Update on Aceh

22
Update on Aceh Challenges to Reconstruction

description

Update on Aceh. Challenges to Reconstruction. houses needed: 150,000 units houses committed: 135,162 houses completed & under construction: 36,963 houses occupied 50-60% UN Habitat-BRR 28 Feb 2006. - PowerPoint PPT Presentation

Transcript of Update on Aceh

Page 1: Update on Aceh

Update on Aceh

Challenges to Reconstruction

Page 2: Update on Aceh
Page 3: Update on Aceh
Page 4: Update on Aceh
Page 5: Update on Aceh
Page 6: Update on Aceh
Page 7: Update on Aceh
Page 8: Update on Aceh
Page 9: Update on Aceh
Page 10: Update on Aceh
Page 11: Update on Aceh
Page 12: Update on Aceh
Page 13: Update on Aceh
Page 14: Update on Aceh
Page 15: Update on Aceh
Page 16: Update on Aceh

• houses needed: 150,000 units• houses committed:

135,162• houses completed &

under construction: 36,963

• houses occupied 50-60%

UN Habitat-BRR 28 Feb 2006

Page 17: Update on Aceh

• key challenges: material supply & demand

bricks 10,000 per house

2-2.5 billion bricks demand 1.35 billion bricks capacity

Page 18: Update on Aceh

• key challenges: material supply & demand

timber 1 m3 for brick houses -structure

9 m3 as fuel for bricks 1.4 million m3 demand 50 K m3 legal supply

Page 19: Update on Aceh

• key challenges: land availability & tenure

12% land loss due to tsunami <15% land legally registered 85% land records lost

Page 20: Update on Aceh

• key challenges: communities & coordination

NGOs as “contractors”

“naming & shaming” poor wat-san integration

Page 21: Update on Aceh

• key challenges: material supply & demand

timber

Page 22: Update on Aceh