8/14/2019 US Army Plumbing III Waste Systems
1/102
SUBCOURSE EDITIONEN5112 A
WASTE SYSTEMS(PLUMBING III)
-
8/14/2019 US Army Plumbing III Waste Systems
2/102
US ARMY PLUMBER
MOS 51K SKILL LEVELS 1 AND 2 COURSE
WASTE SYSTEMS
(PLUMBING III)
SUBCOURSE EN5112
US Army Engineer SchoolFort Leonard Wood, Missouri
Eleven Credit Hours
GENERAL
The waste system subcourse, part of the Plumber MOS 51K Skill Levels 1 and 2 course, is designated to
teach those tasks necessary to prepare, connect, and install pipes in a waste system. The subcourse ispresented in two lessons, each corresponding to a terminal objective as indicated below.
Lesson 1: WASTE SYSTEMS AND MATERIALS
OBJECTIVE: Describe the procedures for preparing cast-iron pipe for installation.
TASK: 051-248-1003, Install cast-iron pipe.
CONDITIONS: Given subcourse booklet EN5112. You will work at your own pace and in your ownselected environment with no supervision.
STANDARDS: Within approximately 3 hours, you should be able to study the lesson resources, answerthe practice exercise questions, and select the correct response for each examination questions. You
must respond correctly to 70 percent of the examination questions in order to receive credit for thesubcourse.
i
-
8/14/2019 US Army Plumbing III Waste Systems
3/102
-
8/14/2019 US Army Plumbing III Waste Systems
4/102
Lesson 2: WASTE SYSTEM ROUGHING-IN
OBJECTIVE: Describe the procedures for installing cast-iron pipes for a rough-in waste system.
TASK: Task 051-248-1003, Install cast-iron pipe (connect and install pipe).
CONDITIONS: Given subcourse booklet EN5112. You will work at your own pace and in your own
environment with no supervision.
STANDARDS: Within approximately 8 hours, you should be able to study the lesson resources, answerthe practice exercise questions, and select the correct response for each examination question. You mustrespond correctly to 70 percent of the examination questions in order to receive credit for the subcourse.
ii
-
8/14/2019 US Army Plumbing III Waste Systems
5/102
TABLE OF CONTENTS
Section Page
TITLE PAGE .................................................................................................................................... i
TABLE OF CONTENTS ............................................................................................................... iii
INTRODUCTION.............................................................................................................................v
Lesson 1: WASTE SYSTEMS AND MATERIALS .......................................................................1
Learning Event 1: Classifying Types of Piping ........................................................................ 3
Learning Event 2: Measuring Pipes .......................................................................................... 9
Learning Event 3: Preparing Piping Materials ........................................................................20
Learning Event 4: Identifying Fittings and Using Joint
Connections for Rigid Plastic Pipe ...................................................................................31
Learning Event 5: Identifying Fittings and Using Joint
Connections for Galvanized Steel Pipe ............................................................................ 35
Learning Event 6: Identifying Fittings and Using Joint
Connections for Rigid Copper Tubing ............................................................................. 41
Review Exercise....................................................................................................................... 45
Review Exercise Solutions ......................................................................................................50
Lesson 2: WASTE SYSTEM ROUGHING-IN .............................................................................51
Learning Event 1: Installing Sewer Pipelines ......................................................................... 53
Learning Event 2: Installing Drain Lines and Stacks ..............................................................57
Learning Event 3: Venting the Waste System......................................................................... 65
Learning Event 4: Installing Piping Material ..........................................................................75
Learning Event 5: Supporting Pipeline Runs ..........................................................................85
Learning Event 6: Testing the System for Leaks .................................................................... 89
Review Exercise ...................................................................................................................... 93
Review Exercise Solutions ......................................................................................................96
iii
-
8/14/2019 US Army Plumbing III Waste Systems
6/102
INTRODUCTION
A plumber must know how to join and install different kinds of pipe to complete a waste system in abuilding. Made of different materials, these pipes must sometimes be cut and their ends prepared to take
fittings. The pipe-to-pipe or pipe-to-fitting connections are made with lead, collars, threads, solventcement, and solder, depending on the pipe material used. As the pipe system is installed, it must besupported with hangers and holders. Sometimes a plumber must cut into the building structure to install
the waste and vent pipeline runs for lavatories, sinks, water closets, and urinals. Once the system ofrough-in waste pipelines with venting is installed, it is tested for leaks.
-
8/14/2019 US Army Plumbing III Waste Systems
7/102
Lesson 1
WASTE SYSTEMS AND MATERIALS
OBJECTIVE
At the end of this lesson, you will be able to describe the procedures for preparing cast-iron pipe for
installation.
TASK
Task 051-248-1003, Install cast-iron pipe
CONDITIONS
You will have subcourse booklet EN5112. You will work at your own pace and in your own selectedenvironment with no supervision.
STANDARDS
Within approximately 3 hours, you should be able to study the lesson resources, answer the practiceexercise questions, and select the correct response for each examination question. You must respondcorrectly to 70 percent of the examination questions in order to receive credit for the subcourse.
REFERENCES
FM 5-51K1/2
TM 5-551K
1
-
8/14/2019 US Army Plumbing III Waste Systems
8/102
Lesson 1
WASTE SYSTEMS AND MATERIALS
The waste system is that part of a piping system that carries liquid and semisolid waste to a point
of disposal. The waste system includes venting for elimination of sewer gases. The variouscomponents in a waste system are illustrated below.
This lesson covers the classification of piping used in a waste system, the measurementof piping, and the preparation of piping material for installation. This lesson also coversthe identification of fittings and the use of joint connections.
2
-
8/14/2019 US Army Plumbing III Waste Systems
9/102
Lesson 1/Learning Event 1
Learning Event 1:
CLASSIFYING TYPES OF PIPING
The types of piping that can be used in a waste system are cast-iron soil pipe, rigidplastic pipe (two kinds), galvanized steel pipe, and rigid copper tubing. The type of rigid
copper tubing used in a waste system is called drain waste vent (DWV).
Cast-Iron Soil Pipe
Cast-iron soil pipe is used for waste lines and venting. It is cast in 5- and l0-foot lengths
and in three different styles--single-hub, double-hub, and no-hub.
Single-hub pipe. This pipe has a hub on one end and a spigot on the other. The spigot
of one section fits into the hub of the next. It is used for pipe-to-pipe and/or pipe-to-fitting connections.
Double-hub pipe. This pipe has a hub on each end. It is cut and used when pieces of
pipe shorter than 5 feet are needed. Waste is minimized because two usable lengths ofpipe result. It is used for pipe-to-pipe or pipe-to-fitting connections.
No-hub pipe. This pipe has plain ends. It is used for pipe-to-pipe and pipe-to-fittingconnections. No-hub pipe enables a faster method of joining than the method used forpipes with hubs. These methods will be discussed in Learning Event 4.
3
-
8/14/2019 US Army Plumbing III Waste Systems
10/102
Lesson 1/Learning Event 1
Rigid Plastic Pipe
Rigid plastic pipe can be used anywhere in the waste system. Plastic pipe is joined withsolvent cement. There are two types-acrylonitrile-butadienestyrene (ABS) and polyvinyl
chloride (PVC). ABS and PVC have the same uses. They both have a rigid, plasticappearance. PVC is white or sometimes pastel, and ABS is black or grey. Both come in10-and 20-foot lengths.
