UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

download UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

of 285

Transcript of UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    1/285

    " UPS Distribution System" UPS Distribution System

    andand

    UPS FundamentalsUPS Fundamentals

    In The Petrochemical IndustIn The Petrochemical Indust

    Presented to the:

    IEEE PCIC 2006 Conferenc

    Philadelphia, Pennsylvania September 14, 200

    Presenters:

    Roy E. Coss, Jr., P.E. Donald G. DunnPowell Electrical Systems, Inc. Lyondell Chemicals P

    Houston, TX Channelview, TX

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    2/285

    TuTu

    Introduction (general, historical perspective) Purpose of a UPS

    UPS system (types, configurations, trends, redundancy, hoperation)

    Battery selection

    Magnetic components used in UPS systems (feisolation and constant voltage transformers, re

    UPS system application (system design and integratioof distribution and protection equipment in Usecondary networks)

    Review load types and design application cons

    Power system analysis and harmonic consideratypical applications

    System acceptance (testing, commissioning, performanmaintenance)

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    3/285

    IntroductionIntroduction

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    4/285

    UPS systems installed in petrochemical faciprovide uninterruptible power to process costandby and other critical equipment. Accepinstallation, verification and maintenance asis continuously available. This intensive haltutorial provides the needed background to understand UPS distribution systems and Uapplications in petrochemical industry appli

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    5/285

    Historical PHistorical P

    UPS Distribution Systems Are Copied FromProject To The Next

    Industry practice

    This is the way we have always done it

    Time-Current Curves not produced Internal protective device not considered

    System selectivity not reviewed

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    6/285

    Historical PHistorical P

    UPS Systems Supply Critical Process Load

    DCS & PLCs

    Critical Process Alarm Systems

    SIS Systems

    APC & Custody Transfer Systems Process Analyzers

    Gas Detection Systems

    Fire Protection Systems

    Critical Telephone Circuits

    Emergency Lighting Custom Load and Driver Control Systems

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    7/285

    What is the PurposeWhat is the Purpose

    Uninterruptible PowUninterruptible PowSystem (UPS)?System (UPS)?

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    8/285

    It is a modular unit or assembly of componenprovide quality and continuity of AC power fmanufacturing unit or units

    Note: The MAJORITY of instruments, process me

    process control devices rely the UPS for electrical e

    In many instances, a UPS provides AC powerequipment that is deemed MISSION CRITIC

    Safety

    EnvironmentalReliability & Operational Cost

    Purpose of a Uninterruptible Power

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    9/285

    Critical Crit ical

    Not all instruments and control devices are critical If the LOSS of an instrument or control system creates a ha

    condition, can cause an environmental incident, or trips a pis typically deemed a CRITICAL device or system.

    Examples

    Process Measurement DevicesTransmitters and Switches used in process control

    Basic Process Control Systems (BPCS)DCS, PLCs etc.

    SIS Systems

    Non-critical InstrumentsExamples

    Process Measurement Devices that are for indication only

    BPCS for non-critical control

    Purpose of a Uninterruptible Power

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    10/285

    Critical PowCritical Pow

    ComplexMultiple Power Supplies

    Can be 120 VAC powered 24 VDC sources

    UPS System

    Batteries

    DistributionShort Circuit Protection

    Typical Power Source Motor Control Cente

    Thermal-Magnetic Breaker

    Single Transformer

    Typically Double-Ended without Automatic Switch

    Separate Power Sources for increased reliability

    (i.e. Separate Feeders from Separate Transforme

    the Main Substation)

    Purpose of a Uninterruptible Power

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    11/285

    Critical Power System ExCritical Power System Ex

    Provides Reliable Power

    Maintains Critical Loads During AbnoSituations

    Disturbances such as sags, swells, surges

    Short Circuits

    Maintenance can be provided online

    Purpose of a Uninterruptible Power

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    12/285

    What is a UPS?What is a UPS?

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    13/285

    TypTyp

    Management and Operations Believe it

    Unreliable Power System

    Trips process units during maintenance

    Unavailable Power System

    System that has unlimited capacity

    OR ALL OF THE ABOVE!

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    14/285

    UPS Actual CoUPS Actual Co UPS Components

    Rectifier/Charger

    Inverter

    Ferro & PWM Technologies

    Alternate Input

    Static Switch Manual Bypass Switch

    Battery

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    15/285

    RectifiRectifi

    Rectifier/Charger Full-wave controlled rectifier for changing

    Typically it is a phase-controlled, silicone

    rectifier circuit combined with a voltage re

    Provides voltage and current control ofoutput

    Feeds the battery system

    Feeds the UPS inverter

    Appropriately Sized Sized for load and to charge the batter

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    16/285

    Inverter The inverter converts a DC waveform (supplied by

    Rectifier/Charger/Battery) into an AC waveform

    Output will be supplied to either the load terminals

    the static transfer switch (depends of system config

    There are two different technologies to accom Ferroresonant

    Norm for many years

    Larger System

    Commutated square wave bridge with an oscil

    filtering components PWM (Pulse Width Modulation)

    Utilizes solid-state power electronic devices

    Minimum parts count and reduced magnetic el

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    17/285

    FeFe

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    18/285

    UU

    Cybe

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    19/285

    UU

    SCI

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    20/285

    AlternAltern

    Alternate Source Redundant Power to UPS system

    Inverter synchronizes to Alternate Source

    Waveforms are in sync (eliminates tran

    Power Source During the Following: Inverter fails

    Normal Power Source is lost

    And battery system is discharged

    Short-circuit or overload conditions Provides BYPASS power for off-line main

    the Rectifier and Inverter

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    21/285

    ManuManu

    Manual Bypass Permits the power to flow from the alterna

    the load by bypassing the Inverter and Sta

    Permits UPS isolation

    Permits maintenance to be performed on thcomponents

    Permits start-up and shut-down of the syst

    Can be internally or externally mounted

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    22/285

    AlternatAlternate

    Manual Bypass SwManual Bypass Sw

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    23/285

    ManuManu

    SwSw

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    24/285

    WhaWhat

    Static Switch FAST acting

    Typically can transfer within cycle (4 m

    Is supposed to transfer output power from

    to the Alternate Source without any power

    Transfer normally at the zero-wave crossin

    waveform monitoring

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    25/285

    Input CircuInput Circui

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    26/285

    Meters and MMeters and M

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    27/285

    PP

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    28/285

    UPS SYSTEMSUPS SYSTEMS

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    29/285

    System Types

    Hardware Components / Block Diagr

    Configurations

    Redundancy

    Applicable To Petrochemical Industry

    TopicTopic

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    30/285

    System Types (from energy storage p Static (chemical energy)

    High Efficiency, High EMI / THD pollution

    High Reliability and Availability

    Most popular

    Poor performance with non-linear/non-balanced

    High Cost to achieve very high reliability Rotary (kinetic energy)

    More reliable than Static UPS

    Availability lower from Static UPS

    Large size

    Electro-mechanical i.e. involved maintenance

    Desirable for high power and/or non-linear/non-bapplications

    High transient overload capabilities

    High efficiency, Low EMI / THD pollution

    Hybrids (of static, rotary and engines) (mixture o

    SysSys

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    31/285

    System Types (from switching perspe Dual Conversion

    On-Line UPS

    Off-Line UPS

    Single Conversion Line-Interactive UPS

    SysSys

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    32/285

    Static, On-Line UPS

    StatiStati

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    33/285

    Static, Off-Line UPS #1

    StatiStati

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    34/285

    Static, Off-Line UPS #2

    StatiStati

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    35/285

    Static, Line-Interactive UPS #1

    StaticStatic Line Line

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    36/285

    Static, Line-Interactive UPS #2

    StaticStatic Line Line

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    37/285

    Rotary UPS

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    38/285

    Hybrid, Static-Rotary UPS

    HybridHybrid StSt

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    39/285

    Most Popular Industrial Systems Con On-Line

    Technology

    Ferroresonant

    PWM

    Magnetic / PWM Hybrid / Active Filter / PFC Re

    Power

    1-phase (< 5-10kVA)

    3-phase (>15kVA)

