UNIT II - DESIGN CONCEPTS - WordPress.com · UNIT 1 INTRODUCTION – THEORY AND BEHAVIOUR Basic...
Transcript of UNIT II - DESIGN CONCEPTS - WordPress.com · UNIT 1 INTRODUCTION – THEORY AND BEHAVIOUR Basic...
Sl.No Contents Page No.
PRESTRESSED CONCRETE STRUCTURES
UNIT I - THEORY AND BEHAVIOUR
1.1 Pre-stressed concrete 2
1.2 Types of pre-stressing 2
1.3 Losses 3
UNIT II - DESIGN CONCEPTS
2.1 Analysis of beam section - concept 18
2.2 Elastic Design for flexure 38
2.3 Permissible stresses for flexure member 41
2.4 End block 54
UNIT III CIRCULAR PRESTRESSING
3.1 Design Procedure for circular tanks Computations 61
3.2 Circular pre-stressing 66
3.3 Design of pipes 70
3.4 Design of circular water tanks 74
UNIT IV COMPOSITE CONSTRUCTION
4.1 Introduction 78
4.2 serviceability limit state 78
4.3 Ultimate strength 81
4.4 Horizontal shear 81
UNIT V PRESTRESSED CONCRETE BRIDGES
5.1 Prestressed concrete bridges 85
CE PRESTRESSED CONCRETE STRUCTURES L T P C 3 0 0 3
OBJECTIVE
A t the end of this course the student shall have knowledge of methods of prestressing advantages ofprestressing concrete, the losses involved and the design methods for prestressed concrete elementsunder codal provisions.
UNIT 1 INTRODUCTION – THEORY AND BEHAVIOUR
Basic concepts – Advantages – Materials required – Systems and methods of prestressing – Analysis of
sections – Stress concepts – Strength concepts – Load balancing concept – Effect of loading on the
tensile stresses in tendons – Effect of tendon profile on deflections – Factors influencing deflections –Calculation of deflections – Short term and long term deflections – Losses of prestress – Estimation ofcrack width .
UNIT II DESIGN CONCEPTS
Flexural strength – Simplified procedures as per codes – strain compatibility method – Basic concepts inselection of cross section for bending – stress distribution in end block, Design of anchorage zonereinforcement – Limit state design criteria – Partial prestressing – Applications.
UNIT III CIRCULAR PRESTRESSING
Design of prestressed concrete tanks – Pipes.
UNIT IV COMPOSITE CONSTRUCTION
Analysis for stresses – Estimate for deflections – Flexural and shear strength of composite members.
UNIT V PRESTRESSED CONCRETE BRIDGES
General aspects – pretensioned prestressed bridge decks – Post tensioned prestressed bridge decks –Principle of design only.
TOTAL: 45 PERIODS
TEXT BOOKS
1. Krishna Raju N., Prestressed concrete, Tata Mcgraw Hill Company, New Delhi, 19982. Mallic.S.K. and Gupta A.P., Prestressed concrete , Oxbord and IBH publishing Co.Pvt.Ltd 1997.
3. Rajagopalan, N” Prestressed Concrete”, Alpha Science, 2002.REFERENCES1. Ramaswamy G.S.Modern prestressed concrete design, Arnold Heinimen, Newdelhi, 19902. LinT.Y., Design of prestressed concrete structures, Asia Publishing House, Bombay, 1995
3. David A.Sheppard, William R and Philphs, Plant Cast precast and prestressed concrete – Adesign guide, McGraw Hill,Newdelhi 1992
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Chapter -1INTRODUCTION – THEORY AND BEHAVIOUR
Basic concepts – Advantages – Materials required – Systems and methods of prestressing – Analysis of
sections – Stress concepts – Strength concepts – Load balancing concept – Effect of loading on the
tensile stresses in tendons – Effect of tendon profile on deflections – Factors influencing deflections –Calculation of deflections – Short term and long term deflections – Losses of prestress – Estimation ofcrack width .
1.1 Pre-stressed concreteDefinition: Concrete in which there have been introduced internal stresses of such magnitude anddistribution that the stresses resulting from given external loadings are countered to a desired degree -ACI
1.2 Types of pre-stressing
1.2.1 Pre-tensioning & Post-tensioningIn pre-tensioning the tendons are tensioned before the concrete is placed. The tendons are temporarilyanchored to abutments or stressing beds. Then the concrete member is cast between and over thewires. After the concrete has attained the required strength, the wires are cut from the bulkhead andpre-stress is transferred to the concrete member.
In post-tensioning the concrete member is cast with ducts for the wires. After concrete has attainedsufficient strength, wires are threaded into the ducts, tensioned from both or one end by means ofjack/jacks and at the precise level of pre-stress the wires are anchored by means of wedges to theanchorage plates at the ends.
1.2.2 Bonded & Un-bonded tendonIn post-tensioned members, the wires are either left free to slide in the ducts or the duct is filled withgrout. In the former, the tendon is un-bonded and in the latter it is bonded.
Stages of loading
Initial stageThe member is under pre-stress but is not subjected to any superimposed external loads. Furthersubdivision of this stage is possible.
1. Before pre-stressing: Concrete is weak in carrying loads. Yielding of supports must be prevented.2. During pre-stress:
a. Steel: This stage is critical for the strength of tendons. Often the maximum stress towhich the wires will be subjected throughout their life may occur at this stage.
b. Concrete: As concrete has not aged at this stage, crushing of concrete at anchorages ispossible, if its quality is inferior or the concrete is honeycombed. Order of pre-stressingis important to avoid overstress in the concrete.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
3. At transfer of pre-stress: For pre-tensioned members, where transfer is within a short period,and for post-tensioned members where transfer may be gradual, there are no external loads onthe member except its own weight.
4. De-shuttering: The removal of form-work must be done after due considerationThus the initial pre-stress with little loss imposes a serious condition n the concrete and often controlsthe design of the member.
Final stageThis is the stage when actual working loads come on the structure. The designer must consider variouscombinations of live loads on different parts of the structure with lateral loads such as wind andearthquake forces and strain loads produced by settlement of supports and temperature. The majorloads in this stage are:
1. Sustained load: It is often desirable to limit the deflection under sustained loads sue to its ownweight and dead loads.
2. Working load: The member must be designed for the working load. Check for excessive stressand deflection must be made. But this design may not guarantee sufficient strength to carryoverloads.
3. Cracking load: Cracking in a pre-stress member signifies a sudden change in bond and shearingstresses. This stage is also important
4. Ultimate load: This strength denotes the maximum load the member can carry before collapse.
1.3 Losses
Elastic Shortening (ES) – Cl 18.5.2.4Shortening in steel that occurs as soon as Fi is transferred to the concrete member and the member as
a whole shortens.
Fi = Pre-stress just before transfer
F = Final stress after losses
Fo = Immediately after transfer – very difficult to estimate
Note: The value of Fo may not be known, but it is not necessary, as the losses from Fi to Fo is only a
small percentage of Fi . Total accuracy is relative anyway, as Ec – the young’s modulus of concrete –cannot be determined accurately.
Therefore
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
S
ES = E s
f c
EC
F O
AC EC
where is the shortening in steel that occurs as soon as Fi is transferred to the
concrete member and the member as a whole shortens. Thus is the shortening in the
member due to Fi at the level of steel.
FES O E
AC EC
Since
S
f c is the stress in concrete at level of steel and isFO
AC
FES O E
ESTaking nEC
AC EC
F n O
AC
As Fo cannot be estimated, Fi can be used to calculate ES.
at level of steel Fi
AC EC AS ES
ES Es
Es
Fi
AC EC AS ES
nFi
AC nAS
Taking At AC EC AS ES
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Ac
nFES i
AT
whichever way the ES is calculated
ES = n (concrete stress at level of steel)
If external loads are acting on the member, then concrete, then concrete stress due toall loads at level of steel must be determined.
F F e 2 M ef c
O
AG
O
I G
I
Note: AG , the gross-area, instead of the transformed sectional area, leads to simpler calculations and
fairly accurate results.
Fo 0.9Fi for pre-tensioned member
f FO
G
ES nf c
Creep (CR) Cl 18.5.2.1Among the many factors affecting creep are volume to surface ratio, age of concrete at time of pre-stress, relative humidity, type of concrete (lightweight / normal). Creep is assumed to occur in themember after permanent loads are imposed after pre-stress. Creep occurs over a long period of timeunder sustained load. Part of initial compressive strain induced in concrete immediately after transfer isreduced by the tensile strain produced by superimposed permanent loads.
Therefore for bonded members, loss due to creep
CR n f cir f cds f c
En S
EC
= Creep coefficient – Cl 4.5.3 & Cl 5.2.5.1
f cir = concrete stress at level of steel immediately after transfer.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
fcds = stress in concrete at steel level due to superimposed dead loads applied to the
member after transfer of pre-stress
Shrinkage of concrete (SH) Cl 18.5.2.2Factors like volume to surface ratio, relative humidity, time from end of moist curing to application ofpre-stress, affect shrinkage in concrete. Shrinkage is time-dependant and about 80% of the final loss dueto shrinkage occurs in the first year and 100% after several years.
Shrinkage strain
sh 0.0003 for pretensioned member
0.0002
log10 t 2 for posttensioned member and
may be increased by 50% in dry condition
but not more than 0.0003
Cl 5.2.4.1
Relaxation of steel (RE) Cl 18.5.2.3When elongation is sustained over pre-stressing cable for a long time, the pre-stress will decrease
gradually. The RE – loss due to relaxation depends on type of steel, time, as well as the ratio off i wheref p
f i is the initial pre-stress and f p is the characteristic strength of steel.
RELAXATION LOSSES FOR PRESTRESSING STEEL AT 1 000 H AT 27°C
INITIAL STRESS RELAXATION
INITIAL STRESS RELAXATION LOSS
N/mm2
0.5 fp
0.6 fp
0.7 fp
0.8 fp
0
35
70
90
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Anchorage slip (ANC) Cl 18.5.2.5In post-tensioning, when the jack is released, the full pre-stress is transferred to the anchorage and theytend to deform, allowing the tendon to slacken. Friction wedges will slip a little before they grip the wirefirmly. So, in post-tensioning the wedges are positively engaged before the jack is released. In pre-tensioning also, the anchorage slip is compensated for during stressing operation.
The loss is caused by a fixed shortening of the anchorages, so the percentage loss ishigher in shorter wires than in long ones.
If a tendon is stressed to 1035 MPa, with Es 2105 MPa and the anchorage slips by 2.5 mm,
Total 1035
0.0051752105
In a cable of 3m length, elongation l 0.005175 3000 15.53 mm , ie % l 2.5
15.53100 16%
But in a cable of 30 m length, elongation l 0.005175 30000 155.30 mm , ie
% l 2.5
100 1.6% only155.30
Frictional loss Cl 18.5.2.6Frictional loss comprise of two parts: (1) The length effect and (2) The curvature effect.
The length effect or the wobble effect of the duct is the friction that will exist between straight tendonand the surrounding material. This loss is dependant on the length and stress in the tendon, thecoefficient of friction between the contact materials, the workmanship and the method used in aligningand obtaining the duct.
The curvature effect is the loss due to intended curvature of the tendon. This again depends on thecoefficient of friction between the materials and the pressure exerted by the tendon on the curvature.
For un-bonded tendon, lubrication, in the form of grease and plastic tube wrapping can be used toadvantage.
For bonded tendon lubricant in the form of water soluble oils are used during stressing operation andflushed off with after before grouting.
Jacking from both ends of the beam will also reduce loss due to friction.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
5 5
For straight or moderately curved structures, with curved or straight cables, the value of pre-stressingforce Px at a distance x meters from tensioning end and acting in the direction of the tangent to thecurve of the cable, shall be calculated as below:
Px = Poe– ( μα + kx ).
Where Po = pre-stressing force in the pre-stressed steel at the tensioning end acting in the direction of
the tangent to the curve of the cable, α = cumulative angle in radians through which the tangent to thecable profile has turned between any two points under consideration, μ = coefficient of friction in curve;
unless otherwise proved by tests, μ may be taken as: 0.55 for steel moving on smooth concrete, 0.30 forsteel moving on steel fixed to duct, and 0.25 for steel moving on lead, k = coefficient for wobble or waveeffect varying from 15 × 10–4 to 50 × 10–4 per meter. The expansion of the equation for Px for small
values of (μα + kx) may be Px = Po (1 – μα – kx).
Examples
To calculate ES in Pre-tensioned beam - eccentric tendonA pre-tensioned beam of 100 mm x 300 mm is pre-stressed by straight wires with Fi = 150 kN at an e =
50 mm. ES = 2.1x10 MPa, EC = 0.35x10 MPa and AP = 188 mm2. Estimate ES.
AG = 100 x 300 = 30000 mm2
1003003
I =12
= 225x106 mm4
2.10n =
0.35= 6.0
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
c
F F e2
f i i
AG I
f c = 150103
30000
150103 5050
225106= -6.67 MPa
ES nf c
ES = 66.67 = 40.02 MPa
Loss =40.02188
150103= 5.02%
ES in Pre-tensioned beam - concentric tendonA straight pre-tensioned beam 12 m long of 380 mm x 380 mm is concentrically pre-stressed with 780
mm2 wires anchored to bulkheads with a f = 1035 MPa. E = 2x105 MPa, E = 0.33x105 MPa.
Estimate ES at transfer.i S C
Fi = 1035 x 780 = 807.30 kN
AG
AC
= 380 x 380
= AG - AS
= 144400 – 780
= 144400 mm2
= 143620 mm2
AT = AC + nAS
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Ac
Ac
5 5
= 143620 + 6x780 = 148300 mm2
2.00n =
0.33= 6.0
Ff i
T
807.30103
f c = = -5.44 MPa148300
ES nf c
ES = 65.44 = 32.66 MPa
If Fo 0.9Fi
FO = 0.90x807.30 = 726.57 kN
Ff O
G
726.57103
f c = = 5.03 MPa144400
ES = 5.03x6 = 30.18 MPa
ES in Pre-tensioned beam - Eccentric tendons at top & botA pre-tensioned beam of 200 mm x 300 mm is pre-stressed with 15#5mm wires located at 65 mm
from the bottom of the beam and 3#5mm wires located at 25 mm from the top of the beam. f i =
840 MPa. ES = 2.1x10 MPa, EC = 0.315x10 MPa. Estimate ES at transfer.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Aw = Area of one wire
52
=4
= 19.63 mm2
Fi = 18x19.63x840 = 296.81 kN
200 3003
I =12
= 450x106 mm4
n =
eeq =
2.10
0.315
1519.6384085 319.63840125
1819.63840
= 6.67
= 50 mm
fCTop Fi AG
Fi e yI t
fCTop
296.81103
= 60000
296.81103 50
450106125 = -0.824 MPa
fCBot Fi AG
Fi e yI t
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
i
5 5
fCBot
296.81103
= 60000
296.81103 50 85450 106
= -7.75 MPa
ES nf c
ESTop = 6.670.824
ESBot = 6.677.75
= 5.50 MPa
= 51.69 MPa
To calculate ES in Post-tensioned beamA straight post-tensioned beam 12 m long of 380 mm x 380 mm is concentrically pre-stressed with 780
mm2 wires made up of 4 tendons with 195 mm2 and the tendons are pre-stressed sequentially with a f
= 1035 MPa. ES = 2x10 MPa, EC = 0.33x10 MPa. Estimate ES at transfer.
