Understanding apiicp653 reading 2 650 selected reading

116
Understanding APIICP653 Reading 2 APIST650-Selected Reading BOK Referred Sections 2016 exam My Pre-exam Self Study Notes 27 th October 2015 Charlie Chong/ Fion Zhang

description

Understanding apiicp653 reading 2 650 selected reading

Transcript of Understanding apiicp653 reading 2 650 selected reading

Page 1: Understanding apiicp653 reading 2 650 selected reading

Understanding APIICP653 Reading 2APIST650-Selected ReadingBOK Referred Sections 2016 examMy Pre-exam Self Study Notes27th October 2015

Charlie Chong/ Fion Zhang

Page 2: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Oil Terminal

Page 3: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Petroleum Tank

Page 4: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Petroleum Tanks

Page 5: Understanding apiicp653 reading 2 650 selected reading

API 653 Exam Administration -- Publications Effectivity Sheet FOR: November 2015, March 2016 and July 2016

Listed below are the effective editions of the publications required for this exam for the date(s) shown above.

API Recommended Practice 571, Damage Mechanisms Affecting Fixed Equipment in the Refining Industry, Second Edition, April 2011

Charlie Chong/ Fion Zhang

Page 6: Understanding apiicp653 reading 2 650 selected reading

API 653 Exam Administration -- Publications Effectivity Sheet FOR: November 2015, March 2016 and July 2016 Listed below are the effective editions of the publications required for this exam for the date(s) shown above. API Recommended Practice 571, Damage Mechanisms Affecting Fixed Equipment in the Refining Industry, Second Edition, April 2011

Charlie Chong/ Fion Zhang

Page 7: Understanding apiicp653 reading 2 650 selected reading

ATTENTION: Only the following sections / mechanisms from RP 571 are included on the exam:

Section 3, Definitions Par. 4.2.7 Brittle Fracture 4.2.16 Mechanical Fatigue 4.3.2 Atmospheric Corrosion 4.3.3 Corrosion Under insulation (CUI) 4.3.8 Microbiologically Induced Corrosion (MIC) 4.3.9 Soil Corrosion 4.3.10 Caustic Corrosion 4.5.1 Chloride Stress Corrosion Cracking (Cl-SCC) 4.5.3 Caustic Stress Corrosion Cracking (Caustic Embrittlement) 5.1.1.10 Sour Water Corrosion (Acidic) 5.1.1.11 Sulfuric Acid Corrosion

Charlie Chong/ Fion Zhang

Page 8: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

• API Recommended Practice 575, Inspection of Atmospheric and Low-Pressure Storage Tanks, Third Edition, April 2014

• API Recommended Practice 577 – Welding Inspection and Metallurgy, Second Edition, December 2013

• API Standard 650, Welded Tanks for Oil Storage, Twelfth Edition, March 2013 with Addendum 1 (September 2014), Errata 1 (July 2013), andErrata 2 (December 2014).

• API Recommended Practice 651, Cathodic Protection of AbovegroundPetroleum Storage Tanks, Fourth Edition, September 2014.

• API Recommended Practice 652, Lining of Aboveground Petroleum Storage Tank Bottoms, Fourth Edition, September 2014

• API Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction, Fifth Edition, November 2014.

Page 9: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

• American Society of Mechanical Engineers (ASME), Boiler and Pressure Vessel Code, 2013 Edition i. ASME Section V, Nondestructive Examination, Articles 1, 2, 6, 7 and

23 (section SE-797 only) ii. Section IX, Welding and Brazing Qualifications (Welding Only)

See end of this study note for API Official BOK

Page 10: Understanding apiicp653 reading 2 650 selected reading

http://greekhouseoffonts.com/Charlie Chong/ Fion Zhang

Page 11: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Page 12: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

The Magical Book of Tank Inspection ICP

Page 13: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Page 14: Understanding apiicp653 reading 2 650 selected reading