    Galvanic Isolation

    Redundancy

    2x100% or 3x100% Feed-Through

    Trends in IndustriaTrends in Industria

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    40/285

    2x100% or 3x100% with load sharing

    ReRe

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    41/285

    2x100% with load sharing, with galvanic is

    ReRe

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    42/285

    Typical of OneTypical of One

    Rectifier

    Inverter

    StaticSwitch

    MBS

    AltSourceInputBattery

    Set

    OutputCircuit

    Breaker

    InputCircuit

    Breaker

    UPS System Limitations Difficult to Replace

    All Output Power

    Runs Through MBS

    Not all components

    can be PMd orRepaired

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    43/285

    AlteAlte

    ConfiConfigthe samethe same

    Second TapAlternate SCan Backfe

    Distribution

    Controvers

    Allows for ComponentReplacing ESystem witOutage

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    44/285

    AlteAlte

    CoCoof Anotheof Anothe

    Second TapAlternate Sfeed into se

    Distribution

    Allows for ComponentReplacing ESystem wit

    Outage

    Rectifier

    Inverter

    StaticSwitch

    MBS

    AltSource

    InputBatterySet

    OutputCircuit

    Breaker

    InputCircuit

    Breaker

    AltSourceXfmr

    UPS System

    Custom Distribution

    Panel (Dual Mains w/

    independent branch

    circuits)

    UPS System

    480V Distribution

    Sources (segregated

    from main substation)

    A B

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    45/285

    Feed-through, concept

    ReRe

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    46/285

    ReRe

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    47/285

    BATTERY SELECTIONBATTERY SELECTION

    UPS SYSTEMUPS SYSTEM

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    48/285

    Battery Selection F

    Battery

    Battery Basics (definitions, technologyconstruction, sizing and capacity)

    Battery Comparison

    Other Considerations

    Maintenance

    Derating

    Standards

    Hydrogen Emission Generation

    TopicTopic

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    49/285

    Battery Selection F

    BatteryIn general, storage of electrical energy requireconversion into another form of energy. A Badevice that uses chemical compounds as the smedium. During discharge, a chemical procesthat generates energy, which can be drawn fro

    battery in the form of an electric current at a cvoltage.

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    50/285

    BatterBatter

    Battery Selection F

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    51/285

    BatterBatter

    Battery Selection F

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    52/285

    BatterBatter

    Battery Selection F

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    53/285

    Voltage - Force which puts electrons into motiNominal Battery Voltage Voltage measured battery terminal which represents the average va discharge period

    End of Discharge Voltage (Cut-off Voltage)

    which the battery discharge is terminated Maximum System DC System Voltage Max

    voltage which can be tolerated by the loads

    Minimum System DC Voltage Minimum Vowhich the loads will continue to operate

    Nominal System Voltage Arbitrary equipmewhich has been standardized by NEC (12, 24, 110, 220, 240, 360 or 480V)

    Battery Selection F

    Battery BasicsBattery Basics --

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    54/285

    Battery Selection F

    Battery BasicsBattery Basics -- TT

    Nickel Cadmium Battery Discharge Profile

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    55/285

    Battery Selection F

    Nickel Cadmium Battery Discharge Profile

    Battery BasicsBattery Basics -- TT

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    56/285

    Battery Selection F

    Deep Discharge

    Lead Acid Battery cycle life is limited to less than 15

    discharge cycles (The more you discharge the battery th

    will reach the end of life)

    Discharge below 1.8 volts per cell can permanently d

    acid batteries

    Battery will sulfate causing higher internal resistancapacity

    Severe deep discharge for extended periods of time

    internal short circuit failure

    For short durations, the end of discharge voltage may

    if the discharge is followed by an immediate recharge:

    Battery BasicsBattery Basics -- TT

    1.65 1 HOUR OR LESS

    1.70 3 HOUR OR LESS

    1.75 5 HOUR OR LESS

    1.80 8 HOUR OR LESS

    END OF DISCHARGE

    VOLTAGE

    DISCHARGE

    RATE

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    57/285

    Battery Selection F

    Proper Sizing and Cell Selection (Most ImportaVoltages Required)

    Maximum System DC Voltage (Determines the max

    number of cells that can be equalize charged without da

    loads)

    Minimum System DC Voltage (Determines the end

    voltage)

    Both of the Following Equations Must be True

    Battery BasBattery Basi

    sMax.DCVolt cellltsEqualizeVo

    ofcells

    /

    #

    DCVoltsMin. = geVolraEndofDisch

    ofcells#

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    58/285

    Battery Selection F

    Float Charging Voltage Normal float charginmaintains a steady float charge to keep the battcharged

    Equalize Charging Voltage Elevated charginused to fast charge the battery or as a maintena

    Boost Charge Charging elevated above an eqcharge for reviving a battery after manufactureabuse

    Battery BasicsBattery Basics --

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    59/285

    Battery Selection F

    Capacity Measure of the usable energy that cdischarged from a battery (typically the larger tthe more active material to create energy)

    Capacity is a Function of:

    Temperature

    Discharge RateVoltage Window

    Battery Age

    State of Charge

    Note: The slower the battery discharge, the more

    energy can be extracted from the battery

    Battery BasicsBattery Basics

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    60/285

    Battery Selection F

    Capacity varies by end of discharge voltage:

    Battery BasicsBattery Basics

    [ ]min60/1min1 hr amps 92.9595 =

    [ ]min60/1min1 hr amps 32.5319 =

    Amps X the time period, the more capacity is the lower end voltage: 1.00 EODV: at 60 seconds

    1.14 EODV: at 60 seconds

    Amps to 1.00 EODV

    Cell 8 5 60 5 1

    Type hr hr min min min s

    SBM231 29.1 46.2 173 427 595 8

    Amps to 1.14 EODV

    Cell 8 5 60 5 1

    Type hr hr min min min s

    SBM231 27.7 43.4 105 228 319 4

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    61/285

    Battery Selection F

    Battery BasicsBattery BasicsNickel Cadmium Battery Discharge Profile

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    62/285

    Battery BasicsBattery BasicsNickel Cadmium

    Deep Discharges DO NOT Affect Performance and

    Permanent Damage to NICADS

    Allows Long Term Open Circuit Storage

    Nickel Cadmium Offer the Most Deep Cycles (Full

    Discharges) of any Technology Available:

    Battery Selection F

    TECHNOLOGY # OF CYC

    Sintered/PBE NICAD > 20

    Pocket Plate NICAD > 15

    Flooded Plate Calcium approx . 50

    Flooded Plate Antimony 600-8

    Flooded Plate Selenium 600-8Flooded Plante' 600-8

    Valve Regulate Lead Acid approx. 50

    * TO 80% DEPTH OF DISCHARGE

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    63/285

    Battery Selection F

    Battery BasicsBattery Basics

    Capacity varies by rate of discharge: Using thagain, more usable energy is extracted at slow

    1.00 EODV at 60 seconds:

    [ ]min60/1min1 hr Ahrsamps 92.9595 =

    [ ]hr8 Ahrsamps 8.2321.29 =

    1.00 EODV at 8 hours:

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    64/285

    Battery Construction

    Battery Components

    Case or Jar

    Each Jar Typically has 3-4

    Cells

    Electrolyte

    Grid or Current Collector

    Active Material

    Separator

    Battery Selection F

    - +

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    65/285

    Battery BasicsBattery Basics

    Lead Acid Chemical Reaction

    Battery Selection F

    Discharge

    PbO2 + Pb + 2H2SO4 2PbSO4+

    Charge

    - + - +

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    66/285

    Battery BasicsBattery Basics

    NiCad Chemical Reaction

    Battery Selection F

    Discharge

    2NiOOH + Cd + 2H2O 2Ni(OH)2+ Cd(OH

    Charge

    - + - +

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    67/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    68/285

    Battery Selection F

    Plate construction

    Plant Plate Grid Plate Tubula

    Battery BasicsBattery Basics Lead Acid CoLead Acid Co

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    69/285

    Electrode Materials of Construction: Pure Lead

    Lead Selenium

    Lead Antimony

    Lead Calcium (Ag, Sn, Zn, Mg)

