University of Central Florida Downtown Campus / Dr. Phillips Academic Commons
Pre-Bid Phase II Package – Structural, Architectural and MEP
Agenda− Introduction (5 minutes)
− UCF Introduction (5 minutes)
− Project Overview (10 minutes)− Package Highlights− Site Logistics & Phasing− Safety− Project Schedule / BIM Coordination− LEED (not included in original presentation)− DOP (not included in original presentation)
− Bid Package Content (20 minutes)− Docupro – online platform for all bidding documents− Plans – Construction – Current Set − Specifications− Bid Manual − Bid Forms− Subcontract Template− Safety Policy− CCIP− MWBE Participation
− Review Scope Packages & Bid Form Breakdowns (30 minutes)
− Q & A (10 minutes)
− Networking (20 minutes)
Project Overview
– Architect
– MEP Engineer
– Civil Engineer
– Structural Engineer
– Commissioning
Schenkel Shultz Architects
TLC Engineering for Architecture
VHB
Walter P. Moore
Exp and PSI
UCF DT Academic CommonsDesign Team
− Approximately 150,000 sqft − Two Buildings – East and West
− Four stories each− Connected by an elevated walkway
− Contains Labs, Classrooms, Open Areas and Offices− Phase I – Foundations – Bid and Awarded− Phase Ia – Glazing and Precast – Bid and in the process
of Award− Sitework, Hardscape and Landscape are not included
UCF DT Academic Commons
General Conditions:− Site Logistic:
− Temp. Fencing; Dumpster; Temp. Toilets
− Cranes / Temporary Hoisting− Surveying− Security
Site Utilities:− Temp. Electric; Temp Water
Site Parking:− Offsite Parking
UCF DT Academic Commons
UCF DT Academic CommonsSite Logistics – Phase II
Safety Program / Stretch and FlexSKANSKA is committed to a culture of Injury Free Environment (IFE)
Employee
Authorization
To Stop Work
Safety Program / Stretch and Flex
Daily
Hazard
Analysis
Project Schedule– Phase I - Foundation : December 2017 – May 2018
– Phase II – Structure: Begins April 2018
– Dry-in West Building: October 2018
– Dry-in East Building: November 2018
– Air on: December 2018
– Substantial Completion: June 14, 2019
– Phase II Bids: Due January 25th, 2018 @ 2pm
– Project Duration: 20 months from Notice To Proceed
BIM Coordination - Revit-format coordination models required from all MEPF
Subcontractors
- HVAC Subcontractor to perform clash detection and model merging
- Weekly BIM Coordination Meetings until coordination/revisions are complete
LEED v4 - Gold Certification Leadership in Environmental and Energy Design(Slide not included in original presentation)Subcontractor-Critical Pursuit Credits (note differences in LEED v4 Credit Requirements against LEED v3 or 2009)
Materials & Resources− Cr. 1 Building Life Cycle Impact Reduction− Cr. 2 Building Product Disclosure & Optimization: EPD’s− Cr. 3 Building Product Disclosure & Optimization: Sourcing Raw Materials− Cr. 4 Building Product Disclosure & Optimization: Material Ingredients− Cr. 5 Construction & Demolition Waste Management
Indoor Environmental Quality− Cr. 2 Low Emitting Materials− Cr. 3 Construction IAQ Management Plan− Cr. 4 IAQ Assessment
Innovation in Design− Exemplary Performance for Construction Waste Management
DOP – Direct Owner Purchase(not included in original presentation)
− Include Vendor PO’s larger than $5,000.
− Process takes 3 weeks− Account for this time in your procurement− Submit PO request immediately after award
(Skanska to coordinate proper forms with Subcontractor)
− Only include material that will be permanently affixed to the building.
− Provide DOP information with bid, on the Bid Form required. − The Bid Form has a specific space for DOP
Bid Package Content
− Download documents:− Docupro online plan room – access to be sent by email.− Contact the following scope specific people:
− Brandon Barber – MEPF [email protected]− Marisol Figueroa – Structural and Enclosure
[email protected]− Tacy Perry – Architectural [email protected]
− Purchase documents:− Free to download from Docupro− New Age Reprographics - Phone: 407-422-8700
Reference: UCF Downtown Dr. Phillips Academic Commons
Phase II PackageBid Documents
Plans and SpecificationsOn Docupro for Download
– Drawings– Construction
– Phase I Construction Volumes 1-4– Phase II Construction Volumes 1-4
– Specs – Construction
– Phase I Construction Volumes 1-2– Phase II Construction Volumes 1-2– UCF Design and Construction Standards
Bid Manual
– Section One – Instructions to Bidders – Section Two – Project Specific Forms– Section Three – Project Schedule– Section Four – Site Logistics– Section Five – CCIP (Sample Manual)– Section Six – Sample Long & Short form
Subcontract– Section Seven – Trade Scopes of Work– Section Eight – Environmental, Health and
Safety Manual – Section Nine – Document Log–
Subcontractors are responsible for the Entire Package
Review Scope Packages Bid Form Breakdowns52 Packages
Structural and Enclosure Scopes - Marisol
3.1 Concrete5.1 Structural Steel5.2 Miscellaneous Metals5.5 Glass Railing7.2 Metal Composite Wall Panels7.3 Roofing7.4 Spray Fireproofing7.5 Foamed-in Insulation7.9 EIFS8.3 Architectural Precast8.4 Interior Glazing41.2 Fall Arrest System
Architectural Scopes - Tacy 1.2 Final Cleaning
6.1 Millwork and Finish Carpentry
7.6 Caulking and Waterproofing
8.1 Doors, Frames, and Hardware
8.2 Overhead Doors
9.1 Drywall
9.2 Tile
9.3 Acoustical Ceilings
9.4 Resilient Flooring
9.5 Painting
9.6 Wood Ceilings
9.7 Carpet
9.8 Acoustic Fabric Wrapped Panels
9.9 Resinous Flooring
9.10 Cork Flooring & Wood Flooring
10.1 Visual Display Units, Defibrillators & Postal Specialties
10.2 Signage, Plaques & Directions
10.3 Toilets Partition & Accessories
10.4 Wall and Corner Guards
10.5 Operable Partitions
10.6 Fire Extinguishers Specialties
10.7 Lockers
10.8 Equipment Screens
11.1 Book Drop - Miscellaneous Equipment
12.1 Window Treatments
12.5 Miscellaneous Furnishings
12.4 Fixed Audience Seating
MEPF - Brandon11.2 Fume Hoods11.3 Laboratory Equipment12.2 Science Casework14.1 Electric Traction Elevators21.1 Fire Suppression22.1 Plumbing23.1 Mechanical23.2 HVAC & Laboratory Controls26.1 Electrical27.1 Low Voltage - Data28.1 FA & Access Control, etc.
Bid Due: January 25, 2018; by 2:00PM – SEALED BIDCallahan Center – Downtown101 N Paramore AveOrlando, FL 32801
Skanska rep on site to receive bids from 9am to 2pm on Bid Day
RFI’s: • Due by January 17, 2018 by 5pm• Structural and Enclosure – Marisol Figueroa
•[email protected]•Architectural – Tacy Perry
•[email protected]•MEPF – Brandon Barber
Summary
Q&A – Thank you for coming!