US-APWR NRC Questions · US-APWR NRC Questions April 18, 2008 Mitsubishi Heavy Industries, Ltd. 1m1...
Transcript of US-APWR NRC Questions · US-APWR NRC Questions April 18, 2008 Mitsubishi Heavy Industries, Ltd. 1m1...
US-APWR
NRC Questions
April 18, 2008
Mitsubishi Heavy Industries, Ltd.
1m1 EI E S, LTD. 4GG-UAP-20080026-0
NRC QUESTION - Starting Air Capacity (1/3) P"-
> The MHI documents state the starting air system isgood for 3 start attempts. The current StandardReview Plan has a recommendation of enoughair for 5 attempted starts. How is MHI addressing thatdelta?
AeW-t-- HAD ',fO~fl• 4SLI IF. LI~U~UUL~UU~U I
NRC QUESTION - Starting Air Capacity (2/3) (u:
The US-APWR is provided with four (4) 50% GTG.If one GTG is in the test mode (or after testing iscompleted), the remaining three (3) GTG canensure that the plant safety system can bepowered, even if a single failure is considered.Therefore, each GTG has sufficient air to allow forthree (3) start capability.
4GG-UAP-20080026-2SiT._SI _HI -9EAV-Y-I•DM T R I E S, LTD.
NRC QUESTION - Starting Air Capacity (3/3)
> It is assumed that the reasons and basis for sufficient air forfive (5) start requirement are:
- The requirement has been provided for a conventional(typical) NPP equipped with two (2) safety trains.
- Each EDG should be able to be tested. If one EDG is intest, only the other EDG is available to perform its safetyfunction.
- It is preferable that each EDG has air storage for twotimes start capability in consideration of test.
- It is not necessary to assume that a LOOP occurswhile one EDG is tested, but it is necessary to assume that aLOOP occurs after the completion of EDG testing.
- The air receiver should have enough capacity. That isminimum 3 times in addition to above two times. Therefore,EDG should have total about 5 times capability.
1,MLMU81-SH-1-HEA-VzY,--4 ;kU-S-TRIES, LTD. 4GG-UAP-20080026-3I~UBI5~R &V~AU~IDUSL1RIES, LTD. 4GG-UAP-20080026-3
NRC QUESTION - Safety vs. Non-safety GTG (us:]O
(1/2)
e Discuss the difference between safety GTGsversus non-safety GTGs
LM LT,_SUBISH I-HE MY| IDIU.5-T1RIES, LTD. 4GG-UAP-20080026-45
NRC QUESTION - Safety vs.(2/2)
Non-safety GTGO u(.
i ý
Rating
Starting
Location
Fuel Supply & Storage
Qualification
Auxiliaries
4500kW, 6.9kV
Air
Independent
Independent
Class 1E
Independent
4000kW, 6.9kV
DC Power
Non Class 1 E
iý_M1_1M11R1QM1 SAIPAI'V 1Mn11QVn11=C lVff% 4•-I IAP.•NNRNN•R..R3*ITU IR~E~aU~A~V~bI~I ITDE~ I T4 A((GJ AP-29Afl02lfl95
NRC Question GTG - STARTING TIME (1/3) ý713P -4A
EPS starting time: 40 sec starting time for GTGsversus 10 sec staring time for Diesels
Why acceptable for LBLOCA and SBLOCA?
MUMMWOWWW"A-IMPUSTRIES, LTD. %kt-U~r-,&UOU/.uO-0
NRC Question GTG - STARTING TIME (2/3) / "•
•System Design (Cont'd),/Advanced Accumulator
-Automatic switching of injection flow rate by flow damper-Integrates function of low head injection system-Long accumulator injection time allows longer time for safety injectionpump to start
Large flow rate Small flow rate
I Topical Report of Advanced Accumulator was submitted to the NRC I:#,% MTSVPI$HI MEAVY INPUSTRIES, LTD. 4GUP2002-4GG-UAP-20080026-7
NRC Question GTG - STARTING TIME (3/3) •
>CS pumps/Heat Exchangers used for RHRfunctions during shutdown
,/In current PWR plants, RHRS functions as the low head safetyinjection system (Common use of RHR and LHSI)
,/In US-APWR, the function of the low head safety injection(LHSI) is integrated into the Advanced Accumulator and safetyinjection pumps (SIP)
Comparison of Systemssystem US-APWR Current PWR
Cwvainent Spray System CSIRHRS CSS
Residual Heat Removal System CS/RHRS RHRSLHSI .
