PRESENTER: Helena Itamba Ministry of Mines and Energy URANIUM MINING PROJECTS RAF 2011, Workshop on Application of United Nations Framework Classification, JHB, RSA, 10-14 November 2014

Transcript of URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o...

Page 1: URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o Environmental Approvals Granted o 6-9 Mlbs U3O8 annual production over a 15 year LoM; o Plans

PRESENTER: Helena Itamba

Ministry of Mines and Energy

URANIUM MINING

PROJECTS

RAF 2011, Workshop on Application of United Nations Framework Classification, JHB, RSA, 10-14 November 2014

Page 2: URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o Environmental Approvals Granted o 6-9 Mlbs U3O8 annual production over a 15 year LoM; o Plans

BACKGROUND

oSeveral uranium projects delayed due to depressed market conditions following the Fukushima incident;

oLHU mine reported record production following three years of operational los;

oRUL return to profitability due to implementation of several cost reduction exercises;

oAreva Namibia continued care and maintenance;

oConstruction of the Husab mine ongoing despite the adverse market conditions;

oSix licensed uranium mines.

Page 3: URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o Environmental Approvals Granted o 6-9 Mlbs U3O8 annual production over a 15 year LoM; o Plans

LOCALITIES OF URANIUM MINES

Page 4: URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o Environmental Approvals Granted o 6-9 Mlbs U3O8 annual production over a 15 year LoM; o Plans

GRADES (PPM)

ValenciaTrekkopje

Husab

EtangoMarenica Rossing Langer Heinrich

Tubas/Tumas/Omahola

Ida Dome0

100

200

300

400

500

600

0 100 200 300 400 500 600 700

Co

nta

ine

d m

eta

l (M

lb

s)

Grade (ppm)

Page 5: URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o Environmental Approvals Granted o 6-9 Mlbs U3O8 annual production over a 15 year LoM; o Plans
Page 6: URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o Environmental Approvals Granted o 6-9 Mlbs U3O8 annual production over a 15 year LoM; o Plans

Rossing Uranium Limited

Langer Heinrich Uranium

Trekkopje (Areva)

Valencia Swakop Uranium (Husab)

o Lower throughput lead to lower production volumes;

o Drilling completed on Z20, 142 holes

o Investigating economic methods on how to extract ore from Z20

o Temporary shut down of milling operation during December –January due to leach tank failure.

o July CNNC , overseas Uranium Holding acquired 25% stake;

o Construction and commissioning of stage 3 complete;

o Currently operating in excess of name plate capacity of 5.2 mlb;

o Stage 4: feasibility to increasing production up to 8.7Mlb U3O8 pa expansion to increase production capacity;

o No exploration activities during 2013.

o AREVA has decided to postpone the Trekkopje Project, which is not economically minable at the present time as a result of poor prevailing conditions in the uranium market.

o Care and maintenance phase since July 2013

o 48 employees 3km in length, 810m width, 36M t of uranium ore per year

o Consolidation of two neighbouring projects;

o Completed drilling program

o Metallurgical test results with higher recoveries

o Environmental Clearance for all aspects of mine construction, operation and closure granted

o Results of a positive engineering cost study for the Norasa Uranium processing plant released.

o Measured and Indicated Resource: 103 Mlbs at 197 ppm U3O8

o Proved and Probable Reserve: 79 Mlbs at 202 ppm U3O8

o Estimated Inferred Resource: 50Mt at 198ppm for 22 Mlbs of U3O8

o Pre-stripping has commenced

o The plan is to ensure that a Run-of-Mine (ROM) stockpile will be ready for processing on completion of the processing plant.

o Annual production capacity 15 Mlbs;

o LoM 20 years.

Page 7: URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o Environmental Approvals Granted o 6-9 Mlbs U3O8 annual production over a 15 year LoM; o Plans

U3O8 ANNUAL PRODUCTION (ST)

0

1000

2000

3000

4000

5000

6000

2005 2006 2007 2008 2009 2010 2011 2012 2013

Page 8: URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o Environmental Approvals Granted o 6-9 Mlbs U3O8 annual production over a 15 year LoM; o Plans

DRILLING AT VALENCIA EAST

Page 9: URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o Environmental Approvals Granted o 6-9 Mlbs U3O8 annual production over a 15 year LoM; o Plans

SWAKOP URANIUM

Blasting Production process

Page 10: URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o Environmental Approvals Granted o 6-9 Mlbs U3O8 annual production over a 15 year LoM; o Plans

ZHONGE RESOURCES oThe Mining Licence was

granted during December

2012;

oreserves of metal U is 40,800 ton, and the average grade

of U3O8 is 185ppm;

oconstruction of the project

was expected in 2015 and the

first product 2018;

oApplied for Mineral Deposit

Retention licence;

oMine construction currently

put on hold.

Page 11: URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o Environmental Approvals Granted o 6-9 Mlbs U3O8 annual production over a 15 year LoM; o Plans

Advanced

Exploration Projects

Page 12: URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o Environmental Approvals Granted o 6-9 Mlbs U3O8 annual production over a 15 year LoM; o Plans

BANNERMAN RESOURCES

o Completed Etango DFS and EISA;

o Environmental Approvals Granted

o 6-9 Mlbs U3O8 annual production over a 15 year LoM;

o Plans underway to construct a demonstration plant by 2015 which will be operated for one year.

Page 13: URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o Environmental Approvals Granted o 6-9 Mlbs U3O8 annual production over a 15 year LoM; o Plans

Stage three crushing

Page 14: URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o Environmental Approvals Granted o 6-9 Mlbs U3O8 annual production over a 15 year LoM; o Plans

Conventional Sulphuric Acid Heap Leach Plant

Page 15: URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o Environmental Approvals Granted o 6-9 Mlbs U3O8 annual production over a 15 year LoM; o Plans

Reptile Uranium-

Deep Yellow

o Multiple deposits

o Pit optimisation and mining cost studies

o Comprehensive Metallurgical test work must still be conducted;

o 12 year LoM, 2.2 Mlbs production rate per annum ;

o Conventional acid leach with solvent extraction;

Page 16: URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o Environmental Approvals Granted o 6-9 Mlbs U3O8 annual production over a 15 year LoM; o Plans

RESOURCES

Page 17: URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o Environmental Approvals Granted o 6-9 Mlbs U3O8 annual production over a 15 year LoM; o Plans

Tubas Sand

Project

o Mineral

resource totals

24Mt at 170

ppm for 12.7

Mlbs U308 at

100 ppm U3O8

cut off;

Bulk sample trench

Page 18: URANIUM MINING PROJECTS - UNECE · BANNERMAN RESOURCES o Completed Etango DFS and EISA; o Environmental Approvals Granted o 6-9 Mlbs U3O8 annual production over a 15 year LoM; o Plans

CHALLENGES o Low Uranium Price;

o Downsizing to contain cost which lead

to the retrenchment of workforce;

o Rising input costs;

o Uninterrupted supply of water and

electricity.