User Organisation OpenHydro - MaRINET2...Lir National Ocean Test Facilities. MaRINET2 is a €10.5...

14
User Organisation OpenHydro Status: Final Version: XX Date: 24/Jan/2018 Infrastructure Access Reports User Project Validation of Environmental Loading on an Open Centre Tidal Energy Converter Project Acronym VELOCeTEC Click or tap here to enter text. Project Reference Number 1272 Infrastructure Accessed Ifremer-Basin of Boulogne sur Mer

Transcript of User Organisation OpenHydro - MaRINET2...Lir National Ocean Test Facilities. MaRINET2 is a €10.5...

Page 1: User Organisation OpenHydro - MaRINET2...Lir National Ocean Test Facilities. MaRINET2 is a €10.5 million project which includes 39 organisations representing some of the top offshore

User Organisation OpenHydro

Status: Final

Version: XX

Date: 24/Jan/2018 Infr

astr

uct

ure

Acc

ess

Rep

ort

s

User Project Validation of Environmental Loading on an

Open Centre Tidal Energy Converter

Project Acronym VELOCeTECClick or tap here to enter text.

Project Reference Number 1272

Infrastructure Accessed Ifremer-Basin of Boulogne sur

Mer

Page 2: User Organisation OpenHydro - MaRINET2...Lir National Ocean Test Facilities. MaRINET2 is a €10.5 million project which includes 39 organisations representing some of the top offshore

ABOUT MARINET

The MaRINET2 project is the second iteration of the successful EU funded MaRINET Infrastructures Network, both

of which are coordinated and managed by Irish research centre MaREI in University College Cork and avail of the

Lir National Ocean Test Facilities.

MaRINET2 is a €10.5 million project which includes 39 organisations representing some of the top offshore

renewable energy testing facilities in Europe and globally. The project depends on strong international ties across

Europe and draws on the expertise and participation of 13 countries. Over 80 experts from these distinguished

centres across Europe will be descending on Dublin for the launch and kick-off meeting on the 2nd of February.

The original MaRINET project has been described as a “model of success that demonstrates what the EU can

achieve in terms of collaboration and sharing knowledge transnationally”. Máire Geoghegan-Quinn, European

Commissioner for Research, Innovation and Science, November 2013

MARINET2 expands on the success of its predecessor with an even greater number and variety of testing facilities

across offshore wind, wave, tidal current, electrical and environmental/cross-cutting sectors. The project not only

aims to provide greater access to testing infrastructures across Europe, but also is driven to improve the quality

of testing internationally through standardisation of testing and staff exchange programmes.

The MaRINET2 project will run in parallel to the MaREI, UCC coordinated EU marinerg-i project which aims to

develop a business plan to put this international network of infrastructures on the European Strategy Forum for

Research Infrastructures (ESFRI) roadmap.

The project will include at least 5 trans-national access calls where applicants can submit proposals for testing in

the online portal. Details of and links to the call submission system are available on the project website

www.marinet2.eu

This project has received funding from the European Union’s Horizon 2020 research and innovation programme under grant

agreement number 731084.

Page 3: User Organisation OpenHydro - MaRINET2...Lir National Ocean Test Facilities. MaRINET2 is a €10.5 million project which includes 39 organisations representing some of the top offshore

Document Details

Grant Agreement Number 731084

Project Acronym MaRINET2

Title Validation of Environmental Loading on an Open Centre Tidal Energy Converter

Distribution Public

Document Reference MARINET-TA1-Project Acronym – Project Number

User Group Leader,

Lead Author

Darragh Clabby OpenHydro [email protected]

User Group Members, Contributing Authors

Darragh Clabby OpenHydro Alexandre Rio Openhydro

Infrastructure Accessed Ifremer-Basin of Boulogne sur Mer

Infrastructure Manager or Main Contact

Gregory Germain

Document Approval Record

Name Date

Prepared by Darragh Clabby 24/01/2018

Checked by

Checked by

Approved by

Document Changes Record

Revision Number

Date Sections Changed Reason for Change

Disclaimer The content of this publication reflects the views of the Authors and not necessarily those of the European Union.

No warranty of any kind is made in regard to this material.