Low Hoed S•fety hInjecton System Advanced Accumulator RHRS4.HSIand SIP
Accumultor Injection System Advanced Accumulator Accumulator
High Head Safety IrI/etion System SIP SIP
*w--_&#,W M-' -_ U - V-ibL V-T NPt I KIIa, LTD. 4GG-UAP-20080026-8
NRC Question -of GTG (1/6)
Governor and Excitation S--
- Discuss the excitation and governor systems ofthe gas turbine
#4iTSURISHF.EAVY INDUSTRIES, LTD. 4GG-UAP-20080026-9
Governor(2/6)
TYPICAL OPERATION. TIMING CHART
S Typical Timing Chart Of Operation
NOteSupphed with QPS1250or largal rnodel
- 70% rpm iOo GPS250and GP8500
-70 sac. og G1PS250and GPS50D
The required time to confirm the black out.
LTD. 4GG-UAP-20080026-10
Governor(3/6) QUs- -1kP4
~z2a.
004 41001440~~~~
cI~~] ~
C® I507I1~0001040154b
10141 400 414 401 510911 1540
Ez~~1~ .4441 044 1w544954550.011
407014 41ne.~.2M1A
1404 4~50.0.0
ED 144,..54 15000 4414 954154*1 005 1540.
loflI 411145 40540911 1140.
C® 44-40
o-X lsvoslon.oonh400aooow
140 515400444as
110041414 1154. 0044444094041400e514-451 .t±1AS20405
k4051 - P401 4040455090401
5454440 I.4.0 ISIS
04.00541404400444.
1i011TWSIUMH -HIrAV-T--IH PU 5 T KI 5, LTD. 4GG-UAP-20080026-11
Governor(4/6)
GTO P-S
4GG-UAP-20080026-12
Governor(5/6)
FuelV-p
___-Erý Contrco Boy
0 Fu
02t
etConitra Vatve
i' Fuel PuripNory S~ý av
ver Set- peed fl5xd6 etMso
KIPo•
Gox e',rnor Systom
*MRT$UBISHI 14FAVY INDUSTRIES, LTD. 4GUP2002-4GG-UAP-20080026-13
Voltage Regulator (6 of 6)!AP]W
Brushless Exciter
/Eliminates maintenance associated with brush typegenerator field
> Permanent Magnet Alternator
/ Supplies continuous power to Voltage Regulatorv/ Superior motor starting capabilities
Static Voltage RegulatorV- Two AVRs supplied, manual and automaticv/ Voltage regulator motor operated potentiometersV Overexcitation protection/ Underfrequency/Overvoltage Protection
II
-IU HI-HEAv-Y-NDUSTRiES LTD. d(~~IJAP-2OflRflfl2R-id4GG-UAP.20080026.14
i
NRC Question - Droop & Isochronous modesfor G TG (1/3)
/-US
> Droop Operation - GTG operating parallel to thegrid. Speed control is a governor function whichreduces the governor reference speed as enginefuel position (kW load) increases and vice versa,increases the governor reference speed asengine fuel position (kW load) decreases.
> Dsochronous Operation - GTG operating on itsSafety Related Bus. Isochronous speed control isthe ability to return to the original engine speedafter a change in kW load.
LTD.4GG-UAP-20080026-15I1RI$HI~HEAVY..INPU5TRIES. LTD. 4GG-UAP-20080026-1 5
NRC Question - Droop & Isochronous modes ... "
for GTG (2/3)
IEEE 387- 2001> 4.5.1.4 Governor operation
If the diesel engine is equipped to operate in both theisochronous and the droop mode, provisions shall be
included to automatically place the engine governorin the proper mode of operation when the dieselgenerator unit is required to operate automatically(see 4.5.2.2).
MI.SjJBISH•I__E YN PPu.S$!RELES, LTD. 4GG-UAP-20080026-16
NRC Question - Droop & Isochronous modesfor GTG (3/3)
IEEE 387- 2001
; 4.5.2.2 Automatic control
iii
Upon receipt of an emergency start-diesel signal, theautomatic control system shall provide automaticstartup and automatic adjustment of speed andvoltage to a ready-to-load condition.
.a) A start-diesel signal shall override all otheroperating modes and return control of the dieselgenerator unit to the automatic control system.
b) An emergency start-diesel signal shall notoverride any manual non-operating modes such asthose for repair and maintenance.
MM I T S A M M_ " 1, H_ E-AX-Yz- I DQ -S-T-5 ki E S, L T D.4GG-UAP-20080026-17-~Mfl3UBISHIHEAV-Y4NDUSTRIES. LTD. 4(~4J AP-2OORflfl2~-1 7
NRC Question - Reliability Analysis (1/4)
A discussion on the Reliability Analyses
ýAPS4
XWWHI9WM-_;P~t,50~kISLTD. ACr.r.l IA P._9AAnRAA9RAA R
NRC Question -Reliability Analysis (2/4) Q
More than 6000 units of GPS Gas Turbine serieshave been supplied in worldwide facilities. TheGPS Gas Turbine series had been developedaiming at Emergency or Backup generator usage.They are designed so that not only performancefor power operation may be ensured but alsoreliability required of emergency start beachieved.
