US CMS Silicon Tracker Project

Joe Incandela

University of California Santa Barbara

Status and scheduleCMS Weekly Meeting

Fermilab

May 14, 2004

Tracker status - Fermilab - May 14, 2004 - J. Incandela 2

North American Group

• Fermilab (FNAL)• M. Demarteau, A. Ronzhin, K. Sogut, L. Spiegel, S. Tkaczyk + technicians

• Kansas State University (KSU):T.Bolton, W.Kahl, R.Sidwell, N.Stanton• University of California, Riverside (UCR)

• P. Gartung, G. Hanson, G. Pasztor• University of California, Santa Barbara (UCSB)

• A. Affolder, S. Burke, C.Campagnari, D. Hale, (C. Hill), J.Incandela, S. Kyre, J. Lamb, S. Stromberg, (D. Stuart), R. Taylor, D. White + technicians.

• University of Illinois, Chicago (UIC)• E. Chabalina, C. Gerber, T. Ten

• University of Kansas (KU)• P. Baringer, A. Bean, L. Christofek, D. Coppage

• University of Rochester (UR)• R.Demina, R. Eusebi, E. Groves, E. Halkiadakis, A. Hocker, S.Korjenevski,

P. Tipton• Mexico Consortium:

• Cinvestav: H. Castilla, R.Perez, A. Sanchez• Puebla: E. Medel, H. Salazar• San Luis Potosi: A. Morelos

• Brown University• R. Hooper, G. Landsberg, H. Nguyen, C. Nguyen

Tracker status - Fermilab - May 14, 2004 - J. Incandela 3

Tracking Requirements

• Efficient & robust• Fine granularity to resolve nearby tracks

• Fast response time to resolve bunch crossings

• Radiation resistant devices for 10y of LHC operation

• ~1-2% PT resolution at ~ 100 GeV

• Asymptotic impact parameter d ~ 20 m

• MOST IMPORTANTLY – We want it to be there and useable as early as possible!

Tracker status - Fermilab - May 14, 2004 - J. Incandela 4

US Responsibilities

5.4 m

2.4

m

Outer Barrel (TOB)

~105 m2

NEW:End Caps (TEC)

50% Modules for Rings 5 and 6 and

hybrid processing for Rings 2,5,6

Tracker status - Fermilab - May 14, 2004 - J. Incandela 5

Outer Barrel Production

• Outer Barrel • Modules

• 4128 Axial (Installed)

• 1080 Stereo (“ “)

• Rods

• 508 Single-sided (“ “)

• 180 Double-sided (“ “)

• US Tasks• All hybrid bonding & test

• All Module assembly & test

• All Rod assembly & test

• Joint Responsibilities with CERN• Installation & Commissioning

• Maintenance and Operation

~20 cm

Modules Built & Tested in US

Tracker status - Fermilab - May 14, 2004 - J. Incandela 6

End Cap Construction

• Central European Consortium requested US help

• We agreed to produce up to 2000 R5 and R6 modules

• After 10 weeks UCSB successfully built the R6 module seen above.

• UCSB has built 27 R6 and 3 R5 modules to date

First TEC Module Built at UCSB

Pisa

ROD INTEGRATION

AachenKarlsruheStrasbourgZurichWien

PETALS INTEGRATION Aachen

Brussels Karlsruhe

Louvain

Lyon Strasbourg

BrusselsWien Lyon

TEC AssemblyTEC Assembly

CERN

Frames:Brussels

Sensors:factories

Hybrids:Strasbourg

Pitch adapter:Brussels

Hybrid:CF carrier

TK ASSEMBLY

CERN

LouvainStrasbourg

Perugia Wien

BariPerugia

Bari FirenzeTorinoPisaPadova

TIB-TID INTEGRATION

FNAL

UCSB

TOB Assembly TIB-TID Assembly

CERN/USA Pisa Aachen Karlsruhe. --> Lyon

KarlsruheSensor QAC

Moduleassembly

Bonding& testing

Sub-assemblies

FNAL

Integrationinto mechanics

PisaRU

FNAL UCSB

UCSB

UCSB

UCSBCatania UCSB

US in the tracker

US carries almost half of the production load

Tracker status - Fermilab - May 14, 2004 - J. Incandela 8

Summary I

• Problems continued to plague components this past year• US contributions have been critical

• US played major role in finding and fixing a series of flaws• In some cases they would have been fatal

• Problems for module components have been addressed • Frames and hybrids:

• Yields and rates are high and rising• Sensors

• US identified CM Noise and other problems with STM sensors• US advocated shifting order to HPK:

• Provided funds for procuring the masks• Pressed for order to be placed with HPK in February –

beyond which we would have delayed HPK production• CMS is reviewing STM now

• Either STM quality reaches adequately high standards or the remainder of the order will be shifted to HPK

• Upshot: no matter what – we’ll have very high delivery rates by July

Tracker status - Fermilab - May 14, 2004 - J. Incandela 9

Summary II

• These issues have meant that the schedule has slipped• We have lost 6-8 months in FY04 due to this last round of problems

• We have responded• In parallel with work to resolve component problems we improved our

production capacity

• Major upgrade of US production lines to achieve significantly higher production capacity to recover lost schedule time.

• New and better methods

• More and better tooling and hardware

• Better software and Quality Control

• Both FNAL and UCSB production lines have since demonstrated more than 100% increases in stable, high quality module production

• Our production capacity is now extreme:• CDF or D0 Run 2 silicon detectors ~ 750k channels each:

• We can produce this many channels in 10, 40-hour weeks

• With overtime we’d need only 6 weeks

Tracker status - Fermilab - May 14, 2004 - J. Incandela 10

Hybrid Problems

• Serious problems were uncovered by US and CERN1. Flex cable fragility (US)

2. Weak wirebonds (CERN)

3. Power via opens (US)

• Found early, solved quickly• Excellent communication

between US and Europe

• Great relationships with vendors

• Problems typically have been diagnosed, understood, and removed in 1-4 weeks

These could have been fatal

Tracker status - Fermilab - May 14, 2004 - J. Incandela 11

Sensor Production

• Thin Sensors (320 m)• 6273 of 6877 (91%) delivered

• Yield > 99% at CMS QC

• Thick Sensors (500 m) • 7000 ordered from HPK

• Deliveries have begun

• HPK has capacity to make all CMS sensors on schedule

• Thick Sensors (500 m)• Initially ~87% yield at CMS QC

• Major efforts by the CMS tracker group and STM yield at CMS QC increased to ~ 98%

• Still concerns …

Hamamatsu Photonics (HPK) SGS Thomson (STM)

Tracker status - Fermilab - May 14, 2004 - J. Incandela 12

1. CMN Noise Issue

•Example: Sensors31215014 and 14308304

•Channels causing the problem• 203 at 70V

• 251 at 130V

30200020005110

100

1000

10000

100000

1000000

0 100 200 300 400 500

Voltage

Bia

s C

urr

en

t (n

A)

Current(DB)

Current(probing)

Current(Bonded)

CMN problem first reported by US in July 2003. Understood to be a pt. discharge/breakdown effect

Tracker status - Fermilab - May 14, 2004 - J. Incandela 13

First IV in standard Vienna qtc setup: sensor outside specifications (20µA)

Vacuum switched off: Sensor perfect 0.5 µA

Vacuum switched on again: Sensor again bad (20µA)

Sensor 30211431541220

2. Vacuum – effect (single strip!)

without vacuum

with vacuum

Tracker status - Fermilab - May 14, 2004 - J. Incandela 14

We identify some sensors with odd noise structure:

Good sensor

3. Time structure in leakage current

Tracker status - Fermilab - May 14, 2004 - J. Incandela 15

Deliveries as of mid February show a new class of sensors:All sensors have currents >1.5 µA : all grade B (have to be fully tested 100%)

IV curve in most cases flat, sensors good?

4. Large processing changes

Tracker status - Fermilab - May 14, 2004 - J. Incandela 16

Module Components Summary

• We exerted a major positive influence.

• Many problems (most found by US) led to delays

• Module breakage in transport → 2 months

• Hybrid Cable problem → +3 months

• ST Sensor issues → +5 months

• Hybrid via problem (found April 04) → no added delay

• ST sensors are the remaining concern

• Shifted order of 7000 (out of 18000 thick sensors) to HPK

• Re-qualifying STM final process now with decision in July

• Timing such that we can shift all production to HPK without impact on schedule if STM fails qualification

Tracker status - Fermilab - May 14, 2004 - J. Incandela 17

Hybrids Progress

Yield is stabilizing above 90%

Tracker status - Fermilab - May 14, 2004 - J. Incandela 18

Rods

• Component issues resolved• OptoHybrids

• Frames

• CCU modules were an issue last month.