The loss in the 1st tendon is due to the shortening of concrete by the pre-stressing of the previous 3
Fitendons. We can assume that Fi in each of these tendons are constant and f c n .AG
for the 1st tendon
31951035ES1 = 6 = 25.16 MPa
380380
for the 2nd tendon
21951035ES2 = 6 = 16.77 MPa
380380
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
st
nd
rd
th
for the 3rd tendon
11951035ES3 = 6 = 8.39 MPa
380380
There is no loss in the 4th tendon
The average loss
ESav =25.16 16.77 8.39
4= 12.58 MPa
When there are many cables, it is quite enough to assume that ESav1
of the loss in the 1st cable.2
Thus ESav =125.16
2= 12.58 MPa
If it is desired that there should be no loss at all, then the cables can be overstressed before anchorage.
So,
f i in 1 cable = 1035+25.16 = 1060.16 MPa
f i in 2 cable = 1035+16.77 = 1051.77 MPa
f i in 3 cable = 1035+8.39 = 1043.39 MPa
f i in 4 cable = 1035.00 MPa
But this stressing pattern is highly theoretical.
To calculate CR, SH and RE in post-tensioned beamA straight post-tensioned beam of size 100 mm x 300 mm is pre-stressed with 5 wires of 7 mm . The
5average pre-stress after short-term losses is f pe = 1200 MPa. The gae at loading is 28 days. ES = 2x105MPa, EC = 0.35x10 MPa. Estimate CR, SH and RE assuming fp = 1715 MPa.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
= 1.6 T.2c.1, Cl 5.2.5.1
2.00n =
0.35= 5.71
Aw = Area of one wire
7 2
=4
= 38.45 mm2
Fpe = 5x38.45x1200 = 230.7 kN
AG = 300 x 100 = 30000 mm2
1003003
I =12
= 225x106 mm4
F F ef cir
pe
AG
pe yI
= 230700
23070050
50 = -10.25 MPa30000 225106
CR = 1.6 5.7110.25 = 93.64 MPa
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
t = 28 days
sh 0.0002
log10 t 2Cl 5.2.4.1
0.0002 -4=log10 28 2 = 1.35x10
SH = sh ES
= 1.35x10-4 x (2x105) = 27 MPa
f pe = 1200 MPa
f pe
f p
1200=
1715= 0.699
70 %
f pe = 0.70 f p
RE = 70 MPa T.4, Cl 18.5.2.3
To calculate frictional losses – tensioned from one endA post-tensioned beam 100 mm × 300 mm of le = 10 m is stressed by successive tensioning andanchoring of 3 cables A, B, and C respectively as shown in figure. Each cable has cross section area of
200 mm2 and has initial stress of 1200 MPa. If the cables are tensioned from one end, estimate the
percentage loss in each cable due to friction at the anchored end. Assume μ = 0.35, K = 0.0015 / m.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
8y, the cable being considered a parabola of segment length = x and y = central sag.
x
L = 10000 mm for all cables
= 0.35
K = 0.0015 / m
Let F1 be the pre-stress at beginning of the 1st segment
Cable Lmm
KL y
mm
rad
KL eKL Stress @end of seg
A 10000 0.015 100 0.08 0.028 0.043 0.958 0.958F1
B 10000 0.015 50 0.04 0.014 0.029 0.971 0.931F1
C 10000 0.015 0 0 0 0.015 0.985 0.917F1
Loss = 1 – 0.917 = 0.08
= 8%
To calculate frictional losses – tensioned from both endsA pre-stressed concrete beam is continuous over two spans and its curved tendon is to be tensionedfrom both ends. Compute the percentage of loss of pre-stress due to friction from one end to the centerof the beam (A-E). The coefficient of friction between the cable and the duct is 0.40 and the averagewobble or length effect is represented by k = 0.0026/m. The cable is straight between A-B and C-D. Thechange in angle between BC is 0.167 radians and that between DE is 0.100 radians.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Segment L
m
KL
rad
KL eKL Stress @end of seg
AB 5.334 0.014 0 0 0.014 0.986 0.986F1
BC 7.620 0.020 0.167 0.067 0.087 0.917 0.904F1
CD 5.334 0.014 0 0 0.014 0.986 0.892F1
DE 3.048 0.008 0.100 0.040 0.048 0.953 0.850F1
Loss = 1 – 0.850 = 0.15
= 15%
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Chapter 2
DESIGN CONCEPTS
Flexural strength – Simplified procedures as per codes – strain compatibility method – Basic concepts inselection of cross section for bending – stress distribution in end block, Design of anchorage zonereinforcement – Limit state design criteria – Partial prestressing – Applications.
2.1 Analysis of beam section - concept
Sign convention1. Tension is (+)2. Compression is (-)
Different conceptsDifferent concepts can be applied to the analysis if PSC concrete beams, namely
1. Pre-stressing transforms concrete into an elastic material.2. Pre-stressing is a combination of high-strength steel and concrete.3. Pre-stress balances loads.
Elastic materialThis concept treats concrete as an elastic material and is the most common among engineers. Hereconcrete is visualized as being subjected to:
1. Internal pre-stress2. External loads.
So long as there are no cracks in the section, the stresses, strains and deflections of the concrete due tothe two systems of forces can be considered separately and superimposed if needed.
Due to a tensile pre-stressing force F, thee resulting stress at a section is given below.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
f F
Fey
My
A I I
The concrete stress at a section due to pre-stress f is dependant only on the magnitude and location of
pre-stress at that section, ie., F and e, regardless of how the tendon profile varies elsewhere along the
beam.
[Note: Stresses are calculated with force and eccentricity in steel.]
Ex 1A pre-stress concrete rectangular beam of size 500 mm x 750 mm has a simple span of 7.3 m and isloaded with a udl of 45 kN/m including its self-weight. An effective pre-stress of 1620 kN is produced.Compute the fiber stresses in concrete at mid-span section.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
F = 1620 kN
A
e
= 500 x 750 = 375000 mm2
= 145 mm
5007503
I =12
= 1.758 x1010 mm4
750y =
2= 375 mm
45 7.32
M =8
= 299.76 kN-m
f F
Fey
My
A I I
f = 1620000
375000
1620000145375
1.7581010
299.76106 375
1.7581010
= 4.32 5.01 6.39
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
f top = 4.32 5.01 6.39 = -5.70 MPa
f bot = 4.32 5.01 6.39 = -2.94 MPa
High strength steel and concreteThis considers the pre-stressed concrete as combination of steel and concrete similar to RCC. Tensionexists in steel and compression in concrete. These two form a internal resisting couple against external
moment produced by loads.
f C
Cey
A I
[Note: Stresses are calculated with force and eccentricity in concrete. e is the eccentricity of C, thecompressive force in concrete.]
Ex 2Solve Ex.1 using this concept.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
45 7.32
M =8
= 299.76 kN-m
C = T = 1620 kN
MLever arm a =
C
299.76106
=1620103
= 185 mm
C acts at = 185 + 230 = 415 mm from top
750e for C = 415 = 40 mm
2
f C
Cey
A I
f = 1620000
162000040375
375000 1.7581010
= 4.32 1.38
f top = 4.32 1.38 = -5.70 MPa
f bot = 4.32 1.38 = -2.94 MPa
Load balancingThe effect of pre-stressing is considered as the balancing of gravity loads so that the member underbending will not be subjected to flexural stresses under a given loading condition.
wup 8Pe
L2
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
wup 4Pe
L
wup Pe
aL
Due to a parabolic tendon of length l, sag h and stressed to F, wb 8Fh
l 2
f F
Mywhere M is the moment due to net loads.
A I
Ex 3Solve Ex.1 using this concept.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
w 8Fh
bl 2
wb =816200.145
7.32= -35.30 kN/m (up)
Net udl = 45.0 – 35.30 = 9.70 kN/m (down)
9.7 7.32
M =8
= 64.60 kN-m
f F
Myc A I
f c =1620000
375000
64.60106 375
1.7581010
= 4.32 1.38
f top = 4.32 1.38 = -5.70 MPa
f bot = 4.32 1.38 = -2.94 MPa
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
G
Analysis of beam section for flexure
Stress in concrete and steel due to pre-stress only
If
F = pre-stress (whether initial or final) and applied through the centroid.
Ff c =
Awhere A is the area of concrete
Using the transformed method, stress in concrete is uniform even at the level of steel
f c = Fi
AC nAS
F F= i or i
AT AG
Stress in steel
f s = n f c
nF= i
AC nAS
nF= i Which represents the immediate reduction in pre-stress in steel at transfer.
AT
But is approximated to,
nF= i where A
AG
is the gross area, the error being about 2% to 3 %
Example - Pre-tensioned member – concentric tendonA pre-tensioned beam of size 200 mm x 300 mm is concentrically pre-stressed with 520 mm2 wires
anchored to bulkheads with a f i = 1035 MPa. Assuming n = 6, compute the stresses in concrete and
steel immediately after transfer due to pre-stress only.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
AG = 200 x 300 = 60000 mm2
Fi = 520 x 1035 = 538.20 kN
538.20 103
f c = at level of steel = -8.9760000
ES
= 68.97 = -53.82 MPa
f Pe (aft. loss) = 1035.00 – 53.82 = 981.00 MPa
f cTop,Bot (aft. loss)
F= e
AG
981520= = -8.50 MPa
60000
Example - Pre-tensioned member – eccentric tendonA pre-tensioned beam of size 200 mm x 300 mm is eccentrically pre-stressed with 520 mm2 wires
anchored to bulkheads with a f i = 1035 MPa. The cgs is 100 mm above the bottom of the beam.
Assuming n = 6, compute the stresses in concrete and steel immediately after transfer due to pre-stressonly.
Fi = 1035 x 520 = 538.20 kN
e
AG
= 150 – 50
= 200 x 300
= 50 mm
= 60000 mm2
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Ac
c
200 3003
I =12
= 450 x106 mm4
F F e2
f i i at level of steelAG I
f c = 538.20103
60000
538.20103 5050
450106= -11.96 MPa
ES nf c
ES = 611.96 = 71.76 MPa
f Pe (aft. loss) = 1035.00 – 71.76 = 963.24 MPa
Fe = 983.24 x 520 = 500.88 kN
f cTop,Bot (aft. loss)
Fe= AG
Fe ey
I
3 3
= 500.8810
500.8810 50
15060000 450106
= 8.348 8.348
f top = 8.348 8.348 = 0 MPa
f bot = 8.348 8.348 = -16.70 MPa
f c at level of steel could also be approximated to
Ff i
G
In that case
500.88103
f c = = 8.34860000
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
ES nf c
ES = 6 x 8.348 = 53.82 MPa
f Pe (aft. loss) = 1035.00 – 53.82 = 981.18 MPa
Fe = 981.18 x 520 = 510.21 kN
f cTop,Bot (aft. loss)
3 3
=510.2110
510.2110 50
15060000 450106
f top = 8.50 8.50 = 0 MPa
f bot = 8.50 8.50 = -17.0 MPa
Which show that the approximate method is fast and quite accurate.
Example - Post-tensioned member – eccentric tendonA post-tensioned beam of size 200 mm x 300 mm is eccentrically pre-stressed with 520 mm2 wires
stressed to a f i = 1035 MPa. The cgs is 75 mm above the bottom of the beam. Immediately after
transfer the stress reduces by 5% owing to anchorage and other losses. The size of the duct is 50 mm x
75 mm. Compute the stresses in concrete and steel immediately after transfer due to pre-stress only.
Fi = 1035 x 520 = 538.20 kN
Fe = 0.95 x Fi
= 0.95 x 538.20 = 511.29 kN
e = 150 – 50 = 50 mm
AG = 200 x 300 = 60000 mm2
200 3003
I =12
= 450 x106 mm4
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
f cTop,Bot (aft. loss)
Fe= AG
Fe ey
I
3 3
= 511.2910
511.2910 75
15060000 450106
= 8.52 12.78
f top = 8.52 12.78 = 4.26 MPa
f bot = 8.52 12.78 = -21.30 MPa
Stress in concrete due to pre-stress & loadsStresses in concrete produced by external bending moment, whether due to the beam’s self-weight orapplied load is:
f M
yc I
The resulting stress in concrete due to both the pre-stress and loads is:
f F
Fey
Myc A I I
Example - Post-tensioned member with loadsA post-tensioned beam of size 300 mm x 600 mm and le = 12 m is pre-stressed with1575 kN which
eventually reduces to 1350 kN due to losses. The cgs is 175 mm above the bottom of the beam. Thebeam carries two live loads of 45 kN each in addition to its self-weight of 4.5 kN/m. Compute theextreme fiber stresses at mid-span for (a) initial condition with full pre-stress and no live load and (b)pre-stress after losses with full live load.
Fi = 1575 kN
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Fe = 1350 kN
e
AG
= 300 – 175
= 300 x 600
= 125 mm
= 180000 mm2
3006003
I =12
= 5400 x106 mm4
MG =4.5103 122
8= 81 kN-m
ML = 45 4.5 = 202.5 kN-m
MT = 81 + 202.5 = 283.50 kN-m
Initial condition
F F e Mf i i y yc A I I
3 3 6
= 157510
157510 125
300 8110
300180000 5400106 5400106
= 8.75 10.94 4.5
f cTop = 8.75 10.94 4.5 = -2.31 MPa
f cBot = 8.75 10.94 4.5 = -15.19 MPa
Final condition
F F e Mf e e y yc A I I
3 3 6
=135010
135010 125
300 283.510
300180000 5400106 5400106
= 7.5 9.38 15.75
f cTop = -13.87 MPa
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
f cBot = -1.13 MPa
Example - Post-tensioned member with loadsSolve Ex 6.2.1 by locating the center of pressure C for concrete section.
Fe = 1350 kN
MT = 81 + 202.5 = 283.50 kN-m
283.50106
a =1350103
= 210 mm
e = 210 – 125 = 85 mm
C = Fe = 1350 kN
f C
Ceyc A I
3 3
= 135010
135010 85
300180000 5400106
= 7.5 6.37
f cTop = 7.56.37 = -13.87 MPa
f cBot = 7.5 6.37 = -1.13 MPa
Stress in steel due to loadsIn RCC members, the lever arm between the resultant compression and tension remains almostconstant but the tension in steel increases almost proportionately with increasing moment till yielding.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
In pre-stress concrete resistance to external bending moments is furnished by a lengthening of the leverarm between the resisting forces C and T which remain relatively unchanged in magnitude.
After cracking, the stress in pre-stressing steel increases rapidly with moment.
The following sketch explains the variations of the stress in pre-stressing steel
The variations are shown for bonded and un bonded tendons.
f p with increasing load.
After the pre-stress is transferred while the member is supported at the ends, the stress will tend to
increase from the value after losses f po due to the moment under self weight. Simultaneously the stress
will tend to drop due to the time dependent losses such as creep, shrinkage and relaxation. The
effective pre-stress after time dependent losses is denoted as f pe .