    Alloys in the lead current collector offer NO teadvantage

    Used to reduce manufacturing costs by makingeasier to mass produce

    Battery Selection F

    Battery BasicsBattery Basics Lead Acid CoLead Acid Co

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    70/285

    Pure Lead

    Lead Selenium

    Lead Antimony

    Lead Calcium

    Battery Selection F

    Battery BasicsBattery Basics Lead Acid CoLead Acid Co

    Best ElectricalPerformance

    L

    Poorest ElectricalPerformance

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    71/285

    Pure Lead

    Lead Selenium

    Lead Antimony

    Lead Calcium

    Battery Selection F

    Battery BasicsBattery Basics Lead Acid CoLead Acid Co

    Most Reliable H

    Least Reliable

    + Plate

    Poisoning

    + Plate

    Growth

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    72/285

    Plastic Bonded ElectrodePowdered active material

    Plastic bonded to perforated steel strip

    Withstand extreme temperatures

    Sintered Plate Electrode

    Powdered nickel materialSintered onto perforated steel strip

    Impregnated with active material

    Pocket Plate ElectrodePowdered active material

    Suspended in perforated steel envelope

    Fiber Plate ElectrodeMetallic sponge nickel

    Impregnated active materials

    Battery Selection F

    Battery BasicsBattery Basics Nickel Cadmium CoNickel Cadmium Co

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    73/285

    Plastic Bonded Electrode

    Sintered Plate Electrode

    Pocket Plate Electrode

    Fiber Plate Electrode

    Battery Selection F

    Battery BasicsBattery Basics Nickel Cadmium CoNickel Cadmium Co

    Best Cycle Life

    Poorest Cycle Life

    NOTE: Fiber plates are not recommended for continuous float charge to hotspots and can short circuit on float charge and cycling

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    74/285

    Battery Selection F

    Plate construction

    Pocket PlateSintered Plate Fiber P

    Battery BasicsBattery Basics Nickel Cadmium CoNickel Cadmium Co

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    75/285

    Battery Selection F

    Battery BasicsBattery Basics Technology CTechnology C

    Battery Type Nickel Cadmium LeElectrolyte Potassium Hydroxide Su

    Symbol KOH

    Specific Gravity 1.2 1.215, 1.21

    Inert to all internal

    components

    Reacts w

    Does not change propertieswith state of charge

    Changes po

    Battery System

    Advantages/Disadvantages

    Chemically and physically

    strong

    Chemica

    Minimum maintenanceregardless of temperature

    More mai

    More resistant totemperature extremes

    Sensitive

    e

    More resistant to electrical

    abuses

    Le

    * different plate technologies have different SG's

    Electrolyte

    Advantages/Disadvantages

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    76/285

    Battery Selection F

    Despite all of the advances in power electronics UPS systems

    Battery remains the key component in determining syst

    Battery chemistry has not changed much over the years

    Batteries have a finite age

    They are expensiveTheir life is shorter than the manufacturer warrants

    Require a tremendous amount of maintenance

    One weak cell can yield the complete battery stri

    While design and installation are critical, the key

    UPS system is BATTERY MAINTENANCEIncludes: connection maintenance, internal diagnostics

    leaking post seals

    Battery BasicsBattery Basics Other ConsOther Cons

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    77/285

    Battery Selection F

    Battery sizing is based on the time and load powRefer to IEEE 485 and 1184 for more details

    UPS batteries must be matched to the application

    Choice of battery design depends on the environmaintenance and application

    Maintain approximately 77 deg F for longer battevery + 15 deg F cuts life in half

    Colder is not necessarily better because CAPACITY is

    New battery assemblies should be certified priorcommissioning

    Refer to IEEE 450 for commissioning details

    Battery BasicsBattery Basics Other ConsOther Cons

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    78/285

    Battery Selection F

    Care should be taken when storing batteries prioservice after manufacturer date

    Lead Antimony refreshing charge for every 3 months

    Lead Calcium refreshing charge for every 6 months o

    VRLA storage times vary based on storage temperature

    manufacturer)

    FAILURE TO GIVE A REFRESHING CHARGE befo

    recommended storage interval may result in plate sulfa

    adversely affect battery capacity

    Battery BasicsBattery Basics Other ConsOther Cons

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    79/285

    Battery Selection F

    Float current demand in specification ap

    when the electrolyte temperature is 77

    (25C). The value will double for every (8C) of temperature rise. If temperature

    the current value will be halved for ever

    (8C) decrease. Some battery float curr

    demand will increase with aging.

    Float adjustment

    Battery BasicsBattery Basics MMa

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    80/285

    Battery Selection F

    Float characteristics

    Battery BasicsBattery Basics MMa

    SOURCE: H. A. KIEHNE, BATTERY TECHNOLOGY HANDBOOK, 2003

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    81/285

    Proper Flo

    Maximize

    Maximize

    Reduces b

    Battery Selection F

    Battery BasicsBattery Basics MMa

    Battery Type

    (Specific gravity 1.24)

    Lead Antimony Types:

    (Specific gravity 1.215)Lead Calcium Flooded Types:

    (Specific gravity 1.215)

    Lead Calcium Flooded Types:

    (Specific gravity 1.250)

    Lead Calcium Flooded Types:

    (Specific gravity 1.30)

    Pure Lead Plante' Types:

    (Specific gravity 1.210)2.27 @ 20 deg C

    volts per cell

    (-2.4 mv per deg C

    rise over 20 deg C

    2.15 to 2.25 volts

    per cell

    Recommended

    Float Voltage

    RangeLead Selenium / Low

    Antimony Al loy Type:

    Lead Calcium Valve

    Regulated Types:

    2.15 to 2.25 volts

    per cell

    2.15 to 2.17 volts

    per cell2.17 to 2.25 volts

    per cell

    2.23 to 2.33 volts

    per cell

    2.28 to 2.37 volts

    per cell

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    82/285

    Initial Charge

    Recommended voltages and time periods

    Battery Selection F

    Battery BasicsBattery Basics MMa

    Lead Antimony Types

    Cell Volts Cell Volts

    2.24 444 - - 2.24 200

    2.27 333 - - 2.27 150

    2.30 210 - - 2.30 120

    2.33 148 333 - 2.33 90

    2.36 100 235 400 2.36 75

    2.39 67 160 267 2.39 60

    2.42 48 108 182

    2.45 38 73 125

    2.48 36 55 83

    2.50 32 44 60

    NOTE: Time periods listed in Tables are for cell temperatures from 70

    deg F to 90 deg F. For temperatures 55 deg F to 69 deg F double the

    number of hours. For temperatures 40 deg F to 54 deg F use four times

    the number of hours.

    Time-Hrs.

    1.250

    S.G.

    Time-Hrs.

    1.300

    S.G.

    Lead Calcium Types

    Time-

    Hrs.

    1.215

    Time-Hrs.

    1.215

    S.G.

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    83/285

    Battery Selection F

    Battery BasicsBattery Basics MMa

    Float Voltage Float voltage can be a misleadinWhile voltage readings of individual cells are importanThe sum of voltages of all the batteries MUST equal t

    charger (resistive losses excluded)

    Normal reading does not necessarily indicate the condi

    An abnormal reading requires further investigation

    Specific Gravity ReadingsSulfate is part of the electrochemical process

    Discharged State - some of the sulfate migrates to thacid is reduced in specific gravity

    Fully Charged State sulfate is in the acid and the s

    normalThe difficulty in interpreting specific gravity readings

    cell and ambient temperatures

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    84/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    85/285

    Battery Selection F

    Battery BasicsBattery Basics MMa

    Temperature Effects of temperature extremes (internal) and ambient (external) conditions impTypical battery systems are designed for 20 years @ 7

    15 deg F increase in temperature cuts battery life in ha

    Increased temperature causes faster positive grid corroother failure modes

    Discharge Current and Time Online monitorindischarge current and time calculations to determhours removed and replaced Presumably the benefit allows one to calculate battery

    Currently, the only sure way to determine true capacity

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    86/285

    Battery Selection F

    Battery BasicsBattery Basics MMa Intercell Connection Resistance

    One of the more important parameters to testMore than 50% of battery bank failures are related to loose o

    connectors

    If resistance measurement exceeds the lower end of the ohm

    is inadequate

    Capacity (load test) Only true method of deterbattery systems actual capacityThe test has limited predictive value depending on how frequ