闭门练功

Charlie C

hong/ Fion Zhang

Page 15: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

API650-2013 BOKSearch Keyword “650”

Page 16: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

REFERENCE PUBLICATIONS: A. API Publications • API Recommended Practice 571, Damage Mechanisms Affecting

Equipment in Refining Industry • API Recommended Practice 575, Inspection of Atmospheric and Low-

Pressure Storage Tanks • API Recommended Practice 577, Welding Inspection and Metallurgy• API Standard 650, Welded Steel Tanks for Oil Storage• API Recommended Practice 651, Cathodic Protection of Aboveground

Petroleum Storage Tanks • API Recommended Practice 652, Lining of Aboveground Petroleum

Storage Tank Bottoms • API Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction

Page 17: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

I. CALCULATIONS & TABULAR EVALUATIONS FOR EVALUATING THICKNESS MEASUREMENTS, WELD SIZES, AND TANK INTEGRITY(NOTE: Paragraph references for all formulas and calculations listed here should be checked for accuracy to the edition, addenda, or supplement for the examination you plan to take per the Publication Effectivity Sheet in the API Examination Application.)

NOTE: Candidates are expected to be able to understand SI units (metric system) and the US customary units (inches, feet, PSI, etc.) and to use both system formulas.

Page 18: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

A. Calculation questions will be oriented toward existing tanks, not new tanks. API Authorized AST Inspectors should be able to check andperform calculations included in the following categories:

2. JOINT EFFICIENCIES The inspector must be able to determine the joint efficiency, "E", of a tank

weld. Inspector should be able to determine: a) Joint Types (API-653 Section 4, Table 4-2)b) Type and extent of radiography performed (API 653, Table 4-2, Section 12;

API 650, Section 8.1, Figure 8-1) c) Joint efficiency by reading API-653, Table 4-2

Determining joint efficiency may be part of a minimum thickness or maximum fill height problem since joint efficiency, "E", is used in the formulas for determining required thickness. (API-653, 4.3.3.1)

Page 19: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

4. WELD SIZES FOR SHELL & ROOF OPENINGS The inspector should be familiar with determining the sizes and spacing of welds for shell openings to the extent of being able to use the information in the following Figures and Tables: a) API-650, Figures 5-7a, 5-7b, 5-8, 5-9, 5-12, 5-14, 5-16, 5-17, 5-19, 5-20, 5-

21b) API-650, Tables 5-6, 5-7, 5-9 c) API-653, Figures 9-1, 9-2, 9-4, 9-5

Page 20: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

8. IMPACT TESTING The inspector should understand the importance of tank materials having

adequate toughness. The inspector should be able to determine: a) Tank design metal temperature (API-650, 4.2.9.3 & Figure 4-2) b) Material Group Number for a plate (API-650, Tables 4-3a and 4-3b) c) If impact testing is required (API-650, Figure 4-1a and 4-1b) d) If impact test values are acceptable (API-650, Table 4-4a and 4-4b)

Page 21: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

10. RECONSTRUCTED TANK SHELL - MINIMUM THICKNESS The inspector should be able to determine the minimum thickness of the shell of a reconstructed tank. The inspector should be able to: a) Determine “Sd”, allowable stress for design condition (API-650, table 5-2,

API-653, 8.4.2) b) Determine “St”, allowable stress for hydrostatic test condition (API-650,

Table 5-2, API-653, 8.4.3) c) Calculate “td”, design shell thickness (API-650, 5.6.3.2, for tanks of 200

foot diameter and smaller) d) Calculate “tt”, hydrostatic test shell thickness (API-650, 5.6.3.2)

Page 22: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

II. WELDING ON ATMOSPHERIC ABOVEGROUND STORAGE TANKSASME Section IX, Welding and Brazing Qualifications (NOTE: Candidates should be familiar with the basic requirements for welding qualifications for procedures and welding personnel contained in ASME Section IX. Brazing is NOT covered on the examination. )

A. The inspector should have the knowledge and skills required to review a Procedure Qualification Record and a Welding Procedure Specification or to answer questions requiring the same level of knowledge and skill. Questions covering the specific rules of Section IX will be limited in complexity and scope to the SMAW and SAW welding processes.

