user’s computer and the LoadSpring server must be performed within the FileManager window.  

 

Page 35: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page34 

The following are guidelines for accessing and transferring files within FileManager:  1. Click on the plus (+) sign to expand a drive or folder. Click on the minus (‐) sign to collapse 

the folder or drive.  

2. The “Site Public on SpringBoard (X)” drive is intended for use by all users. However, only the “General”  folder  is  available  to  all  users.  The  General  folder  is  used  to  store  general information  that  is  available  to  all  users,  including  scheduling  guides,  specifications, standard reports, etc.  

3. The “Project Files” folder under the “Site Public on SpringBoard (X)” drive is intended for use only to VDOT users to whom access has been granted.   The Project Files folder  is used for storing project “XER”  files temporarily  for the purpose of  importing project schedules  into the VDOT Primavera P6 databases.  

4. Each user has a Private drive  (Y), which  is exclusive  to  the user. The Private drive  can be used  for  storing  project  “XER”  files  temporarily when  exporting  a  project  schedule.  The “XER” files can then be moved from the user’s Private drive in the SpringBoard server to the user’s computer for distribution.  

5. To transfer a file within the FileManager window, locate and select the file, then right‐click and click on Copy, then locate and select the folder in which to place the file and then right‐click and click on Paste.  

6. All  file  transfers  between  the  user’s  computer  and  the  SpringBoard  server  should  be performed within the FileManager window.  

                    

Page 36: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page35 

SECTION II  WORKING WITH LAYOUTS                 

1. Overview  2. Working with Project Layouts in the Projects Window   3. Opening a Project  4. Working with Activity Layouts in the Activities Window  

5. Modifying an Activity Layout  

6. Saving an Activity Layout  

7. Exporting a Layout  

8. Importing a Layout  

   

 

 

 

 

Page 37: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page36 

SECTION 

II  

 

 

1. OVERVIEW  

A Layout (also referred to as View)  is a customized view that allows the user to display enterprise, project, or  activity data  in  a  variety of  formats.  Primavera  P6  provides many options  in  creating layouts and available options depend on the selected window. This section provides guidelines for opening, exporting, importing, modifying, and saving layouts in the Projects and Activities windows.    

2. WORKING WITH PROJECT LAYOUTS IN THE PROJECTS WINDOW   In the Projects window, a customized layout can be defined by the user for use in displaying projects and project‐level data. The following are guidelines for working with layouts in the Projects window:   

 

Layout 

Options Bar

Top 

Layout 

Bottom 

Layout 

Page 38: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page37 

1. Layout Options Bar – The Layout Options bar (or Display bar) provides a menu of items that can be used to perform a variety of functions depending on the current window. For instance, in the Projects window the Layout Options bar displays a menu that can be used to perform functions such as opening, modifying, and saving a layout.  

  

  2. Top Layout – The Projects window can be divided  into  top and bottom  layout views. The  top 

layout can be used to view, add, delete, or copy/paste a project; or to open an existing project. To display a top  layout view  in the Projects window, click on View  in the Menu bar or click on the Layouts Option bar, then Show on Top, and then:  

 

Click on the Layout Options bar and then:  

1. Click on Layout to open or save a project layout.  

2. Click on Columns to select project data to display in the Project Table columns.  

3. Click  on  Table  Font  and  Row  to  format  tabular data fonts and row height.  

4. Click  on  Filter  By  to  create, modify,  or  change filters.  

5. Click on Group and sort project or activity data.  

6. Click on Bars to format Bar Chart area elements.  

7. Click  on  Show  on  Top  or  Show  on  Bottom  to select a layout to show on top/bottom. 

Page 39: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page38 

1. Select Project Table to display project list and data in a non‐timescale tabular format.  

   

2. Select Gantt Chart to display project data in a timescale bar‐chart format.  

   

Page 40: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page39 

3. Select Chart View to display projects in a hierarchical chart format based on the EPS.  

   

3. Bottom Layout – In the Projects view, there is only one option for the bottom layout, users can either display Project Details in the bottom layout or show no bottom layout. The Project Details tabs  can  be  used  to  view,  add,  or  edit  detailed  information  about  the  selected  project.  To display the Project Details window in the bottom layout, click on View in the Menu bar or click on the Layouts Option bar, then Show on Bottom, and then select Project Details.   

               

Page 41: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page40 

3. OPENING A PROJECT  

A  project must  be  open  in  order  to work with  activity  layouts.  The  following  are  guidelines  for opening a project in Primavera P6:   1. From  the  Home  page  or  Projects  view,  click  on  the  File menu,  or  right‐click  in  the  Projects 

window pane, and then click on Open to open the “Open Project” dialog box.   

   

2. In the Open Project dialog box, select a project, select an Access Mode, and then click on Open. (Note:  In the Exclusive access mode the current user  is the only user that can edit the project data while the project is open. Other users can only open the project in Read Only mode. In the Shared mode, other users can open, view, add, or edit the project data while the project is open. In the Read Only mode, the user can view the project data, but cannot add or edit the data).  

 

Page 42: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page41 

4. WORKING WITH ACTIVITY LAYOUTS IN THE ACTIVITIES WINDOW  

An Activity Layout is a customized view created by the user for use in displaying the project activities and activity data. The following are guidelines for working with layouts in the Activities window:   

   

1. Activity Layout Options Bar – The Layout Options bar provides a menu of functional items that can be used to open, modify, create, or save a  layout. The Layout Options bar  is available only when  the  Projects, WBS,  Activities,  and  Tracking windows  are  selected.  Click  on  the  Layout Options bar to modify, open, import, export, or save a layout; or to display a selected layout on top or bottom.  

 

Top 

Layout 

Bottom 

Layout 

Layout Options Bar

Click on the Layout Options bar to:  

1. Open or save a layout.  

2. Format activity bars.  

3. Format Bar Chart Area elements.  

4. Format timescale.  

5. Format Activity Table font and row.  

6. Create, modify, or change filters.  

7. Group and sort project or activity data.  

8. Hide/show layout on top/bottom.  

Page 43: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page42 

2. Opening an Activity Layout – Users may select from a list of available standard layouts or they may  create  custom  layouts  for  specific use or  to  share with other users. To open an existing layout.  1. Click on the Layout Options bar, click on Layout, and then click on Open to open the Open 

Layout dialog box.  

   

2. Click on the No button to leave the current layout as is. If changes to the current layout are needed for future use, see steps for “Saving a Layout” below.  

   

3. In  the Open  Layout dialog box,  select a  layout, and  then  click Apply  to view  the  selected layout  to  ensure  that  the  correct  layout was  selected.  Then  click on Open  to display  the layout and close the Open Layout dialog box.  

 

Page 44: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page43 

3. Top  Layout  –  In  the  Activities  window,  the  top  layout  displays  on  top,  information  about activities for the open project. The top layout can be used to view activity information or to add, delete, copy/paste, or edit activities. Click on View on  the Menu bar,  then Show on Top, and then select from the list of view options an Activity view to display on top:  

   

1. Activity  Table:  Select  Activity  Table  view  to  display  activities  for  the  open  project  in  a 

spreadsheet  format. Click on   Columns  to open  the Columns dialog box  to modify  the columns of data shown in the table as needed.   

 

Page 45: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page44 

2. Gantt Chart: Select Gantt Chart view  to display activities  for  the open project  in a  tabular and bar‐chart  format. The  left side of  the window displays an Activity Table, which shows the activity data in columns. And the right side displays a Bar Chart Area, which shows time‐phased bar‐chart plots of the activities.   

   

3. Activity  Usage  Spreadsheet:  Select  Activity  Usage  Spreadsheet  view  to  display  the resource/cost data associated with  the activities. The  left side of  the window displays  the Activity Table, which shows the activity data in a tabular format. And the right side displays the Spreadsheet Area, which shows the units, cost, or earned value data for the activities, as defined by the user.   

 

Page 46: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page45 

4. Activity Network:  Select Activity Network  view  to display  in a network  logic diagram,  the inter‐relationships  between  the  activities.  The  left  side  of  the window  displays  the WBS hierarchy. And the right side displays a network diagram depicting the network relationships between the activities.  

 

   

4. Bottom  Layout  –  In  the  Activities  window,  the  Bottom  layout  displays  on  bottom  detailed information about the selected activity. To display/hide the Bottom layout, click on View, click on Show on Bottom, and then click on an item to display on the bottom layout.   

 

Page 47: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page46 

Users may  select No Bottom  Layout or display on  the bottom one of  the  following  available layouts: Activity Details, Activity Table, Gantt Chart, Activity Usage Spreadsheet, Resource Usage Spreadsheet, Activity Usage Profile, Resource Usage Profile, and Trace Logic. The following are a few examples of layouts that can be shown on the bottom:  1. Activity Details:  Select  the Activity Details  view  to  display  on  bottom  the Activity Details 

form showing detail information about the selected activity. The Activity Details form can be used to view, add, or edit detailed information about the selected activity.  

   

2. Activity Usage Profile: Select the Activity Usage Profile view to display a graphical plot of the units, cost, or earned value histograms and/or curves for all activities or selected activities, as defined by the user.  

  

Page 48: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page47 

3. Activity  Trace  Logic:  Select  the Activity  Trace  Logic  view  to display  in  a network diagram format,  the  predecessor  and  successor  activities  associated  with  a  selected  activity.  To specify  the number of predecessor and  successor  levels  to display,  right  click  in  the Trace Logic window, and then click on Trace Logic Options to open the Trace Logic Options dialog box.  

  

                   

Page 49: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page48 

5. MODIFYING A LAYOUT  

Users may modify existing  layouts to create customized  layouts for a specific use or to share with other users.   

  

To modify a layout, click on the Layout Options bar or View menu, then select an item of the layout to be modified as follows:  

1. Bars – Click on the Bars   button to open the Bars dialog box to add, delete, display, hide, or modify Activity bars:   

 

Page 50: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page49 

1. Click on the Add button to add an Activity bar to the current  layout. Edit the bar name, as necessary.  

2. Click on the Delete button to delete the selected Activity bar. To remove a specific bar from the layout display without deleting it from the form, clear the Display checkbox next to the bar.  

3. Double‐click  the  timescale  to select  from a drop down menu  the  type of  time‐scaled data that the bar represents.  

4. Double‐click  the  filter  to  select  from a drop down menu a  filter applied  to  the data  item represented by the bar type.  

5. Click on the Bar Style tab to define the shape, color, and pattern of the selected bar's start endpoint, the bar itself, and the finish endpoint; as well as the position of the selected bar in the Gantt Chart.  

6. Click on the Bar Settings tab to define the grouping band settings for summarizing activity bars or the bar necking settings for necking bars.  

7. Click on the Bar Labels tab to add/delete a bar’s  label for the selected bar or to define  its position.  

8. Use the Shift up or Shift down to move a bar upward or downward, as necessary.  

9. Mark the Display checkbox to show the selected bar in the Gantt Chart. Clear the checkbox to hide.  

10. Click on Apply to apply the changes and OK close the Bars dialog box.  

2. Bar Chart Options  – Click on Bar Chart Options  to open  the Bar Chart Options dialog box  to modify  items displayed  in the Bar Chart Area. Click on Apply and OK to apply the changes and close the dialog box.  

 

Page 51: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page50 

3. Columns – Click on   Columns to open the Columns dialog box to select Activity data fields to display on the Activity Table as needed.  

   

1. Click on the Available Options category “+” button to expand the list of available options for the selected category.  

2. Click on  the  single  arrow directional buttons  to move  items back  and  forth between  the Available Options window and the Selected Options window.  

3. Click on the double arrow buttons to move all items.  

4. Click on the up and down arrow buttons to move items up or down to specify the position of the columns.  

5. Click on Apply and OK to apply the changes and close the dialog box.                 

Page 52: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page51 

4. Timescale – Click on   Timescale  to open  the Timescale dialog box to modify the timescale format displayed  in  the Bar Chart Area. Click on OK  to apply  the changes and close the dialog box.  

   

5. Table Font, Color, and Row Height – Click on Table Font and Row to open the Table Font and Row dialog box to modify the Activity Table font, color, and row height. Click on OK to apply the changes and close the dialog box.  

       

Page 53: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page52 

6. Filters – Click on  Filters to open the Filters dialog box to add, modify, apply, or delete filters for  the  current  display.  Filters  are  used  to  specify what  items  are  displayed.  In  the  Projects window,  filters can be used  to specify which projects are displayed. Likewise,  in  the Activities window, filters can be used to specify which activities are displayed  in the current  layout or to highlight  activities  in  the  current  layout  that meets  the  criteria.  Filters  are  grouped  into  four possible categories: Default, Global, Layout Filters, and User Defined. Users may select  from a list of available default filters or they may create specific filters for use by the user, all users, or applied to a layout and saved with the layout.  

   

The following are guidelines for creating, modifying, and applying a filter:  

1. Mark the All Activities checkbox to display all activities in the open project. (Note: This box is marked by default when no other filters are selected).  

2. When multiple filters are selected, mark All selected filters to display activities that meet the selection criteria  for each selected  filter. Mark Any selected  filter  to display activities  that meet the criteria for any selected filter.  