    (each load test subtracts from the life expectancy of the batte

    Most manufacturers recommend capacity tests every 3 to 5 y

    Impedance Internal impedance tests measure tof a cell to deliver currentComponents of impedance (resistive and capacitive reactanc

    capacity

    Although the correlation is not 100% it is an excellent way to

    Impedance is inversely proportional to capacity

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    87/285

    Battery Selection F

    Battery BasicsBattery Basics MMa

    As impedance increases, battery capacity decrea Batteries do not have to be offline to test interna

    End Voltage vs. Impedance

    0

    0.5

    1

    1.5

    2

    2.5

    Data Points

    Impedance(milliohms)

    Cell Number 11 15 16 3 18 22 13 24 10 14 23 20 5 9 6 4 21 8 1 12 2

    Z 0.3 0.3 0.3 0.6 0.6 0.6 0.70.7 0.7 0.7 0.7 0.8 0.8 0.8 0.8 0.8 0.9 0.9 0.90.9 1.0

    Vdc 2.0 2.0 2.0 2.0 2.0 1.9 1.91.9 1.9 1.9 1.9 1.9 1.9 1.8 1.8 1.8 1.8 1.8 1.81.7 1.8

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    88/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    89/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    90/285

    Derating with ambient temperature

    Battery Selection F

    Battery BasicsBattery Basics

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    91/285

    Battery Selection F

    Typical discharge characteristics

    (equal weight same discharge conditions)

    Derating rate of discharge and design margin

    Battery BasicsBattery Basics

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    92/285

    Battery Selection F

    Derating rate of discharge and design marginBattery BasicsBattery Basics

    SOURCE: H. A. KIEHNE, BATTERY TECHNOLOGY HANDBOOK, 2003

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    93/285

    Battery Selection F

    Derating internal resistance change

    Battery BasicsBattery Basics

    SOURCE: H. A. KIEHNE, BATTERY TECHNOLOGY HANDBOOK, 2003

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    94/285

    Battery Selection F

    Discharge available capacity available with amtemperature change

    Battery BasicsBattery Basics

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    95/285

    Specification and Sizing:

    IEEE 485 Recommended Practice for Sizing L

    Batteries for Stationary Applications

    IEEE 1115 Recommended Practice for Sizing N

    Cadmium Batteries for Stationary Applications

    IEEE 1184 Guide for the Selection and Sizing

    Uninterruptible Power Supplies

    IEEE 1106 Recommended Practice for Installa

    Maintenance, Testing, and Replacement of Vente

    Batteries for stationary Applications

    Battery Selection F

    Battery BasicsBattery Basics

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    96/285

    Hydrogen Emission Generation

    Battery Selection F

    Battery BasicsBattery Basics

    Hydrogen Gas Evolution Calculation

    VH2IF CapAhr, K, N, CType,( ) IFCapAhr

    100 K N CType

    Where:

    VH2 - Volume of evolved hydrogen per hour

    IF - Float current per 100Ahr of installed battery bank capacity in [A] and

    temperature compensated

    CapAhr - Installed battery bank capacity in [Ahr]

    K - Maximum hydrogen evolution rate constant dependent on plate type:

    KAntimony_US 2.67 104

    ft

    3

    A

    KAntimony_SI 7.56 106

    m

    3

    A

    KLead_US 1.474 102

    ft3

    A

    N - Number of cells in battery bank

    CType - Constant dependent on battery construction:

    CFlooded 1.00

    CGNB_AbsolyteIIP 0.01

    Hydrogen Gas Evolution Calculation

    VH2IF CapAhr, K, N, CType,( ) IFCapAhr

    100 K N CType

    Where:

    VH2 - Volume of evolved hydrogen per hour

    IF - Float current per 100Ahr of installed battery bank capacity in [A] and

    temperature compensated

    CapAhr - Installed battery bank capacity in [Ahr]

    K - Maximum hydrogen evolution rate constant dependent on plate type:

    KAntimony_US 2.67 104

    ft

    3

    A

    KAntimony_SI 7.56 106

    m

    3

    A

    KLead_US 1.474 102

    ft3

    A

    N - Number of cells in battery bank

    CType - Constant dependent on battery construction:

    CFlooded 1.00

    CGNB_AbsolyteIIP 0.01

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    97/285

    Hydrogen Emission Generation

    Battery Selection F

    Battery BasicsBattery Basics

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    98/285

    Hydrogen Emission Generation

    Battery Selection F

    Battery BasicsBattery Basics

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    99/285

    What does this mean?

    Battery Selection F

    Need to verify with standards and local jurisd

    API RP500, Section 6.3.2.1 (2ndEd. Nov 1997) (below 25% of LFL - Low Flammable Limit )

    Or

    NEC 2005, Art 500, Table 5.1

    Or Local jurisdiction requirements

    Battery BasicsBattery Basics

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    100/285

    In the example, the hydrogen concentration in room for 8-hour period is much less than 25% allowable requirement for adequate ventilationrequirement per API RP500.

    The NFPA 497, Table 2-1 lists Hydrogen LFL=4%

    The API RP500 required 24% of LFL=4% calcula Calculated H2 concentration the room is 0.00391%

    If flooded batteries were used, H2 concentration w

    0.391%

    Battery Selection F

    Battery BasicsBattery Basics

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    101/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    102/285

    Hysteresis Influence on Performance

    Transformer

    Isolation Transformer

    Ferroresonant Transformer / Constant VoltaTransformer

    Reactor / Multi-winding Reactor / Combina

    Magne

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    103/285

    Hysteresis Influence on Performance

    Magn

    iL

    =

    HysteresisHysteresis

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    104/285

    Hysteresis Influence on PerformanceMagnetic Losses, Regulation and Inrush Current

    %100*)()()(

    loadfullU

    loadfullUloadnoU

    = 10*loadcu

    PP

    histFe PPP eddy +=

    2max**

    2* )( BfdPFe =

    cHBfPhist max***2=

    RIPCu *2=

    N

    lHo

    **4.0

    )(Im

    =

    Magne

    HysteresisHysteresis

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    105/285

    Transformer

    Magne

    TTr

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    106/285

    Construction

    Magne

    TransformerTransformer -- CoCo

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    107/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    108/285

    Constant Voltage Transformer (CVT) / FerrTransformer

    Advantages:

    Constant voltage output for variation in inpu

    Blocks harmonics from saturation in the CVand from input and output of the CVT

    Ride through ability (prime reason to use

    systems)

    Disadvantages

    Low efficiency

    Intolerant to frequency changes

    Magne

    Transformer CVT &Transformer CVT & FerFer

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    109/285

    Constant Voltage Transformer (CVT) / FerrTransformer

    AC INPUT

    POWER

    AC OUTPUT

    POWER

    LC RESONANT

    CIRCUIT

    TANK CIRCUIT

    Magne

    Transformer CVT &Transformer CVT & FerFer

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    110/285

    Constant Voltage Transformer (CVT) / FerrTransformer

    Magne

    Transformer CVT &Transformer CVT & FerFer

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    111/285

    Constant Voltage Transformer (CVT) / FerrTransformer

    Magne

    Transformer CVT &Transformer CVT & FerFer

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    112/285

    Reactor, Multi-Winding Reactor, Combinat

    Increase input impedance

    Provide di/dt smoothing component

    Part of LC filters

    Part of specialized filters with different in and pa(Harmonic Mitigating Transformer)

    Magne

    ReactoReacto

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    113/285

    UPS SYSTEM APPLICAUPS SYSTEM APPLICA

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    114/285

    System Components

    System Design and Integration Consideratio

    Distribution and Protection Component Sele

    Additional Design Consideration:o Load Types

    o Static Switch Operation

    UPS Sy

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    115/285

    System Components

    UPS Package:

    Components discussed previously in the pre

    Primary network:Components connected to UPS System upst

    as seen from load perspective

    Secondary network:

    Components connected to UPS System dowUPS as seen from load perspective

    UPS Sy

    System CoSystem Co

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    116/285

    System Design and Integration Consideratio

    General

    Reliability

    UPS System

    Primary network Secondary Network

    Enhancement

    Special Considerations

    Application Location (Onshore, Offshor

    etc. ) Unusual requirements

    Voltage, Power and Energy Flow effects on

    Specification

    UPS Sy

    System Design & System Design &

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    117/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    118/285

    General:

    System design and space planning

    UPS system primary purpose

    Operating Hours

    Type (see previous chapters) Capacity (centralized, local)

    Battery (see previous chapters)

    Systems

    Expansion provisions

    Cost

    UPS Sy

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    119/285

    General:

    Installation and environment

    Loading / Offloading conditions

    Space (installation, operation and maint

    Installation practices

    Environment (temperature, humidity, ha

    classification etc.)