Galvanized Steel Pipe
Galvanized steel pipe is generally used in venting. It is the same kind used in a watersystem-made from mild carbon steel and galvanized to prevent rust. It is joined with a
threaded joint in pipe-to-pipe or pipe-to-fitting connections. Galvanized steel should notbe used underground. It comes in 21-foot lengths.
Rigid Copper Tubing (DWV)
Rigid copper tubing is marked with a yellow stripe in the DWV sizes, and it is
expensive. Rigid copper tubing can be used anywhere in the waste system, but it is mostoften used for the drain waste vent. It is connected to fittings by a soldered joint. Itcomes in 10-and 20-foot lengths and can be assembled before making permanentconnections.
4
-
8/14/2019 US Army Plumbing III Waste Systems
11/102
Lesson 1/Learning Event 1
5
-
8/14/2019 US Army Plumbing III Waste Systems
12/102
Lesson 1/Learning Event 1
6
-
8/14/2019 US Army Plumbing III Waste Systems
13/102
Lesson 1/Learning Event 1
Lesson 1
Learning Event 1
SELF-CHECK EXERCISE
1. Name the four types of piping used in a waste system.
2. Identify each type of cast-iron soil pipe.A.B.C.
3. Which types of rigid plastic pipe are used in a waste system?A. ABS and CPVCB. PE and ABSC. PVC and PB
D. ABS and PVC
7
-
8/14/2019 US Army Plumbing III Waste Systems
14/102
Lesson 1/Learning Event 1
SELF-CHECK EXERCISE SOLUTIONS
1. Cast-iron soil pipeRigid plastic pipe (ABS and PVC)Galvanized steel pipe
Rigid copper tubingNote. Order of listing s not important.2. A. Single-hub pipe
B. Double-hub pipeC. No-hub pipe
3. D. ABS and PVC plastic pipe
If your responses are the same, GREAT. Continue on with the lesson. If not, go back and reviewthe material.
8
-
8/14/2019 US Army Plumbing III Waste Systems
15/102
Lesson 1/Learning Event 2
Learning Event 2:
MEASURING PIPES
The measurement for a length of pipe required for installation includes the amount of pipe engagement and the dimension of the fitting. This learning event describes
engagement, fitting dimensions, and pipe length. The last section of this learning eventexplains how to use these three factors to determine the amount of pipe required forinstallation.
Engagement
Engagement for cast-iron soil pipe (single-hub). Different sizes of pipes requiredifferent amounts of engagement. A pipe engagement occurs when the spigot end of one
pipe fits into the hub end of another pipe. A fitting engagement occurs when the end of afitting fits into the hub end of a pipe. Always measure the distance inside the hub for atrue pipe or fitting engagement.
9
-
8/14/2019 US Army Plumbing III Waste Systems
16/102
Lesson 1/Learning Event 2
Engagement for rigid plastic pipe (ABS and PVC). Different sizes of pipes requiredifferent amounts of engagement. Engagement occurs when the end of a pipe fits intothe collar of a fitting. Always measure the distance inside the collar for a true fittingengagement.
10
-
8/14/2019 US Army Plumbing III Waste Systems
17/102
Lesson 1/Learning Event 2
Engagement for galvanized steel pipe. Different sizes of pipe require different amountsof engagement. Engagement occurs when the threaded end of a pipe fits into the collarof a fitting. Always measure the distance inside the collar for a true fitting engagement.
11
-
8/14/2019 US Army Plumbing III Waste Systems
18/102
Lesson 1/Learning Event 2
Engagement for rigid copper tubing (DWV). Different sizes of tubing require differentamounts of engagement. Engagement occurs when the end of the tubing fits into thecollar of a fitting. Always measure the distance inside the collar for a true fittingengagement.
Fitting Dimension
The fitting dimension is also needed when determining the amount of pipe required foran installation. The fitting dimensions for all types of waste fittings are determined thesame way. A fitting dimension is the distance from the center of the fitting to the end ofthe fitting.
12
-
8/14/2019 US Army Plumbing III Waste Systems
19/102
Lesson 1/Learning Event 2
Measurement of Pipe Lengths
End-to-end measurement.
End-to-center measurement.
Center-to-center measurement.
13
-
8/14/2019 US Army Plumbing III Waste Systems
20/102
Lesson 1/Learning Event 2
Determination of Amount of Pipe Required for Installation
Pipe-to-pipe. To figure the length of pipe required when using single-hub cast-iron pipe,use the following steps. The example given in italics is from the illustration below.
Measure the end-to-end distance from the place where the new pipe will be installed(42 inches).
Add the amount of engagement (42 + 6= 48).
Take a double-hub pipe and cut off the one end. The remaining piece should equalthe total (48 inches).
Example:end-to-end 42 inches
engagement + 6 incheslength of pipe required = 48 inches
14
-
8/14/2019 US Army Plumbing III Waste Systems
21/102
Lesson 1/Learning Event 2
Pipe-to-fitting. The method for figuring the length of pipe required for a pipe-to-fittingconnection is the same for all types of piping. Use the following steps. The examplegiven in italics is from the illustration below.
Measure the end-to-center distance from the place where the new pipe will be
installed (60 inches).
Subtract the fitting dimension (60 - 6= 54).
Add the amount of engagement (54 + 2 = 56 ).
Cut a pipe the length of the total (56inches).
Example:end-to-center 60 inches
fittingdimension - 6 inches
engagement + 2 incheslength of pipe required = 56 inches
15
-
8/14/2019 US Army Plumbing III Waste Systems
22/102
Lesson 1/Learning Event 2
Center-to-center. The method for figuring the length of pipe required for a connection between fittings is the same for all types of piping. Use the following steps. Theexample given in italics is from the illustration below.
Measure the center-to-center distance from the place where the new pipe will be
installed (66 inches).
Subtract both fitting dimensions (66- 5 - 5 = 56).
Add the amount of engagement r both fittings (56+ 2 + 2 = 60).
Cut a pipe the length of the total (60 inches).
Example:center-to-center 66 inchesboth fitting dimensions - 10 inchesengagement + 4 inches
length of pipe required = 60 inches
16
-
8/14/2019 US Army Plumbing III Waste Systems
23/102
Lesson 1/Learning Event 2
Lesson 1
Learning Event 2
SELF-CHECK EXERCISE
1. To determine the amount of engagement into a fitting, where should you measure?
A. Inside the hub or collar of a fittingB. End-to-end on a fittingC. From end-to-center of a fitting
2. From the illustration below, what is the fitting engagement, in inches, in the hub for 3-inch
pipe?
3. Which fitting shows a correct fitting dimension? Circle one.A.B.C.
D.
17
-
8/14/2019 US Army Plumbing III Waste Systems
24/102
Lesson 1/Learning Event 2
4. From the illustration below, what length of waste pipe, in inches, is required whenyou use an end-to-end measurement?
5. From the illustration below, what length of waste pipe, in inches, is required whenyou use an end-to-center measurement?
6. From the illustration below, what length of waste pipe, in inches, is required whenyou use a center-to-center measurement?