ý,MI-I-SUOISHI-MkV . XIKýC-INWQS IES, LTD.4GG-UAP-20080026-19~MLTSUBISHE-HEAV-Y~INDUSTRIES. LTD. £l(~-IJ AP-2OARnO2R-1 Q
NRC Question- Reliability Analysis (3/4) -
GPS GTG Packages have industrial based fielddata available for estimating the startingreliability collected from starting eventsconfirmed, as shown in table 7.2-1.
V Number of Units 375/ Start Attempts 7394V Failed Starts 2
Based on the field data, starting reliability isestimated as below;
(1 - 217394) x 100 = 99.97%3.0 x 10-4 per demand
Sl3 TUSHUI-HEAVY.-!NDU ST R!ES, LTD. 4GG-UAP-20080026-20
NRC Question - Reliability Analysis (4/4)
> The probability'of failure to start of the EPS GTGis lower than that of any DGs (3.5 x 10- perdemand) as reported in NUREG/CR-6928"Industry-Average Performance for Componentsand Initiating Events at U.S. Commercial NuclearPower plant, February 2007".
1__M1,_TSURMHVHEJW- --I T IES, LTD.ý:_Y 9jQ5_ _k4GG-UAP-20080026-211.1SUBSHIHEAVNJNDJJSLTRIES. LTD. 4GG-UAP-20080026-21
NRC Question - GTG Fuel
Fuel specifications for the gas turbine and howthey might differ from the fuel used in dieselgenerators.
:AEPS 4
The KHI GTG can use:a. #2 Diesel Fuel (low sulfur fuel)
b. Kerosene
A decision was made to use typical #2 Diesel Fuel.Therefore there is no difference between GTG andDG in the type of fuel used.
T-.s tI.mTmH-;B_ = HAY!_U$_TsrR1ES, LTD. 4GG-UAP-20080026-22
NRC Question- Site Testing (1 of 3)
On-site testing requirements of RG 1.9, Positions2.2 and 2.3; RG 1.41, Position 1 and 2; andrequirements of Section 7, "Site Testing" of IEEE-387.
LNI:XU01ýSHI, i X IES, LT6.RAX_,jjM9kUSjrR_ 4GG-UAP-20080026-23~L,~IE~IIBJ~J.ILHEAVY.INDUSTRIES, LTD. 4GG-UAP-20080026-23
NRC Question Site Testing (2 of 3)
Site Testing
QA A
/ IEEE 387 Section 7.2, RG 1.9 Section 2.2
" Site Acceptance Testing
" Pre-Operational Testing" Periodic Testing (ongoing)
/Tests occur at site after final assembly
v/ ESI simulates many of the tests at factory
v/ Final performance of site testing by utility withMHI/KHI/ESI oversight as required
K ML? i IRcuELn IMAivy lEliE • iCf l 1"1 A(.r .. 1 ]AP.•tflARNfl9R-9A•5,•.a: illii +almall ~ l iI llWV,.l • iikalr..,.• ll . v v A l -200vvvv -- 2
NRC Question Site Testing (3 of 3)
Rde-e,.se: T..t Site Pr. Ar flnbLUte 1e-t% Stt, m J.drp..denc,IEEE 387 ses-ptes.. rpretikn,,t (7.4.2.1) speeltie ttf
Cas:t~f, tests (Ss,.te~lse.) tests: t0 yr.s
(SW. (7..1)1 sbutd- o (7.4.L,)'MnI~thty 6 MoottO nt~elisg
57.4.7.2)*
77.+2 Stottiro X X
72.1.1 Losd x X
T2.L.1 tt8 4•a. d x X
7.'a14 Load Rgt~n. X
7.21.6 Subt x
7 3.3 Rediawflil, X
73.t. Startt X6 X
7.5.M Fted R-e X 76
7.5.3 Ft btS- 76 x
7.M,4 LOOP X x
75.5 SIAS 7
7.Z.6 C-tshin X 7
715.7 Soge -,Ld x X
7,5.8 DtiIntoad X 7
7.5.9 ad-cs -d Vo 7
7.5.!o Ho!etz x x
7 tt I S ho-i-g X X
73.5.12 Ptottttt-, trip x x
.5.t3 Test xdr X X
745.14 ltdeesd- X 7
SiUu 7 d. 2 b
/_037
I-- ý10IF
Table 1 taken from RG1.9 Rev. 3, & IEEE-387
I'll Ild 111-1111
U11 IES, LTD.1AH__1=_HKAV=Y 4GG-UAP-20080026-25~MI~SUBISHI-HEAV~INp3J.S1RIES, LTD. 4GG-UAP-20080026-25