Table of Contents Table of Contents ..................................................................................................................................... 3

1 Introduction & Background ................................................................................................................. 5

1.1 Introduction ............................................................................................................................... 5

1.2 Development So Far .................................................................................................................... 5

1.2.1 Stage Gate Progress ............................................................................................................. 5

1.2.2 Plan For This Access ............................................................................................................. 6

2 Outline of Work Carried Out ................................................................................................................ 7

Page 4: User Organisation OpenHydro - MaRINET2...Lir National Ocean Test Facilities. MaRINET2 is a €10.5 million project which includes 39 organisations representing some of the top offshore

2.1 Setup ......................................................................................................................................... 7

2.2 Tests ......................................................................................................................................... 7

2.2.1 Test Plan ................................................................................ Error! Bookmark not defined.

2.3 Results ....................................................................................................................................... 7

2.4 Analysis & Conclusions ................................................................................................................ 8

3 Main Learning Outcomes .................................................................................................................... 8

3.1 Progress Made ............................................................................................................................ 8

3.1.1 Progress Made: For This User-Group or Technology ................................................................. 9

3.1.2 Progress Made: For Marine Renewable Energy Industry ........................................................... 9

3.2 Key Lessons Learned ................................................................................................................... 9

4 Further Information ........................................................................................................................... 9

4.1 Scientific Publications .................................................................................................................. 9

4.2 Website & Social Media................................................................................................................ 9

5 references ....................................................................................................................................... 10

6 Appendices ..................................................................................................................................... 10

6.1 Stage Development Summary Table............................................................................................ 10

6.2 Any Other Appendices ................................................................................................................. 0

Page 5: User Organisation OpenHydro - MaRINET2...Lir National Ocean Test Facilities. MaRINET2 is a €10.5 million project which includes 39 organisations representing some of the top offshore

1 Introduction & Background

1.1 Introduction

OpenHydro, a Naval Energies company, specialises in the design, manufacture, installation and maintenance of

marine turbines generating renewable energy from tidal streams. OpenHydro’s Open Centre Turbine (OCT)

technology is currently being demonstrated in pre-commercial arrays in preparation for transition to industrial

development. OpenHydro are currently engaged in design of the next generation of Open Centre Turbines,

referred to as the Standard Product (SP). Departures of the SP turbine’s geometry from its predecessors, as well

as developments in loading and performance calculation methodologies has led to the undertaking of a program

test campaigns targeted towards design validation. The objectives of the tests implemented under the first call of

the Marinet2 relate to validation of loading on a stalled turbine subject to various environmental flow conditions,

specifically: current, monochromatic & irregular waves, and combined current/wave.

1.2 Development So Far

1.2.1 Stage Gate Progress

Previously completed: ✓

Planned for this project:

STAGE GATE CRITERIA Status

Stage 1 – Concept Validation

•Linear monochromatic waves to validate or calibrate numerical models of the system (25 – 100 waves)

•Finite monochromatic waves to include higher order effects (25 –100 waves)

•Hull(s) sea worthiness in real seas (scaled duration at 3 hours)

•Restricted degrees of freedom (DofF) if required by the early mathematical models

•Provide the empirical hydrodynamic co-efficient associated with the device (for mathematical modelling tuning)

•Investigate physical process governing device response. May not be well defined theoretically or numerically solvable

•Real seaway productivity (scaled duration at 20-30 minutes)

•Initially 2-D (flume) test programme

•Short crested seas need only be run at this early stage if the devices anticipated performance would be significantly affected by them

•Evidence of the device seaworthiness

•Initial indication of the full system load regimes

Stage 2 – Design Validation

•Accurately simulated PTO characteristics

•Performance in real seaways (long and short crested)

•Survival loading and extreme motion behaviour.

•Active damping control (may be deferred to Stage 3)

•Device design changes and modifications

•Mooring arrangements and effects on motion

•Data for proposed PTO design and bench testing (Stage 3)

•Engineering Design (Prototype), feasibility and costing

•Site Review for Stage 3 and Stage 4 deployments

•Over topping rates

Stage 3 – Sub-Systems Validation

Page 6: User Organisation OpenHydro - MaRINET2...Lir National Ocean Test Facilities. MaRINET2 is a €10.5 million project which includes 39 organisations representing some of the top offshore

STAGE GATE CRITERIA Status

•To investigate physical properties not well scaled & validate performance figures

•To employ a realistic/actual PTO and generating system & develop control strategies

•To qualify environmental factors (i.e. the device on the environment and vice versa) e.g. marine growth, corrosion, windage and current drag

•To validate electrical supply quality and power electronic requirements.