18
-
8/14/2019 US Army Plumbing III Waste Systems
25/102
Lesson 1/Learning Event 2
SELF-CHECK EXERCISE SOLUTIONS
1. A. Inside the hub or collar of a fitting2. 2 inches3. C
4. 55 inchesEnd-to-end measurement = 52 inchesEngagement into hub = 3 inches
Length = 52 + 3= 55 inches
5. 63 inches End-to-center measurement = 67 inchesFitting dimension = 7 inchesFitting engagement = 3 inches
Length = 67 - 7 + 3= 60 + 3= 63 inches
6. 64 inchesCenter-to-center measurement = 72 inchesBoth fitting dimensions = 6 + 6 =12 inchesBoth pipe engagements = 2 + 2 = 4 inches
Length = 72 -12 + 4= 60 + 4= 64 inches
If your responses are the same, GREAT. Continue on with the lesson. If not, go back and reviewthe material.
19
-
8/14/2019 US Army Plumbing III Waste Systems
26/102
Lesson 1/Learning Event 3
Learning Event 3:
PREPARING PIPING MATERIALS
Preparing piping material for installation requires that the pipe be measured, marked, cut,and cleaned. The last learning event described how to measure pipes used in a waste
system. This learning event describes how to mark, cut, and clean piping material.
Preparing Cast-Iron Soil Pipe
Marking. When you cut with a hammer and chisel, mark completely around the pipewhere it is to be cut. When you cut with a soil pipe cutter, one mark on the pipe isadequate. Use a crayon or chalk to mark piping material.
Cutting with a soil pipe cutter. This method can be used to cut uninstalled pipes. It canalso be used to cut pipes that are already installed but need to be repaired. Use thefollowing steps:
If the pipe is not installed, set it in a vise.
Place the cutting wheels of the cutter on the measured mark. Tighten the adjustingknob.
Rotate the cutter back and forth around the pipe.
Continue tightening the adjusting knob and rotating the cutter until the pipe is cut.
20
-
8/14/2019 US Army Plumbing III Waste Systems
27/102
Lesson 1/Learning Event 3
Cutting with a hammer and cold chisel. This method can be used to cut cast-iron soilpipe when a cutter is unavailable. Use the following steps:
Lay the pipe on a wooden board or a mound of dirt.
Place the chisel on the measured mark. Tap it lightly with the hammer, scoringcompletely around the pipe.
Using firmer blows, score around the pipe again.
Continue scoring until the pipe breaks off.
Cleaning. Remove foreign matter or moisture on the pipe ends with a rag.
21
-
8/14/2019 US Army Plumbing III Waste Systems
28/102
Lesson 1/Learning Event 3
Preparing Rigid Plastic Pipe (ABS and PVC)
Marking. Mark the pipe with a crayon or chalk at the required length.
Cutting with a hacksaw. Use the following steps:
Place uninstalled marked pipe in a miter box or a vise. If a vise is used, cover thejaws with a rag to prevent damage to the pipe.
Make the cut on the measured mark with a fine-tooth hacksaw. Be certain that thepipe is cut squarely, or it will not join properly.
Removing burrs. Remove the burrs on the pipe's cut end with a pocket knife orsandpaper. When removing the burrs, be careful not to damage the pipe ends.
22
-
8/14/2019 US Army Plumbing III Waste Systems
29/102
Lesson 1/Learning Event 3
Removing gloss and cleaning. For a good joint connection, use sandpaper to remove thegloss from the outside ends of the pipe. Then clean the pipe with an authorized solventcleaner.
Preparing Galvanized Steel Pipe
Marking. Mark the pipe with a crayon or chalk at the required length.
Cutting with a pipe cutter. Use the following steps:
Place the pipe in a vise with the measured mark about 8 inches from the vise.
Set the cutting wheel on the mark and turn the cutter handle clockwise to get a biteon the pipe.
Turn the whole cutter clockwise, applying cutting oil to the cutting wheel.
After each complete turn of the cutter, give the handle a quarter turn until the pipe iscut.
23
-
8/14/2019 US Army Plumbing III Waste Systems
30/102
Lesson 1/Learning Event 3
Cutting with a hacksaw. Use the following steps:
Place the pipe in a vise.
With a fine-tooth hacksaw, cut the pipe on the measured mark.
Make the cut as squarely as possible to simplify threading the pipe when joining.
Removing burrs. Remove burrs on the outside of the pipe's cut end with a fine metalfile. Remove burrs on the inside with a pipe reamer. With the pipe reamer use thefollowing steps:
Push the reamer into the pipe, applying pressure with one hand.
With the other hand, turn the reamer clockwise using short, even strokes until all
burrs are removed.
24
-
8/14/2019 US Army Plumbing III Waste Systems
31/102
Lesson 1/Learning Event 3
Threading. Use a die and die stock to thread the ends of the pipe. Use the followingsteps:
Insert the correct size die in the die stock.
Slide the die stock over the pipe end and apply pressure to the stock with one hand.
With the other hand, turn the stock handle clockwise slowly until the die has taken abite on the pipe.
Give the stock handle one complete clockwise turn and then back off a quarter turn,applying cutting oil as needed.
Repeat this action until inch of the pipe is beyond the die stock.
Remove the die stock by turning the handle in a counterclockwise direction.
Cleaning. Prepare the threaded end for a joint connection by removing excess oil with aheavy rag and any chips with a wire brush.
25
-
8/14/2019 US Army Plumbing III Waste Systems
32/102
Lesson 1/Learning Event 3
Preparing Rigid Copper Tubing (DWV)
Marking. Mark the pipe with a crayon or chalk at the required length.
Cutting with a tube cuter. Use the following steps:
Hold the tubing with one hand, and set the cutting wheel on the measured mark withthe other hand.
Turn the knob on the cutter until the wheel takes a bite on the tubing.
Turn the cutter in a clockwise direction, and, at the same time, turn the knob.
Continue this action until the tubing is cut.
Cutting with a hacksaw. Use the following steps:
Place the tubing in a miter box or vise.
Using a fine-tooth hacksaw, cut the tubing.
Make the cut as squarely as possible for a good joint connection.
26
-
8/14/2019 US Army Plumbing III Waste Systems
33/102
Lesson 1 /Learning Event 3
Removing burrs. You can move burrs from inside the tubing by going around the cutend lightly with a fine-metal file. You can also remove burr with a tube cutter reamerblade. Use the following steps:
Place the reamer blade into the tubing end.
Turn the handle clockwise until all the burrs are removed.
27
-
8/14/2019 US Army Plumbing III Waste Systems
34/102
Lesson 1/Learning Event 3
Cleaning. For a good joint connection, use emery cloth to clean the outside end of thetubing and the inside of the fitting. Clean to a bright shine.
28
-
8/14/2019 US Army Plumbing III Waste Systems
35/102
Lesson 1/Learning Event 3
Lesson 1
Learning Event 3
SELF-CHECK EXERCISE
Fill in the blanks.
Cast-iron soil pipe:
1. You are to cut a cast-iron so pipe with a hammer and chisel. Once you have measured the pipe lengthrequired, the length is marked with crayon or chalk.
2. When you are scoring cast-iron pipe by tapping a cold chisel with a hammer, the score is madecompletely the pipe.
3. When you are cutting cast-iron pipe with a soil pipe cutter, the cutter is rotated andaround the pipe until it is cut.
4. As you rotate the cutter, tighten the until the pipe is cut. Rigid plastic pipe (ABSand PVC):
5. Rigid plastic pipe (ABS and PVC) is cut with a .
6. The burrs from the cut end of plastic pipe can be removed with a or .
7. The from an outside end of plastic pipe is removed with .Galvanized steel pipe:
8. To cut galvanized steel pipe with a single-wheel pipe cutter, the cutting wheel is placed on the .
9. For every one complete turn around the pipe with the pipe cutter, the cutter's handle is given an
additional .