3. Click on Apply to apply the changes without closing the dialog box.  

4. Click on the New button to add a new User Defined filter.  

5. Click on the Delete button to delete the selected filter. You can only delete global,  layout, and user defined filters.  

6. Click on the Copy/Paste buttons to copy and paste the selected filter.  

Page 54: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page53 

7. Click on the Modify button to change the filtering criteria for the selected filter.  

8. Click on the Make Global to make the selected filter a global filter.  

9. Click on Copy As Layout button to make the selected filter available to the currently open layout.  

10. Specify Replace activities  shown  in  the  current  layout  to display only  the activities  in  the current layout that meet the selected filter criteria.  

11. Specify Highlight  activities  in  the  current  layout which match  the  criteria  to highlight  the activities in the current layout that meet the selected filter criteria.  

12. Click on OK to apply the changes and close the dialog box.  

7. Group and Sort – Click on   Group and Sort to open the Group and Sort dialog box to specify a grouping and sorting criteria for the current layout.  

 

   The following are guidelines for modifying a layout using the group and sort dialog form: 

 1. In the Display Options section: 

 1. Mark the Show Group Totals checkbox to display totals in the grouping bands.  

 2. Mark  the  Show Grand  Totals  checkbox  to  show  a  grand  total  row  at  the  top  of  the 

layout.  

Page 55: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page54 

3. Mark  the Show Summaries Only  checkbox  to  show  summarized grouping bands only; details under the grouping bands will be hidden. Clear the checkbox to show grouping bands with corresponding details displayed below each group.  

4. Mark  the Shrink vertical grouping bands checkbox  to decrease  the grouping hierarchy indenting space to allow for more space to display data, as necessary. 

 

2. In the Group By window:  

1. Define the grouping criteria for the current display by selecting from a drop down list of grouping data items. Activities may be grouped by WBS, Activity Code, or other available category.  

2. Double‐click on Font & Color of a grouping  item to change the grouping's display color or font.  

3. In the Group By Options section:  1. Mark  the Hide  if empty checkbox  to hide empty group bands. For  instance, mark  this 

checkbox if you are grouping by WBS in the Activities window and the project has WBS bands that do not contain data items.  

2. Mark the Sort bands alphabetically checkbox to sort the grouping bands in alphabetical order rather  than  their respective hierarchical order. This checkbox  is disabled  for any grouping that is not hierarchical.  

3. Mark the Show Title checkbox to display the field name on the grouping band.  

4. Mark the Show ID/Code checkbox to display the ID or Code value on the grouping band.  

5. Mark the Show Name/Description checkbox to display the Name or Description on the grouping band.  

4. Click on the Apply button to apply the changes without closing this dialog box.  

5. Click on the Delete button to delete the grouping parameters for selected rows.  

6. Click on the Sort button to specify the order in which the data items listed within each group are sorted.  

7. Click on the Default button to apply the default grouping and sorting parameters (by WBS code).  

8. Click on OK to apply the changes and close the Group and Sort dialog box.  

Page 56: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page55 

6. SAVING A LAYOUT  

Users can save layouts for personal use or to share with other users. Layouts can be global, project‐specific,  or  user‐specific.  Layouts  can  be  created  and  saved  in  the  Projects,  WBS,  Activities, Assignment, or Tracking window. The following are guidelines for saving layouts:   1. To save changes to the current layout without creating a new layout, click on the Layout Options 

bar, then Layout, and then Save.   

   

2. To create a new layout, click on Save As to open the Save Layout As dialog box, enter a Layout Name for the new layout, then specify the user(s) to whom the layout will be available, and then click on Save to save the layout and close the dialog box.   

   

   

1. All  Users: Specify All  Users to  save  the  layout  in  the global pool to make it available for use by any user.  

2. Another User: Specify Another User to save the layout in a specific user pool to make it available only to the user.  

3. Current User: Specify Current User to save the  layout  in the  current  user  pool  to make  it  available  only  to  the user who created the layout.  

4. Project:  Specify  Project  to  save  the  layout  in  a project pool to make it available for use by any user with access to the project. 

Page 57: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page56 

7. EXPORTING A LAYOUT  

Layouts created and saved in the Projects, WBS, Activities, Assignment, or Tracking window can be exported and shared with other users. The following are guidelines for exporting a layout:   1. In  the Projects, WBS, Activities, Assignment, or Tracking window, as appropriate,  click on  the 

Layout Options bar, then Layout, and then Open.   

   

2. Click on Yes to save changes to the current layout or NO to avoid saving changes to the current layout.   

             

Page 58: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page57 

3. Select  a  layout  and  then  click  on  the  Export  button  to  create  an  export  file  of  the  selected layout.   

   

4. Select a file location in which to place the “plf” layout file, rename as necessary, and then click on the Save button to save the layout file.   

              

Page 59: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page58 

8. IMPORTING A LAYOUT  

Saved  layout  files  can  be  imported  into  the  user’s  database  layout  menu.  The  following  are guidelines for importing a layout:   1. In  the Projects, WBS, Activities, Assignment, or Tracking window, as appropriate,  click on  the 

Layout Options bar, then Layout, and then Open.   

   

2. Click on Yes to save changes to the current layout or NO to avoid saving changes to the current layout.   

            

Page 60: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page59 

3. Locate and select the “plf” layout file and then click on the Open button to save the layout file.   

   

4. Rename the layout as necessary, and then click on the drop down arrow to specify the user or users to whom the layout will be available, and then click on the Save button.   

   

 5. Select the newly imported layout and click on Open to apply the layout or click on the Close (X) 

button. (Note: The imported layout is placed under a user group specified during the import).   

 

1. All  Users: Specify All  Users  to  save  the  layout  in  the global pool to make it available for use by any user.  

2. Another User: Specify Another User to save the layout in a specific user pool to make it available only to the user.  

3. Current User: Specify Current User to save the  layout  in the  current  user  pool  to make  it  available  only  to  the user who created the layout.  

4. Project:  Specify  Project  to  save  the  layout  in  a project pool to make it available for use by any user with access to the project. 

Page 61: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page60 

SECTION III  DEVELOPING A CPM SCHEDULE                  

1. Overview  2. Creating a New Project  3. Creating and Assigning Calendars  4. Developing a Work Breakdown Structure (WBS)  5. Adding Activities 

 6. Defining and Assigning Activity Codes 

 7. Adding Activity Relationships 

 8. Assigning Constraints 

 9. Scheduling a Project 

   

    

Page 62: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page61 

SECTION 

III   

 

1. OVERVIEW  

Primavera P6 or an equivalent scheduling software application is required to prepare and maintain CPM schedules for VDOT projects with a Category III, IV, V, or Design‐Build scheduling specifications. Contractors  may,  at  their  discretion  use  Primavera  P6  to  prepare  and  maintain  schedules  for Categories M,  I,  and  II  projects.  This  section  of  the  guide  provides  guidelines  for  developing  a Baseline CPM Schedule in Primavera P6 to comply with the VDOT scheduling specifications.    

2. CREATING A NEW PROJECT  

To begin developing a schedule  in Primavera P6, users must first create a new project shell  in the database,  in which  the  activities  that make up  the project will be  added.   A new project  can be created by using the copy/paste command to make a copy of an existing project or by using the New Projects wizard. This guide provides guidelines for creating a project using the New Project wizard.   1. Creating a Project Using the New Projects Wizard – The following are guidelines for creating a 

new project in the database using the New Project Wizard:  

1. From the Projects view, click on File, then New or click on the Add button in the Command bar to launch the Create a New Project wizard.   

 

Page 63: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page62 

2. From  the Create  a New  Project dialog box,  click  on  the  Select  EPS  browse button   to select the Project EPS node under which the new project will be added. Then click on Next to continue.  (Note: The Create a New Project wizard guides the user through the steps for defining the project properties. Depending on the user preference, the Create a New Project wizard may be closed at any  time by clicking on Finish.  In which case,  the user must  then complete the remaining project properties using the Project Details window, as necessary).   

   

3. Enter the Project ID and Project Name. Then click on Next to continue.  

   

Define the Project ID and Project Name as follows:  1. The Project ID must be unique and should be prefixed by the Contract ID as well as 

indicate the type and number of the submission (e.g. C00012345C01_B01).   

2. The Project Name should include a brief description of the project, submission type, 

number, and data date (e.g. Example Project (Baseline #01, DD: 02/01/12). 

Page 64: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page63 

4. Specify  the Planned Start and Must Finish By dates by clicking on  the browse buttons   and selecting the appropriate dates. Then click on Next to continue. (Note: The planned start date is the start date of the first activity on the schedule; typically, the NTP date. The Must Finish By date is the finish date of the last activity; the Contract fixed completion date). 

 

   

5. Specify  the  Responsible Manager  by  clicking  on  the  browse  button   and  selecting  the name of the Project Manager (or Company) responsible for the project. Then click on Next to continue.   

        

Page 65: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page64 

6. Specify the assignment default rate type by clicking on the Rate Type drop‐down button and selecting the rate type Price/Unit. Then click on Next to continue.  

   

7. Specify No, do not run the Project Architect, and then click on Next to continue.  

   

8. Click on Finish to complete creating the project. The project is now available to add activities that make up the project. To modify project properties or to define project properties not covered by the wizard, use the Project Details window.  

 

Page 66: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page65 

2. Defining Project Properties and Settings – When creating a new project in Primavera P6 certain project properties and default settings must be defined. Click on Projects in the Directory bar to open the Projects window, and then click on the Project Details tabs to view, add, or edit project properties and  information about  the currently open project.  (Note: To  select which  tabs are displayed  in  the  Project  Details,  right‐click  on  a  tab  name,  then  click  on  Customize  Project Details, then select from the available tabs menu the project details tabs to be displayed).  1. General Tab: Click on  the General  tab  to add/edit general  information about  the project. 

Edit as necessary, the Project ID and Project Name.  

   

1. Project  ID:  The  Project  ID must  be  unique  for  each  schedule  submission. Define  the Project ID using a standard naming convention consisting of the Contract ID number as a prefix, a letter (B=Baseline, U=Update, SIA=Schedule Impact Analysis), and a number to indicate  which  schedule  is  being  submitted  (e.g.  C00012345C01_B01, C00012345C01_U01, C00012345C01_SIA01, etc.).  

2. Project Name: Define the Project Name to provide a concise description of the project, submission number, and current data date (e.g. I‐95 Bridges Project ‐ Baseline #01 DD: 2/01/12).  

2. Dates Tab: Click on the Dates tab to add/edit the Planned Start and Must Finish By dates for 

the project. Click on the browse   buttons and select the appropriate dates.  

   

1. Planned Start: For  initial baseline schedule,  the Planned Start date  is  the start date of the earliest activity in the schedule; typically, the NTP date.  

2. Must Finish By: The Must Finish By date is the Contract completion date. 

Page 67: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page66 

3. Defaults Tab: Click on  the Defaults  tab  to add/edit  the project default  settings  for adding new activities. (Note: Default settings apply to new activities only. Activity properties can be modified for each individual activity as necessary).  

 

   

Define the project default settings as follows:  

1. Duration Type: Specify Fixed Duration & Units as the default duration type.  

2. Percent Complete Type: VDOT  recommends Physical as  the default percent  complete type. However, the percent complete type may be defined as follows:  1. Specify Duration percent complete type when the percent complete of an activity is 

based  on  the  remaining  duration  rather  than  amount  of work  performed.  (Note: When Duration percent complete type is used, the percent complete and remaining duration  of  an  activity  are  linked.  Therefore,  changing  the  percent  complete  or remaining duration will automatically affect the other).  

2. Specify Physical percent complete type when the percent complete is defined by the user based on amount of work performed  rather  than  remaining duration.  (Note: When Physical percent complete type  is used, the percent complete and remaining duration  of  on‐going  activities must  be  individually  specified  based  on  amount  of work remaining).  

3. Specify Units percent  complete  type when  the percent  complete  is based on  the actual labor or non‐labor units expended.  

3. Activity Type: Specify Task Dependent as the default activity type. The Activity Type may be modified for each individual activity, as necessary.   

4. Calendar:  Specify  a  default  Project  calendar  that  will  be  assigned  to  new  activities. Specific calendars may be assigned to individual activities, as necessary. 

 5. Auto‐numbering Defaults: Users may specify a user‐defined Activity ID auto‐numbering 

system for new activities by defining the default Activity ID Prefix, Activity ID Suffix, and Increment.   

Page 68: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page67 

4. Resources  Tab:  Click  on  the  Resources  tab  to  view/edit  the  project  default  settings  for resource assignments.   

   

Define the Assignment Defaults and Resource Assignments settings as follows:  

1. Specify the default Rate Type for new assignments as Price/Unit for use in cost‐loading or resource‐loading.  

2. Mark the Drive activity dates by default checkbox to allow the assigned resources dates to be dependent on the activity dates and vice versa for new resource assignments.  

3. Clear  the  Resource  Assignments  checkbox  to  prevent  the  same  resource  from  being assigned to an activity more than once.  

5. Settings Tab: Click on the Settings tab to view/edit the project default settings for defining the baseline  schedule used  for performing earned  value  calculations  and  the method  for defining the critical activities.  