Page 23: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

A. The inspector should have the knowledge and skills required to review a Procedure Qualification Record and a Welding Procedure Specification or to answer questions requiring the same level of knowledge and skill. Questions covering the specific rules of Section IX will be limited in complexity and scope to the SMAW and SAW welding processes.

1. Questions will be based on: a) No more than one process b) Filler metals limited to one c) Essential, non-essential, variables only will be covered d) Number, type, and results of mechanical tests e) Base metals limited to P1 f) Additional essential variables required by API-650 or API-653

Page 24: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

C. API-650 and API-653: General welding requirements: 1. API Standard 650, Welded Steel Tanks for Oil Storage: The inspector

should be familiar with and understand the general rules for welding in API-650, Section 9 and other rules for welding in API-650 such as those for:

a) typical joints and definitions b) weld sizes c) restrictions on joints d) maximum allowable reinforcement e) inspection requirements

Page 25: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

III. NONDESTRUCTIVE EXAMINATION ASME Section V, Nondestructive Examination NOTE: The examination will cover only the main body of each referenced Article, except as noted:

F. API-650 and API-653: General nondestructive examination requirements: 1. API Standard 650, Welded Steel Tanks for Oil Storage: The inspector

should be familiar with and understand the general rules for NDE in API-650, Section 8.

2. API Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction: The inspector should be familiar with and understand the general rules for NDE in API-653, Section 12

Page 26: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

IV. PRACTICAL KNOWLEDGE - GENERALB. Typical code requirements that candidates will NOT be expected to know

for purposes of this certification examination. 1. Required thickness calculations for wind, earthquake, and small internal

pressures2. Nozzle calculations for external loads; 3. Flange calculations; 4. Brazing requirements; 5. Calculating venting requirements (API 650 5.8.5); 6. Ladder, stairway, and other structural type calculations; 7. NDE requirements for eddy current, and motion radiography per ASME

Section V, Article 9 8. Technical interpretations of API & ASME Codes and Standards 9. Welding process requirements other than shielded metal arc welding

(SMAW) and submerged arc welding (SAW)

Page 27: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

10. API 650, Annex D 11. API 650, Annex E 12. API 650, Annex F 13. API 650, Annex G Except for G1. 14. API 650 Annex I Except for 1.1 and 1.2 15. API 650, Annex J 16. API 650, Annex K 17. API 650, Annex L 18. API 650, Annex M Except for M1. 19. API 650 Annex O Except for O1 & O2 20. API 650, Annex P. 21. API 650, Annex R 22. API 650, Annex S Except for S1 23. API 650, Annex SC 24. API 650, Annex T. 25. API 650, Annex V. 26. API 650, Annex W. 27. API 650, Annex X 28. API 650, Annex Y

Page 28: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

V. PRACTICAL KNOWLEDGE - SPECIFIC A. Each reference publication relative to study for the examination is listed below. A list of topics, which may be covered, is listed for each publication. Some topics may be listed under more than one publication. For example; ASME Section IX is the basic document for welding requirements as referenced by API-650 and API-653. The referencing API documents contain additional welding requirements and exceptions or additions to those contained in ASME Section IX. Therefore, welding requirements may be listed under all three documents and all three documents may be listed under the general heading of “Welding on Tanks”.

Page 29: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

API Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction and the related portions of API Standard 650, Welded Steel Tanks for Oil Storage (NOTE: all of API-653 is applicable to the examination unless specifically excluded.)