• Now receiving good devices

• Mounting/cabling at CERN is underway• Can reach production rate of 50 rods/month

• One issue with potential damage in shipping• Several good solutions under study

Tracker status - Fermilab - May 14, 2004 - J. Incandela 19

US Productivity Enhancements

• Gantry (robotic) module assembly• Redesigned: more robust, flexible,

easily maintained

• Surveying and QA• Automated use of independent

system (OGP)

• More efficient, accurate, fail-safe

•Module Wirebonding• Fully automated wirebonding

• Faster and more reliable bonding

• Negligible damage or rework

•Taken together:• Major increase in US capabilities

• Higher quality

• Could build 750k channels (equal to CDF or D0 in Run 2) in 6 weeks!

Tracker status - Fermilab - May 14, 2004 - J. Incandela 20

Testing & QA

• US has led in many respects • US testing macros and test stand

configurations now used everywhere

• Critical contributions• Discovered and played lead role in

solution of potentially fatal problems

•Taken together• Averted disaster

• Higher quality

Tracker status - Fermilab - May 14, 2004 - J. Incandela 21

Module Mechanical Precision

• Tolerances are stringent

• x of sensors most critical

• 97% modules in specs

• Second order corrections:

• All new modules in specs!

x(Frame-Sensor) (m)

x(Sensor-Sensor) (m)

(Frame-Sensor) (mdeg)

(Sensor-Sensor) (mdeg)

Tracker status - Fermilab - May 14, 2004 - J. Incandela 22

Bonding

• All centers fully operational

• UCSB and FNAL both keep pace with 15/d rate with ease!

Tracker status - Fermilab - May 14, 2004 - J. Incandela 23

Hybrid & Module Electrical Testing

• Specification < 2% faulty channels per module

• Module testing has matured significantly• Minimum set of tests is now defined

• Fault finding algorithms:

• >99% faults found & correctly identified >90% of time

• Less than 0.1% of good channels are flagged faulty

• Performance standardization• Easy comparison of results at different sites

Tracker status - Fermilab - May 14, 2004 - J. Incandela 24

Module Fault Finding

Noisy

1 sensor open

2 sensor open

Pinholes

Bad Channel Flags

Noise Measurement Pulse Height Measurement (Using Calibration Pulse)

Bad Channel Flags

Shorts

Pinhole

Opens

Tracker status - Fermilab - May 14, 2004 - J. Incandela 25

Module Quality

• Goal of less than 1% faulty channels per module• Single Sensor Modules

• 0.20% Faulty Channels Per Module

• Production introduced faults at less than 0.1% rate!

• Two Sensor Modules

• 0.55% Faulty Channels Per Module

• Production introduced faults at less than 0.1% rate!

• Unprecedented low rate of faulty channels

Tracker status - Fermilab - May 14, 2004 - J. Incandela 26

Substructure Integration

•Shells, petals, rods underway

•Systems tests helping to finalize components and procedures

Tracker status - Fermilab - May 14, 2004 - J. Incandela 27

Rod Assembly, Test, Transport

• US contributions• Module installation

• Single rod test stands

• Multi-rod burn-in stands

• Definition of tests & methods

• Transportation

Tracker status - Fermilab - May 14, 2004 - J. Incandela 28

Rod Testing and Transport

Tracker status - Fermilab - May 14, 2004 - J. Incandela 29

Current Tracker Schedule

Tracker status - Fermilab - May 14, 2004 - J. Incandela 30

US Module Production(as determined by A. Cattai, J. Incandela, S. Schael)

• This is our current module production schedule:• USA module final production

• TOB modules: Early June 2004 to May 2005

• TEC modules: Late June 2004 to mid-April 2005

• Paced by sensors & hybrids

• Currently it appears they will arrive simultaneously

Tracker status - Fermilab - May 14, 2004 - J. Incandela 31

Other Considerations

• Rods are expected to keep pace with module assembly• Most system integration will now occur in FY06

• Meanwhile, we analyzed all systems for potential sources of downtime in production

• Stocked critical spares of fabrication tooling and equipment

• Cross-training fabrication personnel

• Developed satellite hybrid processing capacity in Mexico

• Specialized testing and diagnostics facility at UC Riverside

Tracker status - Fermilab - May 14, 2004 - J. Incandela 32

Summary

• The tracker is one of the main strengths of CMS

• The US tracker group is making critical contributions

• Module component problems have been solved

• We’ve accumulated more delays …

• … But we’re on much more solid ground

• Consequence for schedule: • Final assembly of the wheels at CERN slips into FY06.