Upstream, Produced WaterTreatment
© Siemens AG 20XX All rights reserved.
• Top tier oil producer• Deep water offshore platform• New construction
Produced Water SolutionOffshore Deep Water
Customer name
Challenge
• A compact produced water treatment system• Less that 5 ppm effluent discharge• Reduced operation expense
§ 85,000 BPD treatment capacity§ 2,000 ppm free oil & grease influent§ 5 ppm and less free oil and grease effluent
Project description
© Siemens AG 20XX All rights reserved.
Produced Water SolutionOffshore Deep Water
• Liquid/Liquid Hydrocyclone• No moving parts
• Spinsep flotation vessel with DGF Bubble maker• Compact Footprint• Most efficient form of flotation
• Walnut shell filter for water polishing• A renewable media filter• Internal backwash system• No moving parts
Implemented products and services
Reason for choosing Siemens
• Reduced operation expense by using a renewablemedia for water polishing
• Compact solution where a limited footprint wasavailable
© Siemens AG 20XX All rights reserved.
Ecopetrol, STAP 3 and 4 site
Ecopetrol
Challenge
Objectives
• A turnkey solution from a single supplier
• A 480,000 bpd produced water treatmentsolution
• Delivered in 40 weeks from date of PO
• Ecopetrol• STAP Sites in Colombia
Colombia
Colombia
© Siemens AG 20XX All rights reserved.
Produced Water SolutionEcopetrol, Colombia
Implemented products
• Offering:• Corrugated Plate Separator• Induced Gas Flotation• MonosepTM High-Flow Walnut Shell Filter
• Project Location: Colombia• Project Capacity: 480 MBPD• Date of Award: 2012• Date of Operation: 2nd Quarter 2015
Solution Benefits
• Less equipment on site• Lower total installed cost• Lower operational expense• Ease of operation• One supplier for coordination
© Siemens AG 20XX All rights reserved.
Reduced Design and Installation Cost
Project Summary
Challenge
• A custom solution that could be ordered multipletimes over a span of 10 years
• Recurring order every 12 to 18 months withminimal design changes per order
• Canadian oil producer• SAGD recovery method• Objective was to decrease project execution
costs and total ownership of water treatmentfacility
• Strategy was to replicate a plant, with minimaldesign changes and decrease the total installedcost by 20%
Fort McMurray, Canada
Fort McMurray,Canada
© Siemens AG 20XX All rights reserved.
Reduced Design and Installation Cost
Facts and figures
Reason for choosing Siemens
• Siemens was able to meet the client’s requirementof a custom solution
• Decrease the client’s delivery time• Decrease capital expenses by 8%• Decrease operation expense by 12%
• Flow Rate: 135,000 BPD• Performance:
• Influent: 200 ppm• Effluent:< 20 ppm• Low API oil: API 8 to API 13• Design Temp: 90 Deg. C.
© Siemens AG 20XX All rights reserved.
Sulphate Removal
Page 8
© Siemens AG 20XX All rights reserved.
Sulfate RemovalCustomer Challenges
Page 9
Example of scaling in piping
Mixing injected and formation water may result insulfate/barium scaling
• Limit formation of barium and strontium saltsin injection well, piping and equipment
• Production well control• Radioactive scaling or NORM• Allows anti-scalants to perform on full
effectivenessReservoir Souring
• Limit well souring at water breakthrough as NFremoves all contaminants grater than 1/1000thsof a micron
• Reduce environmental safety & health issuesby less chemical injection
• Lower level of hardness (magnesium/calciumions)
© Siemens AG 20XX All rights reserved.
Sulfate Removal
Page 10
Benefits
• One of the original Dow/Marathonmembrane suppliers – having 17 years ofexperience
• Compact system design• Single source turnkey supply
Scope of Supply• Dow SR membranes (external
technology)• SRU train with valves/instruments• Cleaning in Place (CIP) package skid• Feed booster pumps• Loose skids or module with pre-
treatment
Treatment
• Removes sulfate from seawater toprevent scaling caused bybarium/strontium in the formation water
• Nano-filtration spiral wound membranesremoves sulphate ions down to 15 ppm
• Reduces risk of souring in the reservoir
© Siemens AG 20XX All rights reserved.
Sulfate Removal
Page 11
SIEMENS UF OFFSHORE REFERENCES
Nexen (UK) Inc. / Golden Eagle Wellhead platformLOCATION: Coast of UKSTART-UP: 2Q 2014CAPACITY: 990 m³/hDESIGN:: SCUF60 7 x 17% units, Siemens Memcor L20membranesAPPLICATION: Seawater pre-treatment to Sulfate Removal System
Samsung H.I. & Teekay / BG Knarr FPSOLOCATION: Coast of NorwaySTART-UP: 1Q 2014CAPACITY: 990 m³/hDESIGN : SCUF60 7 x 17% units, Siemens Memcor L20membranesAPPLICATION: Seawater pre-treatment to Sulfate Removal System
Lundin ASA / Edward Grieg platformLOCATION: Coast of NorwaySTART-UP: 2Q 2015CAPACITY: 390 m³/hDESIGN : SCUF60 4 x 50% units, Siemens Memcor L20membranesAPPLICATION: Seawater pre-treatment to Sulfate Removal System
• First onshore UF installation forseawater service in 1995
• Several hundred UF systems asseawater pre-treatment to ROmembrane plants onshore
• 17 years of onshore operationalexperience
• A “fit for purpose” offshore system(SCUF) was re-designed and tested2009-2011
• First offshore contract for SCUFsigned April 2011