Value-for-money in practice

38
Value-for-money in practice 6 June 2008 EU Twinning Project: “Implementing PPP policy”

description

Value-for-money in practice. EU Twinning Project: “Implementing PPP policy”. 6 June 2008. Content. On Value-for-Money in practice: Real-life examples Its sources Its drivers Its management The affordability-dilemma The do’s and don’ts. Morning session. Afternoon session. - PowerPoint PPT Presentation

Transcript of Value-for-money in practice

Page 1: Value-for-money in practice

Value-for-money in practice

6 June 2008

EU Twinning Project: “Implementing PPP policy”

Page 2: Value-for-money in practice

Content

On Value-for-Money in practice:

1. Real-life examples

2. Its sources

3. Its drivers

4. Its management

5. The affordability-dilemma

6. The do’s and don’ts

Morning session

Afternoon session

Page 3: Value-for-money in practice

Real-life examples

Page 4: Value-for-money in practice

N31 Motorway Project

• A 25 km provincial road

• Upgrading to a two-lane motorway

• Road infrastructure, bridge and aqueduct.

• DBFM-contract

• Contract value: € 80 million

• Contract duration: 15 years

Page 5: Value-for-money in practice

N31 PPP Motorway Project

Value-for-money 21%

Value-for-money 21%

Cost savings from different material use

Cost savings from different material use

25% less lane closures

25% less lane closures

11 months shorter

construction

11 months shorter

construction

Page 6: Value-for-money in practice

A’dam – Brussels High Speed Rail Link

• A 125 km high-speed rail line

• Greenfield + Upgrading existing rail

• Infrastructure and superstructure.

• 2 DBFM-contracts / 1 O-contract

• Contracts value: € 7 billion

• Contract duration: 15 – 25 years

Page 7: Value-for-money in practice

A’dam – Brussels High Speed Rail Link

Value-for-money 2%

Value-for-money 2%

Non-application of unproven technologies

Non-application of unproven technologies

Greater availability

Greater availability

Embedded-rail Embedded-rail

Page 8: Value-for-money in practice

Renovation Finance Ministry

• Accommodation of Finance Ministry

• Renovation

• 1 DBFMO-contract

• Contracts value: € 175 million

• Contract duration: 25 years

Page 9: Value-for-money in practice

Renovation Finance Ministry

Value-for-money 15%

Value-for-money 15%

Energy efficiencyEnergy efficiencyImproved logistics

Improved logistics

Page 10: Value-for-money in practice

Montaigne School Building

• School building

• Greenfield

• DBFM-contract

• Contracts value: € 27 million

• Contract duration: 30 years

Page 11: Value-for-money in practice

Montaigne School Building

Value-for-money (Quality)

Value-for-money (Quality)

Multi-purpose rooms

Multi-purpose rooms

Large “learning spaces”

Large “learning spaces”

