Transcript of V1 1 United in Purpose : Canada’s Operational Command Colonel Chuck Mathé J4 UNCLASSIFIED.
v11
United in PurposeUnited in Purpose: :
Canada’s Operational CommandCanada’s Operational Command
Colonel Chuck MathéColonel Chuck MathéJ4J4
UNCLASSIFIED
v12
Overview
• Op Renaissance
• Video
• Questions
v13
Operation RENAISSANCE
v14
CC177AN124
747CC177AN124
ACSAUS sust flts(C17 / 747)
In Flow – Strategic LOC
30-40 hours one-way
v15
Movement – Intra-theatre LOC
DART Con O ($400k)JTFSC Elm
World Fuel Contract
JOA
Air-bridge (TBC)Mil or Con
CC130CC177
IL76
CC177AN124
IL76
RoadPhil Army 100kms
v16
JOA
MSR
Movement – Tac level (integral DART/Phil Army/Contract)
v17
DART – Major Equipment
2 x LSVW Amb
13 x LSVW Cargo
REMAIN IN TRENTON IN THEATRE
1 X LSVW CP1 X LSVW CP
LSVW MRT
2 X MLVW HIAB
2 X MLVW Cargo
2 x MPEV
4 x Skidsteer
5 x Crew Cab
2 x RTFL3 x POLARIS
3 x HESV PLS
3 x ROWPU
BAGGER
2 x BAGGER
3 x CH-146
MECC
1 X MECC 1 x ROWPU
ROWPU
1 X Dump Box
MEDICAL
5 x TRICAN
HLVW Bowser (AVN)5 x POLARIS
1 x TRICAN
MEDICAL
1 X HESV w Dump Box
1 X MLVW Cargo
v18
Deployment Assets
X 9: 787K lbs / 167 pax
X 2: 10K lbs / 134 pax
X 5: 176K lbs
X 1: 8 pax
First Depl Flight: 11 Nov 13
Last Depl Flight: 27 Nov 13
Last Sust Flight: 1 Dec 13
v19
Sustainment• 7 DOS IMP (each member)• 14 DOS bottled water (each member)• 10 DOS IMP (pre-position for Task Force)• Contracted
– Fuel– Water– Materiel Handling Equipment– Ground Transportation– Fresh rations– G&T
v110
Redeployment Timeline
15 Dec 19 Dec
DART Complete in
Iloilo
Mission Closure Team Remains for Ship Loading
as Required
Liner Service
75 Day transit (door to door)
Jan 14 Mar 14
TBC
Consolidation in Iloilo
MCT Redeploy
CAL
All Equip in Trenton
Clean, Pack, Load (Pri sensitive equip)
Reconstitution
14 Dec
Slip Crews
Departs Trenton
4 x C-17 Chalks for PAX & Critical Eqpt
18 – 23 Dec
Chalk 3
24 pax /
3 x CH 146
22 Dec18 Dec
Chalk 1
119 Pax / Freight
Chalk 2
118 Pax / Freight
23 Dec
Chalk 4
35 Pax /
Freight
13 Dec
MovCon Det
Departs
Cease
Ops
25 Dec
v111
Redeployment Assets
X 4: 296 pax 3 x CH-146 8 ACCS
First Redepl Flight: 18 Dec 13
Last Redepl Flight: 23 Dec 13
Liner Service Contract
v112
Lessons Observed
• Expectation management - LOCs
• DART “capabilities” were not modularized
• Nightly logistics tele-conferences were key
• Contracted airlift minimized depl timeline
• Pre-posn of sups reduced no of sust flts
• Lean forward was key to redepl success
v113