•To quantify survival conditions, mooring behaviour and hull seaworthiness

•Manufacturing, deployment, recovery and O&M (component reliability)

•Project planning and management, including licensing, certification, insurance etc.

Stage 4 – Solo Device Validation

•Hull seaworthiness and survival strategies

•Mooring and cable connection issues, including failure modes

•PTO performance and reliability

•Component and assembly longevity

•Electricity supply quality (absorbed/pneumatic power-converted/electrical power)

•Application in local wave climate conditions

•Project management, manufacturing, deployment, recovery, etc

•Service, maintenance and operational experience [O&M]

•Accepted EIA

Stage 5 – Multi-Device Demonstration

•Economic Feasibility/Profitability

•Multiple units performance

•Device array interactions

•Power supply interaction & quality

•Environmental impact issues

•Full technical and economic due diligence

•Compliance of all operations with existing legal requirements

1.2.2 Plan For This Access

The test plan implemented for this access period covers Stage 1 – Concept Validation. The primary objective of

this test campaign was measurement of global loads applied to a 1:20 scale model of the Open Centre Turbine

with fixed (non-spinning) rotor. The simulated environmental conditions may be summarised as follows:

• Flow Tests: High and low turbulence intensity;

• Wave Tests: Monochromatic waves & irregular seas;

• Combined Flow/Wave Tests; low turbulence intensity with monochromatic waves & irregular seas;

Tests were implemented across a range of turbine heading angles such that flows and/or waves with inflow

spanning 0 degrees to 180 degrees were simulated. The resulting loads will be used to validate drag and added

inertia coefficients used in OpenHydro’s load derivation methodology.

In addition to the primary objective described above, the following secondary objectives would be pursued subject

to early completion of the primary objectives:

• Load measurements for the Sub-Sea Base only (i.e. without the turbine attached);

• Wake characterisation using Particle Image Velocimetry (PIV).

Page 7: User Organisation OpenHydro - MaRINET2...Lir National Ocean Test Facilities. MaRINET2 is a €10.5 million project which includes 39 organisations representing some of the top offshore

2 Outline of Work Carried Out

2.1 Setup

2.1.1 Model Configuration

The 1:20 scale model of the Open Centre Turbine consisted of the following components:

• Turbine: comprising the stator, and the fixed rotor;

• Sub-Sea Base (SSB).

The model was attached to the 6 degree of freedom load cell via an interface which allowed for adjustment of its

heading relative to the incident flow.

2.1.2 Flow Measurement

Flow conditions were measured by primarily using a Lased Doppler Velocimeter (LDV), with secondary

measurements provided by a Nortek Vectrino Acoustic Doppler Velocimeter (ADV). For flow characterisation tests

LDV measurements were taken at 4 stream-wise positions (2 upstream, turbine location, and downstream) and

multiple vertical positions. During load tests LDV measurements were taken downstream at a vertical position

corresponding to hub height.

Figure 2.1 Model installed with 170 degrees orientation relative to incident flow; LDV & ADV in downstream position

2.2 Tests

Table 2.1 summarises the tests implemented over the course of the access period.

Page 8: User Organisation OpenHydro - MaRINET2...Lir National Ocean Test Facilities. MaRINET2 is a €10.5 million project which includes 39 organisations representing some of the top offshore

Start Day End Day

Flow Characterisation 1 4

Load Tests (SSB only) High Turbulence Intensity 4 4

Load Tests, High Turbulence Intensity 4 6

Load Tests, Low Turbulence Intensity 7 8

Load Tests, Medium Turbulence Intensity 8 8

Load Tests, Combined Wave & Flow 8 8

Wake Characterisation 9 9

Load Tests (SSB only) Low Turbulence Intensity 10 10

Table 2.1 Overview of tests

2.3 Results

Analysis of the measured data is ongoing. Results from the flow characterisation tests demonstrate that the flow

conditions are consistent in terms of velocity profile and turbulence intensity across the mean flow velocities

tested. This is illustrated in Figure 2.2.