 

   

Define the default settings as follows:  

1. Project  Settings:  Specify Project baseline  as  the baseline  for performing earned  value calculations.   

2. Define Critical Activities:  Specify  Longest Path as  the method  for defining  the project critical activities. 

Page 69: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page68 

6. Calculations Tab: Click on the Calculations tab to view/edit  the project default settings  for calculating  cost  and  resource  usage  when  updating  a  cost‐loaded  or  resource‐loaded schedule.  

 

   

Define the Calculations default settings as follows:  

1. Activities: In the Activities section of the form:   

1. Mark the Link Budget and At Completion Cost for not started activities checkbox to make the Budgeted Cost and At Completion Cost the same for activities that have not started.  

2. Specify  Reset  Remaining  Duration  and  Units  to  Original  to  reset  the  remaining duration and units of an activity  to  their original values when an activity  status  is changed to not started.   

2. Resource Assignments: In the Resource Assignment section:   1. Specify Subtract Actual from At Completion, when updating Actual Units or Cost. 

 2. Set  the  Recalculate  Actual  Units  and  Cost  when  duration  %  complete  changes 

checkbox as follows:  

i) For  Design‐Bid‐Build  projects,  clear  the  checkbox  to  prevent  the  application from  automatically  re‐calculating  the  actual  units  and  cost when  the  activity duration % changes to allow the user to define the actual units and costs.  

ii) For  Design‐Build  projects, mark  the  Recalculate  Actual  Units  and  Cost  when duration % complete changes checkbox to allow for Auto Compute Actuals.   

3. Mark  the Update units when  costs  changes on  resource assignments  checkbox  to allow the application to re‐calculate the units based on the price/unit when the cost is changed.  

4. Mark  the Link Actual and Actual This Period Units and Cost checkbox  to allow  the application  to  automatically  change  the  Period  Actual Units  and  Costs when  the Actual Units and Costs are changed and vice versa. 

Page 70: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page69 

3. CREATING AND ASSIGNING CALENDARS  Each activity  in a schedule  is assigned a calendar, which  is used by the application to calculate the project  schedule  to determine when  the  activity  can be performed.  The  start date/time  and  the finish date/time of an activity are based on the available workdays and work hours defined  in the assigned calendar. The calendar assigned to the project when it is created is automatically assigned to  each  new  activity  by  default.  However,  additional  calendars may  be  created  as  needed  and assigned to  individual activities to reflect specific project requirements. For example, a standard 5‐day workweek calendar may be defined as the project default calendar and assigned to majority of the  activities, while  a 7‐day  calendar or other  special  calendars may be  created  and  assigned  to specific activities based on project‐specific requirements. The  following are guidelines  for creating and assigning calendars in Primavera P6.   1. Types of Calendars – In Primavera P6, there are three types of calendars global, resources, and 

project:  

   1. Global:  Global  calendars  are  defined  within  the  global  calendar  pool  and  are  therefore 

available for use on any project or resource within the database. When global calendars are used, there is the possibility of contaminating or overwriting the global calendars in another database with identical calendar names when the projects are exchanged as in the case with contractor  schedules  created  in  the  contractor’s  database  and  imported  into  the  VDOT database. Hence, use of global calendars is not allowed for contractor submitted schedules as required by specifications.  

2. Resource: Resource calendars are defined within the global resource calendar pool for use on resources only and can be used by any resource within the database. Resource calendars are used  to determine  the  availability of  resources  and  timing of  activities with  resource dependent activity types. 

 3. Project: Project calendars are defined within the project calendar pool and are only available 

for  use  on  the  project  in  which  they  are  created.  (Note:  Project‐specific  calendars  are required by specifications for contractor submitted schedules. Use of global calendars is not allowed and will result in rejection of the schedule). 

Page 71: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page70 

2. Creating Calendars – The following are guidelines for creating calendars:  1. Click  on  Enterprise  in  the Menu  bar,  and  then  click  on  Calendars  to  open  the  Calendars 

dialog box.  

   

2. In the Calendars dialog box, specify Project, and then click on the Add button to open the Select Calendar To Copy From dialog box.  

        

Page 72: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page71 

3. In the Select Calendar To Copy From dialog box, select an appropriate global calendar from which to copy. Then click on the Select (+) button to copy the selected global calendar into the project calendar pool.  

   

4. Select the newly added project calendar and rename, as appropriate.  

   

5. Select  the newly  created  calendar,  and  then  click on  the Modify button  to  view/edit  the calendar’s working hours, working days, and non‐working days, as necessary.  

       

Page 73: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page72 

6. Click on the Inherit holidays and exceptions from Global Calendar drop down  list, and then select <None> to detach the selected project calendar from the global calendar from which it was created.  

 

   

7. Click on the Total work hours/day radio button, and then click on the Workweek button to view/edit the Standard work hours for each day for the selected calendar. Then click on OK to accept the changes and close the dialog box. (Note: Unless it is necessary to schedule by the hour, all project calendars should be defined based on the same Standard work hours for each day (typically 8 hours), regardless of number of work hours/day planned). 

 

 

Page 74: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page73 

8. Click on the Detailed work hours/day radio button, and then click on the Workweek button to view/edit the standard work hours for each day. Select each day of the week to view/edit the work hours for the day, as necessary. Then click on OK to accept the changes and close the dialog box. (Note: Each day of the week should start and finish at the same times for a standard 8 hour work day, if the Time Period Hours/Day for each day is set to 8 hours).    

   

9. Click on the Time Periods button to view/edit the default number of hours per time period for converting activity duration and resource units, as necessary. Then click on OK to accept the changes and close the dialog box.  

 

Page 75: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page74 

10. To modify a calendar  to change a non‐work day(s)  to work day(s) or vice versa, select the date(s), and then click on the Work button or Nonwork button, as applicable. To make the selected date(s) normal work day(s), click on the Standard button. Then click on OK to apply the changes and close the calendar. (Tip: Use the “shift” or “ctrl” key to select multiple dates at once).  

   

11. To  display  the  calendar  for  the  previous month,  click  on  the  “<”  button.  To  display  the calendar for next month, click on the “>” button.   

   

Page 76: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page75 

12. To change the display from a monthly calendar to a yearly calendar or vice versa, click on the month/year tab. To display the calendar for the previous year, click on the “<” button. To display the calendar for next year, click on the “>” button.  

   

3. Assigning  a  Calendar  – When  an  activity  is  added  to  a project,  the default  calendar defined when  the project was created  is automatically assigned  to  the new activity. The  following are guidelines for assigning a different calendar, if necessary:  1. In  the Activities window,  select  an Activity  to which  a  specific  calendar will  be  assigned. 

Then  click on  the General  tab  in  the Activity Details  form,  and  then  click  on  the Activity 

Calendar   browse button to open the Select Activity Calendar window.  

 

Page 77: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page76 

2. In the Select Activity Calendar dialog box, click on the Display bar, and then click on Project Calendars to display list of available project calendars.  

    

3. Select a calendar  from  the project calendar  list, and  then click on  the Select  (+) button  to assign the calendar to the selected activity.  

   

4. To copy an assigned calendar to other activities  in the Activity Table, click on the Calendar cell of the activity from which to copy, then select the activities to which the new calendar will be assigned using the “Shift” or “Ctrl” keys as applicable, then right‐click, and then click on Fill Down.  

 

Page 78: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page77 

4. DEVELOPING A WORK BREAKDOWN STRUCTURE (WBS)  

A WBS  is a hierarchical breakdown of the project  into  logical and manageable work packages. The project WBS  provides  a  structured  framework  with  which  to  develop  and  organize  the  project schedule for effective use. The following are guidelines for creating a WBS in Primavera P6.   1. Click on the WBS button in the Directory Bar to open the WBS window. (Note: A project must be 

open in order to create or modify the WBS).  

   

2. In  the Work  Breakdown  Structure window,  select  the  parent  node  under which  a  new WBS element will be added, and then click on the Add button in the Command Bar to add a new child WBS element. (Note: By default, the Project is the root node of the WBS). 

 

 

Page 79: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page78 

3. In the General tab, define a unique WBS Code and WBS Name for each added WBS element.  

   

4. Repeat steps 2 and 3 above, as often as necessary to breakdown the project  into manageable and measurable work packages. The arrow buttons  in the Command Bar can be used to move the WBS elements within the hierarchy, as needed. The up and down arrow buttons can be used to move WBS elements upward or downward vertically. The left arrow can be used to promote (decrease  indent  level)  of  the  selected WBS  element.  And  the  right  arrow  can  be  used  to demote (increase indent level) the selected WBS element, as needed.   

 

Page 80: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page79 

5. ADDING ACTIVITIES  Depending on the User Preference settings, activities can be added using the New Activities wizard. Once a user becomes more familiar with the application, the New Activity wizard may be disabled and  the  activity  properties  can  then  be  defined  using  the Activity Details  form  or Activity  Table columns. The  following are guidelines  for adding activities  in Primavera P6 using  the New Activity wizard.   1. In the Activities window, select  the WBS node under which a new activity will be added, then 

click on the Add button  in the Command bar to  launch the New Activity wizard that will allow the user to enter/edit the activity properties for the new activity. 

 

   

2. In the New Activity dialog box, edit the Activity ID and Activity Name as needed, and then click on Next. 

  

 

Note: The New Activity wizard guides 

the  user  through  the  process  of 

defining  necessary  Activity  properties 

and  information  when  adding  new 

activities. Users may disable  the New 

Activity  wizard  by  checking  the  “Do 

not  show  this  wizard  again”  box.  In 

which case, the Activity properties and 

information must  then  be  entered  in 

the  Activity  Details  form.  See  User 

Preferences  for  guidelines  on  turning 

on/off the New Activity Wizard. 

Page 81: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page80 

3. Click on  the browse button   to  verify/select  a WBS node under which  the Activity will be added, then click on Next. 

 

   

4. Click on the drop down button to select an Activity Type for the selected activity, if the default Activity Type is inappropriate, and then click on Next.  

 

   

The following are guidelines for specifying Activity Types:  

1. WBS Summary: A WBS Summary activity type can be used for a summary‐level activity that represents the overall timing and duration of all activities under a WBS node. The start date of a WBS summary activity is based on the start date of the earliest activity within the WBS group and  its  finish date  is based on  the  finish date of  the  latest activity. Unlike “Level of Effort” activities, WBS Summary activities do not require logic. 

Page 82: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page81 

2. Start Milestone: A  Start Milestone  activity  type  can  be  used  for milestone  activities  that mark  the  start  date  of  a major  portion  of  the Work  such  as  a  phase  or  stage.  A  Start Milestone activity has a start date, but not a finish date because its duration is zero.  

3. Finish Milestone: A Finish Milestone activity  type can be used  for milestone activities  that mark  the  finish  date  of  a major  portion  of  the Work  such  as  a  phase  or  stage. A  Finish Milestone activity has a finish date, but not a start date because its duration is zero.  

4. Task Dependent: A Task Dependent activity type can be used for activities whose start and finish  dates  are  dependent  on  network  logic  and  the  calendar  assigned  to  the  activities rather than the calendar of their assigned resources. Task Dependent is the default Activity Type and should be used for most activities.  

5. Level  of  Effort:  A  Level  of  Effort  (LOE)  activity  type  can  be  used  for  on‐going  tasks  that typically  span  an  indefinite  time  period,  whose  start  dates  are  dependent  on  their predecessors and finish dates are dependent on their successors. LOE activities may be used for certain administrative or project management  tasks  that  typically  span  indefinite  time periods such as MOT, project surveying, and maintenance of erosion control systems, etc.  

6. Resource Dependent: A Resource Dependent activity type can be used for activities whose assigned  resources  are  dependent  on  the  resources  calendars  rather  than  the  activity’s calendar. Therefore,  the  activity durations and dates are dependent on  the  calendar and availability of  the  driving  resources.  Such  activities  are  scheduled  to be  performed when their assigned resources are available.   

5. In  the Assign Resources dialog box,  leave blank,  then click on Next.  (Note: This box  is used  to assign  resources  to  the  selected  activity when  cost‐loading  or  resource‐loading  the  schedule. Assigning Resources will be covered later in the guide).  

   

Page 83: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page82 

6. In the Duration Type dialog box, click on the Duration Type drop down button, then select Fixed Duration & Units, and then click on Next.  

   

7. In the Activity Units and Duration dialog box, enter the Activity Duration (number of workdays required to complete the activity), then click on Next.  

   

8. In the Dependent Activities dialog box, specify No, continue, and then click on Next. Predecessor and successor relationships will be defined later.  

 

Page 84: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page83 

9. In the More Details dialog box, specify No, thanks, and then click on Next. Remaining required properties will be defined later.  

   

10. Click on Finish to add the new activity and to close the New Activity Wizard.  

  

           

Page 85: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page84 

6. DEFINING AND ASSIGNING ACTIVITY CODES  Activity  code  is  an  activity  property  that  can  be  used  to  filter,  group,  or  organize  activities  by category for the purposes of creating layouts and reports or analyzing schedules. The following are guidelines for defining and assigning activity codes in Primavera P6.   1. Defining  Activity  Codes  –  Before  assigning  activity  codes  to  activities,  an  Activity  Codes 

dictionary must first be defined. The following are guidelines for defining activity codes:  1. Click on Enterprise  in  the Menu bar, and  then click on Activity Codes  to open  the Activity 

Codes dialog box.  