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Due to the moment under service loads, the stress in the pre-stressing steel will slightly increase from
f pe . The increase is more at the section of maximum moment in a bonded tendon as compared to the
increase in average stress for an un bonded tendon.
The stress in a bonded tendon is not uniform along the length. Usually the increase in stress is neglectedin the calculations under service loads. If the loads are further increased, the stress increases slightly tillcracking.
After cracking, there is a jump of the stress in the pre-stressing steel. Beyond that, the stress increases
rapidly with moment till the ultimate load. At ultimate, the stress is f pu .
Similar to the observation for pre-cracking, the average stress in an un bonded tendon is less than thestress at the section of maximum moment for a bonded tendon.
As discussed above, at the section of maximum moment, the stresses in the un bonded tendonincreases more slowly than that for bonded tendon. This is because any strain in an un bonded tendonwill be distributed throughout its entire length.
If MR is the resultant moment in at a cross-section of a bonded beam and the beam deflects downwards,there is an increase in steel stress due to this bending given by
f s nf c nM R yI
Let M be the moment at any given point of an un bonded beam, f c the stress in concrete at a section,
f M
yc I
If c is the strain in concrete in that section
c f
Ec
M
yEc I
Then , the total strain along the cable is,
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
E I
M dx
c
ydx
M
L Ec
ydxIL
is the average strain
The stress in steel f s
E s Mf s E s
n
L Ec
M
ydxIL
ydxL I
Example – stress in steelA post-tensioned beam of span le = 12 m and size 300 mm x 600 mm, carries a superimposed load of 11kN/m in addition to its own weight of 4.5 kN/m. The initial pre-stress in steel is 950 MPa and reduces to820 MPa after all losses and assuming no bending in beam. The cable of are 1600 mm2 is parabolic. N=6.Compute the stress in steel at mid-span assuming (a) the steel is bonded by grouting and (b) the steel isun bonded and entirely free to slip.
Bonded tendon:
Fi = 1600 x 950 = 1520 kN
Fe = 1600 x 820 = 1312 kN
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
s
e at mid span = 125 mm
A = 300 x 600 = 180000
3006003
I =12
= 5400 x106 mm4
wt ws wG
= 4.5 + 11.0 = 15.50 kN/m
w l 2
M t eT 8
15.5103 12 2
=8
= 279 kN-m
Moment due to Fe
= 1312 x 125 = -164 kN-m
MR = 279 – 164 = 115 kN-m
At level of steel
f M R yc I
115106
= 1255400106
= 2.66 MPa
Increase in stress in steel
f s = nf c
= 6 x 2.66 = 15.97 MPa
Resultant f s = 820 + 16 = 836 MPa
Un bonded beam
f n M
L Iydx
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
2
2
2
L
from the BMD and y diagram
M M 1 x
o L
2
y y 1x
o L 2
2
2
f nM y 1
x dxs LI2
o o l
2
f 8n M o yo where
nM o yo is the stress at mid span of a bonded beam = 16 MPa.s 15 I I
f 8
16 = 8.53 MPas 15
Resultant f s = 820 + 8.53 = 828.53 MPa
Cracking momentMoments producing first crack in a pre-stressed concrete beam, assuming cracks start when tensile
stress in the extreme fiber of concrete reaches its modulus of rupture, f cr ,
f cr 0.7 f ck cl 5.2.2
Therefore cracks appear when
F F e Mf e e y
y orcr A I I
F I f IM F e e cr
e Ay y
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
ExampleFor the problem in 6.3.1 compute the total dead and live load that can be carried by the beam for (a)
zero tensile stress at bottom fiber and (2) cracking in the bottom fiber assuming
1350 kN.
f cr 4.2MPa and Fe =
To obtain zero stress in the bottom fiber, the center of pressure must be located at the top kern point
a = (e+kt)
= 125 + 100 = 225 mm
M = Fe x a
w 8M
Tl 2
= 1350000 x 225 = 303.75 kN-m
8303.75106
=12000 2
= 16.87 kN/m
For cracking moment, additional moment
f cr I=
y
4.25400106
=300
= 75.6 kN-m
M = 303.75 + 75.60 = 379.35 kN-m
wT =8379.35106
12000 2= 21.07 kN/m
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
At transfer: At working load
Fi Fi e M GTop: A
Z
Z f tt (1)
Fi Fi e M GBot: A
Z
Z f ct (2)
Fe Fee M G M LTop: f cw (3)A Z Z Z
Fe Fee M G M LBot: f tw(4)A Z Z Z
2.2 Elastic Design for flexure
Derivations
t t t t t
b b b b b
TakingFe Fi
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
t f b f
tt ct
t
b
F F e M F F e M i i f G (1) i i f G (2)
A Z t Z t A Z b Z b
Fi Fi e M G M L Fi Fi e
M G M L
A Z t Z t Z t
f cw(3)
A Z b Z b Z b
f tw(4)
M G M G M L M G
M G M L f tt Z t
Z t Z t
f cw(3) f ct Z b
Z b Z b
f tw(4)
M G 1nM L
Z t
f cw f tt f tr (3)M G 1nM L
Z b
f tw f ct f cr (4)
M 1 nM M 1 nMZ G L (5)
tr
Z G L (6)cr
Max. pre-stressing force is limited by
1. Tension at top - f tt during transfer – Eq.1
2. Min. Comp stress at bottom - f tw during working load – Eq.4
Therefore from Eq.1 and Eq.2 and taking
F F ef i i
t A Z
F F ef i i
b A Z
f t f tt
M G (7) form Eq.1
Z t
f b M G Z b
M L
Z b
f tw(8) from Eq.4
M M
f 1 f G L (8)b tw
Z b
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
t
b
bt
b
A
A
Also, since:
f Fi
Fi e(a)A Z t
F F ef i i (b)
A Z b
Fi e f t
Fi ZA
t
(a)
f Fi fb A
t Fi
Z t (b)A Zb
f Fi Zb Z t f
Z t b A Z Z
F f Z f Zi b b t t (9)A Z b Z t
f F 1
e (a )t i Z t
f F 1
e (b )b i Zb
f t Zb Ae Z t
fb Z t Ae Zb
Z Z f f Ae b t b t (10)
f t Z t fb Zb
Remember, in these equations:
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
i
b
b
i
f t f tt
M G
Z t
1 M M f b f tw
G L Z b
When MG is large as will be the case for long span and/or heavy girders, the computed eccentricity efrom Eq.10, may fall below the bottom of the beam. In that case, the e available is worked out and Fi isincreased suitably.
Fi for know eccentricity e working load is:
F F e 1 M M f i i f G L from Eq.4b A Z
twZ b
From the first part of the above equation
F F ef i i
A Z b
Z Ae F b
AZ b
f AZ F b b (11)
Z b Ae 2.3 Permissible stresses for flexure member
Steel – Cl 8.5.1Steel stress for pre-tensioned tendons immediately after transfer or post-tensioned tendons afteranchorage is:
f pi 0.87 f pu
Where f pi = Maximum initial pre-stress, and f pu = Ultimate tensile stress in tendon.
Concrete in compression – Cl 22.8.2.1, 22.8.1.1Concrete stress after transfer and before losses in extreme fiber
Compression = 0.54 fck to 0.37 fck (for M30 to M60) for post-tension
= 0.51 fck to 0.44 fck (or M40 to M60) for pre-tension
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Concrete stress at service loads after transfer and after losses in extreme fiber
Compression = 0.41 fck to 0.35 fck (for M30 to M60) for post-tension
= 0.34 fck to 0.27 fck (or M40 to M60) for pre-tension
Concrete in tension – Cl 22.7.1Concrete stress after transfer and before losses in extreme fiber
1. For Type 1 members, Tension = 0.2. For Type 2 members, Tension = 3.0 MPa to 4.5 MPa3. For Type 3 members, Tension = 4.1 MPa to 4.8 MPa
Concrete stress at service loads after transfer and after losses in extreme fiber
Tension = same as at transfer before losses
Example
Depth not restricted - beamDesign a post-tensioned beam of le = 12 m to carry a live load of 12 kN/m throughout its length. The
width of beam b = 250 mm. f ct f cw 17MPa and f tt f tw 1.4MPa . = 0.85.
Assume depth of beam = h mm
A = 250h mm2
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
f
0.25
h 22412
MG = 1000
8= 0.108h kN-m
ML =1212 2
8= 216 kN-m
Min Z is governed by Zb. From Eq.4
f cr
f cr
f tw f ct
= 1.4 0.8517
= 15.85 MPa
M 1 nMZ G L (6)b f cr
0.108h10.85106 216106
=15.85
106 216 0.0162h=
15.85
Z b also =250h 2
6
From which
h = 580 mm
A = 250 x 580 = 145x103 mm2
Zt = Zb = Z =2505802
6= 14x106 mm3
MG = 62.64 kN-m
f t f tt
M G
Z t
= 1.462.64106
14106= 5.87 MPa
1 M M f b tw
G L Z b
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
=
6
1 62.64 216106 1.4
6= -21.76 MPa
0.85 1410
F f Z f Zi b b t t (9)A Z b Z t
=21.765.8714106
2 14106
= 7.945
Fi = 7.945 x 145 x103 = 1152 kN
Z Z f f Ae b t b t (10)
f t Z t fb Zb
14141012 21.76 5.87=
14106 5.87 21.76= 24.3436x10
e = 167.89 mm
Depth restricted - slabA post-tensioned concrete bridge slab of le = 10 m is 380 mm thick. It is stressed with parallel cables
stressed to 360 kN each. wL = 25 kN/m2. Losses are 20%.
spacing of cable at mid-span.
f tt f tw 0.7MPa . Calculate the emax and
= 0.80
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
1
f
A = 1000 X 380 = 380000 mm2
10003803
I =12
= 4572.66 x106 mm4
Zt = Zb = Z =4572.6610 6
380
= 24.07 x106 mm3
2
ws = 1 x 0.38 x 24 = 9.12 kN/m
MG =9.1210 2
8= 114 kN-m
ML =25102
8= 312.50 kN-m
M G
Z
114106
=24.07 106
= 4.74
M L
Z
312.5106
=24.07106
= 12.98
At mid-span
f t f tt
M G
Z t
= 0.7 4.74 = 5.44 MPa
1 M M f b tw
G L Z b
= 0.7 4.7412.980.8
= -21.275 MPa
F f Z f Zi b b t t (9)A Z b Z t
=21.2755.4424.07106
2 24.07106
= 7.9175
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
6
tw
Fi = 7.9175 x 380 x103 = 3008.65 kN
Z Z f f Ae b t b t (10)
f t Z t fb Zb
24.0724.071012 21.275 5.44=
24.07106 5.44 21.275= 40.6081 x10
e mid-span = 106.86 mm
At support
MG = ML = 0
e at support = 68.944
A more complicated solution is:
At mid-span, the stress at top and bottom at transfer and working load are respectively.
Fi A
Fi e Z t
M G
Z t
f tt (1)
Fe Fe e M G M L A Z b Z b Z b
f tw(4)
ie. Fi A
Fi e Z b
M G Z b
M L
Z b
f tw(4)
Multiplying Eq.1 by and adding it to Eq.4 above, and remembering Zt = Zb = Z,
2Fi 1 M G
M L f f ttA Z Z
Fi 20.8 1 0.8 4.74 12.98 0.7 0.80.7 from whichA
Fi = 3009 kN
Likewise, multiplying Eq.1 by and subtracting it from Eq.4 above,
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
tw 2Fi e 1M G
M L f f ttZ Z Z
Fi e 20.8 1 0.8 4.74 12.98 0.7 0.80.7A
e at mid-span = 106.358 mm
At support
MG = ML = 0
Fi A
Fi e
Z t
0 f tt (1)
6 6
300910
300910 e
0.7380000 24.07106
e at support = 68.944
Spacing of cables
Fi = 3009 kN
Force per cable = 360 kN
No of cables =3009103
3601039 Nos
Spacing =1000
9= 112 mm c/c
Depth not restricted - slabA post-tensioned concrete one-way bridge slab of le = 10 m is stressed with parallel cables stressed to
500 kN each. wL = 25 kN/m2. Losses are 20%. f ct f cw 15MPa and f tt f tw 0 .
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
= 0.80
Assume depth of slab = h mm
Width of slab = 1000 mm
A = 1000h mm2
1
h 22410
MG = 1000
8= 0.3 kN-m
ML =25102
8= 312.5 kN-m
Min Z is governed by Zb. From Eq.4
f cr
f cr
f tw f ct
= 00.815
= 12 MPa
M 1 nMZ G L (6)b f cr
0.3h1 0.8106 312.5106
=12
106 312.5 0.06h=
12
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
f
=
6
Z b also =100h 2
6
From which
h = 410 mm
A = 1000 x 410 = 410000 mm2
Zt = Zb = Z =1000410 2
6= 28.02x106 mm3
MG = 123 kN-m
f t f tt
M G
Z t
123106
= 028.02106
= 4.39 MPa
1 M M f b tw
G L Z b
1 123 312.50106 0
6= -91.43 MPa
0.8 28.0210
F f Z f Zi b b t t (9)A Z b Z t
19.43 4.39=
2= 7.52
Fi = 7.52 x 410000 = 3083.20 kN
Z Z f f Ae b t b t (10)
f t Z t fb Zb
28.02106 19.43 4.39=
4.3919.43= 443.774 x10
e mid-span = 108.24 mm
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
No of cables =3084 103
500 1037 Nos
Spacing =1000
7= 143 mm c/c
Depth restricted - beamA pre-tensioned simply supported beam of size 80 mm x 120 mm and le = 3 m caries two 4 kN loads at
third points along the span. Losses are 20%. f tt 0, f tw 1.4MPa . Design the beam with 3mm wires
for f i 1400 MPa each.
= 0.80
A = 80 X 120 = 9600 mm2
801203
I =12
= 11.52 x106 mm4
Zt = Zb = Z =11.5210 6
120
= 0.192 x106 mm3
2
ws = 0.08 x 0.12 x 24 = 0.23 kN/m
MG =0.23 32
8= 0.2592 kN-m
ML = 41 = 4.0 kN-m
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
1
f
6
M G
Z
0.2592106
=0.192106
= 1.35
M L
Z
4.0106
=0.192 106
= 20.83
At mid-span
f t f tt
M G
Z t
= 01.35 = 1.35 MPa
1 M M f b tw
G L Z b
= 1.4 1.35 20.830.8
= -25.975 MPa
F f Z f Zi b b t t (9)A Z b Z t
=25.9751.35
2= 12.3125
Fi = 12.3125 x 9600 = 118.20 kN
Z Z f f Ae b t b t (10)
f t Z t fb Zb
0.192106 25.975 1.35=
1.35 25.975= 0.213x10
e = 22.193 mm
Aw = Area of one wire
32
=4
= 7.07 mm2
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
f
=
6
f i in one wire = 7.07 x 1400 = 9.896 kN
No of cables =118.20 103
9.896 10312 Nos
Spacing =1000
9= 112 mm c/c
below bottom in heavy girder - beamAn unsymmetrical I section has the following sectional property: h = 1000 mm, A = 345 000 mm2, Zt = 95x106 mm3, Zb = 75 x 106 mm3, cgc = 440 mm from top, MG = 1012 kN-m, ML = 450 kN-m. Design the
section if f ct f cw 15MPa and f tt f tw 0 . = 0.85
f t f tt
M G
Z t
= 01012x106
95106= 10.65 MPa
1 M M f b tw
G L Z b
1
1012 450106
0 6
= -22.93 MPa0.85 7510
F f Z f Zi b b t t (9)A Z b Z t
22.93 7510.6595=
75 95= 4.1647
Fi = 4.1647 x 345000 = 1436.82 kN
Z Z f f Ae b t b t (10)
f t Z t fb Zb
75951012 22.9310.65=10.6595 22.93 75106
= 361.339 x10
e = 1047.36 mm
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
i
eavil = yb – cover
= (1000-440) – 100 = 460 mm
For this eavil, the Fi required is:
f AZ F b b (11)
Z b Ae
Fi =22.93 34500075106
75106 345000460= 2538.78 kN
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
2.4 End block
Bursting forceA portion of a pre-stressed member surrounding the anchorage is the end block. Through the length ofthe end block, pre-stress is transferred from concentrated areas to become linearly distributed fiberstresses at the end of the block. The theoretical length of this block, called the lead length is not morethan the height of the beam.