Figure 2.2 Normalised average stream-wise velocity (left) & turbulence intensity (right) measured by LDV at model position

2.4 Analysis & Conclusions

Analysis of data is ongoing.

3 Main Learning Outcomes

3.1 Progress Made

All primary and secondary objectives described in Section 1.2.2 were achieved during the tests.

Page 9: User Organisation OpenHydro - MaRINET2...Lir National Ocean Test Facilities. MaRINET2 is a €10.5 million project which includes 39 organisations representing some of the top offshore

3.1.1 Progress Made: For This User-Group or Technology

It is anticipated that the results of these tests will enable validation of OpenHydro’s loading methodology for the

idealised case of a stalled rotor. The next stages will involve similar tests for rotor conditions representative of

free spin and normal operation (i.e. PTO simulation).

3.1.2 Progress Made: For Marine Renewable Energy Industry

These tests are expected to add to the pool of knowledge relevant to loading of ducted tidal turbines subject to

realistic flow and wave conditions.

3.2 Key Lessons Learned

The following difficulties were encountered and overcome during the course of the tests:

• The model was designed so that it would be attached to the load cell outside of the tank and the full

system (model & load cell) would be installed on the tank floor in a single operation. However, it was not

practical to remove the load cell from the tank. As a result the model was installed in stages: SSB first,

then turbine. Since a significant part of the turbine’s volume was constructed from rigid polyurethane

foam, additional ballast was required to overcome buoyancy. The required ballast was easily calculated

and attached to the turbine prior to its installation;

• The model’s design did not account for the fact that the top of the load cell was coincident with the false

floor. As a result, it was installed on purpose fabricated spacers which achieved the intended clearance

between the bottom of the SSB and the false floor. This problem was recognised on the first day of tests,

and fabrication of the spacers was completed on the second day. Since the first four days were allocated

for characterisation of flow in the absence of the model, the test plan was not delayed;

• The ADV did not produce reliable measurements. This was attributed to the fact that the tank’s water was

not appropriately seeded for this instrument (i.e. it was too clean). Rather, seeding particles appropriate

for laser systems (LDV & PIV) were prioritised. Since the ADV represented a secondary measurement of

velocity (the LDV represented the primary measurement) the poor quality of ADV data was not a significant

issue;

• The majority of the model was constructed from Aluminium which was not anodized. A pair of sacrificial

zinc anodes were installed on the model to protect against corrosion induced by the tank’s chlorinated

fresh water. Nevertheless, significant residue (assumed to be a result of corrosion) formed on the

aluminium surfaces. For the purpose of these tests this was not considered a significant issue since the

majority of the residue was removed by the flow;

4 Further Information

4.1 Scientific Publications

List of any scientific publications made (already or planned) as a result of this work:

4.2 Website & Social Media

Website:

YouTube Link(s):

LinkedIn/Twitter/Facebook Links:

Page 10: User Organisation OpenHydro - MaRINET2...Lir National Ocean Test Facilities. MaRINET2 is a €10.5 million project which includes 39 organisations representing some of the top offshore

Online Photographs Link:

5 references

6 Appendices

6.1 Stage Development Summary Table

The table following offers an overview of the test programmes recommended by IEA-OES for each Technology

Readiness Level. This is only offered as a guide and is in no way extensive of the full test programme that should

be committed to at each TRL.

Page 11: User Organisation OpenHydro - MaRINET2...Lir National Ocean Test Facilities. MaRINET2 is a €10.5 million project which includes 39 organisations representing some of the top offshore

NASA Technology Readiness Levels1

1 https://www.nasa.gov/directorates/heo/scan/engineering/technology/txt_accordion1.html

Page 12: User Organisation OpenHydro - MaRINET2...Lir National Ocean Test Facilities. MaRINET2 is a €10.5 million project which includes 39 organisations representing some of the top offshore

NASA TRL Definition Hardware Description Software Description Exit Criteria

TRL Definition Hardware Description Software Description Exit Criteria

1 Basic principles

observed and

reported.

Scientific knowledge generated underpinning

hardware technology concepts/applications.

Scientific knowledge generated underpinning

basic properties of software architecture and

mathematical formulation.

Peer reviewed publication of

research underlying the

proposed

concept/application.