   

2. In the Activity Codes dialog box, specify Project to add/edit project‐level activity codes, and then click on Modify to open the Activity Code Definitions – Projects dialog box.   

 

Global: Global activity codes are created at the global level and are available for use on any activity within the database. (Note: Use of Global or EPS Activity Codes is not allowed and will result in rejection of the schedule).  

EPS: EPS activity codes are created at the EPS level and are available for use on any activity within the EPS node.  

Project: Project activity codes are created at the project level and are only available for use on activities in the project for which they are created.  

Page 86: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page85 

3. In  the Activity Code Definitions dialog box, click on  the Add button  to add a New Activity Code category, and then re‐name to define the activity code category. Define the following activity codes, as applicable: Responsibility, Phase, Stage, Feature of Work, Area, Location, Work Type, Crew, Contract Modification, etc. Once the activity codes have been added and defined,  click  on  the  Close  button  to  close  the  Activity Definitions window.  (Note:  After Activity Codes have been created, Code Values must then be defined for each Activity Code).  

   

4. In the Activity Codes dialog box, click on the drop down button, then select from the list of available activity codes, an activity code to which activity code values will be defined. Then click  on  the  Add  button  as  often  as  necessary  to  add  new  code  values  for  the  selected activity code. Define for each code value, the Code Value and Description, as applicable.   

        

Page 87: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page86 

2. Assigning  Activity  Codes  – One  or more  activity  codes  can  be  assigned  to  an  activity  or  to multiple activities at once. The following are guidelines for assigning activity codes:  1. Assigning  Activity  Codes  to  an  Activity:    Activity  codes  can  be  assigned  to  an  activity  as 

follows:   1. In the Activities window, select an activity to which activity codes will be assigned. Then 

click on the Codes tab in the Activity Details, and then click on the    button or click on the Activity Codes button on the Command bar to open  the Assign Activity Codes dialog box.   

   

2. In the Assign Activity Codes dialog box, specify Project, then select the applicable activity 

code value(s), and then click on the Assign     button to assign the selected code(s) to 

the selected activity, and then click on the Close    button. (Note: To assign multiple Activity Codes, use the “Shift” or “Ctrl” key on your keyboard, as appropriate).  

 

Page 88: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page87 

2. Assigning Activity Codes  to Multiple Activities:   An activity code or multiple activity codes can be assigned to multiple activities at once as follows:   1. In the Activities window, select the activities to which activity code(s) will be assigned. 

Then click on the Activity Codes button on the Command bar to open the Assign Activity Codes dialog box. (Note: To select multiple activities, use the “Shift” or “Ctrl” key on your keyboard, as appropriate).  

   

2. In  the  Assign  Activity  Codes  dialog  box,  specify  Project,  then  select  the  applicable 

activity code value(s), and  then click on  the Assign    button  to assign  the  selected 

code(s)  to  the  selected activities, and  then  click on  the Close    button  to  close  the Assign Activity Codes dialog box.  

 

Page 89: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page88 

7. ADDING ACTIVITY RELATIONSHIPS  Critical Path Method  (CPM)  schedules  require activity  relationships  to establish  the network  logic with which the project schedule  is calculated and the project critical path  is defined. The network logic defines the inter‐relationships between the activities and the order in which the activities must be performed. Based on user preference, activity relationships can be created in the Activity Details form, Gantt Chart view, or Activity Network view; or by using the right‐click function in the Activity Table. The following are guidelines for creating relationships using the Activity Details form.  1. In the Activities window, click on the Relationships tab  in the Activity Details form to open the 

Predecessors and Successors forms. Then select an activity to which relationships will be added.  

   

2. To assign a predecessor relationship, click on the Predecessors button  in the Command bar or 

the Assign   button in the Predecessors form to open the Assign Predecessors dialog box from which to select and assign predecessor activities to the selected activity. 

 

  

1. In the Assign Predecessors window, select the predecessor activities, and 

then click on the Assign    button to assign the predecessor relationships.  

2. To select multiple predecessor activities, use the “Ctrl” or “Shift” keys on your keyboard accordingly.  

3. Click on the Close   button to close the Assign Predecessors window. 

Page 90: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page89 

3. To assign a successor  relationship, click on  the Successors button  in  the Command bar or  the 

Assign   button in the Successors form to open the Assign Successors window from which to select/assign successor activities to the selected activity. 

 

   

4. After assigning the predecessor or successor relationships, the relationship type and/or lag may be edited as necessary.  

 

   1. Click on the predecessor or successor activity Relationship Type field to select from a drop 

down menu, one of four relationship types as applicable.  

2. Click  on  the  predecessor  or  successor  activity  Lag  field  to  adjust  the  relationship  lag  as necessary.  

3. To  delete  a  predecessor  or  successor  relationship,  select  the  predecessor  or  successor 

activity, and then click on the Remove    button.  

4. To jump to a predecessor or successor activity from the Predecessor or Successor window, 

select the activity and click on the GoTo   button.  

    

1. In  the  Assign  Successors  window, select  the  successor  activities,  and 

then  click  on  the  Assign   button to assign the successor relationships.  

2. Multiple successor activities can be selected by using the “Ctrl” or “Shift” keys on your keyboard as appropriate.  

3. Click on the Close   button to close the Assign Successors window.  

Page 91: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page90 

8. ASSIGNING CONSTRAINTS  A constraint is a scheduling property that allows the user to specify when a project or an activity can or must begin or be completed to reflect project‐specific requirements. The following are guidelines for assigning constraints in Primavera P6.   1. Assigning  a Project Constraint  – Project‐level  constraints  can be used  to  restrict  the  start or 

finish of a project. As  required by  specifications, a Must Finish By project  constraint must be assigned  at  the  project‐level  to  establish  the  latest  date  by  which  the  project  must  be completed.  The  project  Must  Finish  By  constraint  date  is  the  latest  date  from  which  the backward  pass  calculation  is  performed  to  determine  the  Total  Float.  The  following  are guidelines for assigning a project‐level constraint:  1. In  the  Projects  window,  select  the  project  to  which  a  project‐level  constraint  will  be 

assigned, then click on the Dates tab in Project Details to open the Project Dates form.  

   

2. In the Dates form, click on the Must Finish By browse button   to select the date by which the project must be finished (i.e. Contract completion date). 

 

 

 

 

   

Page 92: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page91 

2. Assigning an Activity Constraint – An activity‐level constraint can be used to restrict the start or finish of an activity to reflect project‐specific requirements or when logic alone is not sufficient to accurately reflect realistic situations. However, constraints should be used sparingly and on a case by case basis as required by specification or as approved by the Engineer. Some constraints violate network logic while others affect float calculation.   The following are guidelines for assigning an activity‐level constraint:   1. In the Activities window, click on the Status tab in Activity Details to open the Status form in 

which to assign an activity constraint:  

   

2. In  the Constraints  section of  the Status  form, click on  the Primary constraints drop down 

button  to specify an activity‐level constraint. Then click on  the Date browse   button  to select the constraint date. A Secondary constraint may also be assigned, as necessary. 

 

  

Page 93: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page92 

The following are definitions, effects, and guidelines for using activity‐level constraints in Primavera P6:  

1. Start On: Specify Start On to define a specific date on which an activity must begin, as allowed by network  logic. This constraint may be used when an activity must begin on the specified date such as the date on which a subcontractor must mobilize or material must be delivered. The Start On constraint does not violate network  logic; however,  it delays the Early Start (ES) and accelerates the Late Start (LS) dates to the specified date, thereby reducing the activity’s available Free Float by the number of days delayed and the Total Float to zero.  

2. Start On or After: Specify Start On or After to define the earliest possible date that an activity can begin, as allowed by network  logic. This constraint may be used when an activity cannot begin prior to a specified date. The Start On or After constraint does not violate  network  logic;  however,  it  delays  the  ES  date  to  the  specified  date,  thereby reducing  the  activity’s  available  Free  Float  and  Total  Float  by  the  number  of  days delayed.  

3. Start On or Before: Specify Start On or Before to define the latest possible date that an activity can begin, as allowed by network  logic. This constraint may be used when an activity must  begin  by  a  specified  date.  The  Start  On  or  Before  constraint  does  not violate network logic; however, it accelerates the LS date to the specified date, thereby reducing the activity’s available Total Float by the number of days accelerated.  

4. Finish On: Specify Finish On to define a specific date on which an activity must finish, as allowed  by  network  logic.  This  constraint  may  be  used  when  an  activity  must  be completed  on  a  specified  date  such  as  monthly  MOT  or  QA/QC  or  other  such  re‐occurring  activities  that must  finish  at  the  end  of  the month  or  progress  period,  as applicable. The Finish On constraint does not violate network  logic; however,  it delays the Early Finish (EF) date and accelerates the Late Finish (LF) date to the specified date, thereby reducing the activity’s available Free Float by the number of days delayed and the Total Float to zero.  

5. Finish On or After: Specify Finish On or After to define the earliest possible date that an activity  can  be  completed,  as  allowed by network  logic.  This  constraint may be used when  an  activity  cannot  be  finished  prior  to  a  specified  date.  The  Finish On  or After constraint does not violate network logic; however, it delays the EF date to the specified date, thereby reducing the activity’s available Free Float and Total Float by the number of days delayed.  

6. Finish On or Before: Specify Finish On or Before to define the latest possible date that an activity  can  be  completed,  as  allowed by network  logic.  This  constraint may be used when  an  activity  must  be  completed  by  a  specified  date.  The  Finish  On  or  Before constraint  does not  violate network  logic; however,  it  accelerates  the  LF date  to  the specified  date,  thereby  reducing  the  activity’s  Total  Float  by  the  number  of  days accelerated.  If an  interim  completion milestone  is  specified  in  the Contract,  the  finish milestone activity should be constrained with a Finish On or Before constraint.  

Page 94: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page93 

7. As Late As Possible: Specify As Late As Possible to restrict the start of an activity to the latest possible  early dates,  as  allowed by network  logic.  This  constraint may be used when it is necessary to delay the completion of an activity until its successor is scheduled to begin. The As Late As Possible constraint does not violate network logic; however, it delays  the ES and EF dates  to  the  latest possible early dates based on available  Free Float,  thereby  reducing  the  activity’s  Free  Float  to  zero  and  the  Total  Float  by  the number of Free Float days consumed.   

8. Mandatory Start: This constraint restricts the early and late start dates of an activity to the specified date regardless of network  logic. The Mandatory Start constraint violates network  logic;  it  forces  the  ES  and  LS  dates  to  occur  on  the  specified  date,  thereby reducing  the  activity’s  Free  Float  and  Total  Float  to  zero.  Use  of  Mandatory  Start constraint  that violates network  logic  is not allowed and will  result  in  rejection of  the schedule.   

9. Mandatory Finish: This constraint restricts the early and late finish dates of an activity to the specified date regardless of network logic. The Mandatory Finish constraint violates network  logic;  it  forces  the  EF  and  LF  dates  to  occur  on  the  specified  date,  thereby reducing  the  activity’s  Free  Float  and  Total  Float  to  zero.  Use  of Mandatory  Finish constraint  that violates network  logic  is not allowed and will  result  in  rejection of  the schedule.  

 3. Assigning an Activity Constraint Notebook Topic – Upon assigning a constraint  to an activity, 

add  a  Constraints  note  to  the  constrained  activity  using  a  Constraints  Notebook  Topic  to describe  the  reason  for  assigning  the  constraint.  The  following  are  guidelines  for  adding  a Constraints Notebook Topic:   1. In Activity Details, click on the Notebook tab, and then click on the Add button to open the 

Assign Notebook Topic dialog box to add a Constraints Notebook Topic.  

        

Page 95: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page94 

2. In the Assign Notebook Topic dialog box, select Constraints, then click on the Add (+) button 

to assign the Constraints Notebook Topic, and then click on the Close   button to close the Assign Notebook Topic dialog box. 

 

   

3. In  the  Constraints  Notebook  Topic  notepad,  enter  a  note  to  describe  the  reason  for assigning the constraint. 

 

    

  

               

Page 96: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page95 

9. SCHEDULING A PROJECT  Upon developing, updating, or revising a project schedule, the schedule should always be scheduled (calculated) to ensure that activity dates and other schedule data are calculated to reflect current network  logic, durations, or other schedule changes made since  the schedule was  last calculated. The following are guidelines for scheduling a project in Primavera P6:   1. Schedule Calculation Settings – When scheduling a project in Primavera P6, define the schedule 

calculation  settings  as  follows  to  conform  to  the  scheduling  requirements  and  to  ensure consistency with the Department’s standard schedule calculation settings:  1. In the Projects or Activities window, click on Tools from the main menu, and then Schedule; 

or click on the Schedule icon on the Tool bar; or simply press the F9 key on your keyboard to open the Scheduling window.  

   

2. Click on the Options button to open the Schedule Options dialog box.  

 

Page 97: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page96 

3. In the Schedule Options dialog box, click on the General tab to view/edit the project general schedule calculation settings.  