But the stress distribution within this block is rather complicate.
The larger transverse dimension of the end zone is represented as yo. The corresponding dimension ofthe bearing plate is represented as ypo. For analysis, the end zone is divided into a local zone and ageneral zone.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
The local zone is the region behind the bearing plate and is subjected to high bearing stress and internalstresses. The behavior of the local zone is influenced by the anchorage device and the additionalconfining spiral reinforcement.
The general zone is the end zone region which is subjected to spalling of concrete. The zone isstrengthened by end zone reinforcement.
The transverse stress (σt) at the CGC varies along the length of the end zone. It is compressive for adistance 0.1yo from the end and tensile thereafter, which drops down to zero at a distance yo from theend.
The transverse tensile stress is known as splitting tensile stress. The resultant of the tensile stress in atransverse direction is known as the bursting force (Fbst).
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Besides the bursting force there is spalling forces in the general zone.
Fbst for an individual square end zone loaded by a symmetrically placed square bearing plate according
to Cl 18.6.2.2 is,
y po Fbst PK 0.32 0.3
yo
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Where, PK = pre-stress in the tendon;
dimension of the end zone.
y po = length of a side of bearing plate; yo = transverse
It can be observed that with the increase in size of the bearing plate the bursting force
Fbst reduces.
End Zone reinforcementTransverse reinforcement - end zone reinforcement or anchorage zone
reinforcement or bursting link - is provided in each principle direction based on the value of Fbst. Thereinforcement is distributed within a length from 0.1yo to yo from an end of the member.
The amount of end zone reinforcement in each direction Ast is:
FA bst
st f s
The parameter represents the fraction of the transverse dimension covered by the
bearing plate.
The stress in the transverse reinforcement, f s = 0.87fy.
When the cover is less than 50 mm, f s = a value corresponding to a strain of 0.001.
The end zone reinforcement is provided in several forms, some of which are proprietary of theconstruction firms. The forms are closed stirrups, mats or links with loops.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Bearing plate & End blockDesign the bearing plate and the end zone reinforcement for the following bonded
post-tensioned beam. The strength of concrete at transfer is 50 MPa. A pre-stressing force of 1055 kN isapplied by a single tendon. There is no eccentricity of the tendon at the ends.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Bearing Plate
Assume area of bearing plate to be 200 mm x 300 mm
Pf K
br Apun
PK = 1055 kN
Apun = 200 x 300 = 60000 mm2
f br
1055103
=60000
= 17.58 MPa
Abr
f 0.48 f
= 400 x 600 = 240000 mm2
Abrbr,all ci Apun
= 0.4850240000
60000= 48 MPa
0.8 f ci = 40 MPa
fbr fbr,all 40MPa
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
End Block
In vertical direction
y po Fbst PK 0.32 0.3
yo
1055
.32 0.3300
= 179.35 kN= 0 600
In horizontal direction
y po Fbst PK 0.32 0.3
yo
1055
.32 0.3200
= 179.35 kN= 0 400
Ast =Fbst
0.87 f y
179.35103
=0.87250
= 824.60 mm2
Provide 10 mm 2L stirrups in both directions as Fbst is same in those
Aw = 10 2
4= 78.54 mm2
No of stirrups =
2 rd
824.60
2 78.54
1 rd
= 6 Nos
Provide3
Ast from 0.1 yo = 60 mm to 0.5 yo = 300 mm and3
Ast from 0.5 yo = 300 mm to yo = 600
mm, both vertically and horizontal.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Chapter III
CIRCULAR PRESTRESSING
Design of prestressed concrete tanks – Pipes.
3.1 Design Procedure for circular tanks Computations
1. Minimum wall thickness
2. Circumferential Prestress
3. Vertical Prestress.
Estimate
1) Maximum, ring tension Nd
2) Bending Moment Mw
3) Minimum wall thickness = Ndηfct – fmin.w
Minimum cover 35mm
4) Circumferential Prestress
fc = Nd + fmin.w N/mm2
ηt η
5) Spacing of wires
As = Cross sectional area of wire coinding, mm2
Wt = average radial Pressure of wires at transfer at a given section N/mm2
D = Diameter of the tank, mm
S = Spacing of wires at the given section mm
fs – Stress in wires at transfer, N/mm2
t – Thickness of the tank wall, mm
fc – compressive stress in concrete, N/mm2
Hoop compression due toprestressing
= wt . D2
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Equating wt. D = fs As2 S1
Wt = 2 fs AssD
Nd – hoop tension due to hydrostatic working pressure, Ww
Nt – hoop compression due to radial pressure of wires, wt
Then Nt = Nd wtWw
Also Nt = t fc
Spacing of the wire winding
S = 2 Nd . fs. As mmWw fc. Dt
Mt = Mw wtWw
Where Mt = Vertical moment due to the prestress at transfer.
Mw = Vertical moment due to hydrostatic pressure.
The compressive prestress required
Fc = fmin. W + Mwη ηz
When the tank is empty
fc = fmin. W + Mtη Z
Vertical prestressing force is required
P = fc. Ac
(Note: Vertical Prestressing force = 30% of hoop compression.]
1. A cylindrical prestressed concrete water tank of internal diameter 30m is required to storewater over a depth of 7.5m. The permissible compressive stress in concrete at transfer is 13
N/mm2 and the minimum compressive stress under working presuure is 1 N/mm2. The loss ratiois 0.75. Wires of 5mm diameter with an initial stress of 1000N/mm2 are available for
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
circumferential winding and freyssinet cables made up of 12 wires of 8mm diameter stressed to1200N/mm2 are to be used for vertical prestressing. Design the tank walls assuming the base asfixed. The cube strength of concrete is 40N/mm2.Solution:
From table 16.1Assume t = 150mm
H2 = 7.52 = 12.5Dt 30 x 0.15
Ww = wH = 10 x 7.5 = 75kN/m2 = 0.075N/mm2
From table 16.2 & 16.3
Maximum ring tension Nd = (coefficient) wHR kN/m
= 0.64 x 10 x 7.5 x 15
= 720kN/m = 720N/mm.
Moment in tank wall for the fixed base condition = (coefficient) Wh3 kNm/m
= 0.01 x 10 x 7.53
= 42.5 kNm/m
= 42500Nmm/mm
Minimum wall thickness = t = Ndηfct –fmin.w
= 720 = 82.3mm0.75 x 13 – 1
Net thickness available (allowing for vertical cables of diameter 30mm) is (150 – 30) = 120mm
fc = Nd + fmin.wηt η
= 720 + 1 = 9.42N/mm2
0.75 x 120 0.75
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Spacing of circumferential wire winding at base.
S = 2 Nd fs. AsWw fc. Dt
= 2 x 720 x 1000 x π/4)(5)2
0.075 x 9.4 x 30 x 103 x 120
= 11.4mm
Number of wires / metre = 87
Ring tension Nd at 0.1 H (0.75m) from top
Nd = (coeff) wHR kN/m
= 0.097 X 10 X 7.5 X 15 = 109 kN/m = 109N/mm
fs = 2 x 109 x 1000 x 200.075 x 2.5 x 30 x 103 x 120
= 64mm
Number of wires / metre t the top of tank = 16
Vertical moment = Mw wtWw
Wt = 2 fs As = 2 X 1000 X 20 = 0.117 N/mm2
Sd 11.4 x 30 x 103
Mt = 42500 0.117 = 67,000 Nmm / mm = 67 x 106 Nmm / m.0.075
Considering one metre length of tank
Along the circumferential
Z = 100 x 1502 = 375 x 104mm3
6
fc = fmin. w + Mtη Z
= 1 + 67X 106 = 19.20N/mm2
0.75 375 X 104
Since this stress exceeds the permissible value of fct = 13N/mm2, the thickness of the tank wall of base isincreased to 200mm.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Z = 1000 x1002 = 666 x104 mm3
6
fc = 1 + 67 x 106 = 12N/mm2
0.75 666 x 104
Vertical Prestressing force = fc = A = 12 x 1000 x 2001000
= 2400kN
Using 8mm diameter (12Nos.) Freyssinet cables
Force / cable = π/4 x 82 x 12 x 1200 = 720kN1000
Spacing = 1000 x 720 = 800mm2400
App. Vertical Prestress = 0.3 fc
= 0.3 x 9.4 = 2.82 N/mm2
Vertical prestressing force = 2.82 x 1000 x 2001000
= 564kN
Ultimate tensile force = 87 x 20 x 1500 = 2610kN1000
Load factor = 2610 / 720 = 3.6
Direct tensile strength of concrete = 0.267 √40
= 1.7N/mm2
Cracking load = 1000 x 200 0.75 x 9.4 + 1.71000
= 1760Kn
F.S against cracking = 1760 / 720 = 2.45
Nominal reinft. 0.2 percent circumferential & longitudinal directions
8mm ф @ 300mm spacing on both faces at a cover of 20mm.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
A
Ac
3.2 Circular pre-stressing
Circumferential pre-stressCircumferential pre-stressing is done to resist hoop tension in circular structures, like water-tanks andpipes. Essentially each horizontal slice of the wall forma a ring subjected to uniform internal pressure.This ring may be considered as a pre-stresses concrete member under tension.
Considering one half of a thin cylindrical slice of a tank as a free-body: under the action of pre-stress Fi insteel, the total compression C in the concrete equals Fi. The C-line coincides with the cgs line, which is aconcordant cable linearly transformed.
Due to pre-stress, initially after transfer of pre-stress,
Ff i , A = Area of concretec C
c
Ff e
c
which after losses in pre-stress reduces to
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Ac
c
When internal liquid pressure is acting at working load stage, the internal pressure intensity,
f pR
T
where
p = internal pressure intensity
R = internal radius of the vessel
AT = transformed area = Ac nAp
AP = area of steel
The resultant stress in concrete at working load due to internal pressure ‘p’ and pre-stress Fe is
F pRf e (1)
Ac AT
In Eq.1, if it is assumed that hoop tension is entirely carried by the effective pre-stress, Fe pR .
And since At Ac ,
concrete.
f c is always negative, implying that there is always a residual compressive stress in
Design method 1Ap = area of steel
Ac = area of concrete
f ct = permissible stress at transfer in concrete
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
f
f
A A
f cw = permissible stress at working load in concrete
Fi = initial pre-stress
Fe = effective pre-stress after losses
m = factor of safety
En s
Ec
Fi Ap f i
Fe Ap f e
At transfer
A Fi (2)c
ct
At working load
Fe
Ac
pR
AT
f cw (3) where At Ac nAp
Assuming that hoop tension is entirely carried by the effective pre-stress, Fe pR ,
A pR
p f e
Fi Ap f i
FA i from Eq.2c
ct
F pRf e
from Eq.3cw
c T
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
c
Design method 2If both f ct and f cw are to be kept in concrete, which may be the case when a tensile stress f cw =
cracking stress, may be allowed, and if a factor of safety ‘m’ is required, then Eq.2 and Eq.3 can becombined together into the following from.
Ap = area of steel
Ac = area of concrete
f ct = permissible stress at transfer in concrete
f cw = permissible stress at working load in concrete
Fi = initial pre-stress
Fe = effective pre-stress after losses
m = factor of safety
En s
Ec
Fi Ap f i
Fe Ap f e
At transfer
F f i ApA i f ct f ct
At Ac nAp Ap
f(n i )
f ct
At working load
F mpR e
f cwAc AT
f e Ap mpR f cw
Ap
f i
f ct
Ap n
f i f ct
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
ct
i ct
Ap f ct
f e
f i
f cw
mpR
nf ct f i
f ct
f e f ct f i f cw mpR
Ap
f i
nf ct f i
f ct
AmpR
p nf f i f e f ct f i f cw fct f i
mpR
f ct f i f f f n ct 1 f f e f i
cw f i f ct
mpR
f f f e f i
cw 1 n ct f ct f i
3.3 Design of pipesPre-stressed concrete pipes are suitable when the internal pressure is within 0.5 to 2.0
Mpa. There are two types of pre-stressed concrete pipes:
1. Cylinder type which has a steel cylinder core, over which the concrete is cast and pre-stressed.2. Non-cylinder type which is made of pre-stressed concrete only.
IS:784-2001 Pre-stressed Concrete Pipes (Including Specials), provides guidelines for the design of pre-stressed concrete pipes with the internal diameter ranging from 200 mm to 2500 mm. The pipes aredesigned to withstand the combined effect of internal pressure and external loads. The minimum gradeof concrete in the core should be M40 for non-cylinder type pipes.
The pipes are manufactured either by,
1. Centrifugal method: In the centrifugal method the mould is subjected to spinning till theconcrete is compacted to a uniform thickness throughout the length of the pipe.
2. Vertical casting method: In the vertical casting method, concrete is poured in layers up to aspecified height.
After adequate curing of concrete, first the longitudinal wires are pre-stressed. Subsequently, thecircumferential pre-stressing is done by the wire wound around the core in a helical form. The wire iswound using a counter weight or a die. Finally a coat of concrete or rich cement mortar is applied overthe wire to prevent from corrosion. For cylinder type pipes, first the steel cylinder is fabricated andtested. Then the concrete is cast around it.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
5
f
Example 1 – non-cylinderDesign a non-cylinder pre-stressed pipe for the following specifications: R = 300 mm, p = 1.05 MPa, f i =
1000 MPa, f e = 800 MPa, f ct = -14 MPa, f cw =-0.7 MPa, Es = 2.1x10 MPa, Ec = 0.35 x 105 MPa and 2.5
mm wires are used. And what would be the internal pressure ‘p’ required to balance the pre-stress attransfer before losses to maintain a stress of -0.7 in concrete?