10. Galvanized steel pipe can also be cut with a .
11. The burrs from the inside of the cut end of the pipe are removed with a .
12. A completely threaded steel pipe should extend inch(es) beyond the die stock.Rigid copper tubing (DWV):
13. Rigid copper tubing (DWV) can be cut with a or a .
14. The buns from the cut end can be removed with a or a .
15. The outside cut end of rigid copper tubing (DWV) is cleaned to a bright shine with .
29
-
8/14/2019 US Army Plumbing III Waste Systems
36/102
Lesson 1/Learning Event 3
SELF-CHECK EXERCISE SOLUTIONS
1. Around the pipe
2. Around
3. Back and forth
4. Adjusting knob
5. Hacksaw with fine-tooth blade
6. Knife, sandpaper
7. Gloss, sandpaper
8. Measured mark
9. Quarter turn
10. Hacksaw
11. Pipe reamer
12. inch
13. Tube cutter, hacksaw
14. Reamer blade, metal file
15. Emery cloth
If your responses are the same, GREAT. Continue on with the lesson. If not, go backand review the material.
30
-
8/14/2019 US Army Plumbing III Waste Systems
37/102
Lesson 1/Learning Event 4
Learning Event 4:
IDENTIFYING FITTINGS AND USING
JOINT CONNECTIONS FOR RIGID PLASTIC PIPE
This learning event illustrates rigid plastic pipe fittings (ABS and PVC). This learning
event also explains how to make a joint connection on rigid plastic pipe.
Fittings
The illustration below shows fittings for ABS plastic pipe. Fittings for PVC plastic pipe
are the same except that the color is white or pastel.
31
-
8/14/2019 US Army Plumbing III Waste Systems
38/102
Lesson 1/Learning Event 4
Joint Connections
Joint connections for ABS and PVC plastic pipe are made with a solvent cement.
Types of cement. Use the following chart to determine which type of cements can be
used with ABS and PVC pipe.
Steps for making the joint connection. The joint connection on plastic pipe should bemade as fast as possible without error because the solvent cement dries very quickly.Use the following steps:
Place the fitting on the pipe. Mark both the pipe and the fitting to show proper fittingdirection.
Apply solvent cement to the outside of the pipe end.
Apply solvent cement to the inside of the fitting's marked end.
Place the fitting on the pipe, using a quarter turn to spread the cement evenly. Then lineup the marks, and hold the fitting firmly to the pipe for at least 30 seconds.
Wipe off all excess cement.
32
-
8/14/2019 US Army Plumbing III Waste Systems
39/102
Lesson 1/Learning Event 4
Lesson 1
Learning Event 4
SELF-CHECK EXERCISE
1. Match each plastic pipe fitting with its description.
Adaptor, plastic to hub cast-iron pipeVent teeAdaptor, plastic to no-hub cast-iron pipe90-degree vent elbow
2. What type of solvent weld cement can be used to connect ABS plastic pipe joints?A. Styrene cementB. ABS cement
C. PVC cementD. Portland cement
3. Where is the solvent cement applied to form a rigid plastic pipe joint?A. Inside of fitting onlyB. Outside of pipe end onlyC. Inside of fitting and outside of pipe endD. Outside of pipe end and fitting end
33
-
8/14/2019 US Army Plumbing III Waste Systems
40/102
Lesson 1 /Learning Event 4
SELF-CHECK EXERCISE SOLUTIONS1. A. Vent tee
B. 90-degree vent elbowC. Adaptor, plastic to hub cast-iron pipeD. Adaptor, plastic to no-hub cast-iron pipe
2. B. ABS cement can be used for ABS plastic pipe3. C. Solvent cement is applied to the outside of pipe end and to inside of fitting end tobe attached.If your responses are the same, GREAT. Continue on with the lesson. If not, go backand review the material.
34
-
8/14/2019 US Army Plumbing III Waste Systems
41/102
Lesson 1 /Learning Event 5
Learning Event 5:
IDENTIFYING FITTINGS AND USING JOINT
CONNECTIONS FOR GALVANIZED STEEL PIPE
This learning event illustrates threaded drainage fittings for galvanized steel pipe. This
learning event also explains how to make a threaded joint connection on galvanized steelpipe.
Fittings
Drainage fittings for galvanized steel pipe used in a waste system are cast with a recessedshoulder. This design allows a smooth flow of waste material. The illustration belowshows threaded drainage fittings.
36
-
8/14/2019 US Army Plumbing III Waste Systems
42/102
Lesson 1/Learning Event 5
Joint Connections
Slope of horizontal drainage pipes. The threads of drainage fittings are at a slight angle.This angle causes horizontal drainage pipes to slope approximately inch per foot.
36
-
8/14/2019 US Army Plumbing III Waste Systems
43/102
Lesson 1 /Learning Event 5
Steps for making the Joint connection. To make a threaded joint connection, use thefollowing steps:
Apply pipe joint compound or Teflon tape, in a counterclockwise direction, to the
pipe threads.
Screw the fitting onto the pipe until it is hand tight.
Tighten the fitting using two pipe wrenches-one to hold the pipe, and the other totighten the fitting by turning clockwise.
Clean the joint with a rag.
37
-
8/14/2019 US Army Plumbing III Waste Systems
44/102
Lesson 1/Learning Event 5
Lesson 1
Learning Event 5
SELF-CHECK EXERCISE
1. Match the galvanized pipe fittings with their description.
60-degree elbowT-Y, long sweepTrap22 -degree elbow
38
-
8/14/2019 US Army Plumbing III Waste Systems
45/102
Lesson 1/Learning Event 5
2. Which fitting, A or B, is a steel pipe drainage fitting? Circle one.A.
B.
Fill in the blanks.3. Pipe joint compound is applied to the .4. The fitting is screwed onto the pipe until it is and then tightened withwrenches.
39
-
8/14/2019 US Army Plumbing III Waste Systems
46/102
Lesson 1 /Learning Event 5
SELF-CHECK EXERCISE SOLUTIONS
1. A. TrapB. 22 -degree elbowC. T-Y, long sweep
D. 60-degree elbow2. A3. Pipe thread4. Hand tightIf your responses are the same, GREAT. Continue on with the lesson. If not, go back
hand review the material.
40
-
8/14/2019 US Army Plumbing III Waste Systems
47/102
Lesson 1/Learning Event 6
Learning Event 6:
IDENTIFYING FITTINGS AND USING
JOINT CONNECTIONS FOR RIGID COPPER TUBING
This learning event illustrates fittings used for rigid copper tubing (DWV). This learning
event also explains how to make a soldered joint connection on rigid copper.
Fittings
The illustration below shows fittings for rigid copper tubing (DWV).
41
-
8/14/2019 US Army Plumbing III Waste Systems
48/102
Lesson 1/Learning Event 6
Joint Connections
Joint connections for rigid copper tubing (DWV) are made with flux, solder, and asource of heat. The flux permits the even spreading of molten solder over the surfaces tobe soldered. The molten solder flows into the space between the fitting and the tubing.
Steps for making the joint connection. Flux, 50-50 solder, and a torch are needed tomake the joint. Use the following steps:
Apply flux to outside end of the tubing.
Apply flux to the inside end of a fitting.