Page 12: Value-for-money in practice

Delfuent Water Sanitation Plant

• Water sanitation plant

• Greenfield & modernization

• DBFMO-contract

• Contracts value: € 450 million

• Contract duration: 30 years

Page 13: Value-for-money in practice

Delfuent Water Sanitation Plant

Value-for-money 17%

Value-for-money 17%

Lower exploitation

costs

Lower exploitation

costs

Process innovations

Process innovations

Shorter construction

Shorter construction

Page 14: Value-for-money in practice

Real estate development

• Port and accommodation

• Greenfield, expansion & renovation

• Multiple DBFM-contracts

Value-for-moneyValue-for-money

FlexibilityFlexibility

Phased-implementation

Phased-implementation

Alternative usage

Alternative usage

Page 15: Value-for-money in practice

The sources of value-creation

Page 16: Value-for-money in practice

The main principles

QualityQuality

Page 17: Value-for-money in practice

The Value-tree

Timing Cost-savingRevenue-generation

FlexibilityQuality-

improvement

Value-for-money

Life-cycle costing

InnovationsExploiting

commercial value

Off-balance financing

Technical know-how

Business process

skills

Commercial expertise

Incentive structure

Risk allocation

Output specifications

Payment mechanism

CompetitionProject scoping

Page 18: Value-for-money in practice

Key Value-drivers: N31 Motorway Project

Page 19: Value-for-money in practice

Output specifications

Functional output specifications on safety and comfort standards

By Ministry of Transport

Conditions tree

Technical specifications By private

partner

Page 20: Value-for-money in practice

Responsibility matrix

L and ac quis ition

Infras truc ture

S upers truc ture

B ridg e

Aqueduct

T raffic and s afety manag ement

G overnmentP rivate consortium

Infraprovider

Manag eDes ig n B uild Maintain F inanc e

Page 21: Value-for-money in practice

Risk allocation

Government Private consortium

Design K

Construction Risk K

Maintenance risk (infrastructure) K

Interface Risk K

Budget Risk K

Political risk (including amendments to laws) K

Act-of-god / force majeure K

Page 22: Value-for-money in practice

Incentive structureQ

ual

ita

tiv

e

Procurement Contract implementation

€ Financial selection criteria

Minimum requirements

Market testing

Payment mechanism

Output specifications

Page 23: Value-for-money in practice

Payment mechanism

Payment Timing Basis & reason

One-off or milestone payment

On construction completion • To ensure timely availability• To lower budget risk for financiers and thus lower financing costs• the amount is predetermined during tender

Compensation for delay in availability

Subsequent to scheduled availability

• To prevent construction / availability delays • Daily penalty (with a maximum total)• the amount is predetermined during tender

Bonus for early completion and availability

Prior to scheduled availability • To stimulate early availability• Daily amount

Availability payments During the “operational” phase • Performance-based payments• To promote maximum availability, quality service delivery, and compliance with safety standards.• See next sheet for further details

Page 24: Value-for-money in practice

Payment mechanism – N31 / trends

Gross availability payments • Monthly performance-based payment • Level determined at contract close• Fixed indexation formula

Availability deductions • Deductions in case of (partial) lane closures or temporary speed limits • Level of deductions depends on traffic volumes and duration (see upcoming sheet)

Penalties • Predetermined (during tender stage) penalty regime• Concerns safety and planning issues (see upcoming sheet)

Nett availability payments • Equals Gross availability payments - / - Availability deductions - / - Penalties

Page 25: Value-for-money in practice

Payment mechanism

Traffic volumes (number of vehicles)

Availability value (EUR/hour)

Lane closure Temporary speed limit

Partial lane closure

0 – 1.000 1.000 250 250

1.000 – 1.500 1.500 375 375

1.500 – 2.000 2.000 500 500

2.000 – 2.500 4.000 1.000 1.000

2.500 – 3.000 8.000 2.000 2.000

> 3.000 or with a traffic jam 15.000 2.000 2.000

Page 26: Value-for-money in practice

Payment mechanism

Safety

1. A traffic accident has occurred with one or more casualties due to a shortcoming of the private consortium

10

2. A traffic accident has occurred without casualties due to a shortcoming of the private consortium

6

3. A shortcoming of the private consortium has put users at risk 4

4. A shortcoming of the private consortium has put third-parties, construction or maintenance workers, or emergency service personel at risk

3

Process management

5. A shortcoming of the private consortium with respect to contract clause 10.11 (Managementsystem)

3

6. A contract deviation not caused by a shortcoming of the contracting enity or a supervening event

1

7. A contract deviation or shortcoming by the private consortium is not reported timely to the contracting authority

4

8. Failure to timely rectify the shortcoming (as laid down in the contract). 4

Page 27: Value-for-money in practice

Competition

Stages

Key Decision-making points

FinalEvaluation

Phase

Selection Phase

Dialogue Phase 1

DialoguePhase 2

FinalNegotiation

phase

Announcement Invitation for Dialogue Ph. 1 (Incl. Selection)