Method 1:
Assuming that hoop tension is entirely carried by the effective pre-stress, Fe pR ,
A pR
p f e
Ap =1.05103 300
800= 394 mm2
Fi Ap f i
Fi
FA i
= 3941000 = 394 kN
cct
Ac =394103
14= 28143 mm2
Taking a 1000 mm height of the pipe
28142t = = 29 mm
1000
30 mm
Ac = 301000 = 30000 mm2
Checking for final stress
At Ac nAp
At = 30000 6394 = 32364 mm2
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
A A
F pRf e cw
c T
f cw
394800=
30000
1.05103 300
32364= -0.77 MPa
Since f cw is slightly more than specified -0.7 MPa, another trail could be made in the design.
Aw = 2.52
4= 4.91 mm2
ApNo of wires =
Aw
394=
4.9181 wires
Spacing =1000
81= 12 mm
Method 2:
Ap mpR
f f f e f i
cw 1 n ct f ct f i
Ap =
1.05103 300
0.7 14
= 388 mm2
8001000
1 614
1000
Fi = 3881000 = 388 kN
Ac =388103
14= 27715 mm2
27715t = = 28 mm
1000
Ac = 281000 = 30000 mm2
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
5
Checking for final stress
At = 28000 6388 = 30328 mm2
f cw
388800=
28000
1.05103 300
30328= -0.70 MPa
At transfer before losses,
f cw
3881000=
28000
p103 300
30328= -0.7 MPa
p = 1.33 MPa
Example 2 – non-cylinderDesign a non-cylinder pre-stressed pipe for the following specifications: R = 800 mm, p = 1 MPa, f i =
1000 MPa, f e = 800 MPa, f ct = -12 MPa, f cw = 0, Es = 2.1x10 MPa, Ec = 0.35 x 105 MPa and 5 mm wires
are used. If cracking stress is +2 MPa, what is the F.S against cracking?
Ap mpR
f f f e f i
cw 1 n ct f ct f i
Ap =
1103 800
0 12
= 933 mm2
800 1000
1 612
1000
Fi = 9331000 = 933 kN
Ac =933103
12= 77750 mm2
77750t = = 78 mm
1000
Checking for stresses
Ac = 781000 = 78000 mm2
At = 78000 6933 = 83598 mm2
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
f cw
933800=
78000
1103 800 = 0
83598
If cracking stress is allowed, f cw = 2 MPa
Ap mpR
f f f e f i
cw 1 n ct f ct f i
m1103 800
933 = 2 12 8001000
1 612
1000
m = 1.2
3.4 Design of circular water tanksConcrete liquid retaining structures must be impervious. Hence, their design is based on no in crackingin concrete. Circular pre-stressed liquid retaining structures, are stressed to avoid tension in concrete.
Pre-stressed concrete liquid retaining structures require low maintenance and resist seismic forcessatisfactory.
Circular pre-stressed concrete tanks are used in water treatment, water distribution, storm watermanagement, large industrial tanks, bulk storage tanks and for storing liquefied natural gas (LNG).
The construction of the circular tanks is in the following sequence. First, the concrete core is cast andcured. The surface is prepared by sand or hydro blasting. Next, the
circumferential pre-stressing is applied by strand wrapping machine. Shotcrete is
applied to provide a coat of concrete over the pre-stressing strands.
IS:3370-1967 (1-4) Code of Practice for Concrete Structures for the Storage of Liquids providesguidelines for the analysis and design of liquid storage tanks. The four sections of the code are titled asfollows:
Part 1: General Requirement.
Part 2: Reinforced Concrete Structures.
Part 3: Pre-stressed Concrete Structures.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Part 4: Design Tables.
In IS:3370-1967 (3), the design requirements for pre-stressed tanks are mentioned. A few of them are:
1. The computed stress in the concrete and steel, during transfer, handling and construction, andunder working loads, should be within the permissible values as specified in IS:1343-1980.
2. The liquid retaining face should be checked against cracking with a load factor of 1.2.3. The ultimate load at failure should not be less than twice the working load.4. When the tank is full, there should be compression in the concrete at all points of at least 0.7
N/mm2. When the tank is empty, there should not be tensile stress greater than 1.0 N/mm2.Thus, the tank should be analyzed both for the full and empty conditions.
5. There should be provisions to allow for elastic distortion of the structure during pre-stressing.Any restraint that may lead to the reduction of the pre-stressing force should be considered.
6. The cover requirement is as follows. The minimum cover to the pre-stressing wires should be 35mm on the liquid face. For faces away from the liquid, the cover requirements are as perIS:1343-1980.
The general equations from Eq 1 to Eq 3, would serve well for the design of circular pre-stressedliquid retaining structure.
Example 1Determine the area of steel required per meter height of a circular pre-stressed water tank with aninside diameter of 18 m and a height of 6 m water pressure. Compute the thickness of concrete
required.
f i = 1034 MPa, f e = 827 MPa, f ct = -5.17, MPa and n = 10.
Design for the following two cases:
1. Assume that the entire hoop-tension is carried by the effective pre-stress.2. For a load factor of 1.25, producing zero stress in concrete. f ct = -5.17, f cw =0.
Case 1:
p =6101000
106(on an area of 1m x 1m) = 0.06 MPa
Assuming that hoop tension is entirely carried by the effective pre-stress, Fe pR ,
A pR
p f e
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
f
A A
Ap =0.06103 9000
827= 653 mm2
Fi Ap f i
Fi
FA i
= 6531034 = 675 kN
cct
Ac =675103
5.17= 130600 mm2
Taking a 1000 mm height of the pipe
t =130600
= 130.60 mm1000
140 mm
Ac = 1401000 = 140000 mm2
Checking for final stress
At Ac nAp
At = 140000 10 653
F pRf e
= 146530 mm2
cwc T
f cw
653827=
140000
0.06103 9000
146530= -0.172 MPa
Case 2:
Ap mpR
f f f e f i
cw 1 n ct f ct f i
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Ap =
1.250.06103 9000= 778 mm2
0 5.17 827 1034
1105.17
1034
Fi = 7781034 = 805 kN
Ac =805103
5.17= 156 x103 mm2
156103
t =1000
= 156 mm
165 mm
Ac = 1651000 = 165000 mm2
Checking for final stress
At = 165000 10 778 = 172780 mm2
f cw
778827=
165000
0.06103 9000
172780= -0.77 MPa
If we had provided the actual
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Chapter IV
COMPOSITE CONSTRUCTION
Analysis for stresses – Estimate for deflections – Flexural and shear strength of composite members.
4.1 INTRODUCTIONMany applications of prestressed concrete involve the combination of precast prestressed concretebeams and in situ reinforced concrete slabs. Some examples of such composite construction are shownin Fig. 10.1. An in situ infill between precast beams is shown in Fig. 10.1(a) while an in situ topping isshown in Fig. 10.1(b). The former type of construction is often used in bridges, while the latter iscommon in building construction. The beams are designed to act alone under their own weight plus theweight of the wet concrete of the slab. Once the concrete in the slab has hardened and provided thatthere is adequate horizontal shear connection between them, the slab and beam behave as a compositesection under design load. The beams act as permanent formwork for the slab, which provides thecompression flange of the composite section. The section size of the beam can thus be kept to aminimum, since a compression flange is only required at the soffit at transfer. This leads to the use ofinverted T-, or ‘top-hat’, sections.
4.2 SERVICEABILITY LIMIT STATEThe stress distributions in the various regions of the composite member are shown in Fig. 10.2(a)–(d).The stress distribution in Fig. 10.2(a) is due to the self weight of the beam, with the maximumcompressive stress at the lower extreme fibre. Once the slab is in place, the stress distribution in thebeam is modified to that shown in Fig. 10.2(b), where the bending moment at the section, Md is thatdue to the combined self weight of the beam and slab.
Once the concrete in the slab has hardened and the imposed load acts on the composite section, theadditional stress distribution is shown in Fig. 10.2(c). This is determined by ordinary bending theory, butusing the composite section properties.The final stress distribution is shown Figure
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Stress distribution within a composite section.
The floor slab shown in Fig. 10.3 comprises precast pretensioned beams and an in situ concrete slab. Ifthe span of the beams is 5 m and the imposed load is 5 kN/m2 (including finishes), determine the stress
distributions at the various load stages. Assume all long-term losses have occurred before the beams areerected and that the net force in each wire is 19.4 kN. Section properties of the beams:Ac=1.13×105 mm2Ic=7.5×108 mm4Zt=Zb=6×106 mm3.Eccentricity of the wires=125−40=85 mm.(i) Self weight of the beams=0.113×24=2.7 kN/m.Mo=(2.7×52)/8=8.4 kNm.Total prestress force after all losses have occurred is given byßPo=6×19.4=116.4 kN.The stress distribution in the beams is thus given by
(ii) The weight of the slab is supported by the beams acting alone, so that Md=8.4+0.075×0.6×24×52/8=11.8 kNm.The stress distribution within the beams is now given by(iii) The imposed load of 5 kN/m2 is supported by the composite section and the
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
section properties of this are now required. To find the neutral axis of the composite section, takingmoments about the soffit of the beams gives(1.13×105+75×600)y=(1.13×105×125+75×600×288)∴y=171 mm.Icomp=7.5×108+1.13×105 (171–125)2+(753×600)/12+(75×600)/(288–171)2=1.63×109 mm4.The imposed load bending moment, (Mdes−Md)=0.6×5×52/8=9.4 kNm.The stress distribution within the composite section under this extra bending momentis given by
The maximum compressive stress occurs at the upper fibres of the beams, but is significantly lower thanthe level of stress had the beam carried the total imposed load alone. This explains the advantage ofinverted T-sections in composite construction, where only a small compression flange is required forbending moments Mo and Md, the
Stress distribution for composite section in Example 10.1 (N/mm2): (a) beam; (b)beam and slab; (c)beam and slab and imposed load.
compression flange for bending moment Mdes being provided by the slab. The maximum compressivestress in the slab is much lower than in the beam and, for this reason, in many composite structures alower grade of concrete is used for the in situ portion. The modulus of elasticity for this concrete islower than that for the beam and this effect can be taken into account in finding the composite sectionproperties by using an approximate modular ratio of 0.8.The in situ slab in Example 10.1 lies above the composite section neutral axis and, therefore, the slab isin compression over its full depth under the total design load. However, for composite sections asshown in Fig. 10.1(a) the in situ portion of the section extends well below the neutral axis, so that thelower region is in tension. If the tensile strength of this concrete is exceeded then the composite sectionproperties must be determined on the basis of the in situ section having cracked below the neutral axis.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
4.3 ULTIMATE STRENGTHThe basic principles for the analysis of prestressed concrete sections at the ultimate limit state offlexural strength described in Chapter 5 are also applicable to composite sections. For the section shownin Fig. 10.5(a), it may be assumed initially that, at the ultimate limit state, the neutral axis lies within theslab and the section may then be treated effectively as a rectangular beam. The position of the neutralaxis should later be checked to see whether it does, indeed, fall within the slab. For the section shown inFig. 10.5(b), the position of the neutral axis may be determined on the assumption that the section isrectangular,
but the different strengths of the concrete in the slab and beam regions of the compression zone shouldbe taken into account.
4.4 HORIZONTAL SHEARThe composite behaviour of the precast beam and in situ slab is only effective if the horizontal shearstresses at the interface between the two regions can be resisted. For shallow members, such as thatshown in Fig. 10.3, there is usually no mechanical key between the two types of concrete, and reliance ismade on the friction developed between the contact surfaces. For deeper sections, mechanical shearconnectors in the form of links projecting from the beam are used, which provide a much better shearconnection. The determination of the horizontal shear resistance is based on the ultimate limit state,and if this condition is satisfied it may be assumed that satisfactory horizontal shear resistance isprovided at the serviceability limit state. A simply supported composite section carrying a uniformlydistributed load is shown in Fig. 10.8(a) and the free-body diagram for half the length of the in situ slabis shown in Fig. 10.8(b). At the simply supported end there must be zero force in the slab, while themaximum force occurs at the midspan. The distribution of shear forces on the underside of the slab isalso shown in Fig. 10.8(b), being zero at midspan and reaching a maximum at the support. Thisbehaviour is similar to that in an elastic beam, where the vertical and horizontal shear stresses increasetowards the support for a uniformly distributed load.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
The following expression is given in Part 1–3 of EC2 for the horizontal shear stress, where ß is the ratioof the longitudinal force in the slab to the total longitudinal force, given by Msd/z, both calculated for agiven section; Vsd is the transverse ultimate shear force; z is the lever arm; and bj is the width of theinterface.
The design shear resistance for horizontal joints with vertical shear reinforcement is given byτRdj=kTτRd+μσN+0.87 fykϱ μ≤0.33 vfck,where kT is a coefficient with kT=0 if the joint is subjected to tension;τRd is the basic design shear strength from Table
Horizontal shear: (a) composite section; (b) free-body diagram for in situ slab.
DIFFERENTIAL MOVEMENTSThe fact that the slab of a composite member is usually cast at a much later stage than the beam meansthat most of the time-dependent effects of shrinkage of the slab take place with the section actingcompositely. Most of the shrinkage of the beam will already have occurred by the time the slab is inplace, and the movement due to the shrinkage of the slab will induce stresses throughout the whole ofthe composite section. The water content of the slab concrete is often higher than that of the beam,since a lower strength is required, and this aggravates the problem of differential shrinkage. These extrastresses, which occur even under zero applied load, are not insignificant and should be considered indesign. Both the slab and beam undergo creep deformations under load and, although some of thecreep deformations in the beam may have taken place before casting of the slab, the level ofcompressive stress is higher in the beam, and so the creep deformations are larger.
Load-deflection curve for composite section in Example 10.4.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Differential movements.
composite section which tend to reduce those set up by differential shrinkage. A problem which isencountered, particularly in connection with bridge decks, is that of varying temperature across acomposite section, although this may still be a problem in composite members used as roof structures.The hotter upper surface tends to expand more than the cooler lower surface and stresses are inducedthroughout the composite section.
A method for determining the stresses due to differential shrinkage will now be outlined, and this can beadapted to find the stresses due to differential creep and temperature movements. Consider acomposite member as shown in Fig. 10.13, where the slab is shown to have a free shrinkage movementof δsh relative to the beam. In reality this movement is restrained by the shear forces which are set upbetween the slab and beam, putting the slab into tension and the beam into compression. Themagnitude of the tensile force in the slab is given byT=εshAc,slabEc,slab,where Ac,slab and Ec,slab are the cross-sectional area and modulus of elasticity of the slab, respectively,and εsh is the free shrinkage strain of the slab concrete.The compressive force in the beam must be numerically equal to this tensile force. In addition to thedirect stresses described above, bending stresses are also introduced by restraint of the free differentialshrinkage. In order to determine these stresses, the free bodies of the slab and beam are considered, asshown in Fig. 10.14. Initially, the slab can be regarded as having a force T applied through its centroid, sothat its length is equal to that of the beam. There must be no net external force on the compositemember due to differential shrinkage alone, so a pair of equal and opposite compressive forces must beapplied to maintain equilibrium. However, these compressive forces act on the composite section andinduce a bending moment at the ends of the member of
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Internal stress resultants due to differential movements.
Stresses due to differential movements.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
Chapter V5.1 PRESTRESSED CONCRETE BRIDGES
General aspects – pretensioned prestressed bridge decks – Post tensioned prestressed bridge decks –Principle of design only.