2 Technology

concept and/or

application

formulated.

Invention begins, practical application is

identified but is speculative, no experimental

proof or detailed analysis is

available to support the conjecture.

Practical application is identified but is

speculative, no experimental proof or detailed

analysis is available to support the conjecture.

Basic properties of algorithms, representations

and concepts defined. Basic principles coded.

Experiments performed with synthetic data.

Documented description of

the application/concept that

addresses feasibility and

benefit.

3 Analytical and

experimental

critical function

and/or

characteristic proof

of concept.

Analytical studies place the technology in an

appropriate context and laboratory

demonstrations, modelling and simulation

validate analytical prediction.

Development of limited functionality to

validate critical properties and predictions using

non-integrated software components.

Documented

analytical/experimental

results validating predictions

of key parameters.

4 Component and/or

breadboard

validation in

laboratory

environment.

A low fidelity system/component breadboard

is built and operated to demonstrate basic

functionality and critical test environments,

and associated performance predictions are

defined relative to the final operating

environment.

Key, functionally critical, software components

are integrated, and functionally validated, to

establish interoperability and begin architecture

development.

Relevant Environments defined and

performance in this environment predicted.

Documented test

Performance demonstrating

agreement with analytical

predictions. Documented

definition of relevant

environment.

5 Component and/or

breadboard

validation in

relevant

environment.

A medium fidelity system/component

brassboard is built and operated to

demonstrate overall performance in a

simulated operational environment with

realistic support elements that

demonstrates overall performance in

critical areas. Performance predictions are

made for subsequent development phases.

End-to-end software elements implemented and

interfaced with existing systems/simulations

conforming to target environment. End-to-end

software system, tested in relevant

environment, meeting predicted performance.

Operational

environment performance predicted. Prototype

implementations developed.

Documented test

performance demonstrating

agreement with analytical

predictions. Documented

definition of scaling

requirements.

6 System/sub-

system model or

prototype

demonstration in

an operational

environment.

A high fidelity system/component

prototype that adequately addresses all

critical scaling issues is built and operated in

a relevant environment to demonstrate

operations under critical environmental

conditions.

Prototype implementations of the software

demonstrated on full-scale realistic problems.

Partially integrate with existing

hardware/software systems. Limited

documentation available. Engineering

feasibility fully demonstrated.

Documented test

performance demonstrating

agreement with analytical

predictions.

7 System prototype

demonstration in

an operational

environment.

A high fidelity engineering unit that

adequately addresses all critical scaling

issues is built and operated in a relevant

environment to demonstrate performance in

the actual operational environment and

platform (ground, airborne, or space).

Prototype software exists having all key

functionality available for demonstration and

test. Well integrated with operational

hardware/software systems demonstrating

operational feasibility. Most software bugs

removed. Limited documentation available.

Documented test

Performance demonstrating

agreement with analytical

predictions.

8 Actual system

completed and

"flight qualified"

through test and

demonstration.

The final product in its final configuration

is successfully demonstrated through test

and analysis for its intended operational

environment and platform (ground, airborne,

or space).

All software has been thoroughly debugged and

fully integrated with all operational hardware

and software

systems. All user documentation, training

documentation, and maintenance

documentation completed. All functionality

successfully demonstrated in simulated

operational scenarios. Verification and

Validation (V&V) completed.

Documented test

performance verifying

analytical predictions.

9 Actual system

flight proven

through

successful mission

operations.

The final product is successfully operated in

an actual mission.

All software has been thoroughly debugged and

fully integrated with all operational

hardware/software systems.

All documentation has been completed.

Sustaining software engineering support is in

place. System has been successfully operated in

the operational environment.

Documented mission

operational results

Page 13: User Organisation OpenHydro - MaRINET2...Lir National Ocean Test Facilities. MaRINET2 is a €10.5 million project which includes 39 organisations representing some of the top offshore
Page 14: User Organisation OpenHydro - MaRINET2...Lir National Ocean Test Facilities. MaRINET2 is a €10.5 million project which includes 39 organisations representing some of the top offshore

Rue d’Arlon 63-65 | 1040 Brussels |Tel. +32 (0)2 400 1040 | E. [email protected] | www.ETIPOcean.eu

6.2 Any Other Appendices