Unit 228 Powerpoint

13
Unit 204 Scientific Principles Understand and carry out site preparation and pipework fabrication techniques for RAC systems www.cardiffandvalecollege.ac.uk Luke Gonzales TMInstR EngTech LCIBSE

Transcript of Unit 228 Powerpoint

Page 1: Unit 228 Powerpoint

Unit 204Scientific Principles

Understand and carry out site preparation and pipework fabrication

techniques for RAC systems

www.cardiffandvalecollege.ac.uk

Luke Gonzales TMInstR EngTech LCIBSE

Page 2: Unit 228 Powerpoint

Class Rules / Rheolau Dosbarth

Mobile Phones on silent – In Pockets

Appropriate Language

Questions throughout

www.cardiffandvalecollege.ac.uk

Page 3: Unit 228 Powerpoint

Lesson Objectives / Amcanion Gwersi

Identify appropriate equipment for applying leak & strength tests to

RAC Pipework

State the procedure for completing a leak & strength test to RAC

pipework according to industry standards

Please note throughout the duration you will be

required to complete the worksheet

www.cardiffandvalecollege.ac.uk

Page 4: Unit 228 Powerpoint

Why do we Leak & Strength Test?

The purpose of a pressure test is to ensure that the pipe work and system components can withstand

the pressures that they are likely to be subjected to once a system is charged with refrigerant.

• A strength test should comply with EU Standard EN378:2008

– Due to be revised September 2016

www.cardiffandvalecollege.ac.uk

*Leak Test is also referred to as tightness testing**Pressure Testing includes both leak & strength testing*

Page 5: Unit 228 Powerpoint

Equipment for Leak & Strength Testing

www.cardiffandvalecollege.ac.uk

Page 6: Unit 228 Powerpoint

Equipment

Oxygen Free Nitrogen

Oxygen Free Nitrogen Pressure Testing Regulator

Pressure Test Manifold & Metal Braided Hoses

NOT – Normal Refrigerant Lines or A Manifold with a Sight glass – Why?• Leak Spray

www.cardiffandvalecollege.ac.uk

Offer

Page 7: Unit 228 Powerpoint

Leak & Strength Test ProcedureSystems need to be divided into high & low sides for pressure testing – Heat Pump?

This is required for manufactures test pressures to be applied – Shell & Tube Evaps / Condensers

Be mindful of system components – PRV, Pressure Switches, TEVs, Solenoid Valves.

www.cardiffandvalecollege.ac.uk

Page 8: Unit 228 Powerpoint

Leak Test Calculation

Whilst carrying out a pressure test within the UK we use the Maximum Allowable Pressure outlined within EN378;• 32⁰C For The Low Side • 43 ⁰C For The High Side –

Water Cooled• 55 ⁰C For The High Side – Air

Cooled

Please Complete Example Activity 4 -

Worksheet

www.cardiffandvalecollege.ac.uk

Page 9: Unit 228 Powerpoint

Strength Test CalculationCyfrifiad Prawf Cryfder

The Strength test pressure should be between 1.1 and 1.43 times the maximum allowable pressure of the system.Example:R410A system Air Cooled High side Pressure test55⁰C = …… Bar Gauge

….. x 1.43 = 47.44 Bar Gauge47.44 Bar is your Strength Test Pressure

www.cardiffandvalecollege.ac.uk

Page 10: Unit 228 Powerpoint

Task 1 – WorksheetTaflen Waith

You have a total of 10 Minutes to complete the worksheet.*Key Points*

• 32⁰C For The Low Side • 43⁰C For The High Side – Water Cooled• 55⁰C For The High Side – Air Cooled• Use 1.43 to work out your Strength Test

Ask if you require any assistance

www.cardiffandvalecollege.ac.uk

Page 11: Unit 228 Powerpoint

Worksheet Feedback

• Task 1: EN 378• Task 3: Manifold with sight glass & normal

gauge lines• Task 4: 33.18 Bar Gauge• Task 5: 47.44 Bar Gauge• Task 6: 9.99 Bar Gauge • Task 7: 14.28 Bar Gauge• Task 8: 23.73 Bar Gauge• Task 9: 33.93 Bar Gauge

Please swap your worksheet with your partner

www.cardiffandvalecollege.ac.uk

Page 12: Unit 228 Powerpoint

Recap of Objectives

Have we achieved the following objectives?• Identify appropriate

equipment for applying leak & strength tests to RAC Pipework

• State the procedure for completing a leak & strength test to RAC pipework according to industry standards

Any questions?

www.cardiffandvalecollege.ac.uk

Cwestiynau?

Please could you fill out the feedback form I have provided, Thank you.

Page 13: Unit 228 Powerpoint

Apps to DownloadAvailable for IOS & Android

Danfoss - Refrigerant Slider Bitzer – PT Reference

www.cardiffandvalecollege.ac.uk