3. The inspector should have an understanding of the requirements for performing repairs and alterations such as:

a) definitions of repairs and alterations b) repairs to foundations, shell plates, welds, tank bottoms, nozzles & penetrations, roofs, seals c) knowledge of the repair/alteration material and toughness requirements d) use of unidentified materials for repairs/alterations e) hot tap requirements and procedures f) inspection and NDE requirements for repairs and alterations g) hydrostatic and leak testing requirements h) lap welded patch plates (API-653, 9-3) i) new bottoms supported by grillage API-650, Annex I, excluding calculations)

Page 30: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

The Reading

Page 31: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

A. Calculation questions will be oriented toward existing tanks, not new tanks. API Authorized AST Inspectors should be able to check andperform calculations included in the following categories:

2. JOINT EFFICIENCIES The inspector must be able to determine the joint efficiency, "E", of a tank

weld. Inspector should be able to determine: a) Joint Types (API-653 Section 4, Table 4-2)b) Type and extent of radiography performed (API 653, Table 4-2, Section 12;

API 650, Section 8.1, Figure 8-1) c) Joint efficiency by reading API-653, Table 4-2

Determining joint efficiency may be part of a minimum thickness or maximum fill height problem since joint efficiency, "E", is used in the formulas for determining required thickness. (API-653, 4.3.3.1)

Page 32: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

SECTION 8—METHODS OF EXAMINING JOINTSNOTE In this standard, the term inspector, as used in Sections V and VIII of the ASME Code, shall be interpreted to mean the Purchaser’s inspector.8.1 Radiographic MethodFor the purposes of this paragraph, plates shall be considered of the same thickness when the difference in their specified or design thickness does not exceed 3 mm (1/8 in.).

Page 33: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

8.1.1 ApplicationRadiographic examination is required for shell butt-welds (see 8.1.2.2, 8.1.2.3, and 8.1.2.4), annular-plate butt-welds (see 8.1.2.9), and flush-type connections with butt-welds (see 5.7.8.11).

Radiographic examination is not required for the following: roof-plate welds, bottom-plate welds, welds joining the top angle to either the roof or shell, welds joining the shell plate to the bottom plate, welds in nozzle and manway necks made from plate, or appurtenance welds to the tank. (?)

Comments:RT mandatory on;■ Annular plate butt-weld■ Shell-to-shell butt-weld

welds in nozzle and manway necks made from plate? 0RT?

Insert plate’s welds? 100RT? (see 8.1.2.2 (d))

Page 34: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

8.1.2 Number and Location of Radiographs8.1.2.1 Except when omitted under the provisions of A.3.4, radiographs shall be taken as specified in 8.1.2 through 8.1.9.

8.1.2.2 The following requirements apply to vertical joints.a) For butt-welded joints in which the thinner shell plate is less than or equal

to 10 mm (3/8 in.) thick, one spot radiograph shall be taken in the first 3 m (10 ft) of completed vertical joint of each type and thickness welded by each welder or welding operator. The spot radiographs taken in the vertical joints of the lowest course may be used to meet the requirements of Note 3 in Figure 8.1 for individual joints. Thereafter, without regard to the number of welders or welding operators, one additional spot radiograph shall be taken in each additional 30 m (100 ft) (approximately) and any remaining major fraction of vertical joint of the same type and thickness. At least 25 % of the selected spots shall be at junctions of vertical and horizontal joints, with a minimum of two such intersections per tank. In addition to the foregoing requirements, one random spotradiograph shall be taken in each vertical joint in the lowest course (see the top panel of Figure 8.1).

Page 35: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Figure 8.1—Radiographic Requirements for Tank Shells (1/4)

Page 36: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Figure 8.1—Radiographic Requirements for Tank Shells (2/4)

≦10mm?

Page 37: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Figure 8.1—Radiographic Requirements for Tank Shells (3/4)

Page 38: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Figure 8.1—Radiographic Requirements for Tank Shells (4/4)

Notes:1. Vertical spot radiograph in accordance with 8.1.2.2, Item a: one in the first

3 m (10 ft) and one in each 30 m (100 ft) thereafter, 25 % of which shall be at intersections.