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
CE2404 Prestressed Concrete Structures
SCE Dept of Civil
PRE STRESSED CONCRETE VII/IV CIVIL ENGINEERING
1 P.JAGATEESH 2015-16
UNIT-I
INTRODUCTION-THEORY AND BEHAVIOUR PART A
1. What are the advantages of PSC construction
In case of fully prestressed member, which are free from tensile stresses
under working loads, the cross section is more efficiently utilized when
compared with a reinforced concrete section which is cracked under working
loads.
The flexural member is stiffer under working loads than a reinforced
concrete member of the same length.
2. Define Pre tensioning and Post tensioning
Pre tensioning: A method of Pre stressing concrete in which the tendons are
tensioned before the concrete is placed. In this method, the prestress is
imparted to concrete by bond between steel and concrete.
Post tensioning: A method of pre stressing concrete by tensioning the
tendons against hardened concrete. In this method, the prestress is imparted
to concrete by bearing.
3. What is the need for the use of high strength concrete and tensile steel in Pre
stressed concrete?
High strength concrete is necessary for prestress concrete as the material
offers highly resistance in tension, shear bond and bearing. In the zone of
anchorage the bearing stresses being hired, high strength concrete is
invariably preferred to minimizing the cost. High strength concrete is less
liable to shrinkage cracks and has lighter modulus of elasticity and smaller
ultimate creep strain resulting in a smaller loss of prestress in steel. The use
of high strength concrete results in a reduction in a cross sectional
dimensions of prestress concrete structural element with a reduced dead
weight of the material longer span become technically and economically
practicable.
Tensile strength of high tensile steel is in the range of 1400 to 2000 N/mm2
and if initially stress upto 1400 N/mm2 their will be still large stress in the high
tensile reinforcement after making deduction for loss of prestress. Therefore high
tensile steel is made for prestress concrete.
4. Define Kern Distance.
Kern is the core area of the section in which if the load applied tension
will not be induced in the section
Kt = Zb/A, Kb = Zt/A,
If the load applied K Compresser will be the maximum at the top most fiber
and zero stress will be at the bottom most fiber. If the load applied at Kb
compressive stress will be the maximum at the bottom most fiber and zero
stress will be at the top most fiber.
PRE STRESSED CONCRETE VII/IV CIVIL ENGINEERING
2 P.JAGATEESH 2015-16
5. What is Relaxation of steel?
When a high tensile steel wire is stretch and maintained at a constant strain
the initially force in the wire does not remain constant but decrease with
time. The decrease of stress in steel at constant strain is termed relaxation of
steel.
6. What is concordant prestressing?
Pre stressing of members in which the cable follow a concordant profile. In
case of statically indeterminate structures. It does not cause any changes in
support reaction.
7. Define bonded and non bonded prestressing concrete.
Bonded prestressing: Concrete in which prestress is imparted to
concrete through bond between the tendons and surrounding concrete.
Pre tensioned members belong to this group.
Non-bonded prestressing: A method of construction in which the tendons
are not bonded to the surrounding concrete. The tendons may be placed in
ducts formed in the concrete members or they may be placed outside the
concrete section.
8. Define Axial prestressing
Members in which the entire cross-section of concrete has a uniform
compressive prestress. In this type of prestressing, the centroid, of the
tendons coincides with that of the concrete section.
9. Define Prestressed concrete.
It is basically concrete in which internal stresses of a suitable magnitude
and distribution are introduced so that the stresses resulting from external
loads (or) counteracted to a desire degree in reinforced concrete member
the prestress is commonly introduced by tensioning the steel reinforcement
10. Define anchorage.
A device generally used to enable the tendon to impart and maintain
prestress to the concrete is called anchorage. e.g. Fressinet, BBRV
systems,etc.,
PRE STRESSED CONCRETE VII/IV CIVIL ENGINEERING
3 P.JAGATEESH 2015-16
PART-B
1. a) What are the advantages of Prestressed Concrete
In case of fully prestressed member, which are free from tensile stresses
under working loads.
The cross section is more effectively utilized when compared with a
reinforced concrete section which is cracked under working loads.
Within certain limits, a permanent will be counteracted by increasing the
eccentricity of the prestressing force in a prestressed structural elements, thus
effecting saving in the use of materials.
Prestressed concrete members possess improved resistance to shearing forces,
due to the effect of compressive prestress, which reduces the principal tensile
stress.
The use of high strength concrete and steel in prestressed members
results in lighter and slender members than is possible with reinforced
concrete.
It is free from cracks, contributes to the improved durability of the structure
under aggressive environmental conditions.
The economy of prestressed concrete is well established for long span
structures.
A prestressed concrete flexural member is stiffer under working loads
than a reinforced concrete member of the same depth.
PRE STRESSED CONCRETE VII/IV CIVIL ENGINEERING
4 P.JAGATEESH 2015-16
b) Describe briefly Fressinet system of post tensioning
PRINCIPLES OF POST-TENSIONING:
In post-tensioning, the concrete units are first cast by incorporating ducts
or grooves to house the tendons. When the concrete attains sufficient strength, the high-
tensile wires are tensioned by means of jack bearing on the end face of the member and
anchorags by wedges or nuts.
FREYSSINET SYSTEM OF POST TENSIONING:
The Freyssinet system of post-tensioning anchorages which was
developed in 1939.
The Freyssinet anchorage system, which is widely used in Europe and
India, consists of a cylinder with a conical interior through which the high-tensile wires
pass and against the walls of which the wires are wedged by a conical plug lined
longitudinally with grooves to house the wires. The main advantages of the Freyssinet
system is that a large number of wires or strands can be simultaneously tensioned using
the double-acting hydraulic jack.
2. a) Discuss about the importance of control of deflections and the factors
influencing the deflection of PSC beams
Importance of control of deflection:
The structural concrete members shall designed to have adequate stiffness to limit
deflections, which may adversely affect the strength or serviceability of the
structure at working loads.
Suitable control on deflection is very essential for the following reasons:
Excessive, sagging of principal structural members is not only unsightly,
but at times, also renders the floor unsuitable for the intended use.
Large deflections under dynamic effects and under the influence of
variable loads may cause discomfort to the users.
Excessive deflections are likely to cause damage to finishes, partitions
and associated structures.
FACTORS INFLUENCING DEFLECTIONS:
The deflections of prestressed concrete members are influenced byy the following
salient factors:
Imposed load and self weight
Magnitude of the prestressing force
Cable profile
Second moment of area of cross section
Modulus of elasticity of concrete
Shrinkage, creep and relaxation of steel stress
Span of the member
Fixity conditions
PRE STRESSED CONCRETE VII/IV CIVIL ENGINEERING
5 P.JAGATEESH 2015-16
b) Describe the various types of losses in prestress. What steps may be taken to reduce
these losses
LOSS DUE TO ELASTIC DEFORMATION OF CONCRETE:
The loss of prestress due to elastic deformation of concrete depends on the
modular ratio and the average stress in concrete at the level of steel.
If fc= prestress in concrete at the level of steel.
Es= modulus of elasticity of steel.
Ec= modulus of elasticity of concrete.
αe= Es/ Ec = modular ratio.
Strain in concrete at the level of steel = (fc/ Ec)
Stress in steel corresponding to this strain = (fc/ Ec) Es
Loss of stress in steel = αe fc
If the initial stress in steel is known, the percentage loss of stress due to the
elastic deformation of concrete can be computed.
LOSS DUE TO SHRINKAGE OF CONCRETE:
The shrinkage of concrete in prestressed members results in a shortening
of tensioned wires and hence contributes to the loss of stress. The
shrinkage of concrete is influenced by the type of cement and aggregates
and the methowd of curing used of high-strength concrete with low water
cement ratios result in a reduction in shrinkage and consequent loss of
prestress.
According IS1343 for the loss of prestress due to the shrinkage of
concrete
Єcs = total residual shrinkage strain having values of 300x106
for pre
tensioning and [200x106/log10(t+2)]
Where, t = age of concrete at transfer in days.
The loss of stress in steel due to the shrinkage of concrete is estimated as,
Loss of stress = Єcs x Es
LOSS DUE TO CREEP OF CONCRETE:
The sustained prestress in the concrete of a prestressed member results in
creep of concrete which effectively reduces the stress in high-tensile steel.
The loss of stress in steel due to creep of concrete can be estimated if the
magnitude of ultimate creep strain or creep coefficient is known.
ULTIMATE CREEP STRAIN METHOD:
If Єcc = ultimate creep strain for a sustained unit stress
fc = Compressive stress in concrete at the level of steel.
Es = modulus of elasticity of steel.
Loss of stress in steel due to creep of concrete = Єcc fc Es
CREEP COEFFICIENT METHOD:
PRE STRESSED CONCRETE VII/IV CIVIL ENGINEERING
6 P.JAGATEESH 2015-16
If = creep coefficient
Єc = creep strain
Єe = elastic strain
αe = modular ratio
fc = stress in concrete
Es = modulus of elasticity of steel.
Ec = modulus of elasticity of concrete.
Creep coefficient( ) = (Єc/ Єe)
Loss of stress in steel = fc αe
LOSS DUE TO RELAXATION OF STRESS INN STEEL:
Most of the code provides for the loss of stress due to relaxation of steel as
a percentage of the initial stress in steel. The Indian standard code
recommends a value varying from 0 to 90 N/mm2
for stress in wire
varying from 0.5 fup to 0.8 fup .
LOSS OF STRESS DUE TO FRICTION:
On tensioning the curved tendons, loss of stress occurs in the post-
tensioned members due to friction between the tendons and the
surrounding concrete ducts. The magnitude of this loss is of the following
types:
(a) Loss of stress due to the curvature effects, which depends upon
the tendon from or alignment which generally follows a curved profile along the
length of the beam.
(b) Loss of stress effect, which depends upon the local deviation
in the alignment of the cable. The wobble or wave effect is the result of accidental
or unavoidable misalignment, since ducts or sheaths cannot be perfectly located to
follow predetermined profile throughout the length of the beam.
Px = Poe-(µα+ kx)
LOSS DUE TO ANCHORAGE SLIP:
In most post-tensioned system, when the cable is tensioned and the jack is
released to transfer prestress to concrete, the friction wedges, employed to
grip the wires, slip over a small distance before the wires are firmly
housed between the wedges. The magnitude of slip depends upon the type
of wedge and the stress in the wire.
∆ = (PL/AEs)
Where ∆ = slip of anchorage, mm
L = length of the cable,mm
A = cross sectional area of the cable, mm2
Es = modulus of elasticity of steel.
P = Prestressed force in the cable.
PRE STRESSED CONCRETE VII/IV CIVIL ENGINEERING
7 P.JAGATEESH 2015-16
3.A prestressed concrete beam of section 120 mm wide by 300 mm deep is
used over an effective span of 6 m to support a uniformly distributed load
of 4 kN/m, which includes the self-weigbt of the beam. The beam is
prestressed by a straight cable carrying a force of 180 kN and located at an
eccenlricity of 50mm. Determine the location of the thrust-line in the
beam and plot its position at quarter and central span sections.
P=180kN
E=50mm
A=36000mm2
z=1800000mm3
Stresses due to prestressing force:
P/A(180X10^3/36X10^3) = +5 N/mm2
Pe/Z = (180 x 103 x 50) /(18x10^5) = +5 N/mm^2
Bending moment at the centre of the span= (0.125 x 4 x 62) =
18 kN m
Bending stresses at top and bottom=(18x10^6/18x10^5) =+ 10 N/mm^2
Resultant stresses at the central section :
At top =(5-5+10)=10 N/mm^2
At bottom =(5+5-10)=0 N/mm^2
Shift of pressure –lne from cable –line(M/P)=( (180 x 106) /(18x10^4)=100mm
Bending moment at quarter span section=(3/32)qL2= (3/32)x4x62
=13.5kNm
Bending stresses at top and bottom =(13.5x10^6/18x10^5)=7.5 N/mm^2
Resultant stresss at quarter span section:
At top =(5-5+7.5)=7.5 N/mm^2
At bottom =(5+5-7.5)=2.5 N/mm^2
Shift of pressure –lne from cable –line(M/P)=( (13.5x 106) /(18x10^4)=75mm
PRESTRESSED CONCRETE IV/VII CIVIL ENGINEERING
1 P.JAGATEESH 2015-16
PRESTRESSED CONCRETE STRUCTURES
UNIT-II
DESIGN CONCEPTS
PART-A
1. What is meant by end block in a post tensioned member?
The zone between the end of the beam and the section where only longitudinal
stress exists is generally referred to as the anchorage zone or end block.
2. List any two applications of partial prestressing.
Used in large diameter concrete pipes
Used in railway sleepers
Water tanks
Precast concrete piles to counter tensile stress during transport and erection.
used in bridges construction
3. What is meant by partial prestressing?
The degree of prestress applied to concrete in which tensile stresses to a limited
degree are permitted in concrete under working load. In this case, in addition to
tensioned steel, a considerable proportion of untensioned reinforcement is
generally used to limit the width of cracks developed under service load.
4. Define degree of prestressing
A measure of the magnitude of the prestressing force related to the resultant
stress occurring in the structural member at working load.
5. Define Bursting tension.
The effect of transverse tensile stress is to develop a zone of bursting tension in a
direction perpendicular to the anchorage force resulting in horizontal cracking.
6. Define Proof stress
The tensile stress in steel which produces a residual strain of 0.2 percent of the
original gauge length on unloading.
7. Define cracking load.
The load on the structural element corresponding to the first visible crack.
8. Define Debonding.
Prevention of bond between the steel wire and the surrounding concrete.
9. Write formula for Moment of resistance in BIS code.
Mu = Apb Aps (d-dn)
10. What are the types of flexural failure?
Fracture of steel in tension
Failure of under-reinforced section
Failure of over-reinforced section
Other modes of failure
PRESTRESSED CONCRETE IV/VII CIVIL ENGINEERING
2 P.JAGATEESH 2015-16
PART-B
1. a) What is meant by partial prestressing? Discuss the advantages and disadvantages when
partial prestressing is done
PARTIAL PRESTRESSING:
The degree of prestress applied to concrete in which tensile stresses to a
limited degree are permitted in concrete under working load. In this case,
in addition to tensioned steel, a considerable proportion of untensioned
reinforcement is generally used to limit the width of cracks developed
under service load.
ADVANTAGES:
Limited tensile stresses are permitted in concrete under service
loads with controls on the maximum width of cracks and
depending upon the type of prestressing and environmental
condition.
Untensioned reinforcement is required in the cross-section of a
prestresseed member for various reasons, such as to resist the
differential shrinkage, temperature effects and handling stresses.
Hence this reinforcement can cater for the serviceability
requirements, such as control of cracking, and partially for the
ultimate limit state of collapse which can result in considerable
reduction in the costlier high tensile steel.
Saving in the cost of overall structure.
DISADVANTAGES:
The excessive upward deflections, especially in bridge structure
where dead loads from a major portion of the total service loads,
and these deflections may increase with time of creep.
PRESTRESSED CONCRETE IV/VII CIVIL ENGINEERING
3 P.JAGATEESH 2015-16
(b) Explain about the types of flexure failure occurs in prestressed concrete section
PRESTRESSED CONCRETE IV/VII CIVIL ENGINEERING
4 P.JAGATEESH 2015-16
PRESTRESSED CONCRETE IV/VII CIVIL ENGINEERING
5 P.JAGATEESH 2015-16
2. (a) Explain concept of limit states, partial safety factor.
