Update on Aceh
Challenges to Reconstruction
• houses needed: 150,000 units• houses committed:
135,162• houses completed &
under construction: 36,963
• houses occupied 50-60%
UN Habitat-BRR 28 Feb 2006
• key challenges: material supply & demand
bricks 10,000 per house
2-2.5 billion bricks demand 1.35 billion bricks capacity
• key challenges: material supply & demand
timber 1 m3 for brick houses -structure
9 m3 as fuel for bricks 1.4 million m3 demand 50 K m3 legal supply
• key challenges: land availability & tenure
12% land loss due to tsunami <15% land legally registered 85% land records lost
• key challenges: communities & coordination
NGOs as “contractors”
“naming & shaming” poor wat-san integration
• key challenges: material supply & demand
timber