Push the fitting onto the tubing, giving it a quarter turn to spread the flux evenly.
With the torch, apply heat to the fitting only until the flux begins to bubble.
Keeping the flame on the fitting, apply solder to the joint. Melt the solder around thejoint. A well-soldered joint should have an even bead around the entire joint.
Remove the flame.
Clean the joint with a wet cool rag. Be careful not to burn your fingers.
42
-
8/14/2019 US Army Plumbing III Waste Systems
49/102
Lesson 1/Learning Event 6
Lesson 1
Learning Event 6
SELF-CHECK EXERCISE
1. Match the rigid copper (DWV) fittings with their descriptions.
Sanitary T with side outlet45-degree Y branch with cleanoutAdaptor for cast-iron pipe bend, long sweep
2. The soldering flux is spread evenly by giving the fitting a-A. Full turnB. turnC. turnD. turn
3. To form a soldered joint, where is the heat applied?
A. To the tubingB. To the fittingC. To the solderD. To the tubing and the fitting
43
-
8/14/2019 US Army Plumbing III Waste Systems
50/102
Lesson 1/Learning Event 6
SELF-CHECK EXERCISE SOLUTIONS
1. A. Sanitary T with side outletB. bend, long sweepC. 45-degree Y branch with cleanout
D. Adaptor for cast-iron pipe2. D. The fitting is given a turn to spread the soldering flux evenly.3. B. Heat only the fitting.If your responses are the same, GREAT. Continue on with the Review Exercise. If not,go back and review the material.
44
-
8/14/2019 US Army Plumbing III Waste Systems
51/102
Lesson 1/Review Exercise
Lesson 1
REVIEW EXERCISE
Check your understanding of Lesson 1 by completing this review exercise. Try toanswer all of the questions without looking back at the lesson. When you are finished,
turn to the solutions at the end of the exercise and check your responses. If you missedany, go back and restudy the information.
1. How many types of general piping can be used in a waste system?A. Four
B. ThreeC. TwoD. One
2. From the illustration below, what is the pipe engagement for 3-inch cast-iron soilpipe?
A. 3 1/8 inchesB. 3 inchesC. 2 inches
D. 2 inches
3. From the illustration below, what is the length of cast-iron soil pipe when you use anend-to-end measurement?
A. 47 inchesB. 48 inchesC. 49 inchesD. 52 inches
45
-
8/14/2019 US Army Plumbing III Waste Systems
52/102
Lesson 1/Review Exercise
4. Which fitting, A, B, C, or D, shows a correct fitting dimension? Circle one.A.
B.C.D.
5. From the illustration below, what is the length of rigid copper tubing (DWV) whenyou use an end-to-center measurement?
A. 47 inchesB. 45 inchesC. 44 inches
D. 43 inches
46
-
8/14/2019 US Army Plumbing III Waste Systems
53/102
Lesson 1/Review Exercise
6. How is cast-iron soil pipe marked for cutting with a hammer and chisel?
A. Mark top of pipeB. Mark bottom of pipeC. Mark completely around the pipe
D. Mark hub of pipe
7. What two tools are used to cut cast-iron pipe?A. Hammer and short chiselB. Hammer and long chisel
C. Hammer and cold chiselD. Hammer and curved chisel
8. What tool is used to cut ABS and PVC plastic pipe?A. KnifeB. HacksawC. Coping sawD. Back saw
9. What is the final step required to prepare ABS and PVC plastic pipe for a jointconnection?
A. Remove gloss from inside of pipe endB. Remove gloss from outside of pipe endC. Remove gloss from inside and outside of pipe endD. Remove gloss from outside of pipe end and fitting
10. What tool is used to cut galvanized steel pipe?A. Hydraulic pipe cutter
B. Tube cutterC. Pipe cutter
D. Soil pipe cutter
11. A completely threaded steel pipe should extend how many inches beyond the diestock?
A. 1/8 inchB. inch
C. 3/8 inchD. inch
12. What is the material used on rigid copper tubing (DWV) to bring the cut end to abright shine?
A. Sandpaper
B. Emery clothC. Cleaning solventD. Clean rag
47
-
8/14/2019 US Army Plumbing III Waste Systems
54/102
Lesson 1/Review Exercise
13. What is used to connect no-hub cast-iron soil pipe?
A. ClampB. CouplingC. Coupling and clamp
D. Coupling and cement
14. What type of solvent weld cement is needed to connect ABS and PVC rigid plasticpipe?
A. ABS cement
B. Styrene cementC. Portland cementD. All purpose cement
15. Where is the solvent weld cement applied to form a joint for rigid plastic pipe?A. Outside ends of pipe and fittingB. Outside end of pipe onlyC. Outside end of pipe and inside end of fittingD. Inside end of fitting only
16. Where is the heat applied to make a soldered joint for rigid copper tubing (DWV) ?A. PipeB. FluxC. FittingD. Solder
17. Where is the joint compound applied for a threaded drainage fitting joint for steelpipe?
A. Fitting threads onlyB. Pipe threads only
C. Pipe and fitting threadsD. All threads
48
-
8/14/2019 US Army Plumbing III Waste Systems
55/102
Lesson 1/ Review Exercise
THIS PAGE INTENTIONALLY LEFT BLANK.
49
-
8/14/2019 US Army Plumbing III Waste Systems
56/102
Lesson 1/Review Exercise
REVIEW EXERCISE SOLUTIONS
1. A (Page 3)2. C (Page 9)3. D (Page 14)
4. B (Page 13)5. B (Page 15)6. C (Page 20)7. C (Page 21)8. B (Page 22)9. B (Page 23)
10. C (Page 23)11. B (Page 25)12. B (Page 28)13. C (Page 3)14. D (Page 32)15. C (Page 32)16. C (Page 42)17. B (Page 37)
50
-
8/14/2019 US Army Plumbing III Waste Systems
57/102
Lesson 2
WASTE SYSTEM ROUGHING-IN
OBJECTIVE
At the end of this lesson, you will be able to describe the procedures for installing cast-
iron pipe for a rough-in waste system.
TASK
Task 051-248-1003, Install cast-iron pipe.
CONDITIONS
You will have subcourse booklet EN5112. You will work at your own pace and in yourown selected environment with no supervision.
STANDARDS
Within approximately 8 hours, you will be able to study the lesson resources, answer the practice exercise questions, and select the correct response for each examinationquestion. You must respond correctly to 70 percent of the examination questions inorder to receive credit for the subcourse.
REFERENCES
FM 5-51K1/2
TM 5-551K
51
-
8/14/2019 US Army Plumbing III Waste Systems
58/102
Lesson 2
WASTE SYSTEM ROUGHING-IN
Roughing-in is the installation of all parts of a waste system that can be completed before
the installation of fixtures. These are the parts of a waste system that will be out of sight(behind walls and floors). These parts of a waste system must be carefully installed.After the walls and flooring are in place, it is difficult and expensive to make repairs to
the rough-in waste system.
The rough-in waste system includes a building drain line, stack, branch lines, venting,and fittings. The building drain line ties into the building sewer line. Of the four typesof piping discussed in Lesson One, cast-iron and plastic are most often used in a rough-in
waste system. No matter which type of piping is used, the process of roughing-in will bethe same except for the joint connections.
This lesson covers all the jobs involved in roughing-in a waste system-the installation ofsewer pipelines, drain lines, stacks, venting, and piping material. This lesson also coversthe methods for supporting pipeline runs and testing a system for leaks.