Partial safety factors, are therefore used for each limit state being reached.
The values of partial safety loads recommended in the British, Indian
and American codes.
IS code:
Load combination Limit state of collapse Limit state of serviceability
DL LL WL DL LL WL
DL+LL 1.5 1.5 - 1.0 1.0 -
DL+WL 1.5 - 1.5 1.0 - 1.0
DL+LL+WL 1.2 1.2 1.2 1.0 0.8 0.8
Partial safety factor for materials has a values which depends on the
important of limit states being materials to which is applies difference between
strength of materials when tested and when incorporated in construction during the
service life.
(b) Discuss difference in load deflection of under prestressed, partially prestressed and
fully prestressed.
The load deflection characteristics of a typical prestressed concrete members
and discussed below:
If the beam is sufficient loaded, tensile stresses is develop in the soffit and
when this exceed the tensile strength of concrete, cracks are likely to develop in the
member.
PRESTRESSED CONCRETE IV/VII CIVIL ENGINEERING
6 P.JAGATEESH 2015-16
The load deflection curve is approximately linear upto the stage of visible
cracking, but beyond this stage the deflection increase at a faster rate due to the
reduced stiffness of the beam.
In the port- cracking of the beam of beam is parallel to that of reinforced
concrete member.
The deflection of cracked structural member, may be estimated by the unilinear or
bilinear method recommended by the ECC.
In the unilinear method, the deflection will be,
a= βL2M/ Ec Ir
where a = Max deflection
L = Effective span
M = Max moment
Ec = Modulus of elasticity of concrete
Ir = IInd
commend of area.
In the bilinear method, the moment curvature is approximately by second straight
line.
The instantaneous deflection in the post cracking stage is obtained as the sum
of deflection upto cracking load based on gross section and beyond the cracking
load considering the cracked section.
Hence deflection are estimated by
a= βL2
{(Mcr/ EcIc)+((M-Mc)/0.85Ecfck)}
PRESTRESSED CONCRETE IV/VII CIVIL ENGINEERING
7 P.JAGATEESH 2015-16
3. The end block of a post-tensioned PSC beam, 300 x 300 mm is subjected to a
concentric anchorage force of 832.8 kN by a Freyssinet anchorage of area
11720 mm2. Design and detail the anchorage reinforcement for the end
block.(NOV-DEC 2009)
Prestressing Concrete,P= 832800 N
Average compressive stress, fc= (832800/300x300) =9.3 N/mm2
2ypo = (π/4xd2)
(1/2) = √(11720x4/π = 123mm
2yo = 300/2 = 150mm
Ypo/yo = (123/300)=0.41
Fc = P/A = 832.8/(300x300) = 9.25N/mm2
Tensile stress Fv(max) =fc(0.98 – 0.825 ypo/yo) = 9.3(0.98 – 0.825x0.41) = 6 N/mm2
Bursting tension Fbst = p(0.48 – 0.4 ypo/yo)
= 832800(0.48-0.4x0.41)
= 264000N
Using 10mm diameter mild steel links with yield stress of 260
N/mm2
Ast = Fbst/0.87fy = (260x103)/(0.87x260) = 706.85mm
2
Number of reqd =(264000/(0.87x260x79))= 15
The reinforcement is to be arranged in the zone 0.2 yo=(0.2x150)
=30mm
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
1 P.JAGATEESH 2015-16
UNIT III
Circular prestressing
Part A
1. Sketch the loop reinforcement, hair-pin bars in end blocks.(NOV-DEC 2009)
2. Sketch the correct arrangement of sheet cage in anchorage zone.(NOV-DEC 2009)
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
2 P.JAGATEESH 2015-16
3. Define two stage constructions.(NOV-DEC 2012)
One-stage construction: Construct and initialize the object in one stage, all
with the constructor.
Two-stage construction: Construct and initialize the object in two separate
stages.
The constructor creates the object and an initialization function initializes it.
4. Write any two general failures of prestressed concrete tanks.(NOV-DEC 2012)
deformation of the pre-cast concrete units during construction
Manufacturing inaccuracies led to out of tolerance units being delivered to the
site under investigation and may have affected the ability to achieve a good
seal.
5. Mention the importance of shrinkage in composite construction?
(NOV-DEC 2010)
The time dependent behavior of composite prestressed concrete
beams depends upon the presence of differential shrinkage and creep of the
concretes of web and deck, in addition to other parameters, such as relaxation
of steel, presence
of untensioned steel, and compression steel etc.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
3 P.JAGATEESH 2015-16
Part B
1. Explain the effect of varying the ratio of depth anchorage to the depth of end block
on the distribution of bursting tension. (8) (NOV-DEC 2012)
Bursting tensile forces
a) The bursting tensile forces in the end blocks, or regions of bonded post-
tensioned members, should be assessed on the basis of the tendon jacking load.
For unbonded members, the bursting tensile forces should be assessed on the basis
of the tendon jacking load or the load in the tendon at the limit state of collapse,
whichever is greater ( see Appendix B ).
The bursting tensile force, Fbst existing in an individual square end block loaded
by a symmetrically placed square anchorage or bearing plate, may be derived from
the equation below:
b) The force Fbst will be distributed in a region extending from 0.1 yo to yo from
the loaded face of the end block. Reinforcement provided to sustain the bursting
tensile force may be
assumed to be acting at its design strength (0.87 times
characteristic strength of reinforcement) except that the stress should be limited to
a value corresponding
to a strain of 0.001 when the concrete cover to the
reinforcement is less than 50 mm.
c) In rectangular end
blocks, the bursting tensile forces in the two principal
directions should be assessed on the basis of 18.6.2.2. When circular anchorage or
bearing plates are used, the side of the equivalent square area should be used.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
4 P.JAGATEESH 2015-16
Where groups of anchorages or bearing plates occur, the end blocks should be
divided into a series of symmetrically loaded prisms and each prism treated in the
above manner. For designing end blocks having a cross-section different in shape
from that of the general cross-section of the beam, reference should be made to
specialist literature.
d) Compliance with the requirements of (a), (b) and (c) will generally ensure that
bursting tensile forces along the load axis are provided for. Alternative methods of
design which make allowance for the tensile strength of the concrete may be used,
in which case reference should be made to specialist literature.
e) Consideration should also be given to the spalling tensile stresses that occur in
end blocks where the anchorage or bearing plates are highly eccentric; these reach
a maximum at the loaded face.
2.(i) Explain the junctions of tank wall and base slab with neat sketch. (8)
(NOV- DEC 2012)
Joint in the concrete introduced for convenience in construction at which
special measures are taken to achieve subsequent continuity without provision for
further relative movement, is called a construction joint. A typical application is
between successive lifts in a reservoir.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
5 P.JAGATEESH 2015-16
The position and arrangement of all construction joints should be predetermined
by the engineer. Consideration should be given to limiting the number of such
joints and to keeping them free from possibility of percolations in a similar
manner to contraction joints.
A gap temporarily left between the concrete of adjoining parts of a structure which
after a suitable interval and before the structure is put into use, is filled with mortar
or concrete either completely ( Fig. 5A) or as provided below, with the inclusion
of suitable jointing materials ( Fig. 5B and SC). In the former case the width of the
gap should be sufficient to allow the sides to be prepared before filling.
Where measures are taken for example, by the inclusion of suitable jointing
materials to maintain the water tightness of the concrete subsequent to the filling
of the joint, this type of joint may be regarded as being equivalent to a contraction
joint ( partial or complete ) as defined above.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
6 P.JAGATEESH 2015-16
3. (a) What are the different types of joints used between the slab of prestressed
concrete tank
Joints shall be categorized as below:
a) Movetnent Joints - There are three categories of movement joints:
contraction joint - A movement joint with a deliberate discontinuity but no initial
gap between the concrete on either side of the joint, the joint being intended to
accommodate contraction of the concrete ( see Fig. 1 ).
A distinction should be made between a complete contraction joint (see Fig. 1A )
in which both concrete and reinforcing steel are interrupted, and a partial
contraction joint (. see Fig. 1B ) in which only the concrete is interrupted, the
reinforcing steel running through.
Expansion joint - A movement joint with complete discontinuity in both
reinforcement and concrete and intended to accommodate either expansion or
contraction of the structure (see Pig. 2).
In general, such a joint requires the provision of an initial gap between the
adjoining parts of a structure which by closing or opening accommodates the
expansion or contraction of the structure. Design of the joint so as to incorporate
sliding surfaces, is not, however, precluded and may sometimes be advantageous.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
7 P.JAGATEESH 2015-16
b) Construction Joint-A joint in the concrete introduced for convenience in
construction at which special measures are taken to achieve subsequent continuity
without provision for further relative movement, is called a construction joint. A
typical application is between successive lifts in a reservoir.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
8 P.JAGATEESH 2015-16
The position and arrangement of all construction joints should be predetermined
by the engineer. Consideration should be given to limiting the number of such
joints and to keeping them free from possibility of percolations in a similar
manner to contraction joints.
c) Temporary Open Joints - A gap temporarily left between the concrete of
adjoining parts of a structure which after a suitable interval and before the
structure is put into use, is filled with mortar or concrete either completely ( Fig.
5A) or as provided below, with the inclusion of suitable jointing materials ( Fig.
5B and SC). In the former case the width of the gap should be sufficient to allow
the sides to be prepared before filling.
Where measures are taken for example, by the inclusion of suitable jointing
materials to maintain the water tightness of the concrete subsequent to the filling
of the joint, this type of joint may be regarded as being equivalent to a contraction
joint ( partial or complete ) as defined above.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
9 P.JAGATEESH 2015-16
(b) Design the circular tank (only procedure).(NOV-DEC 2010) .(NOV-DEC
2010)
in the construction of concrete structures for the storage of liquids, the
imperviousness of concrete is an important basic requirement. Hence, the design
of such construction is based on avoidance of cracking in the concrete. The
structures are prestressed to avoid tension in the concrete. In addition, prestressed
concrete tanks require low maintenance. The resistance to seismic forces is also
satisfactory.
Prestressed concrete tanks are used in water treatment and distribution systems,
waste water collection and treatment system and storm water management. Other
applications are liquefied natural gas (LNG) containment structures, large
industrial process tanks and bulk storage tanks. The construction of the tanks is in
the following sequence. First, the concrete core is cast and cured. The surface is
prepared by sand or hydro blasting. Next, the circumferential prestressing is
applied by strand wrapping machine. Shotcrete is applied to provide a coat of
concrete over the prestressing strands.
Analysis
The analysis of liquid storage tanks can be done by IS:3370 - 1967, Part 4, or by
the finite element method. The Code provides coefficients for bending moment,
shear and hoop tension (for cylindrical tanks), which were developed from the
theory of plates and shells. In Part 4, both rectangular and cylindrical tanks are
covered. Since circular prestressing is applicable to cylindrical tanks, only this
type of tank is covered in this module.
The following types of boundary conditions are considered in the analysis of the
cylindrical wall.
a) For base: fixed or hinged
b) For top: free or hinged or framed.
For base
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
10 P.JAGATEESH 2015-16
Fixed: When the wall is built continuous with its footing, then the base can be
considered to be fixed as the first approximation.
Hinged: If the sub grade is susceptible to settlement, then a hinged base is a
conservative assumption. Since the actual rotational restraint from the footing is
somewhere in between fixed and hinged, a hinged base can be assumed.
The base can be made sliding with appropriate polyvinyl chloride (PVC) water-
stops for liquid tightness.
For top
Free: The top of the wall is considered free when there is no restraint in expansion.
Hinged: When the top is connected to the roof slab by dowels for shear transfer,
the boundary condition can be considered to be hinged.
Framed: When the top of the wall and the roof slab are made continuous with
moment transfer, the top is considered to be framed. The hydrostatic pressure on
the wall increases linearly from the top to the bottom of the liquid of maximum
possible depth. If the vapour pressure in the free board is negligible, then the
pressure at the top is zero. Else, it is added to the pressure of the liquid throughout
the depth. The forces generated in the tank due to circumferential prestress are
opposite in nature to that due to hydrostatic pressure. If the tank is built
underground, then the earth pressure needs to be considered. The hoop tension in
the wall, generated due to a triangular hydrostatic pressure is given as follows.
The hoop tension in the wall, generated due to a triangular hydrostatic pressure is
given as follows.
T = CT w H Ri (9-6.15)
The bending moment in the vertical direction is given as follows.
M = CM w H3 (9-6.16)
The shear at the base is given by the following expression.
V = CV w H2 (9-6.17)
In the previous equations, the notations used are as follows.
CT = coefficient for hoop tension
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
11 P.JAGATEESH 2015-16
CM = coefficient for bending moment
CV = coefficient for shear
w = unit weight of liquid
H = height of the liquid
Ri = inner radius of the wall.
The values of the coefficients are tabulated in IS:3370 - 1967, Part 4, for various
values of H2/Dt, at different depths of the liquid. D and t represent the inner
diameter and the thickness of the wall, respectively. The typical variations of CT
and CM with depth, for two sets of boundary conditions are illustrated.
The roof can be made of a dome supported at the edges on the cylindrical wall.
Else, the roof can be a flat slab supported on columns along with the edges.
IS:3370 - 1967, Part 4, provides coefficients for the analysis of the floor and roof
slabs.
Design
IS:3370 - 1967, Part 3, provides design requirements for prestressed tanks. A few
of them are mentioned.
1) The computed stress in the concrete and steel, during transfer, handling and
construction, and under working loads, should be within the permissible values as
specified in IS:1343 - 1980.
2) The liquid retaining face should be checked against cracking with a load factor
of 1.2. σCL/σWL ≥ 1.2 (9-6.18)
Here,
σCL = stress under cracking load
σWL = stress under working load.
Values of limiting tensile strength of concrete for estimating the cracking load are
Specified in the Code.
3) The ultimate load at failure should not be less than twice the working load.
4) When the tank is full, there should be compression in the concrete at all points
of at least 0.7 N/mm2. When the tank is empty, there should not be tensile stress
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
12 P.JAGATEESH 2015-16
greater than 1.0 N/mm2. Thus, the tank should be analysed both for the full and
empty conditions.
5) There should be provisions to allow for elastic distortion of the structure during
prestressing. Any restraint that may lead to the reduction of the prestressing force,
should be considered.
4. (a) What are the design considerations of prestressed concrete poles? (4)
The pre stressed concrete pole for power transmission line are generally designed
as member with uniform prestress since they are subjected to bending moment of
equal magnitude in opposite directions. The poles are generally designed for
following critical load conditions,
1. Bending due to wind load on the cable and on the exposed face.
2. Combined bending and torsion due to eccentric snapping of wire.
3. Maximum torsion due to skew snapping of wires.
4. Bending due to failure of all the wires on one side of the pole.
5. Handling and erection stresses.
(b) What are the advantages of partially prestressed concrete poles?
Resistance to corrosion in humid and temperature climate and to erosion in
desert areas.
Freeze thaw resistance in cold region.