    System heat rejection vs. environmental

    System heat rejection vs. backup/battery

    UPS Sy

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    120/285

    General:

    Maintenance and operation

    Monitoring (on-line) (voltages, currents

    battery etc.)

    Preventive maintenance (off-line)

    Operation Autonomy

    System Settings

    Connecting components checking

    UPS Sy

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    121/285

    Reliability:

    UPS System

    Primary network

    Secondary Network

    Enhancement

    UPS Sy

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    122/285

    Reliability: UPS System (from vendor)

    Note:

    MTBF, MTTR do not include batteries, interco

    cables outside of enclosure and internal operati

    UPS Sy

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    123/285

    Reliability: Primary network

    Reliability Indices:

    UPS Sy

    servedcustomersofnumberTotal

    onsinterrupticustomerofnumberTotal=SAIFI

    servedcustomersofnumberTotal

    durationsoninterrupticustomerallofSum=SAIDI

    demandedservicehoursCustomer

    tyavailabiliservicehoursCustomer=ASAI

    SAIDI

    SAIFI=CAIDI

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    124/285

    Reliability: Primary network

    Parameters Influencing Indices

    Location

    Routing

    Environmental Exposure Voltage

    Supply configuration

    Improving

    Identifying reliability driving elem

    Evaluation

    UPS Sy

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    125/285

    Reliability: Secondary Network

    Indices not applicable

    How fast can be repaired

    Plant running or not

    Etc.

    Parameters Influencing Reliability

    Location

    Routing

    Environmental, process, and other e

    Voltage

    Supply configuration

    Maintenance

    UPS Sy

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    126/285

    Reliability: Enhancement

    How much reliability is needed (0.9999

    System approach

    Redundancy

    Complete primary, secondary and

    Most fragile components

    Enhanced monitoring

    UPS Sy

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    127/285

    System Design and Integration Consideratio

    Special Considerations

    Application Location

    Onshore (petrochemical, pipeline, c

    etc.)

    Offshore (process, NAV lights, CO

    etc.)

    Overseas (process, control room, sp

    Unusual requirements

    i.e. bump-less transfer time no voltage

    UPS Sy

    System Design & System Design &

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    128/285

    UPS Sy

    System Design & System Design &

    System Design and Integration Consideratio Voltage, Power and Energy Flow

    UPS Load Flow - Link

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    129/285

    Location of equipment

    Application and block diagram

    Type Equipment

    Primary and secondary networkGrounding

    Input Power ratings and quality

    Type of Load

    Output power rating andquality

    Battery and battery charger(options)

    Service condition

    Monitoring requirements

    UPS Sy

    System Design & System Design &

    System Design and Integration Considerat

    Specification List (Minimum Requirement

    Monitoring In

    Installation re

    Provision for (load sharing, current capabi

    Maximum inp

    Maximum loa

    Amps and PF Overload capa

    long

    Steady state v

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    130/285

    Not all UPS Systems areNot all UPS Systems are

    UPS Systems

    Commercial Grade

    Typical utilized in IT applications

    Lack flexibility and robustness

    Tend to utilize PWM

    Static switches are rarely power transist

    Utilize contactors

    Typically use sealed batteries

    UPS Sy

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    131/285

    SizingSizing

    UPS System Sizing Principles

    Size for expected loads plus margin for gr

    Size batteries at full load for a minimum o

    Size normal power source for load for load

    + 25% DO NOT use the typical 125% of UPS

    Typically 1-phase below 50kVA and 3-ph

    UPS Sy

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    132/285

    UPS System LUPS System L

    UPS System Limitations

    Batteries will eventually discharge

    UPS is a complex system

    Will not last forever

    Requires periodic maintenance

    Human error

    UPS Sy

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    133/285

    DistributiDistributi

    Distribution Panels What should I use ? Breaker or a Fuse

    UPS Sy

    Breaker: Can reset a breaker

    Breakers are current limiting

    Fuse: Fuse has to be

    Fuses are curr

    Fuses may

    Will be covered in mover detail later in

    presentation

    SOWhat should be used Breaker or

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    134/285

    Fused Panel

    UPS Sy

    FF

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    135/285

    UPS Sy

    FF

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    136/285

    UPS Sy

    FF

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    137/285

    UPS Sy

    BreBre

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    138/285

    Power SuPower SuUPS Sy

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    139/285

    OnOn

    PP

    UPS

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    140/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    141/285

    PowePowe

    ComCom

    UPS S

    24 VDC

    PowerSupply *

    24 VDC

    PowerSupply *

    24 VDC

    Distribution

    To

    Field Devices

    Typical Dual Input

    Power Supply

    Custom UPS &

    Alternate Source

    Distributio n Panel

    * One or more power supplies as needed.

    Rectifier

    Inverter

    Static

    Switch

    MBS

    Alt

    Source

    InputBattery

    Set

    Output

    CircuitBreaker

    Input

    Circuit

    Breaker Alt

    Source

    Xfmr

    UPS System

    480V Distribution Sources

    (segregated from main

    substation)

    A B

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    142/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    143/285

    Load Types in Secondary Distribution Systemnon-liner with high THD, Regenerative)

    ITI (CBEMA) Curve

    Benchmarks For DCS, PLC and Critical Instru

    Short-Circuit Output Magnitude and The Alter

    Single-Phase or Three-Phase UPS Output Volt

    Protecting The UPS Static Switch

    Molded Case Circuit Breakers Versus Fuses

    UPS System Loads

    Example / Application:

    120V UPS Distribution System Selectivity 240V UPS / 480V Distribution System Sele

    Example

    Application Guideline Summary

    Review Load Types & Design Application

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    144/285

    Load Types from UPS and static switch opeperspective

    RL linear

    RC linear

    RL non-liner with high THD

    Regenerative

    Load Types in Secondary Dis

    LL

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    145/285

    RL linear loads

    Static power supplies

    Distribution transformers

    Long feeders with RL loads

    Inverter: operates in design operating range

    Static Switch: detection time and transfer tim

    increase due to the additional inductance

    RL LinRL Lin

    Load Types in Secondary Dis

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    146/285

    RC linear loads

    Any load connected to long cable (transmission

    Inverter: operates out of design operating ran

    verification with vendor capabilities and stab

    Static Switch: detection time and transfer tim

    increase due to the additional line capacita

    capacitance is so large that influence system

    commutation could be unstable and/or long

    non-bump-less transfer

    RC LinRC Lin

    Load Types in Secondary Dis

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    147/285

    RL non-linear loads with high THD

    Switching power supplies (PC, PLC, DCS etc.)

    Emergency lights

    Assure THD is in operating spec of UPS

    Inverter: operates in design operating range

    Static Switch: detection time and transfer tim

    will increase/decrease due to the voltage dis

    sensing capabilities of UPS circuitry.

    RL LinRL Lin

    Load Types in Secondary Dis

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    148/285

    Regenerative loads:

    Regeneration is power produced by load that has

    is driven by some other force mechanical or chem

    Assure vendor is aware about special requiremen

    of load. UPS components will be damaged.