52
-
8/14/2019 US Army Plumbing III Waste Systems
59/102
Lesson 2/Learning Event 1
Learning Event 1:
INSTALLING SEWER PIPELINES
When a building foundation is under construction, the building sewer pipeline isinstalled in the ground. First, a hole is cut in the main sewer line. Then a fitting is
attached to the main sewer line. Finally the building sewer pipeline is laid, supported,and connected at the correct grade slope.
Connecting the Building Sewer Pipeline to the Main Sewer Pipeline
Cutting the hole in the main sewer pipeline. Cut a hole in the main sewer pipelineabove the normal sewerage flow level. Use the following steps:
Place the fitting on the sewer pipeline where the fitting will be installed. Trace aroundthe fitting with a crayon or chalk. This tracing marks where the hole will be cut.
With a hammer and cold chisel, score the mark to a depth of 1/8 inch.
Knock a hole in the center of the scored area with the hammer.
Starting from the hole and working outward to the scored mark, tap lightly with the
hammer to widen the hole.
Continue until the hole is the correct size.
53
-
8/14/2019 US Army Plumbing III Waste Systems
60/102
Lesson 2/Learning Event 1
Installing the thimble. The thimble is the fitting that connects the main sewer pipelineto the building sewer pipeline. To install the thimble on the main sewer pipeline, use thefollowing steps:
Place the thimble over the made-to-fit hole on the main sewer pipeline.
Support the thimble in place with pieces of scrap lumber.
Pack the connection with oakum and seal it with a portland cement mixture.
Do not remove the support until the joint sets.
Laying the building sewer pipeline. Normally, cast-iron soil pipe is used for sewerpipelines. To install the building sewer pipeline, use the following steps:
Place the piping in a dug-out trench, one length at a time. Start at the sewer thimble
and work toward the building.
Set the pipe to a grade slope of inch per foot with a carpenter's level.
Support the pipe to maintain the grade slope.
After all the pipes are set, make the joint connections.
54
-
8/14/2019 US Army Plumbing III Waste Systems
61/102
Lesson 2/Learning Event 1
Lesson 2
Learning Event 1
SELF-CHECK EXERCISE
Fill in the blanks.
1. When attaching a building sewer pipeline to the main sewer line, mark the location onthe main sewer line by tracing around the to be installed.
2. The mark is scored with a hammer and cold chisel to a depth of .
3. The sewer thimble fitting is supported in place and connected to the main sewerline with and .
4. A building sewer line is installed from the building to the main sewer with a gradeslope of .
55
-
8/14/2019 US Army Plumbing III Waste Systems
62/102
Lesson 2/Learning Event 1
SELF-CHECK EXERCISE SOLUTIONS1. Fitting2. 1/8 inch3. Oakum and portland cement4. inch per foot
If your responses are the same, GREAT. Continue on with the lesson. If not, go backand review the material.
56
-
8/14/2019 US Army Plumbing III Waste Systems
63/102
Lesson 2/Learning Event 2
Learning Event 2:
INSTALLING DRAIN LINES AND STACKS
The building's drain line connects to the building sewer pipeline and continues to thepoint where the stack is to rise vertically. The building's drain pipe must be the same
size as the building sewer pipe.
Installing the Building Drain Line
Installing a drain line under a foundation floor. Use the following steps:
Place the piping in a trench, one length at a time. Start at the building sewer pipelineand work towards the place where stack will be installed.
Set the pipe to a grade slope of inch per foot with a carpenters level. The slopewill rise from the building sewer line to the stack.
Support the pipe at each connection to maintain the grade slope.
After all the pipes are set, make the joint connections. Use a bend, long sweepfitting at the location where the stack will be erected.
57
-
8/14/2019 US Army Plumbing III Waste Systems
64/102
Lesson 2/Learning Event 2
Installing a building drain line through a foundation wall. Use the following steps:
Starting at the building sewer pipeline and using the proper grade slope, determinewhere the foundation wall will be cut. Mark the wall and then cut the hole.
Run a chalk line from the hole to the proposed location of the stack, still using arising grade slope of inch per foot.
Place each length of pipe along the chalk line. Support the joint connections withhangers.
Place a 90-degree Y fitting to form the bottom of the stack.
Support it from the bottom.
Check pipe alignment and make the joint connections.
Patch the foundation wall where the pipe runs through.
Installing the Stack
Sections of the stack. A combination of vertical pipes with fittings forms the stack in a
plumbing waste system. It is used for waste disposal and venting. The main stack iscomposed of three sections--the soil stack, waste stack, and vent stack. A soil stackcarries waste disposal from water closets. A waste stack carries waste disposal from all
other fixtures. A vent stack provides air circulation throughout the waste system andallows for the release of sewer gases.
58
-
8/14/2019 US Army Plumbing III Waste Systems
65/102
Lesson 2/Learning Event 2
Placement of the stack. The stack runs in the building wall, up through each floor, andout through the roof. It is installed after the building framework is in place. Use thefollowing steps:
Use a plumb line to insure the stack will be vertical.
Cut holes in the framework for running the stack vertically.
Set the pipes in place.
Support the fittings.
Be certain the vent stack rises at least 12 inches from the highest point of the hole cutthrough the roof.
Place cleanouts at possible waste stoppage points.
Make the joint connections.
59
-
8/14/2019 US Army Plumbing III Waste Systems
66/102
Lesson 2/Learning Event 2
Connections to the stack. Branch lines are for disposal of wastes. All rough-inhorizontal branch lines in the waste system must slope inch per foot toward the stack.
60
-
8/14/2019 US Army Plumbing III Waste Systems
67/102
Lesson 2/Learning Event 2
Lesson 2
Leaning Event 2
SELF-CHECK EXERCISE
1. Identify each lettered item in the waste system.A.B.C.D.
61
-
8/14/2019 US Army Plumbing III Waste Systems
68/102
Lesson 2/Learning Event 2
2. Identify each lettered type of stack that composes a main stack.
A.B.C.
62
-
8/14/2019 US Army Plumbing III Waste Systems
69/102
Lesson 2/Learning Event 2
3. What is the minimum height that the vent stack must rise from the highest point of the
hole cut through the roof?A. 8 inchesB. 10 inches
C. 12 inchesD. 14 inches
4. Identify the horizontal waste system pipelines that must slope inch per foot towardthe stack. Circle 2 of the 4 letters, A, B, C, or D.
A.B.C.D.
63
-
8/14/2019 US Army Plumbing III Waste Systems
70/102
Lesson 2/Learning Event 2
SELF-CHECK EXERCISE SOLUTIONS1. A. Main sewer line
B. Building sewer lineC. Building drain line
D. Stack2. A. Vent stackB. Waste stackC. Soil stack
3. C. The minimum height that the vent stack must rise is 12 inches from the highestpoint of the hole cut through the roof.4. B and C must slope inch toward the stack.
B is the waste drain line for the lavatory.C is the waste drain lie for the water closet.
If your responses are the same, GREAT. Continue on with the lesson. If not, go backand review the material.