Easy handling due to less weight than other poles
Fire resisting, particularly grassing and pushing fire near ground line.
Easily installed in drilled holes in ground with or without concrete fill.
Lighter because of reduced cross section when compared with reinforced
concrete poles.
Clean and neat in appearance and requiring negligible maintenance for a
number of years, thus ideal suited for urban installation.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
1 P.JAGATEESH 2015-16
UNIT III
Circular prestressing
Part A
1. Sketch the loop reinforcement, hair-pin bars in end blocks.(NOV-DEC 2009)
2. Sketch the correct arrangement of sheet cage in anchorage zone.(NOV-DEC 2009)
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
2 P.JAGATEESH 2015-16
3. Define two stage constructions.(NOV-DEC 2012)
One-stage construction: Construct and initialize the object in one stage, all
with the constructor.
Two-stage construction: Construct and initialize the object in two separate
stages.
The constructor creates the object and an initialization function initializes it.
4. Write any two general failures of prestressed concrete tanks.(NOV-DEC 2012)
deformation of the pre-cast concrete units during construction
Manufacturing inaccuracies led to out of tolerance units being delivered to the
site under investigation and may have affected the ability to achieve a good
seal.
5. Mention the importance of shrinkage in composite construction?
(NOV-DEC 2010)
The time dependent behavior of composite prestressed concrete
beams depends upon the presence of differential shrinkage and creep of the
concretes of web and deck, in addition to other parameters, such as relaxation
of steel, presence
of untensioned steel, and compression steel etc.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
3 P.JAGATEESH 2015-16
Part B
1. Explain the effect of varying the ratio of depth anchorage to the depth of end block
on the distribution of bursting tension. (8) (NOV-DEC 2012)
Bursting tensile forces
a) The bursting tensile forces in the end blocks, or regions of bonded post-
tensioned members, should be assessed on the basis of the tendon jacking load.
For unbonded members, the bursting tensile forces should be assessed on the basis
of the tendon jacking load or the load in the tendon at the limit state of collapse,
whichever is greater ( see Appendix B ).
The bursting tensile force, Fbst existing in an individual square end block loaded
by a symmetrically placed square anchorage or bearing plate, may be derived from
the equation below:
b) The force Fbst will be distributed in a region extending from 0.1 yo to yo from
the loaded face of the end block. Reinforcement provided to sustain the bursting
tensile force may be
assumed to be acting at its design strength (0.87 times
characteristic strength of reinforcement) except that the stress should be limited to
a value corresponding
to a strain of 0.001 when the concrete cover to the
reinforcement is less than 50 mm.
c) In rectangular end
blocks, the bursting tensile forces in the two principal
directions should be assessed on the basis of 18.6.2.2. When circular anchorage or
bearing plates are used, the side of the equivalent square area should be used.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
4 P.JAGATEESH 2015-16
Where groups of anchorages or bearing plates occur, the end blocks should be
divided into a series of symmetrically loaded prisms and each prism treated in the
above manner. For designing end blocks having a cross-section different in shape
from that of the general cross-section of the beam, reference should be made to
specialist literature.
d) Compliance with the requirements of (a), (b) and (c) will generally ensure that
bursting tensile forces along the load axis are provided for. Alternative methods of
design which make allowance for the tensile strength of the concrete may be used,
in which case reference should be made to specialist literature.
e) Consideration should also be given to the spalling tensile stresses that occur in
end blocks where the anchorage or bearing plates are highly eccentric; these reach
a maximum at the loaded face.
2.(i) Explain the junctions of tank wall and base slab with neat sketch. (8)
(NOV- DEC 2012)
Joint in the concrete introduced for convenience in construction at which
special measures are taken to achieve subsequent continuity without provision for
further relative movement, is called a construction joint. A typical application is
between successive lifts in a reservoir.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
5 P.JAGATEESH 2015-16
The position and arrangement of all construction joints should be predetermined
by the engineer. Consideration should be given to limiting the number of such
joints and to keeping them free from possibility of percolations in a similar
manner to contraction joints.
A gap temporarily left between the concrete of adjoining parts of a structure which
after a suitable interval and before the structure is put into use, is filled with mortar
or concrete either completely ( Fig. 5A) or as provided below, with the inclusion
of suitable jointing materials ( Fig. 5B and SC). In the former case the width of the
gap should be sufficient to allow the sides to be prepared before filling.
Where measures are taken for example, by the inclusion of suitable jointing
materials to maintain the water tightness of the concrete subsequent to the filling
of the joint, this type of joint may be regarded as being equivalent to a contraction
joint ( partial or complete ) as defined above.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
6 P.JAGATEESH 2015-16
3. (a) What are the different types of joints used between the slab of prestressed
concrete tank
Joints shall be categorized as below:
a) Movetnent Joints - There are three categories of movement joints:
contraction joint - A movement joint with a deliberate discontinuity but no initial
gap between the concrete on either side of the joint, the joint being intended to
accommodate contraction of the concrete ( see Fig. 1 ).
A distinction should be made between a complete contraction joint (see Fig. 1A )
in which both concrete and reinforcing steel are interrupted, and a partial
contraction joint (. see Fig. 1B ) in which only the concrete is interrupted, the
reinforcing steel running through.
Expansion joint - A movement joint with complete discontinuity in both
reinforcement and concrete and intended to accommodate either expansion or
contraction of the structure (see Pig. 2).
In general, such a joint requires the provision of an initial gap between the
adjoining parts of a structure which by closing or opening accommodates the
expansion or contraction of the structure. Design of the joint so as to incorporate
sliding surfaces, is not, however, precluded and may sometimes be advantageous.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
7 P.JAGATEESH 2015-16
b) Construction Joint-A joint in the concrete introduced for convenience in
construction at which special measures are taken to achieve subsequent continuity
without provision for further relative movement, is called a construction joint. A
typical application is between successive lifts in a reservoir.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
8 P.JAGATEESH 2015-16
The position and arrangement of all construction joints should be predetermined
by the engineer. Consideration should be given to limiting the number of such
joints and to keeping them free from possibility of percolations in a similar
manner to contraction joints.
c) Temporary Open Joints - A gap temporarily left between the concrete of
adjoining parts of a structure which after a suitable interval and before the
structure is put into use, is filled with mortar or concrete either completely ( Fig.
5A) or as provided below, with the inclusion of suitable jointing materials ( Fig.
5B and SC). In the former case the width of the gap should be sufficient to allow
the sides to be prepared before filling.
Where measures are taken for example, by the inclusion of suitable jointing
materials to maintain the water tightness of the concrete subsequent to the filling
of the joint, this type of joint may be regarded as being equivalent to a contraction
joint ( partial or complete ) as defined above.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
9 P.JAGATEESH 2015-16
(b) Design the circular tank (only procedure).(NOV-DEC 2010) .(NOV-DEC
2010)
in the construction of concrete structures for the storage of liquids, the
imperviousness of concrete is an important basic requirement. Hence, the design
of such construction is based on avoidance of cracking in the concrete. The
structures are prestressed to avoid tension in the concrete. In addition, prestressed
concrete tanks require low maintenance. The resistance to seismic forces is also
satisfactory.
Prestressed concrete tanks are used in water treatment and distribution systems,
waste water collection and treatment system and storm water management. Other
applications are liquefied natural gas (LNG) containment structures, large
industrial process tanks and bulk storage tanks. The construction of the tanks is in
the following sequence. First, the concrete core is cast and cured. The surface is
prepared by sand or hydro blasting. Next, the circumferential prestressing is
applied by strand wrapping machine. Shotcrete is applied to provide a coat of
concrete over the prestressing strands.
Analysis
The analysis of liquid storage tanks can be done by IS:3370 - 1967, Part 4, or by
the finite element method. The Code provides coefficients for bending moment,
shear and hoop tension (for cylindrical tanks), which were developed from the
theory of plates and shells. In Part 4, both rectangular and cylindrical tanks are
covered. Since circular prestressing is applicable to cylindrical tanks, only this
type of tank is covered in this module.
The following types of boundary conditions are considered in the analysis of the
cylindrical wall.
a) For base: fixed or hinged
b) For top: free or hinged or framed.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
10 P.JAGATEESH 2015-16
For base
Fixed: When the wall is built continuous with its footing, then the base can be
considered to be fixed as the first approximation.
Hinged: If the sub grade is susceptible to settlement, then a hinged base is a
conservative assumption. Since the actual rotational restraint from the footing is
somewhere in between fixed and hinged, a hinged base can be assumed.
The base can be made sliding with appropriate polyvinyl chloride (PVC) water-
stops for liquid tightness.
For top
Free: The top of the wall is considered free when there is no restraint in expansion.
Hinged: When the top is connected to the roof slab by dowels for shear transfer,
the boundary condition can be considered to be hinged.
Framed: When the top of the wall and the roof slab are made continuous with
moment transfer, the top is considered to be framed. The hydrostatic pressure on
the wall increases linearly from the top to the bottom of the liquid of maximum
possible depth. If the vapour pressure in the free board is negligible, then the
pressure at the top is zero. Else, it is added to the pressure of the liquid throughout
the depth. The forces generated in the tank due to circumferential prestress are
opposite in nature to that due to hydrostatic pressure. If the tank is built
underground, then the earth pressure needs to be considered. The hoop tension in
the wall, generated due to a triangular hydrostatic pressure is given as follows.
The hoop tension in the wall, generated due to a triangular hydrostatic pressure is
given as follows.
T = CT w H Ri (9-6.15)
The bending moment in the vertical direction is given as follows.
M = CM w H3 (9-6.16)
The shear at the base is given by the following expression.
V = CV w H2 (9-6.17)
In the previous equations, the notations used are as follows.
CT = coefficient for hoop tension
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
11 P.JAGATEESH 2015-16
CM = coefficient for bending moment
CV = coefficient for shear
w = unit weight of liquid
H = height of the liquid
Ri = inner radius of the wall.
The values of the coefficients are tabulated in IS:3370 - 1967, Part 4, for various
values of H2/Dt, at different depths of the liquid. D and t represent the inner
diameter and the thickness of the wall, respectively. The typical variations of CT
and CM with depth, for two sets of boundary conditions are illustrated.
The roof can be made of a dome supported at the edges on the cylindrical wall.
Else, the roof can be a flat slab supported on columns along with the edges.
IS:3370 - 1967, Part 4, provides coefficients for the analysis of the floor and roof
slabs.
Design
IS:3370 - 1967, Part 3, provides design requirements for prestressed tanks. A few
of them are mentioned.
1) The computed stress in the concrete and steel, during transfer, handling and
construction, and under working loads, should be within the permissible values as
specified in IS:1343 - 1980.
2) The liquid retaining face should be checked against cracking with a load factor
of 1.2. σCL/σWL ≥ 1.2 (9-6.18)
Here,
σCL = stress under cracking load
σWL = stress under working load.
Values of limiting tensile strength of concrete for estimating the cracking load are
Specified in the Code.
3) The ultimate load at failure should not be less than twice the working load.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
12 P.JAGATEESH 2015-16
4) When the tank is full, there should be compression in the concrete at all points
of at least 0.7 N/mm2. When the tank is empty, there should not be tensile stress
greater than 1.0 N/mm2. Thus, the tank should be analysed both for the full and
empty conditions.
5) There should be provisions to allow for elastic distortion of the structure during
prestressing. Any restraint that may lead to the reduction of the prestressing force,
should be considered.
4. (a) What are the design considerations of prestressed concrete poles? (4)
The pre stressed concrete pole for power transmission line are generally designed
as member with uniform prestress since they are subjected to bending moment of
equal magnitude in opposite directions. The poles are generally designed for
following critical load conditions,
1. Bending due to wind load on the cable and on the exposed face.
2. Combined bending and torsion due to eccentric snapping of wire.
3. Maximum torsion due to skew snapping of wires.
4. Bending due to failure of all the wires on one side of the pole.
5. Handling and erection stresses.
(b) What are the advantages of partially prestressed concrete poles?
Resistance to corrosion in humid and temperature climate and to erosion in
desert areas.
Freeze thaw resistance in cold region.
Easy handling due to less weight than other poles
Fire resisting, particularly grassing and pushing fire near ground line.
Easily installed in drilled holes in ground with or without concrete fill.
Lighter because of reduced cross section when compared with reinforced
concrete poles.
Clean and neat in appearance and requiring negligible maintenance for a
number of years, thus ideal suited for urban installation.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
1P.JAGATEESH 2015-16
UNIT V
PRE-STRESSED CONCRETE BRIDGES
Part A
1. what is main advantage of prestressed concrete bridge deck.
High-strength concrete and high-tensile steel, besides being economical,make for slender sections, which are aesthetically superior.
Prestressed concrete bridges can be designed as class I type structures without any tensilestresses under service loads, thus resulting in a crack-free structure.
In comparison with steel bridges, prestressed concrete bridges require verylittlemaintenance.
Prestressed concrete is ideally suited for composite bridge construction in which precastprestressed girders support the cast in situ slab deck. This type of con• struction is verypopular since it involves minimum disruption of traffic.
2.Typical types Of Pre-Tensioned Prestressed Concrete Bridges .
a. Voided slabb. Single teec. Box beamsd. Double teee. Aasho-type girders with slab(U.S.A)f. Y-tube standard beams with slab
3.what is main advantage of prestressed concrete bridge deck.
High-strength concrete and high-tensile steel, besides being economical,make for slender sections, which are aesthetically superior.
Segmental construction is ideally suited for post –tensioning work. Post-tensioning facilities the use of curved slabs hich improve the shear resistance of
girders.
4.Typical types Of Post-Tensioned Prestressed Concrete Bridges .
a. Solid slab (10-15m)b. Hollow slab(15-25m)c. Tee beams(20-40m)d. Box girders, two cell(30-70m)e. Box girders ,trapezoidal (30-80m)
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
2P.JAGATEESH 2015-16
Part-B
1. what is main advantage of prestressed concrete bridge deck.
High-strength concrete and high-tensile steel, besides being economical,make for slender sections, which are aesthetically superior.
Prestressed concrete bridges can be designed as class I type structures without any tensilestresses under service loads, thus resulting in a crack-free structure.
In comparison with steel bridges, prestressed concrete bridges require verylittlemaintenance.
Prestressed concrete is ideally suited for composite bridge construction in which precastprestressed girders support the cast in situ slab deck. This type of con• struction is verypopular since it involves minimum disruption of traffic.
Post-tensioned prestressed concrete finds extensive applications in long-spancontinuous girder bridges of variable cross-section. Not only does it make forsleek. structures, but it also effects considerable saving in the overall cost ofconstruction.
In recent years, partially prestressed concrete (type-3 structure) bas been pre•ferred for bridge construction, because it offers considerable economy in the useof costly high-tensile steel in the girder.
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
3P.JAGATEESH 2015-16
2.Typical types Of Pre-Tensioned Prestressed Concrete Bridges
(a) Voided slab (b) Single tee
(c) Box beams (d) Double tee
',;,,·,:,(;
. ·~:.~.,_;,..:Ji.,.'
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
4P.JAGATEESH 2015-16
PRESTRESSED CONCRETE VII/IV CIVIL ENGINEERING
5P.JAGATEESH 2015-16