 

 

Modify the schedule calculation settings as follows:  

1. Unmark the Ignore relationships to and from other projects checkbox, as applicable.  

2. Unmark the Make open‐ended activities critical checkbox to avoid treating open‐ended activities as critical.  

3. Mark  the  Use  Expected  Finish  Dates  checkbox  to  allow  the  application  to  schedule activity end dates as expected end dates.  

4. Unmark  the Schedule automatically when a change affects dates checkbox  to prevent the application from scheduling the project automatically every time a change is made.  

5. Unmark the Level resources during scheduling checkbox to prevent the application from resource‐leveling when scheduling open projects.  

6. Unmark  the  Recalculate  assignment  costs  after  scheduling  checkbox  is  unchecked  to prevent the application from recalculating the resource and role assignment costs when scheduling projects.  

Page 98: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page97 

7. Specify  Retained  Logic  when  scheduling  progressed  activities  to  maintain  original network logic. 

 

8. Specify Early Start to calculate the lag for start‐to‐start.  

9. Specify the Longest path as the method for defining critical activities.  

10. Specify Each project to ensure that float is calculated relative to the finish date of each individual project as opposed to all open projects.  

11. Select from the drop down list Finish Float = Late Finish ‐ Early Finish as the method for computing total float.  

12. Select from the drop down  list Predecessor Activity Calendar as the calendar to use for scheduling relationship lag.   

2. Scheduling a Project – After setting the schedule calculation options, calculate the schedule as follows:   

1. Click on  the  Current Data Date   browse button  to  specify  the  current data  date  from which  to calculate  the schedule. The data date  represents  the status date  for progressing completed or on‐going work and  the starting point  for scheduling  the remaining work. All activities to the left of the data date are considered complete and all activities to the right of the data date are considered remaining.  

   

2. Mark  the  Log  to  file  box  to  record  scheduling  results  in  a  log  file.  Then  click  on  the   browse button to specify the filename and location for the schedule calculation log file.   

3. Click on the Schedule button to calculate the schedule.  

4. To view the schedule calculation log after scheduling the project, click on View Log button to open the log text file. Alternatively, users may simply locate the log text file and double‐click on it to open the log. 

Page 99: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page98 

SECTION IV  COST‐LOADING AND RESOURCE‐LOADING A SCHEDULE                 

1. Overview  2. Understanding Resources  3. Working in the Resources Window   4. Software Settings for Resource Assignments   5. Cost‐loading a Schedule 

 6. Resource‐loading a Schedule 

 

Page 100: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page99 

SECTION 

IV   

 

1. OVERVIEW  

For the purposes of this guide and the VDOT scheduling specifications, cost‐loading  is a process of defining  the  quantity  of work  associated with  an  activity  and  amount  of money  the  contractor expects  to be paid  for  accomplishing  the  activity. A  cost‐loaded  schedule provides  a means with which to determine the scope and magnitude of an activity to facilitate review and analysis of the schedule;  as well  as  for payment purposes  for design‐build projects. A  cost‐loaded  schedule also allows  for a more accurate assessment of actual progress of  the Work; as well as  for determining trends and variances in performance, and progress forecasts based on productivity.   Resource‐loading  is  a  process  of  defining  the manpower,  equipment,  and materials  required  to complete  an  activity.  A  resource‐loaded  schedule  provides  a  means  with  which  to  assess  the reasonableness of a  schedule and  the minimum  time  required  to  complete  the project based on resource availability. A resource‐loaded schedule also provides a means with which to plan, utilize, and  manage  resources  efficiently  on  a  project  by  balancing  available  resources  with  project requirements. Resource‐loading demonstrates the contractor’s ability and commitment to complete the project as planned. This section of the guide provides guidelines for cost‐loading and resource‐loading a schedule  in Primavera P6 to comply with VDOT scheduling specifications for Category IV, V, and Design‐Build projects, as applicable.   

2. UNDERSTANDING RESOURCES  

In Primavera P6 resources are required for cost‐loading or resource‐loading a schedule. When cost‐loading or resource‐loading is required by specifications, project‐specific resources must be defined for  use  in  cost‐loading  or  resource‐loading  the  schedule.  Resources  can  generally  be  defined  in terms of  input or output.  Input  resources are generally people, equipment  (machinery), materials required to accomplish an activity. While output resources are generally quantity of work produced or  amount of money  earned  for  accomplishing  an  activity. Resources  are defined  and measured differently based on resource type and as follows: 

 1. Labor  –  Labor  resources  are  used  to  define  the manpower  (people)  needed  to  complete  an 

activity.  When  resource‐loading  is  specified,  labor  resources  should  be  used  to  define  the manpower needed to complete the activity. Labor resources can be defined as follows:  

Page 101: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page100 

1. Labor resources may be defined in terms of named individuals (e.g. John Doe); by Trade (e.g. Laborer,  Labor  Foreman,  Carpenter,  Pipe  Layer,  Ironworker,  Crane  Operator,  Dozer Operator,  etc.);  or  by  Crew  (e.g. Grading  Crew  #1, Drainage  Crew  #1,  Pile Driving  Crew, Drilled Shaft Crew, Concrete Crew, Asphalt Paving Crew, etc.).  

2. Labor resources units are measured in units of time, usually in hours (h). However, the units of  time  for  labor  resource assignments can be defined or displayed  in  terms of hours  (h), days  (d), weeks  (w), months (m), or years (y) based on user preference. For simplicity and ease  of  analysis,  budgeted  units  of  time  for  labor  resource  assignments may  be  defined and/or displayed in terms of days (d) rather than hours (h). 

 2. Non‐Labor  – Non‐labor  resources  are  used  to  define  the  equipment  (machinery)  needed  to 

accomplish an activity. When resource‐loading is specified, non‐labor resources should be used to define the equipment(s) needed to complete the activity. Non‐labor resources can be defined as follows:  1. Non‐labor  resources  should be defined  for each  type of major equipment used  for major 

operations  that  are  expected  to  drive  the  schedule  (e.g.  Cranes,  Backhoes,  Excavators, Dozers,  Graders,  Scrapers,  Dump  Trucks,  Pile  Hammer,  Rollers,  Concrete  Screed,  Paving Machines, etc.).  

2. Non‐labor resources units are measured in units of time, usually in hours (h). However, the units of time for non‐labor resource assignments can be defined and/or displayed  in terms of hours  (h), days  (d), weeks  (w), months  (m), or years  (y) based on user preference. For simplicity and ease of analysis, budgeted units of time for non‐labor resource assignments may be defined and/or displayed in terms of days (d) rather than hours (h).  

3. Material – Material resources are used to define consumables or re‐usable materials needed to accomplish an activity. Material resources are also used to define output of work that an activity represents  for  the purposes of  cost‐loading a  schedule. Material  resources  can be defined as follows:  1. When  cost‐loading  is  required by  specifications, material  resources are  required  for  cost‐

loading  the schedules. Material resources should be defined  for  the contract pay  items as shown in the Schedule of Items (e.g. 00100 ‐ Mobilization, 00120 – Regular Excavation, etc.).  

2. When  resource‐loading a schedule, material  resources should be defined  for each  type of major re‐usable material needed to complete major operations that are expected to drive the  schedule  (e.g.  Foundation  Forms,  Column  Forms,  Falsework,  Overhang  Forms,  Deck Concrete Forms, etc.).  

3. Material  resources  are  typically measured  in units other  than  time based on  the  type of material. For cost‐loading, the material resource unit of measure should match the unit for the pay  item as  shown  in  the Contract Schedule of  Items  (e.g. Each  (EA), Lump Sum  (LS), Linear Foot (LF), Ton (Ton), Pound (LB), Square Foot (SF), Square Yard (SY), Cubic Yard (CY), etc.). 

Page 102: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page101 

3. WORKING IN THE RESOURCES WINDOW  

In Primavera P6, resources are global data that are available for use on any project or activity within the database. The Resources window is used to display the Resource Hierarchy and Resource Details form with which  to view, add, delete, or edit  resources. To open  the Resources window, click on Resources in the Directory bar. 

 1. Resource Hierarchy – The top pane of the Resources window displays the Resource Hierarchy, 

which can be used to view resources  in either a tabular or chart view. The Resource Hierarchy can be used to view, add, delete, or edit resources in the pool.   

   

2. Display Options Bar – The Display Options bar provides a menu of options that can be used to customize the Resources window.  

  

Command 

Bar

Resource 

Details

Display 

Options Bar

Resources 

Hierarchy 

Page 103: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page102 

The Display Options bar can be used to customize the Resources window as described below:  1. Click on Details to display or turn off the Resource Details form, as needed. 

 2. Click on Chart View  to display  the  resources  in a chart view or Table View  to display  in a 

tabular format.  

3. Click on Columns  to customize  the Resource hierarchy by selecting  from available options what resource items to display in the columns.  

4. Click  on  Filter  By  and  then  All  Active  Resources,  All  Resources,  or  Current  Project’s Resources for what resources to display.    

5. Click on Group and Sort By to specify how the resources will be organized and sorted in the Resource hierarchy.   

6. Click on Collapse All or Expand All,  as needed  to  collapse or expand  the entire Resource hierarchy.   

 3. Command Bar  –  The Command bar displays  a menu of  commands  that  can be used  to  add, 

delete, merge, cut/copy/paste, or move resources around in the Resource hierarchy.  

   The command buttons  in the Command bar of the Resources window can be used to manage resources in the Resource hierarchy as described below:  1. Click on  the Add button  to create a new  resource under  the selected  resource within  the 

Resource hierarchy.  

2. Click on the Del/Merge button to delete the selected resource from the Resource hierarchy.  

Page 104: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page103 

3. Click on the Cut button to remove the selected resource from  its current position. Click on the Paste button to place it in the selected position.  

4. Click on the Copy button to create a copy of the selected resource. Click on the Paste button to place it in the selected position.    

5. Click on  the arrow buttons to move the selected resource  from  its current position within the hierarchy.   1. Click  on  the  Up  arrow  to move  the  selected  resource  upwards  vertically within  the 

hierarchy, as needed.   

2. Click on the Down arrow to move the selected resource downwards vertically within the hierarchy, as needed.   

3. Click on  the  Left  arrow  to promote  (decrease  the  indent  level)  the  selected  resource within the hierarchy, as needed.   

4. Click on  the Right  arrow  to demote  (increase  the  indent  level)  the  selected  resource within the hierarchy, as needed.   

4. Resource Details – The Resources Details form can be used to view or edit  information about the selected resource as described below:  1. General Tab: Click on the General tab to view or edit general information about the selected 

resource such as the Resource ID and Resource Name.  

    

Page 105: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page104 

2. Codes Tab: Click on the Codes tab to assign resource codes to the selected resource for use in grouping, sorting, and organizing resources by category. 

 

   

3. Details Tab: Click on the Details tab to view or edit the resource details and properties for the selected resource such as Resource Type, Unit of Measure, Currency, Calendar, Default Units/Time; and settings for Auto Compute Actuals and Calculate costs from units.  

    

Page 106: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page105 

4. Units & Prices Tab: Click on the Units & Prices tab to define the Price/Unit, Max Units/Time, and effective dates of the units and prices for the selected resource.  

   

5. Notes Tab: Click on the Notes tab to add notes and information about the selected resource. The  notes  pad  can  be  used  to  add  a  written  description  about  a  resource  such  as  a description of a crew size and make‐up.  

      

Page 107: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page106 

4. SOFTWARE SETTINGS FOR RESOURCE ASSIGNMENTS   

When  cost‐loading  or  resource‐loading  a  schedule  in  Primavera  P6,  resource‐centric  software settings  required  for  resource  assignments must  be  defined  accordingly  to  ensure  that  resource assignments data are computed and  formatted properly. The  following are guidelines  for defining applicable software settings required for cost‐loading or resource‐loading a schedule: 

 1. User Preferences Settings – Prior to assigning resources to a project schedule for the purposes 

of  cost‐loading  or  resource‐loading  a  schedule,  the  following  applicable  user  preferences settings should be defined as follows:  

1. Click on Edit on the Menu bar, then User Preferences to open the user preferences dialog box.  

   

2. Currency: Click on the Currency tab to specify how monetary values are displayed.  

 

1. Click  on  the  currency  browse button, and then select Dollar.  

2. Mark the Show currency symbol box to show monetary values with the dollar symbol ($).  

3. Mark  the Show decimal digits box to  show  monetary  values  in  two (2) decimal places.  

  

Page 108: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page107 

3. Assistance:  Click on  the Assistance  tab  to  turn on/off  the New Resource or New Activity wizard for assistance when adding new resources or activities based on user preference.  

   

4. Resource Analysis: Click on the Resource Analysis tab to specify which projects are included in  resource  calculations  and which  dates  and  time  intervals  are  used  to  calculate  time‐distributed data for resource spreadsheets and profiles.  

     

Page 109: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page108 

The Resource Analysis user preferences should be defined as follows:  1. All  Projects:  When  All  Projects  are  shown  in  the  Resource  Usage  Spreadsheet  and 

Profile, all opened projects are included as well the closed projects specified below:  

1. Do not specify All closed projects (except what‐if projects), except when electing to 

include data for all closed projects other than what‐if projects.   