64
-
8/14/2019 US Army Plumbing III Waste Systems
71/102
Lesson 2/Learning Event 3
Learning Event 3:
VENTING THE WASTE SYSTEM
The waste system is vented to allow free air circulation within the system, to reduce the
pressure on trap seals, and to remove foul gas odors caused by sewerage. Venting musttie into the stack. The method used to vent the waste system depends on where thefixtures are to be located and how they are grouped. This learning event describes threemethods-unit venting, wet venting, and circuit venting. This learning event alsodescribes water seals and cleanout fittings.
Unit Venting
Unit venting allows two similar fixtures to use the same stack fitting. The waste drainsof the two fixtures must be at the same height from the floor.
65
-
8/14/2019 US Army Plumbing III Waste Systems
72/102
Lesson 2/Learning Event 3
Wet Venting
Wet venting allows the drain line of one fixture to serve also as a vent line for anotherfixture. The size of the wet vent depends on the distance between trap outlets.
66
-
8/14/2019 US Army Plumbing III Waste Systems
73/102
Lesson 2/Learning Event 3
Circuit Venting
Circuit venting can be used when two or more fixtures, such as lavatories, are installed ina row. The circuit vent is connected to the waste drain line between the last two fixtures
in the row. Then the circuit vent is connected to the main vent.
67
-
8/14/2019 US Army Plumbing III Waste Systems
74/102
Lesson 2/Learning Event 3
Water Seals
A water seal stops sewer gases from coming into the building. It is a column of water ina fixture trap. The column is maintained by the atmospheric pressure from the venting
(14.7 pounds per square inch, at sea level).
Water seal for water closets. Water closets have built-in traps that provide a visiblewater seal.
Water seal for other fixtures. Other fixtures require a P-trap to provide a water seal.
The P-trap seal is a column of water (about 2 inches) between the trap's crown weir andthe trap's top dip.
68
-
8/14/2019 US Army Plumbing III Waste Systems
75/102
Lesson 2/Learning Event 3
Cleanouts
A cleanout is a fitting with a removable plug that is placed in a roughed-in waste systemto help clear any stoppage in waste drain lines. Cleanouts are placed at the connection
between the building sewer line and drain line, at the base of a vertical stack, and at allplaces where pipe direction changes 90 degrees.
Cleanout for a building sewer line. This cleanout can be just outside or inside thebuilding. It must be 2 or more inches above the ground or the building floor.
69
-
8/14/2019 US Army Plumbing III Waste Systems
76/102
Lesson 2/Learning Event 3
Cleanout at the base of vertical stack. This cleanout must be 6 inches or more above thefloor.
70
-
8/14/2019 US Army Plumbing III Waste Systems
77/102
Lesson 2/Learning Event 3
Cleanout for a 90-degree change-of-pipe direction. This cleanout is installed to clearany possible stoppage caused by the 90-degree turn in the line.
71
-
8/14/2019 US Army Plumbing III Waste Systems
78/102
Lesson 2/Learning Event 3
Lesson 2
Learning Event 3
SELF-CHECK EXERCISE
1. Match the type of vent with its description.Circuit ventUnit ventWet vent
72
-
8/14/2019 US Army Plumbing III Waste Systems
79/102
Lesson 2/Learning Event 3
2. The water seal in a P-trap between the crown weir and the top dip is-
A. 1 inchB. 2 inchesC. 3 inches
D. 4 inches
3. The cleanout for a building sewer line must be more than-A. 6 inches above floorB. 4 inches above floor
C. 3 inches above floorD. 2 inches above floor
4. The cleanout at the base of a stack in a building must be-A. 2 inches above floorB. 4 inches above floorC. 6 inches above floorD. 8 inches above floor
5. A cleanout is installed when a pipe run changes direction by-A. 22 degreesB. 33 1/3 degreesC. 42 degreesD. 90 degrees
73
-
8/14/2019 US Army Plumbing III Waste Systems
80/102
Lesson 2/Learning Event 3
SELF-CHECK EXERCISE SOLUTIONS1. A. Unit vent
B. Wet ventC. Circuit vent
2. B3. D4. C5. DIf your responses are the same, GREAT. Continue on with the lesson. If not, go back
and review the material.
74
-
8/14/2019 US Army Plumbing III Waste Systems
81/102
Lesson 2/Learning Event 4
Learning Event 4:
INSTALLING PIPING MATERIAL
Roughed-in waste system piping and fittings are installed between and through the
building framework. Installation is done before the exposed wall studs and floor joistsare covered. Installation at this time makes it easier to rough in pipe runs.
75
-
8/14/2019 US Army Plumbing III Waste Systems
82/102
Lesson 2/Learning Event 4
Installing Pipe Runs through Floor Joists
Cutting joists. Use the following steps:
Use a handsaw to cut a notch in the joist. The notch can be cut at the top or bottom ofthe joist. The width of the notch should be slightly larger than the pipe's outsidediameter. The depth of the notch cannot be larger than one quarter of the joist depth.
Example: Joist depth = 8 inches of 8 = 2
Proper notch depth = 2 inches
Use a sharp wood chisel to cut away any wood between the saw cuts.
76
-
8/14/2019 US Army Plumbing III Waste Systems
83/102
Lesson 2/Learning Event 4
Bracing joists. A joist with a notch cut on top is braced with a 2- by 4-inch board oneach side. The boards are nailed in pace and centered under the notch. A joist with anotch cut in the bottom is braced with a steel plate centered on the notch.
77
-
8/14/2019 US Army Plumbing III Waste Systems
84/102
Lesson 2/Learning Event 4
Cutting a joist for a water closet bend. Use the following steps:
Before cutting, make sure there is enough room to install and support a closet bend.
Completely cut out and remove a section of the joist.
Using boards of the same size, called headers, reinforce the joist. Use two headerson each side of the cut.
Install the closet bend.
78
-
8/14/2019 US Army Plumbing III Waste Systems
85/102
Lesson 2/Learning Event 4
Installing Pipe Runs Through Wall Studs
Cutting wall studs. Always measure before cutting. Use the following steps:
The notch can be cut from the top or bottom half of the stud. A notch cut from the topcannot be greater than of the depth of the stud. A notch cut from the bottom cannot begreater than 1/3 of the depth of the stud.
Make sure the notch can take the pipe size to be installed.
Cut the notch with a handsaw.
79
-
8/14/2019 US Army Plumbing III Waste Systems
86/102
Lesson 2/Learning Event 4
Bracing wall studs. Studs with a notch cut at the top or bottom are braced with steelplates over the center of the notch.
80
-
8/14/2019 US Army Plumbing III Waste Systems
87/102
Lesson 2/Learning Event 4
Lesson 2
Learning Event 4
SELF-CHECK EXERCISE
1. Identify each lettered item in the waste system.
A.B.C.D.E.
F.
81
-
8/14/2019 US Army Plumbing III Waste Systems
88/102
Lesson 2/Learning Event 4
2. What is the maximum depth of a notch that can be cut in the top of a floor joist?
A. 1/3 of joist depthB. of joist depthC. of joist depth
D. 5/8 of joist depth
3. What is the maximum depth of a notch that can be cut in the bottom of a floor joist?A. 1/3 of joist depthB. of joist depth
C. of joist depthD. 5/8 of joist depth
4. What is the right way to reinforce the floor joists for installing a closet bend?Circle A or B.
A.B.
82
-
8/14/2019 US Army Plumbing III Waste Systems
89/102
Lesson 2/Learning Event 4
5. What is the maximum depth of notch cutouts for A and B in the wall stud?
A.B.
6. Which is the right way of reinforcing a notch cut at the top of the joist? Circle A orB.
A.B.