Invitation for Dialogue Ph. 2 (Incl. Shortlist of three firms)

Invitation for Submission

BAFO

Selection of preferred

bidder

Contract close / financial

close

Preperation for Realisation

Realisation Phase

Oplevering

Operation Phase

Aanvangs-certificaat

DialoguePhase 3

Invitation for Dialogue Ph. 3

(optional)

Certificate of Completion

Certificate of Commence-

ment

Competitive dialogue procedureCompetitive dialogue procedure

Page 28: Value-for-money in practice

Value-for-money management

Page 29: Value-for-money in practice

Process, instruments and time

PPP potential scan

Business case

ProcurementRequest for

proposals

Conventional implementation

PPP implementationTime

6 months 6 months

Dynamic PPC

QualitativeQualitative QuantitativeQuantitative

Page 30: Value-for-money in practice

Organization

Management

Management support

Technical team Financial team Legal team

Negotiation team

Communication

• Finance (project/ corp./ public)

• Financial modeling

• Investment & valuation

• Risk analysis

• Market supply and demand

• Civil engineering

• Technical evaluations

• Innovative contracting

• Market supply and demand

• Procurement and contract law

• Contract management

• Public finance and tax policy

• Innovative contracting

Project organization

Management

Management support

Technical team Financial team Legal team

Negotiation team

Communication

• Finance (project/ corp./ public)

• Financial modeling

• Investment & valuation

• Risk analysis

• Market supply and demand

• Civil engineering

• Technical evaluations

• Innovative contracting

• Market supply and demand

• Procurement and contract law

• Contract management

• Public finance and tax policy

• Innovative contracting

Management

Management support

Technical team Financial team Legal team

Negotiation team

Communication

• Finance (project/ corp./ public)

• Financial modeling

• Investment & valuation

• Risk analysis

• Market supply and demand

• Civil engineering

• Technical evaluations

• Innovative contracting

• Market supply and demand

• Procurement and contract law

• Contract management

• Public finance and tax policy

• Innovative contracting

Project organization

PPP Unit

Treasury

Market

Page 31: Value-for-money in practice

Contract management

Private consortium

Project organization

Quality management

planShow performance

and contract compliance

Process management / supervision

Contract

management plan

Ministry of Transport

Project organization

Civil works

Maintenance activities

Quality supervision

Page 32: Value-for-money in practice

Contract management

process product

Quality Management

Plan

Process control Product control

Verify processVerify product

quality

Check process directly

Check product directly

Private consortium

Ministry of Transport

Contract management

plan

Main focus’

On an exceptional basis

Page 33: Value-for-money in practice

The affordability-dilemma

Page 34: Value-for-money in practice

Conflicting objectives

Value-for-money

Optimal risk transfer

Affordability

Risk transfer to private sectorRisk transfer to private sector

Page 35: Value-for-money in practice

The do’s and don’ts

Page 36: Value-for-money in practice

The do’s and don’ts

1. Do allow for task-integration by private sector partner

2. Do parallelize the interests of public and private partners

3. Do ensure competitive tendering

4. Do promote cooperation and partnership

5. Do make use of international - both UK and continental - experiences

6. Do not create, but enable value-creation

7. Do not transfer all risks to private sector or keep everything yourself

8. Do not increase project scope indefinitely (do create appetite)

9. Do not create extensive tender procedures causing high transaction costs

10. Do not tender unfeasible projects

Page 37: Value-for-money in practice

Risk transfer

Traditional model

Early DBFM-contracts

New PPP deals. .

Government Private sector

Page 38: Value-for-money in practice

Contact information

Rebelgroup Advisory BVGeert Engelsman

Wijnhaven 3-O, 3011 WG Rotterdam, The Netherlands Tel +31 10 2755995 Fax +31 10 2755999

www.rebelgroup.nl

[email protected]