2. Do not specify All closed projects with  leveling a priority equal/higher than, except 

when electing to include data for all closed projects with a specific leveling priority.  

3. Specify Opened projects only to include data for open projects only. 

 

2. Time‐Distributed Data:  The  Time‐Distributed Data  settings  are  used  to  specify which 

dates  and  time  interval  are  used  to  calculate  time‐distributed  data  for  resource 

spreadsheets and profiles.   

1. Specify  Remaining  Early  dates  to  calculate  remaining  values  based  on  remaining 

start/finish dates.  

2. Do not specify Forecast dates to avoid calculating time‐distributed values based on 

forecast start/finish dates.  

3. Specify Day as the Interval for time‐distributed resource calculations. 

  5. Calculation:  Click  on  the  Calculations  tab  to  specify  how  remaining  values  are  calculated 

when new resource assignments are added to, or removed from activities.   

 

1. Specify Preserve the Units, Duration, and Units/Time  for  existing  assignments  to ensure  that  the  remaining  units, duration,  and  units/time  for  existing resource assignments remain as defined based on the formula (Remaining Units = Remaining  Duration  *  Remaining Units/Time).  

2. Specify  Always  use  the  new  resource’s Units  per  Time  and  Overtime  factor when assigning a resource to an existing assignment.  

3. Specify  Always  use  resource’s  Price  per Unit when a resource and role share an activity assignment.  

Page 110: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page109 

2. Project Settings – Prior  to assigning  resources  to a project schedule  for  the purposes of cost‐loading or resource‐loading a schedule, the following applicable project level settings should be defined as follows:  1. In  the Projects window,  select  and open  a project  to which  the project  level  settings  for 

resource assignments will be defined.  

   

2. In the Projects window, click on the Resources tab  in the Project Details form to view/edit the project default settings for resource assignments.  

   

Page 111: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page110 

Define the Resources default settings as follows:  1. In the Assignment Defaults area:  

1. Specify  the  default  Rate  Type  for  new  assignments  as  Price/Unit  for  use  in  cost‐loading.  

2. Mark the Drive activity dates by default checkbox to link the activity dates with the resource assignments dates  to allow  the  resource assignment  finish dates  to align with the activity finish dates and vice versa for new resource assignments.  

2. Clear  the Resources can be assigned  to  the same activity more  than once checkbox  to prevent unintended multiple assignments of the same resource to an activity. 

  

3. Click on  the Calculations  tab  to view/edit  the project default settings  for calculating costs and resource usage when updating a cost‐loaded or resource‐loaded schedule.  

   Define the Calculations default settings as follows:  1. In the Activities area:  

 1. Specify  $0.00/h  for  Default  Price/Unit  for  activities  without  resource  or  role 

Price/Units  to  prevent  the  application  from  automatically  assigning  costs  to activities  when  labor  or  non‐labor  units  are  defined  with  no  assigned resources/roles or with resources/roles that do not have prices.  

Page 112: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page111 

2. Unmark the Activity percent complete based on activity steps checkbox to prevent the  application  from  calculating  the  activity  percent  complete  based  on  activity steps when using Physical Percent Complete type.  

3. Mark the Link Budget and At Completion Cost for not started activities checkbox to make  the Budgeted Cost equal  the At Completion Cost  for activities  that have not started.  

4. Specify Reset Remaining Duration and Units to Original to ensure that the remaining duration and units of an activity are reset to their original values when an activity is un‐progressed.   

2. In the Resource Assignment area:   1. Specify Subtract Actual from At Completion, when updating Actual Units or Cost. 

 2. The Recalculate Actual Units and Cost when duration % complete changes checkbox 

should be defined as follows:  i) For  Design‐Bid‐Build  projects,  clear  the  checkbox  to  prevent  the  application 

from  automatically  re‐calculating  the  actual  units  and  cost when  the  activity duration %  changes.  This  allows  the  user  to manually  enter  and  control  the actual units and cost for on‐going activities based on actual work performed.   

ii) For  Design‐Build  projects, mark  the  Recalculate  Actual  Units  and  Cost  when duration  %  complete  changes  checkbox  to  allow  the  Auto  Compute  Actuals feature  to automatically calculate actual units and costs  for on‐going activities based on the assigned resource curve.   

3. Mark  the Update units when  costs  changes on  resource assignments  checkbox  to allow the application to re‐calculate the units based on the Price/Unit when the cost is changed.  

4. Mark  the Link Actual and Actual This Period Units and Cost checkbox  to allow  the application  to  automatically  change  the  Period  Actual  Units  and  Costs when  the Actual Units and Costs are changed and vice versa.  

          

Page 113: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page112 

5. COST‐LOADING A SCHEDULE   

Cost‐loading is a process of assigning units and costs to an activity for the purposes of defining the magnitude and dollar value of work  that  the activity  represents. Cost‐loading  is  required only  for Category IV and V and Design‐Build projects. However, contractors may cost‐load other schedules at their discretion, but should do so according to the guidelines provided herein. Cost‐loading  involves two  primary  steps:  1)  creating  cost  resources  and  2)  assigning  cost  resources  to  activities.  The following  are  guidelines  for  cost‐loading  a  schedule  in  Primavera  P6  to  comply  with  the  VDOT scheduling specifications:  1. Creating Cost Resources Using New Resource Wizard – The first primary step in cost‐loading a 

schedule is creating cost (bid item) resources, as required by specifications. Cost resources may be created by  importing resources created  in another database or by using the New Resource Wizard. The following are guidelines for creating cost resources in Primavera P6, using the New Resources Wizard:  1. Create  a  Project  Resource  Node:  If  a  Project  (parent)  resource  node  under  which  the 

individual  contract  bid  item  resources  will  be  nested  does  not  currently  exist,  create  a Project  level  resource  prior  to  creating  the  individual  cost  resources  required  for  cost‐loading the schedule as follows:  1. Prior  to adding  resources  in  the Resources Hierarchy, set  the  filter  to All Resources  to 

display all existing resources. Click on the Display Options bar, then Filter By, and then All Resources.   

         

Page 114: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page113 

2. Select a Contractor resource node (parent) under which the new Project level resource will be added, and then click on the Add button to launch the New Resource Wizard.   

   

3. Define the Project level resource Resource ID and Resource Name.   

   

Define the Project level Resource ID and Resource Name as follows:  

1. Enter  the  Contract  ID  number  (e.g.  C00012345C01)  in  the  Resource  ID  field  to provide a unique identification number/code for the Project level resource. 

 

2. Enter the project name/description in the Resource Name field to provide a brief description for the Project level resource. 

 

3. Click on the Next button.   

Page 115: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page114 

4. In the Resource Type dialog box specify Labor, and then click on the Next button.  

  

5. In the Price/Unit, Default Units/Time, and Max Units/Time fields, enter zero  (0) values for the Project level resource units/time and price, and then click on the Next button.  

          

Page 116: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page115 

6. In the Phone & E‐Mail dialog box, click on the Next button.  

   

7. In the Roles dialog box, click on the Next button.  

         

Page 117: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page116 

8. In  the Resource Calendar dialog box,  specify  Select an  existing  calendar  to  select  the project‐specific  resource calendar  from  the Resource Calendar pool, and  then click on the Next button, if a project‐specific resource calendar was previously created. (Note: If a  project‐specific  resource  calendar  does  not  currently  exist,  specify  Create  a  new calendar  for  this  resource  to  create  a  new  project‐specific  resource  calendar.  It  is recommended  that  a  project‐specific  default  resource  calendar  be  created  for  each project before  creating  the project  resources. For guidelines on  creating new  resource calendars, see Section III, Subsection 3 – Creating and Assigning Calendars).   

   

9. If selecting from an existing calendar, click on the Browse button  in the Select Existing Calendar dialog box, to select from a pool of existing resource calendars, and then click on the Next button. To view or edit the selected calendar, click on the View/Edit button.  

 

Page 118: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page117 

10. In the Auto‐Compute Actuals dialog box, specify Do not auto‐compute actuals, and then click on the Next button.  

   

11. Click on the Finish button to add the Project level resource and close the New Resource Wizard.  

  

     

Page 119: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page118 

2. Create  a  Resource  Category  Node  (If  Applicable): When  resource‐loading  is  required  by specifications, resource category nodes under which the  individual resources will be added should be  created  to  group  resources by  resource  type  (i.e. Cost,  Labor, Equipment,  and Material). Create a Resource category parent node for each resource category, following the steps for creating a Project level resource, as described above.  

   

3. Create Bid Item Resources: When cost‐loading a schedule, project‐specific bid item material resources must  be  defined  for  each  item  of work  as  shown  in  the  Contract  Schedule  of Items, as required by specifications. Cost resources can be created using the New Resource Wizard or by importing the VDOT Standard Bid Item Resources (XER) file. The following are guidelines for creating the individual bid item resources, using the New Resources Wizard:  

1. Select the Project level resource (or Cost category resource, as applicable) under which new  individual project‐specific bid  item resources will be added. And then click on the Add button to launch the New Resource Wizard.   

 

Page 120: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page119 

2. In the New Resource Wizard dialog box define the bid item Resource ID and Name, and then Click on Next. 

 

   

Define the contract bid item Resource ID and Name as follows:  1. Enter a unique Resource ID for the contract bid item using the Contract ID number 

as a prefix followed by a five‐digit VDOT  bid item number as shown in the Contract Schedule of Items (e.g. C00012345C01.00100, etc.). 

 

2. Enter the bid item description in the Resource Name field to define the bid item resource as shown in the Schedule of Items (e.g. Mobilization, etc.).   

3. Specify Material as  the Resource Type, and  then click on  the Unit of Measure browse button to select an appropriate unit of measure, and then click on Next.  

 

Page 121: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page120 

4. In the Units/Time & Prices dialog box, enter in the Price/Unit box, the unit price for the corresponding  bid  item  as  shown  on  the  Schedule  of  Items.  Define  the  Default Units/Time and Max Units/Time, and then click on Finish.   

   

5. Repeat Steps 1  through 4 above, as often as necessary  to add new bid  item material resources for the remaining bid items as shown in the Contract Schedule of Items.  

        

Page 122: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page121 

2. Creating  Cost  Resources  From  VDOT  Standard  Bid  Item  Resources  –  As  an  alternative  to creating  individual  cost  resources  using  the  New  Resource Wizard,  individual  cost  resources needed  for  cost‐loading  a  schedule  can  be  created  from  a  pool  of  VDOT  standard  bid  item resources by importing the VDOT Standard Bid Item Resources (XER) file as follows:   1. Download  a  Copy  of  VDOT  Standard  Bid  Item  Resources  (XER)  File:    The  following  are 

guidelines for downloading a copy of the VDOT standard bid item resources file:  

1. Click  on  the  link  below  or  use  the  web  address  to  access  the  VDOT  Construction Scheduling webpage to download a copy of the VDOT P6 Standard Bid  Item Resources (XER) file.   http://www.virginiadot.org/business/const/constrschresspecs.asp  

2. Locate and click on the VDOT P6 Standard Bid Item Resources link.  

   

3. Click on Save as button to save a copy of the VDOTSTDBIDITEMRES.zip file.  

  

Page 123: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page122 

4. Create  or  locate  a  folder  on  your  computer  in  which  to  save  the VDOTSTDBIDITEMRES.zip file, and then click on Save.  

   

5. Double‐click on the “VDOTSTDBIDITEMRES.zip” file to unzip the file.   

   

6. Select  the “VDOTSTDBIDITEMRES.xer”  file, and  then click on Extract all  files  to extract and save the file.  

 

Page 124: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page123 

7. Browse and select a folder in which to store the file, and then click on Extract to extract and save the file.  

   

2. Import VDOT Standard Bid  Item Resources: The  following are guidelines  for  importing  the VDOT Standard Bid Item Resources:  1. Click on File in the Menu bar and then Import to open the Import Wizard. (Note: Users 

must have import privileges to import projects or resources into a database).  

    

Page 125: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page124 

2. In the Import dialog box, specify Primavera PM/MM – (XER), and then click on Next.  

   

3. Specify Resource Only, and then click on Next.  

             

Page 126: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page125 

4. Click on the browse button to locate the “VDOTSTDBIDITEMRES.xer” file.  

   

5. Select the “VDOTSTDBIDITEMRES.xer” file, and then click on Open.  

           

Page 127: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page126 

6. Click on the Next button.  

   

7. Click on  the Add button  to add a new  Import Configuration  layout  for  importing new resources, if one does not exist. Rename the new layout Add New Resources.  

          

Page 128: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page127 

8. Select the Add New Resources import layout and click on Modify to view/edit its import options.  

   

9. Specify  Insert New  import action  for each Data Type  item to  insert new resource data when  the  same data  exists  in  the  import  file  and  database. And  then  click  on OK  to accept the import configuration and close the Modify Import Configuration dialog box.  

             

Page 129: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page128 

10. Select the Add New Resources import layout and double‐click on No in the Use column to set to Yes, and then click on Next.  

   

11. Click on the Finish button to begin importing.  

           

Page 130: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page129 

12. Click on the OK button when the resources are successfully imported.  

   

13. As  shown  below,  the Resource  ID’s  for  the VDOT  Standard Bid  Item Resources were defined using five‐digit VDOT standard bid item numbers, prefixed by a generic Contract ID  (e.g. C000xxxxxxxx.00100). The  resources are also nested under a generic Contract parent resource (C000xxxxxxxx).  