    Inverter: not design for 2Q / 4Q operation

    Static Switch: detection time and transfer tim

    will increase due to the additional line cap

    case capacitance is so large that influence sycommutation could be unstable and/or long

    non-bump-less transfer

    RegeneraRegenera

    Load Types in Secondary Dis

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    149/285

    What IsWhat Is

    The ITI (CBEMA) CuThe ITI (CBEMA) Cu

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    150/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    151/285

    What Is TheWhat Is The

    New ITI Curve

    Refined for modern electronic equipment

    Curve applies to 120Vrms, 60Hz nominal equipm

    Engineer is responsible for application at other v

    frequencies ITI curve describes seven types of events:

    Not considered: Line Voltage Swell, Low-FrequenRingwave, High-Frequency Impulse, Voltage Sags

    Dropout

    No damage region

    Prohibited region

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    152/285

    1 us.001 c .01 c

    1 m

    100

    200

    300

    400

    500

    Percent

    ofNominalVoltage(RMSorPe

    akEquivalent)

    Duration in

    ITI (

    (R

    What Is TheWhat Is The

    Dropout A voltage includes both

    severe RMS voltage sagsand complete interruptionsof the applied voltage,followed by immediate re-

    application of the nominalvoltage

    This transient typicallyresults from the occurrenceand subsequent clearing offaults in the ACdistribution system

    THE INTERRUPTIONMAY LAST UP TO 20M ILL ISECONDS; FAULTSMUST BE SENSED ANDINTERRUPTED QUICKLY

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    153/285

    1 us.001 c .01 c

    1 m

    100

    200

    300

    400

    500

    PercentofNo

    minalVoltage(RMSor

    PeakEquivalent)

    Duration in C

    ITI (C

    (Re

    What Is TheWhat Is The

    No Damage Region

    Events in this region include

    sags and dropouts (which

    are less than the lower limit

    of the steady state tolerance

    range)

    The normal functional state

    of the Information

    Technology Equipment

    (ITE) is not typically

    expected during theseconditions (no damage to

    the ITE should result)

    NO DA

    REG

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    154/285

    1 us.001 c .01 c

    1 m

    100

    200

    300

    400

    500

    PercentofNo

    minalVoltage(RMSor

    PeakEquivalent)

    Duration in C

    ITI (C

    (Re

    What Is TheWhat Is The

    Prohibited Region

    This region includes any

    surge or swell (which

    exceeds the upper limit of

    the envelope)

    If the ITE is subjected to

    such conditions, damage

    to the ITE may result

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    155/285

    Issues And CIssues And C

    ITI Curve is the Benchmark

    Fast System Fault Interruption

    Voltage Restoration

    Concerns

    UPS Inverters Typically Supply Limited Fault C Depend On The Alternate Source To Provide Fa

    Short-Circuit Sensing

    Fast Fault Interruption

    Compliance With the ITI Curve During Fau

    Requires Fast Transfer to the Static Switch

    Requires Fast Interrupting Protective Devices

    Maintains Operation of Critical Computer Bus

    During Normal and Abnormal System Conditio

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    156/285

    Equipment BenchmEquipment Benchma

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    157/285

    IndInd

    Industry Recognized Voltage Dropout/Rest

    Equipment sample for operating facility

    Data may not represent your facility

    Determine if process equipment will operate with

    interruption Table Shows Typical UPS Loads

    Some of the data is minimum hold-up time with

    Others show the minimum threshold voltage at w

    shutdown

    Equipm

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    158/285

    Sample From Typical

    Petrochemical Facility

    1 DCS Mfg. #1 17 ms 0 Vrms

    2 DCS Mfg. #1 20 ms 0 Vrms

    3 DCS Mfg. #1 40 ms 0 Vrms

    4 DCS Mfg. #1 25 ms 0 Vrms

    5 DCS Mfg. #2 40 ms 0 Vrms

    6 DCS Mfg. #2 40 ms 0 Vrms

    7 DCS Mfg. #3 40 ms 0 Vrms8 DCS Mfg. #3 20 ms 0 Vrms

    9 PLC Mfg. #1 20 ms 0 Vrms

    10 PLC Mfg. #1 5 ms 0 Vrms

    11 PLC Mfg. #1 20 ms 0 Vrms

    12 PLC Mfg. #1 20 ms 0 Vrms

    13 PLC Mfg. #1 0 ms 97 Vrms

    14 PLC Mfg. #2 8.33 ms 0 Vrms

    15 PLC Mfg. #3 40 ms 0 Vrms

    16 PLC Mfg. #3 21 ms 0 Vrms

    17 Other Mfg. #1 0 ms 90 Vrms

    18 Other Mfg. #2 0 ms 88 Vrms

    19 Other Mfg. #3 0 ms 95 Vrms

    20 Other Mfg. #4 0 ms * 102 Vrms

    21 Other Mfg. #5 0 ms * 95 Vrms

    22 Other Mfg. #6 0 ms * 95 Vrms

    23 Relay #1 30 ms 0 Vrms

    24 Relay #2 10 ms 0 Vrms

    Reference

    Number

    * 0 ms below threshold without battery backup

    Minimum

    "Hold-Up"

    Time

    Minimum

    Threshold

    Voltage

    Equipment

    Description

    IndInd

    Equipme

    1 us.001 c .01 c

    1 ms3 m

    100

    200

    300

    400

    500

    PercentofNom

    inalVoltage(RMSorP

    eakEquivalent)

    Duration in Cycl

    ITI (CBE

    (Revis

    SYMBOL DENOTES

    EQUIPMENTSHUTDOWN VS.

    VOLTAGE AND TIME

    FROM TABLE

    EQUIPMENT

    #13, 17, 18, 19,

    20, 21, 22

    EQUIPMENT#1, 10, 14, 24

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    159/285

    GeGe

    Equipm

    SOURCE: M.H.J. BOLLEN, UNDERSTANDING POWER QUALITY PROBLEM

    Regularegulatfor a peduring

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    160/285

    GeGeEquipm

    SOURCE: M.H.J. BOLLEN, UNDERSTANDING POWER QUALITY PROBLEM

    Voltagcurves compumarket

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    161/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    162/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    163/285

    GeGeEquipm

    SOURCE: M.H.J. BOLLEN, UNDERSTANDING POWER QUALITY PROBLEM

    Voltagcurves

    processequipm1 comm

    2- more c

    contr

    3- PLC

    4-PLC ne

    5-AC con

    6-AC conimpo

    (sam

    7-AC con

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    164/285

    GeGeEquipm

    SOURCE: M.H.J. BOLLEN, UNDERSTANDING POWER QUALITY PROBLEM

    Voltagcurves sodium

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    165/285

    GeGeEquipm

    SOURCE: T.A. SHORT, DISTRIBUTION RELIBILITY AND POWER QUALITY

    Ride-thfor an i

    power

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    166/285

    GeGeEquipm

    SOURCE: T.A. SHORT, DISTRIBUTION RELIBILITY AND POWER QUALITY

    Voltagdropouvoltage

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    167/285

    ShortShort--Circuit OutpCircuit Outp

    Magnitude And ThMagnitude And ThAlternate SourceAlternate Source

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    168/285

    What Is UPS Inverter SWhat Is UPS Inverter S

    CurrentCurrent

    Pulse Width Modulated (PWM)

    Typically 1.5 times the full load current for 1/4 c

    Ferroresonant

    Can supply a maximum of 5 times full load amp(Energy Stored In The Output Filter)

    Both Technologies Are Very Limited In SuShort-Circuit Conditions

    Short-Circuit Output Magnitude And The A

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    169/285

    How Are The UPSHow Are The UPS

    System Faults System Faults

    UPS Inverter

    UPS short-circuit current insufficient for downst

    protective device sensing and interruption

    UPS senses the sudden rapid voltage reduction a

    cycle transfers to alternate source

    Alternate Source

    Alternate source has significantly greater short-c

    capability

    Increased fault current is usually adequate for pr

    devices to interrupt the fault

    Short-Circuit Output Magnitude And The A

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    170/285

    Static Switch Alternate Source Issues

    Closure into a short-circuit is a severe condition

    Must be adequately rated

    Must be protected for this severe condition

    Assumes the alternate source is available UPS Specifications Should Include:

    Short-circuit available from the alternate source

    (UPS manufacturer can supply equipment adequ

    conditions)

    Short-Circuit Output Magnitude And The A

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    171/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    172/285

    SingleSingle--PhasePhase

    OrOr

    Three PhaseThree Phase

    UPS Output VoltagUPS Output Voltag

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    173/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    174/285

    Protecting The UPS SProtecting The UPS S

    SwitchSwitch

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    175/285

    Why Does ThWhy Does Th

    Switch RequiresSwitch Requires

    Why Is An Internal Fuse Or Circuit BreakerProtect The Static Switch?

