Update on LS1 Activities
description
Transcript of Update on LS1 Activities
Update on LS1 Activities
W.Baldini, N. Bondar, O.Maev,B. Schmidt
LS1 Muon Meeting May-15th 2014
Ongoing Activities • LS1 activities:
– activities ongoing on C-side M2-5:• Connectivity test slowly resuming, many problems with instabilities of virtual
machines/CCPCs etc… it will take some more time • Problem with TELL1 (mutellc01) fixed (Oleg, Francesco); this week we would like to
take more PDM data • Grounding improvement: almost done (3 more chambers…). Since last Wednesday
it’s not possible to work due to HERSCHEL cable installation (~1 week). • Ferrite filters installation on M5 front done
2
HERSCHEL cabling
Our setup…
Ongoing Activities • HV:
– Conditioning of C side: an M4R4 chamber (11C) found with a gap in short, replaced with a chamber recovered by Dmiitri (PNB094)
– HV Connectors on A side (RDB-racks end) are being improved (Nikolai) before connecting them back
– Check mapping and re-connect to CMBs
3
Several connectors to be improved
Ongoing Activities
• Next commissioning week June 23-27, we will try to turn on PNPI-HV-Chambers on A-side, so far we left the chambers unplugged.
• For more details you can refer to the e-log: http://lblogbook.cern.ch/MUON/
4