     

Page 131: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page130 

3. Select  and  Move  Applicable  Project  Bid  Item  Resources:  Applicable  bid  item  resources needed  for  cost‐loading  a  project  schedule  can  be  created  by  selecting  from  the  VDOT Standard  Bid  Item  Resources  pool  and moving  the  selected  resources  under  the  Project (parent) resource node using the Cut/Paste command as follows:  1. If  a  Project  (or  Cost  category,  as  applicable)  parent  resource  node  under  which 

applicable  bid  item  resources will  be  placed  does  not  exist,  create  a  Project  or  Cost category resource, as necessary using the New Resource Wizard, as described above.  

   

2. Select  from  the  VDOT  Standard  Bid  Item  Resources  pool,  applicable  resources  to  be moved,  then  click  on  the  Cut  button  in  the  Command  bar.  (Tip:  To  select multiple resources select the first resource, then press and hold the “Ctrl” and/or “Shift” keys, as appropriate, while selecting the remaining applicable resources).  

 

Page 132: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page131 

3. Select the Project level parent resource node under which the selected resources will be placed, and then click on the Paste button in the Command bar.  

   

4. Delete Unused VDOT  Standard  Bid  Item  Resources: After moving  the  bid  item  resources needed  for  the project,  the  remaining unused VDOT  standard bid  item  resources may be deleted from the database by selecting the VDOTSTDBIDITEMRES parent resource, and then clicking  on  the Del./Merge  button  in  the  Command  bar. Alternatively,  the  remaining  bid item  resources may  be  reserved  in  the  database  for  future  use.  In  which  case missing resources can be  replaced by  re‐importing  the VDOTSTDBIDITEMRES  resources  file.  (Note: When re‐importing the VDOTSTDBIDITEMRES resources to replace missing resources, use an “Update  Existing”  import  configuration  layout  instead  of  “Insert  New”  to  avoid  creating duplicate resources).  

 

Page 133: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page132 

5. Replace  Generic  Contract  ID’s:  The  generic  Contract  ID  (C000xxxxxxxx.00100)  used  in defining  the Resource  ID’s  for  the VDOT bid  item  resources  should be  replaced with  the project Contract ID to make the resources project‐specific, as required by specifications. The Replace function can be used to find/replace the Resource ID’s as follows:  1. Select  the  first project bid  item resource, then click on Edit  in the Menu bar and then 

Replace to open the Replace dialog box:  

   

2. In the Find what box, enter the generic Contract ID to be replaced (C000xxxxxxxx), then enter  in  the Replace with box,  the project Contract  ID  (e.g. C00012345C02), and  then click on  the Replace button or Replace All button  to  find/replace  the Contract  ID,  as defined. (Note: The Replace button will replace each item that meets the search criteria one‐at‐a‐time, and the Replace All button will replace all items in the Resource pool that meet the criteria all‐at‐once, including any unused VDOT standard bid item resources).  

 

Page 134: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page133 

3. After the generic Contract ID’s have been replaced with the project Contract ID, click on the Close button.  

   

6. Replace the Generic Resource Calendar: A generic 5‐day workweek resource calendar was assigned to the VDOT bid item resources. After importing and creating the project bid item resources, replace the generic resource calendar with a project‐specific resource calendar, as required by specification.   

   The generic resource calendar assigned to the bid item resources can be replaced as follows:  1. Select the first project‐specific bid item resource and double‐click on its Calendar cell in 

the Resource window or click on the Calendar browse button in the Details form of the 

Page 135: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page134 

Resource  Details,  then  select  a  project‐specific  resource  calendar  from  a  list  of previously defined resource calendars, and then click on the Select (+) button to assign the selected calendar to the selected bid item resource.  

   

2. Click on the Calendar cell of the Project  level resource or first project‐specific bid  item resource with the project‐specific resource calendar, then press and hold the “Shift” key on  your  keyboard,  then  scroll  down  and  select  the  Calendar  cell  of  the  last  project‐specific bid  item  resource;  and  then  right‐click,  then  click on  Fill Down.  (Note: When using  the  Fill Down  function; make  sure  to  stay within  the  column  of  the  data  being copied).   

 

Page 136: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page135 

3. Review to make sure that the generic calendar has been properly replaced by a project‐specific resource calendar for each resource.  

   

7. Define Price/Unit: After  creating  the project bid  item  resources, define  the Price/Unit  for each cost resource as follows:  1. Click on  the Units & Prices  tab  in  the Resource Details  to  specify a Price/Unit  for  the 

selected resource.  

     

Page 137: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page136 

2. Select and specify the Price/Unit for each project bid  item resource based on Contract Schedule of  Items.  (Note: For  lump sum  items that will be assigned to single activities, enter the unit price as shown on the Contract Schedule of Items. For lump sum items that will be assigned to multiple activities, enter $1.00 as the Price/Unit).  

                         

Page 138: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page137 

3. Assigning Cost Resources – After creating the bid item cost resources, the next primary step in cost‐loading a  schedule  is  to assign  the  cost  resources  to  their  respective activities. Assigning cost resources involves a process of assigning a cost resource to an activity and then specifying the budgeted units  to define  the magnitude of work and costs  that  the activity  represents. A single cost resource may be assigned to one or more activities at once or multiple cost resources may be assigned to a single activity, as appropriate and as follows:  1. Assigning a Cost Resource  to an Activity: The  following are guidelines  for assigning a cost 

resource to an activity.  1. In  the Activities window,  click on  the Resources  tab  in  the Activity Details  form,  then 

select an activity  to which a cost resource will be assigned, and  then click on  the Add Resource button.  

   

2. In the Assign Resources dialog box, change the Display Filter to All Resources, then select a cost resource, then click on the Assign (+) button to assign the selected resource to the selected activity, and then click on the Close (X) button.  

 

Page 139: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page138 

3. Click on  the Budgeted Units cell and adjust  the quantity, as necessary.  (Note: When a resource is assigned to an activity, Primavera P6 automatically assigns a Budgeted Units value based on the resource default units/time and the activity duration).  

   

2. Assigning a Cost Resource to Multiple Activities: The following are guidelines for assigning a single cost resource to multiple activities at once.  1. Select  activities  to which  the  cost  resource will  be  assigned  using  the  “Ctrl”  and/or 

“Shift” keys, as appropriate, then click on the Resources button in the Command bar.  

 

Page 140: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page139 

2. In the Assign Resources dialog box, change the Display Filter to All Resources, then select a cost resource, then click on the Assign (+) button to assign the selected resource to the selected activities, and then click on the Close (X) button.  

   

3. Click  on  the  Budgeted  Units  cell  and  adjust  the  quantity  for  each  cost  resource assignment, as necessary.  

     

Page 141: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page140 

3. Assigning Multiple Cost Resources to an Activity: The following are guidelines for assigning multiple cost resources to a single activity at once.  1. Select an activity to which the cost resources will be assigned, and then click on the Add 

Resource button.  

   

2. In the Assign Resources dialog box, change the Display Filter to All Resources, then select the applicable cost resources using the “Ctrl” and/or “Shift” keys on your keyboard, as appropriate; then click on the Assign (+) button to assign the selected resources to the selected activity, and then click on the Close (X) button.  

   

Page 142: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page141 

3. Click  on  the  Budgeted  Units  cell  and  adjust  the  quantity  for  each  cost  resource assignment, as necessary to define the magnitude of work that the activity represents.  

   

4. Reviewing  Cost  Resource  Assignments  –  After  assigning  cost  resources,  the  resource assignments  should be  reviewed  to ensure  that all project cost  resources have been assigned and  that all activities that require cost‐loading have been assigned proper cost resources. The following are guidelines for reviewing cost resource assignments:  1. Create an activity  layout  showing  the Budgeted Cost, Actual Cost, Remaining Cost, and At 

Completion Cost. Set the Filter to All Activities, then review to identify any activities without costs that require cost‐loading. If necessary, create and apply a filter to select activities with budgeted cost value equal to zero. Adjust as necessary.  

 

Page 143: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page142 

2. Click on  the Assignments button  in  the Directory bar  to display  the Resource Assignments window.  

   

3. Create  a  Resource  Assignment  layout  showing  the  Original  Duration,  Budgeted  Units, Budgeted Units/Time, and Max Units/Time for each assignment. Review to ensure that the activity  duration  and  budgeted  units  for  each  assignment  are  reasonable  relative  to  the units/time and max units/time. Adjust as necessary. (Note: Budgeted Units/Time is the daily production  rate  required  to  complete  the  activity  as  planned.  Max  Units/Time  is  the anticipated maximum production per day  that  the contractor can perform on  the activity. The Max Units/Time is defined when the cost resource is created).   

  

Page 144: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page143 

4. Create a Resource Assignment layout showing the Price/Unit, Budgeted Units, and Budgeted Cost, as reflected on the Contract Schedule of Items. Review against the Contract Schedule of  Items to ensure that the unit price, summarized budgeted units, and budgeted cost  for each pay item matches.   

   

5. Lastly,  review  to ensure  that  the Budgeted Cost, Remaining Cost, and At Completion Cost values  are  the  same,  that  the  Actual  Cost  values  are  zero  ($0.00),  and  that  the  Total Budgeted Cost for the project matches the total contract value for the baseline schedule.  

   

Page 145: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page144 

5. Defining and Assigning a 20‐80 Resource Curve (Design‐Build Only) – For Design‐Build projects, a 20‐80 resource curve  is required for cost resource assignments to allow for cost calculations for progress payments based on the 20‐80 Rule.   The following are guidelines for defining and assigning a 20‐80 resource curve in Primavera P6:  1. Creating a 20‐80 Resource Curve: The following are guidelines for creating a 20‐80 resource 

curve.  1. Click on Enterprise in the Menu bar, then Resource Curves. 

 

   

2. Click on the Add button.  

         

Page 146: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page145 

3. Select any available Resource Curve, then click on Select (+) button.  

  

 4. Click on the Modify button. 

 

   

5. Modify the Resource Curve to set the Curve Value % for the 0 Duration % to 20 and the 100% to 80, with every value in‐between set to 0, and then click on the OK button.  

 

Page 147: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page146 

6. Rename the New Resource Curve to be project‐specific (e.g. C00012345C01‐20/80), and then click on the Close button.  

   

2. Assigning  a  20‐80  Resource  Curve:  The  following  are  guidelines  for  assigning  a  20‐80 resource curve to the cost resource assignments:  1. Click  on  the  Assignments  button  in  the  Directory  bar  to  display  the  Resource 

Assignments window, and then modify the layout to add a Resource Curve column, and then  double‐click  on  the  Curve  cell  of  the  first  cost  resource  assignment.  (Note:  If necessary, modify the filter to display cost resources for the open project only).  

  

   

Page 148: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page147 

2. Select from the list of resource curves the project‐specific resource curve, and then click on the Select (+) button.  

   3. Click on the Curve cell of the first cost resource assignment, then scroll down to the last 

assignment, then press and hold down the “Shift” key on your keyboard, and then click on the Curve cell of the last resource assignment; and then right click, then click on the Fill Down function to copy the resource curve onto the rest of the assignments.  

    

Page 149: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page148 

4. Review  to ensure  that all  resource assignments have been assigned a 20‐80  resource curve.  

   

6. Defining  Financial  Periods  –  In  Primavera  P6,  activity  or  resource  assignment  data  can  be summarized and stored by week, month, quarter, year, or by financial periods. Financial periods allow  for  summarization,  storage,  and  reporting  of  activity  and  resource  assignment  data  by periodic intervals other than the standard weekly, monthly, quarterly or yearly calendar periods. For Design‐Build and Cat IV and V projects that require cost‐loading, contractors are required by specifications  to  submit  as  part  of  the  Baseline  Progress  Schedule  submission,  a  Progress Earnings  Schedule  using  the  VDOT  Form  C‐13CPM.  The  time‐distributed  monthly  cost  data needed to complete the C‐13CPM form for Cat  IV and V projects must be generated from the cost‐loaded schedule by financial periods based on the contractor’s monthly progress estimate date  (date on which progress estimates are prepared). Financial periods are not  required  for Design‐Build projects since payments are made based on standard monthly calendar periods.  The monthly progress  estimate  periods  for VDOT Design‐Bid‐Build  projects  are based on  the contractor’s name, according to Section 109.08 of the Specifications.   

For projects whose contractor names begin with  the  letters A  through F,  the monthly progress estimates will be prepared on the 4th of each month.  

For projects whose contractor names begin with  the  letters G  through P,  the monthly progress estimates will be prepared on the 11th of each month. 

 

For projects whose contractor names begin with  the  letters Q  through Z,  the monthly progress estimates will be prepared on the 20th of each month.  

 

Page 150: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page149 

To generate the time‐distributed monthly cost data needed to complete the C‐13CPM form, a set of  financial periods must be defined based on  the contractor’s monthly progress estimate date. The following are guidelines for defining financial periods:  1. Click on Admin  in  the Menu bar, and then click on Financial Periods to open  the Financial 

Periods dialog box. (Note: You must have the Edit Financial Period Dates global privilege to add, edit, or delete financial periods in the Financial Period dictionary).   