    For 1 to 5 cycles, a typical static transfer switch h

    circuit rating of 10 times the full load switch rati

    The alternate source short-circuit could exceed th

    withstand capability

    Hence, an internal solid-state fuse or circuit brea

    protect the static transfer switch

    Protecting The UP

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    176/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    177/285

    Static SwitchStatic Switch

    Static Switch Operation

    Switching is performed for one or more conditio

    Overcurrent > 150% of nominal current*

    Undervoltage < 80% of nominal voltage*

    Overvoltage > 110% of nominal voltage* Inverter Fault*

    * - Manufacturer may not provide function and/or value of threshol

    Protecting The UP

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    178/285

    Molded Case CircuMolded Case Circu

    BreakersBreakers

    vs.vs.

    FusesFuses

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    179/285

    Electrical SystElectrical Syst

    Electrical Design Practices

    MCCBs are typically used in indoor panelboard

    switchgear rooms and offices

    Industry practice uses circuit breakers in UPS dis

    systems

    UPS Manufacturers

    Recommend downstream fast-acting, current-lim

    with 1/2 cycle clearing time

    Molded Case Circuit-Bre

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    180/285

    Breaker FunBreaker Fun

    Molded Case Circuit Breaker (MCCB) Inter

    1.1 cycles for 100A frame

    1.5 cycles for 225A-4000A frame

    100A MCCB interrupting time

    1.1 cycles breaker interruption 0.25 cycles static switch transfer time

    1.35 cycles total time

    Marginally exceeds the ITI guidelines for mainta

    critical instrumentation

    This may result in a plant shutdown

    Molded Case Circuit-Bre

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    181/285

    Fuse Fuse

    TYPICAL SELECTIVITY SCHEDULE FOR LOW VO

    Exact ratios vary with ampere ratings, system voltage, acurrent.

    Molded Case Circuit-Bre

    Class L Fuse 601-6000 A 2:1 2:1 2:1 6:1

    Class K1 Fuse 0-600 A 2:1 3:1 8:1

    Class J Fuse 0-600 A 3:1 3:1 8:1

    Class K5 Time-Delay Current

    Limiting Fuse 0-600 A1.5:1 1.5:1 2:1

    Class J Time-Delay Fuse 0-

    600 A1.5:1 1.5:1 8:1

    Load side

    NOTE For illustration only; from [9]. Refer to fuse manufacturer for specific and up-to-da

    Class L

    Fuse

    601-6000 A

    Class K1

    Fuse

    0-600 A

    Class J

    Fuse 0-600

    A

    Class K5

    Time-Delay

    Fuse0-600 A

    Line side

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    182/285

    GeGeEquipm

    SOURCE: T.A. SHORT, DISTRIBUTION RELIBILITY AND POWER QUALITY

    Sensitiprocess

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    183/285

    Breaker FunBreaker Fun

    Authors Opinion

    Based on the collected data

    Modern MCCBs operate faster than clearing tim

    may provide fault clearing in less than 1.0 cycle

    1.1 cycles for 100A frame 1.5 cycles for 225A-4000A frame

    Molded Case Circuit-Bre

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    184/285

    UPS System LoadUPS System Load

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    185/285

    Design ConDesign Con

    During the Project UPSDesign Phase

    Sized for the anticipated

    loads

    Plus a nominal margin

    for future additions

    Try not to procure before

    all UPS loads are

    identified and kW

    requirements are known

    UPS

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    186/285

    ReviewReview

    Very Important To Evaluate All UPS Loads

    Segregate UPS loads from general purpose loads

    Compressor control panels should be thoroughly

    Compressor panels may include lighting, instrum

    and space heater Lighting and space heater should be powered fro

    purpose AC panel,NOT UPS SYSTEM

    Confirm control room creature comfort loads (

    heaters, coffee pots, microwaves etc.) are not connected

    outlets or feeder circuits

    Educate operation and maintenance personnel

    UPS

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    187/285

    Future LoadFuture Load

    To Avoid Overloading The UPS

    Review both existing and new UPS loads

    Review panel loading

    Review UPS loading

    All personnel should know the impact of adding

    UPS

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    188/285

    POWER SYSTEM ANAPOWER SYSTEM ANA

    APPLICABLE TO UAPPLICABLE TO USYSTEMS DESIGSYSTEMS DESIG

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    189/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    190/285

    Additional analysis for special application o

    Harmonic flow (inverter and loads, charger/recti

    network)

    Passive/Active Filters application

    Switching

    System modeling

    Reliability modeling

    EMF/RF modeling

    Power System Anal

    Analysis for Typical ApAnalysis for Typical Ap

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    191/285

    Tools

    No special tools are required for most of the typi

    applications

    Power System Anal

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    192/285

    Helpful tools for applications Standard Software (1PH, 3PH, LF-AC/DC, SC-A

    Harmonic Flow, Filters, battery charge/dischargereliability)

    SKM

    ETAP

    Hand calcs (LF-AC/DC, SC-AC/DC, Filters, battcharge/discharge, arc-flash)

    Excel

    MathCad

    Special Software (Harmonic Flow, passive/activeswitching, control strategy, reliability)

    MathCad

    SPICE

    Matlab

    EMTP type

    Power System Anal

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    193/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    194/285

    ExamplesExamples

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    195/285

    120V UPS Distribution System Selectivity

    Phase 1

    Phase 2

    Phase 2A 240V UPS / 480V Distribution System Sele

    Example

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    196/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    197/285

    All Loads in the Control Room

    UPS

    30KVA

    120V

    1-PHASE

    480 V MCC

    NORMAL

    480 V MCC

    ALTERNATE

    30KVA

    480-120V

    1-PHASE

    125A

    100A 100A 100A

    350A

    15A

    20A

    50A

    120VAC

    PANEL

    L115A

    50A

    LOAD

    120VAC

    PANELR1

    PANELBOARD BP1

    NOTE: BP1 AND L1ARE IN ADJACENT

    M C C C U B I C L E S .

    OTHERWISE, PANEL

    L 1 R E Q U I R E S A N

    I N C O M I N G M A I N

    BREAKER

    2-1/C #2

    100FT

    2-1/C #14

    25FT

    PHASE 1

    FPH1A_

    FPH1B_

    FPH1C_

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    198/285

    Loads Located Greater than 1000 feet

    FPH2B_

    UPS

    30KVA

    120V

    1-PHASE

    480 V MCC

    NORMAL

    480 V MCC

    ALTERNATE

    30KVA

    480-120V

    1-PHASE

    125A

    100A 100A 100A

    350A

    15A

    20A

    100A

    T1

    10KVA

    120-480V

    T2

    10KVA

    480-120V

    120VAC

    PANEL

    R2

    INSTR.

    SKID

    10A

    15A

    20A

    INSTR.

    SKID

    10A

    120VAC

    PANEL

    AR2

    PANELBOARD BP1

    100A

    2 x 2-1/C#500KCMIL

    1000FT

    2-1/C #6

    150FT

    PHASE 2 ALTERNATE

    PHASE 2

    2-1

    FPH1C_

    FPH2A_

    FPH2A1_FPH2A

    FP

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    199/285

    120V UPS 120V UPS

    SelectivitySelectivity

    Fault PWMLocation Isc

    FPH1A_ 375A

    FPH1B_ 360A

    FPH1C_ 310A

    1P

    2-1/C100F

    PANEL

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    200/285

    Fault PWMLocation Isc

    FPH1A_ 375A

    FPH1B_ 360A

    FPH1C_ 310A

    120V UPS 120V UPS

    SelectivitySelectivity

    120

    PA

    2-1/C #2

    100FT

    PANELBO

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    201/285

    120V UPS120V UPS

    SelectivitySelectivity

    Fault PWMLocation Isc

    FPH1A_ 375A

    FPH1B_ 360A

    FPH1C_ 310A

    120

    PA

    2-1/C #2

    100FT

    PANELBO

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    202/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    203/285