7. What type of material is used to reinforce the wall studs?A. Plywood stripes
B. Wooded cleatsC. Steel platesD. Metal fasteners
83
-
8/14/2019 US Army Plumbing III Waste Systems
90/102
Lesson 2/Learning Event 4
SELF-CHECK EXERCISE SOLUTIONSl. A. Stack
B. Bathtub ventC. Bathtub drain connection
D. Water closet bendE. Lavatory drain lineF. Lavatory drain connectionG. Lavatory vent
2. B. Maximum cut is of joist depth.3. B. Maximum cut is of joist depth.4. A5. A. of stud depth
B. 1/3 of stud depth6. B7. C. SteelplatesIf your responses are the same, GREAT. Continue on with the lesson. If not, go backand review the material.
84
-
8/14/2019 US Army Plumbing III Waste Systems
91/102
Lesson 2/Learning Event 5
Learning Event 5:
SUPPORTING PIPELINE RUNS
All pipe runs, whether vertical or horizontal, must be supported in place. The pipe run's
length, location, and joints will determine the kind of support to use and where to use it.The building material and type of pipe will also determine the kind of support to use.
Kinds of Pipe Hangers and Supports
The following illustration shows a sample of hangers and supports.
85
-
8/14/2019 US Army Plumbing III Waste Systems
92/102
Lesson 2/Learning Event 5
Methods of Supporting Vertical Pipe
Vertical pipe must be supported to keep it in a straight, vertical position. The method ofsupport is determined by the location of the pipe run and joists.
Methods of Supporting Horizontal Pipe
Horizontal pipes must be supported to keep them in line and prevent sagging. Themethod and location of support is determined by the type of pipe and location of the piperuns.
86
-
8/14/2019 US Army Plumbing III Waste Systems
93/102
Lesson 2/Learning Event 5
Lesson 2
Learning Event 5
SELF-CHECK EXERCISE
1. Match each item with its description.Hanger, largeClamp support for vertical pipePerforated bandFloor clamp for vertical pipe
87
-
8/14/2019 US Army Plumbing III Waste Systems
94/102
Lesson 2/Learning Event 5
SELF-CHECK EXERCISE SOLUTIONS1. A. Clamp support for vertical pipe
B. Perforated bandC. Floor clamp for vertical pipe
D. Hanger, largeIf your responses are the same, GREAT. Continue on with the lesson. If not, go backand review the material.
88
-
8/14/2019 US Army Plumbing III Waste Systems
95/102
Lesson 2/Learning Event 6
Learning Event 6:
TESTING THE SYSTEM FOR LEAKS
Once the waste system rough-in is completed, test it for leaks. Repair any leaks found
and retest the system. A water test and/or an air test can be used. Testing must be donebefore the walls are put up.
Using Plugs
Mechanical plugs. To test with mechanical plugs, place the rubber spreader into theopening to be plugged. Expand the rubber spreader by turning the wing nut and/orratchet in a clockwise direction.
Inflatable air plugs. To test with inflatable air plugs, place the inflatable plug into the
opening to be plugged. Inflate the plug with the hand-operated air pump.
89
-
8/14/2019 US Army Plumbing III Waste Systems
96/102
Lesson 2/Learning Event 6
Performing a Water Test
A new system with oakum and lead joints must be filled with water at least 12 to 24hours to allow the oakum in the joint to swell and form a water-tight seal. The system is
then drained and tested. For all types of piping used in a waste system, use these steps toperform the test:
Seal off all openings, except the highest vent opening, with plugs. Threaded pipingcan be sealed off with threaded plugs or caps.
Fill the system with water through the highest vent opening and check for waterleaks.
If the water level drops more than 4 inches in 30 minutes, check the system for leaks.
Remove the water from the system.
Repair any leaks.
Retest
Performing an Air Test
Use the following steps:
With plugs, seal off all openings except one for the test equipment and gage.
Force air through the system until the gage reads 5 pounds per square inch (psi).
Let the air pressure remain at 5 psi for 15 minutes.
Put a soapy solution on the joints to test for leaks.
Release the air.
Repair any leaks.
Retest.
90
-
8/14/2019 US Army Plumbing III Waste Systems
97/102
Lesson 2/Learning Event 6
Lesson 2
Learning Event 6
SELF-CHECK EXERCISE
1. List the two types of plugs used to test a rough-in waste system.
2. When performing a water test on a rough-in waste system, you must check for leaks
after the water level has dropped how many inches in 30 minutes?A. 6B. 5C. 4D. 3
3. An air pressure of how many pounds per square inch (psi) must be maintained for 15minutes during an air test in a rough-in waste system?
A. 8
B. 7C. 6D. 5
91
-
8/14/2019 US Army Plumbing III Waste Systems
98/102
Lesson 2/Learning Event 6
SELF-CHECK EXERCISE SOLUTIONS1. Mechanical
Inflatable2. C. If water level drops over 4 inches, check system for leaks.
3. D. Five psi is applied to system for 15 minutes. If psi drops, check for leaks.If your responses are the same, GREAT. Continue on with the review exercise. If not,go back and review the material.
92
-
8/14/2019 US Army Plumbing III Waste Systems
99/102
Lesson 2/Review Exercise
Lesson 2
REVIEW EXERCISE
1. What materials are used to attach a sewer thimble to the main sewer line?
A. Oakum and leadB. Oakum and portland cementC. Oakum and solderD. Oakum and solvent cement
2. What is the grade slope used to install all horizontal drain waste piping in a rough-inwaste system?
A. inch per pipeB. inch per yardC. inch per footD. inch per joint
3. What types of stacks make up a main stack?A. Soil and waste
B. Soil and ventC. Soil, waste, and vent
93
-
8/14/2019 US Army Plumbing III Waste Systems
100/102
Lesson 2/Review Exercise
4. From the illustration below, what type of vent is used for each lavatory?
A. Wet ventB. Unit ventC. Circuit vent
D. Cross vent
94
-
8/14/2019 US Army Plumbing III Waste Systems
101/102
Lesson 2/Review Exercise
5. What is the correct trap seal for a P-trap between the crown weir and the top dip?
A. 3 inchesB. 2 inchesC. 2 inches
D. 1 inches
6. What is the minimum height required for a cleanout above the floor at the base of astack?
A. 2 inches
B. 4 inchesC. 6 inchesD. 8 inches
7. When installing waste pipe runs, what is the maximum depth of a cut-out notch in afloor joist?
A. 1/3 of joist depthB. of joist depthC. of joist depth
D. 5/8 of joist depth
8. When installing waste pipe runs, what is the maximum depth of a cut-out notch at thebottom half of a wall stud?
A. 5/8 of stud depthB. of stud depthC. of stud depthD. 1/3 of stud depth
9. How many minutes is water kept in a rough-in waste system during a water test?A. 15
B. 20C. 25D. 30
10. How many minutes is air pressure of 5 psi kept in a rough-in waste system during anair test?
A. 25B. 20C. 15D. 10
95
-
8/14/2019 US Army Plumbing III Waste Systems
102/102
Lesson 2/Review Exercise
REVIEW EXERCISE SOLUTIONS1. B (Page 54)2. C (Page 54)3. C (Page 58)
4. B (Page 65)5. C (Page 68)6. C (Page 69)7. B (Page 76)8. D (Page 79)9. D (Page 90)
10. C (Page 90)