   

2. In  the  Financial  Periods  dialog  box,  click  on  the Add  button  to  open  the  Select  Financial Period  Timescale dialog box  in which  to  specify  the  start  and  end dates  for  each period. (Note: When the Financial Period dialog box opens, the default start date is the day after the previous period's end date; or the current date, if there are no previously defined periods).  

  

Page 151: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page150 

3. Click  on  the  browse  button  of  the  Start  Date  field  and  select  a  start  date  for  the  first estimate period, then click on the Select button. The Start Date of each period  is the data date  (contractor’s  estimate  date:  4th,  11th,  or  20th,  as  appropriate), which  defines  the beginning of the progress period. (Note: The start date for the first estimate period should be the contractor’s estimate date preceding the earliest start date of the project or projects in the database that are cost‐loaded).  

   

4. Click on the browse button of the End Date box and select an end date for the period, and then click on  the Select button. The End Date  for each period defines  the cut‐off date  for work performed during the progress period, which should be the day before the estimate is prepared: 3rd, 10th, or 19th, as appropriate.  

 

Page 152: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page151 

5. Click on  the Add button  in  the  Select  Financial Period Timescale dialog box  to  create  the financial period.  

   

6. Note  that  the  Select  Financial  Period  Timescale  dialog  box  remains  open  for  the  next financial period. However, the start date is automatically reset to the following day after the end date of the previous financial period.   

      

Page 153: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page152 

7. Repeat Steps 4 and 5 as  shown above, as often as necessary  to define  the End Date and create  the  next  financial  period. Once  all  required  financial  periods  are  defined,  click  on close button to close the Select Financial Period Timescale dialog box. (Note: The Start Date or End Date fields cannot be edited after a period is created. If there is an error in the start date or end date of a period, you must delete the period and re‐create it to correct the error).  

   

8. As  shown below, note  that  the  financial period was  created with  a default Period Name (2014‐01‐04), which is based on the period start date. However, monthly progress estimates are  typically  referred  to  in  terms of  the date  the estimate  is prepared  for work performed during the preceding work cycle rather than the start date of the progress period. Therefore, the period names should be modified accordingly to ensure that the Period Name reflects the date  the  estimate  is prepared  rather  than  the  start date of  the progress period.  For example,  the  financial period  for  the February 4th, 2014 progress estimate should have a Period Name: 2014‐02‐04, with Start Date: 01‐04‐14, and End Date: 02‐03‐14 representing work performed during the preceding month, as shown in Step 10 below.  

 

Page 154: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page153 

9. To edit  the period names  to  reflect  the dates  the estimates are prepared  rather  than  the start date of  the progress period, select the Period Name of the  last period, then edit  the period name by advancing it one month (e.g., rename 2015‐09‐04 to 2015‐10‐04), as shown below.   

   

10. Repeat Step 9 above, working from the bottom to the top until all period names have been modified, as necessary. Review to ensure that the period names are appropriate, have not skipped any period, and  that  the periods are  listed  chronologically  in order of  start date.  And then click on the Close button.  

   

Page 155: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page154 

7. Reviewing Monthly Budgeted Units and Cost Data – Review the monthly budgeted units and cost data to determine  if the amount of work planned each progress period  is reasonable or  if adjustments  to  the  schedule  are  necessary.  The  following  are  guidelines  for  reviewing  the monthly budgeted units and cost data in Primavera P6:  1. Review Monthly Budget Units Data: The following are guidelines for reviewing the monthly 

budgeted units:  1. In  the Resource Assignments window,  click on View  in  the Menu bar,  then Resource 

Usage Spreadsheet to display resource usage in a spreadsheet view.  

   

2. Right‐click  in  the  spreadsheet  area  of  the  Resource  Assignments window  or  click  on Display, then click on Spreadsheet Fields, and then click on Budgeted Units to display for each cost resource assignment the budgeted units for each progress period.  

 

Page 156: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page155 

3. Right‐click  in  the  spreadsheet  area  of  the  Resource  Assignments window  or  click  on Display,  then  click  on  Timescale  to  open  the  Timescale  dialog  box  to  set  the  Date Interval used in displaying the periodic data.  

   

4. In the Timescale dialog box, click on the drop down arrow to define a Date Interval by which the periodic data will be displayed.  Select Year/Month to display data by calendar month. Select Month/Week to display data by week. Select Week/Day to display data by day. Select Year/Financial Period to display data by financial periods (estimate periods).   

   

Page 157: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page156 

5. Review  the  total budgeted units of each cost  resource  to determine  if  the amount of work planned for each period is reasonable. Adjust the schedule, as necessary.  

  

 2. Review Monthly Budget Cost Data  (Cash Flow): The  following are guidelines  for  reviewing 

the monthly budgeted cost (monthly earnings):  1. Right‐click  in  the  spreadsheet  area  of  the  Resource  Assignments window  or  click  on 

Display,  then  click  on  Spreadsheet  Fields,  then  click  on  Customize  to  open  the  Fields dialog box.  

   

Page 158: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page157 

2. In  the Fields dialog box, click on Time  Interval,  then Costs,  then select Budgeted Cost, and then click on the right arrow to move the Budgeted Cost from the Available Options area  to  the Selected Options area. Return other  items  in  the Selected Options area by selecting  them  and  clicking  on  the  left  arrow  button.  Then  click  on OK  to  apply  the selected options and close the dialog box.    

  

3. Review the monthly total budgeted cost for each bid  item resource and the project to determine  if  the  amount  of  work  planned  each  period  is  reasonable.  Adjust  the schedule, as necessary.  

        

Page 159: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page158 

6. RESOURCE‐LOADING A SCHEDULE  

Resource‐loading  is a process of assigning resources  to an activity  for  the purpose of defining  the manpower, equipment, or materials required to complete an activity. Resource‐loading establishes inter‐dependencies  between  activities  and  project  resources, which  allows  for  identification  and correction of potential  resource conflicts or over allocation  resulting  in  reduction of project  risks. Resource  loading  also  allows  for  a more  realistic  resource‐driven  schedule by balancing  available resources with project needs resulting in optimal use of project resources to improve profitability.   Resource‐loading  is required for Category V projects or Design‐Build projects with contract amount exceeding  $35M.  However,  contractors  may  resource‐load  schedules  for  other  projects  at  their discretion, but should do so according to the guidelines provided herein. In Primavera P6, resource‐loading  involves  two  primary  steps:  creating  a  pool  of  resources  and  assigning  the  resources  to activities.  The  following  are  guidelines  for  resource‐loading  a  schedule  to  comply with  the VDOT scheduling specifications:   1. Defining  Resources  for  Resource‐loading  –  Prior  to  assigning  resources  to  activities  for  the 

purpose of resource‐loading a schedule, a pool of project resources from which to select must first  be  defined.  The  following  are  guidelines  for  defining  labor,  non‐labor,  and  material resources in Primavera P6:  1. Create a Resource Category: Create a resource category for each type of resource (i.e. Cost, 

Labor, Equipment, and Material) under which the individual resources will be added:   

1. Select the Project level resource node under which new resource category resources will be added, and then click on the Add button to launch the New Resource Wizard.   

    

Page 160: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page159 

2. In the New Resource Wizard dialog box define the Resource ID and Name.   

  Define the project Resource ID and Name as follows: 

 

1. Enter a unique Resource  ID  for  the  resource  category node using  the Contract  ID number  as  a  prefix  followed  by  a  code  or  short  name  (e.g.  C00012345C01.Cost, C00012345C02.Lab, C00012345C01.Equip, or C00012345C01.Mat). 

 

2. Enter the project name/description in the Resource Name field to define the resource category. 

 

3. Click on the Next button.    

3. Specify the resource type (Labor, Nonlabor, or Material) as appropriate, and then click on the Next button.  

 

Page 161: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page160 

4. Enter zero (0) values for the Price/Unit, Default Units/Time, and Max Units/Time for the resource category node, and then click on the Next button.  

   

5. Click on the Next button.  

         

Page 162: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page161 

6. Specify Select an existing calendar, and then click on the Next button to open the Select Existing Calendar dialog box with which to select a resource calendar.  

   

7. In the Select Existing Calendar dialog box, click on  the Browse button  to select  from a predefined  pool  of  global  or  resource  calendars.  (Note:  To  view  or  edit  the  selected calendar, click on the View/Edit button). Click on the Next button.   

       

Page 163: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page162 

8. In the Auto‐Compute Actuals dialog box, specify Do not auto‐compute actuals, and then click on the Next button.  

   

9. Click  on  the  Finish  button  to  add  the  resource  category  node  and  to  close  the New Resource Wizard.  

        

Page 164: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page163 

10. Repeat  Steps  1  through  9  to  create  a  resource  category  node  for  each  applicable resource category (Cost, Labor, Equipment, or Material), as necessary.  

   

2. Create  Labor  Resources:  For  labor  resources  required  for  resource‐loading  a  schedule, create the individual project labor resources as follows:  

 1. Select  the  Labor  category  resource  node  under  which  new  labor  resources  will  be 

added. And then click on the Add button to launch the New Resource Wizard.   

     

Page 165: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page164 

2. In the New Resource Wizard dialog box define the labor Resource ID (using the Contract ID as a prefix followed by a unique short name or code), then enter the Resource Name (resource description), and then Click on Next.   

   

3. Specify Labor as the Resource Type and then click on Next.   

         

Page 166: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page165 

4. In the Units/Time & Prices dialog box, enter zero dollars ($0.00) for the Price/Unit, then define the Default Units/Time and Max Units/Time, and then click on Finish. (Note: The remaining necessary resource properties can be defined using the Resource Details form as described earlier in this guide).   

   

5. Repeat Steps 1 through 4 above, as often as necessary to add the remaining labor (crew) resources  required  to accomplish  the major operations  that are expected  to drive  the schedule.   

 

Page 167: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page166 

3. Create  Equipment  Resources:  For  the  major  equipment  resources  required  for accomplishing the work, create individual project‐specific non‐labor resources as follows:  

 

1. Select  the  Equipment  category  resource  under which  new  project‐specific  non‐labor (equipment)  resources will be added. And  then click on  the Add button  to  launch  the New Resource Wizard.   

   

2. In the New Resource Wizard dialog box define  the equipment Resource  ID and Name, and then Click on Next.   

     

Page 168: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page167 

3. Specify Nonlabor as the Resource Type and then click on Next.   

   

4. In the Units/Time & Prices dialog box, enter zero dollars ($0.00) for the Price/Unit, then define the Default Units/Time and Max Units/Time, and then click on Finish. (Note: The remaining necessary resource properties can be defined using the Resource Details form as described later in this guide).   

       

Page 169: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page168 

5. Repeat  Steps  1  through  4  above,  as  often  as  necessary  to  add  the  remaining major equipment resources required to accomplish the major operations that are expected to drive the schedule.   

   

4. Create  Material  Resources:  For  the  major  re‐usable  material  resources  required  for accomplishing the work, create individual project‐specific material resources as follows:  

 

1. Select  the  Material  category  resource  under  which  new  project‐specific  material resources will be added. And then click on the Add button to launch the New Resource Wizard.   

 

Page 170: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page169 

2. In the New Resource Wizard dialog box define the material Resource ID and Name, and then Click on Next.   

   

3. Specify Material  as  the Resource  Type,  then  click on  the  browse button  to  select  an appropriate Unit of Measure, and then click on Next.   

        

Page 171: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page170 

4. In the Units/Time & Prices dialog box, enter zero dollars ($0.00) for the Price/Unit, then define the Default Units/Time and Max Units/Time, and then click on Finish. (Note: The remaining necessary resource properties can be defined using the Resource Details form as described later in this guide).   

   

5. Repeat Steps 1  through 4 above, as often as necessary  to add  the  remaining material resources  required  to accomplish  the major operations  that are expected  to drive  the schedule.   

   

Page 172: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page171 

SECTION V  MAINTAINING A SCHEDULE IN PRIMAVERA P6                 

1. Overview  2.   3.   4.   5.   

   

 

 

 

 

Page 173: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page172 

SECTION 

V   

 

1. OVERVIEW                             

Page 174: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page173 

SECTION VI  REPORTING IN PRIMAVERA P6                 

1. Overview  2.   3.   4.   5.   

   

 

 

 

 

Page 175: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page174 

SECTION 

VI   

 

1. OVERVIEW                             

Page 176: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page175 

SECTION VII  MANAGING CONTRACTOR SCHEDULES IN PRIMAVERA P6                 

1. Overview  2.   3.   4.   5.   

   

 

 

 

 

Page 177: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page176 

SECTION 

VII   

 

1. OVERVIEW   

  1. TBD – To be developed: 

 1. TBD. 

   

                  

       

Page 178: VDOT Primavera P6 Scheduling Guide

Virginia Department of Transportation Construction Division 

 

VDOTPrimaveraP6SchedulingGuide(12‐22‐15:UnderConstruction) Page177 

                

For questions, issues, or assistance on assessing or using  the VDOT scheduling application, please contact: 

Frank Gbinije Email: [email protected] 

Phone: (804) 786‐2980