    120V UPS 120V UPS

    SelectivitySelectivity

    Fault PWMLocation Isc

    FPH2A_ 325A

    FPH2B_ 282A

    12PA

    PANELB

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    204/285

    120V UPS 120V UPS

    Selectivity Selectivity

    Fault PWM

    Location Isc

    FPH2A1_ 86A

    FPH2A2_ 58A

    FPH2A3_ 219A

    FPH2A4_ 186A

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    205/285

    120V UPS 120V UPS

    Selectivity Selectivity

    Fault PWM

    Location Isc

    FPH2A1_ 86A

    FPH2A2_ 58A

    FPH2A3_ 219A

    FPH2A4_ 186A

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    206/285

    Fig. 3. Example 240VAC UPS/480V Distribution System O

    Diagram With Traditional Circuit Breaker Protection

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    207/285

    UPS

    50KVA

    240V

    1-PHASE

    480 V MCC

    NORMAL

    480 V MCC

    ALTERNATE

    T3

    50KVA

    480-240V

    1-PHASE

    150AT

    30A

    300A W/O

    TRIP UNIT

    15A

    15A

    125A

    SKID

    LOAD

    10A

    PANELBOARD PB #2

    2 1/C #8

    300FT

    2 1/C #10

    50FT

    300A

    300A

    20A 15A

    TO

    LOAD

    TO

    LOAD

    150A

    T2

    50KVA

    240-480V

    1-PHASE

    F1_

    T1

    10KVA

    480-120V

    1-PHASE

    F2_

    15A

    PB

    #1

    F3_ F4_

    PP

    #1

    240V/480V UPS Distribution System

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    208/285

    Fault PWM

    Location Isc

    F1_ 148A

    F2_ 144A

    F3_ 508A

    F4_ 416A

    240V UPS240V UPS

    SystemSystem

    F1_

    T1

    10KVA

    480-120V

    1-PHASE

    F2_

    PANELB

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    209/285

    240V UPS240V UPS

    SystemSystem

    Fault PWM

    Location Isc

    F1_ 148A

    F2_ 144A

    F3_ 508A

    F4_ 416A

    F1_

    T1

    10KVA

    480-120V

    1-PHASE

    F2_

    PANELB

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    210/285

    Application GuidelApplication Guidel

    SummarySummary

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    211/285

    PoinPoint

    Application Guideline

    Intended as a starting point

    Include additional information

    Fundamentals

    Changes Lessons learned

    Exceptions

    Application Gui

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    212/285

    UPS Distribution System GenerUPS Distribution System Gener

    Application GuideliApplication Guideli1. To avoid overloading UPS systems, review UPS loa

    2. Segregate panel loads with critical process loads on

    3. Perform short-circuit duty check with Alt. Source su

    4. ITI curve is the benchmark for computer business eq

    5. Review critical loads voltage limits with system con

    6. Review UPS static switch timing/triggering paramet

    7. When applicable, specify 1-phase UPS systemsRedundant power supply applications may require 3

    Application Gui

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    213/285

    UPS Distribution System GenerUPS Distribution System Genera

    Application GuideliApplication Guideli8. Transfer to the Alt. Source may not be required with

    because generally have a greater initial (1/4-1 cycle)

    9. UPS manufacturers recommend fast-acting current-

    10. Adequate fault current may minimize Static Sw. Alt

    11. Confirm UPS internal fuse/circuit breaker configuraConfirm the Alt. Source fault does not exceed the U

    12. With UPS internal, single-element CL fuses, includefactory fault testing with upstream and downstream

    13. Fuse sizes should be minimized, i.e., less than typic

    Application Gui

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    214/285

    UPS Distribution System GenerUPS Distribution System Genera

    Application GuideliApplication Guideli14. For selectivity, use fuse selectivity ratio tables

    manufacturer since fuse selectivity tables are obtaine

    15. Specify a 480V MCC fused switch for the feeder the Alternate Source isolation transformer

    16. To assure adequate fault clearing current to remoincreased cable sizes may be required

    17. To increase Alt. Source short-circuit current, thisolation transformer kVA rating may be increased

    18. Use shielded, isolation type Alternate Source transfoOnly use ferroresonant transformers after thorough i

    19. For enhanced system reliability, the Alternate Sopowered from a separate upstream source (not the sa

    Application Gui

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    215/285

    SYSTEM ACCEPTANSYSTEM ACCEPTAN

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    216/285

    System acceptance Factory Acceptance Testing (FAT)

    Commissioning

    Performance verification

    Maintenance

    Sys

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    217/285

    There is no standard for specificationsystem and testing in ANSI world

    Testing and acceptance parameters:

    Client specification

    Vendor internal QA plan

    Fusion of multitude different specificatio

    Sys

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    218/285

    Useful specification: UL 1778 - Standard for Uninterruptible Power Supply

    CSA C22/2 NO.17.1 - Commercial and Industrial Pow

    NEMA PE-1 - Uninterruptible Power Systems Standar

    NEMA PE-5 Utility Type Battery Chargers

    IEC 62040 Uninterruptible Power Systems (UPS)

    Part 1: General and safety requirements

    Part 2: Electromagnetic Compatibility (EMC) Re

    Part 3: Method of Specifying the Performance anRequirements

    ANSI C62.41, Category A & B - Recommended practvoltages in low voltage power circuits

    FCC Rules and Regulations 47, Part 15, Class A - Cercompliance

    IEEE Std. 650 Standard for qualification of class 1E

    Sys

    SpeSpe

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    219/285

    Factory Acceptance Testing (FAT)

    Industry testing

    Vendor internal QC procedures

    Client specification

    Sys

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    220/285

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    221/285

    Commissioning: Assure that FAT testing was performed

    NETA specification as a guide

    Specific application additional requirements i.e. special volta

    dynamic loading, leading power factor, very low power facto

    Compare specific values from FAT and site installation i.e. bbattery resistance, insulation resistance etc.

    Battery charge and discharge test after installation at site

    VERYFY AND RECORD ALL SETTING PARAMETERS

    software

    Separately commission all distribution primary and secondary

    guidelines

    Sys

    ComComm

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    222/285

    Performance verification

    Periodic testing

    Battery test

    Autonomy of operation

    Operation test: (AC input power loss test, A

    return test, Redundancy test (if applicable fo

    applications), Transfer test)

    Grounding operation

    DC ground detection

    AC ground detection

    Thermographic scan

    On-line monitoring:

    Battery status

    UPS controller status

    Sys

    Performance VPerformance V

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    223/285

    Maintenance Every month:

    Check and record meter readings.

    Check indicating lights.

    Every year: Perform Manufacturers recommended serv

    Every T/A:

    Function Check operation by simulating lossource and loss of inverter source.

    At 5/10yr intervals:

    Perform manufacturers recommended compout.

    Sys

    MM

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    224/285

    UpdateUpdate

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    225/285

    InduIndu

    There Is A Need To Revise / Update ExistinSystem Standards (IEEE Std. 944-1986, IEEE Std. 4Or Create A New Standard For The Industr

    Standard Needs Current Information In The Foll

    Construction, system architecture, topology

    Principle of operation and conversion Sizing, redundancy, energy storage

    Static and transient performance

    Protection and selectivity

    Acceptance testing, commissioning, and ma

    Lessons Learned Industry needs to provide feedback to evaluate a

    solutions with the application of UPS systems foloads

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    226/285

    Application Application

    Ferroresonant UPS Systems Have AdditionLimitations: Some UPS systems with output ferroresonant transfor

    overheat during very light load or unloaded condition

    Overloaded ferroresonance transformer tend to collap

    Static Transfer Switch Timing Performance Dependence on:

    Impedance (cables, installation, transformers etc

    sources and switch inputs. Also, impedance of th

    system connected to the switch output

    Voltage detection logic (detection time)

    Changes with:

    Type of loads connected (RL, RC, RLC, regener

    Type of fault (L-G, L-L etc.) and angle when fau

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    227/285

    Resources & ReferenResources & Referen

  • 8/10/2019 UPS Distribution Systems and UPS Fundamentals in the Petrochemical Industry

    228/285

    Technical RTechnical R

    IEEE 485 Recommended Practice for Sizing Lead-AcidStationary Applications IEEE 1115 Recommended Practice for Sizing Nickel- C

    Batteries for Stationary Applications IEEE 1184 Guide for the Selection and Sizing of Batter

    Uninterruptible Power Supplies IEEE 1106 Recommended Practice for Installation, Ma

    Testing, and Replacement of Vented Ni-Cad Batteries forApplications

    NEMA PE-1 Uninterruptible Power Systems IEEE 450 Recommended Practice for Maintenance, Te

    Replacement of Large Lead Storage Batteries IEEE 1188 Recommended Practice for Maintenance, T

    Replacement of VRLA Batteries (Sealed Type) SCI Technical Papers -

    http