2. Horizontal spot radiograph in accordance with 8.1.2.3: one in the first 3 m (10 ft) and one in each 60 m (200 ft) thereafter.

3. Vertical spot radiograph in each vertical seam in the lowest course (see 8.1.2.2, Item b). Spot radiographs that satisfy the requirements of Note 1 for the lowest course may be used to satisfy this requirement.

4. Spot radiographs of all intersections over 10 mm (3/8 in.) (see 8.1.2.2, Item b).

5. Spot radiograph of bottom of each vertical seam in lowest shell course over 10 mm (3/8 in.) (see 8.1.2.2, Item b).

6. Complete radiograph of each vertical seam over 25 mm (1 in.). The complete radiograph may include the spot radiographs of the intersections if the film has a minimum width of 100 mm (4 in.) (see 8.1.2.2, Item c).

Page 39: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

6. Complete radiograph of each vertical seam over 25 mm (1 in.). The complete radiograph may include the spot radiographs of the intersections if the film has a minimum width of 100 mm (4 in.) (see 8.1.2.2, Item c).

≧4 in.

The complete radiograph may include the spot radiographs of the intersections (4)*

Film (6)

Page 40: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

b) For butt-welded joints in which the thinner shell plate is greater than 10 mm (3/8 in.) but less than or equal to 25 mm (1 in.) in thickness, spot radiographs shall be taken according to Item a. In addition, all junctions of vertical and horizontal joints in plates in this thickness range shall be radiographed; each film shall clearly show not less than 75 mm (3 in.) of vertical weld and 50 mm (2 in.) of weld length on each side of the vertical intersection. In the lowest course, two spot radiographs shall be taken in each vertical joint: one of the radiographs shall be as close to the bottom as is practicable, and the other shall be taken at random (see the center panel of Figure 8.1).

c) Vertical joints in which the shell plates are greater than 25 mm (1 in.) thick shall be fully radiographed. All junctions of vertical and horizontal joints in this thickness range shall be radiographed; each film shall clearly show not less than 75 mm (3 in.) of vertical weld and 50 mm (2 in.) of weld length on each side of the vertical intersection (see the bottom panel of Figure 8.1).

Page 41: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

c) Vertical joints in which the shell plates are greater than 25 mm (1 in.) thick shall be fully radiographed. All junctions of vertical and horizontal joints in this thickness range shall be radiographed; each film shall clearly show not less than 75 mm (3 in.) of vertical weld and 50 mm (2 in.) of weld length on each side of the vertical intersection (see the bottom panel of Figure 8.1).

Film (4)

3 in.

4 in.

Page 42: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

d) The butt-weld around the periphery of an insert plate that extends less than the adjacent shell course height and that contains shell openings (i.e. nozzle, manway, flush-type cleanout, flush type shell-connection) and their reinforcing elements shall be completely radiographed.

e) The butt-weld around the periphery of an insert plate which extends to match the adjacent shell course height shall have the vertical and the horizontal butt joints and the intersections of vertical and horizontal weld joints radiographed using the same rules that apply to the weld joints in adjacent shell plates in the same shell course.

e?d?

d?

Page 43: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

8.1.2.3 One spot radiograph shall be taken in the first 3 m (10 ft) of completed horizontal butt joint of the same type and thickness (based on the thickness of the thinner plate at the joint) without regard to the number of welders or welding operators. Thereafter, one radiograph shall be taken in each additional 60 m (200 ft) (approximately) and any remaining major fraction of horizontal joint of the same type and thickness. These radiographs are in addition to the radiographs of junctions of vertical joints required by Item c of 8.1.2.2 (see Figure 8.1).

8.1.2.4 The number of spot radiographs required herein shall be applicable on a per tank basis, irrespective of the number of tanks being erected concurrently or continuously at any location.

8.1.2.5 It is recognized that in many cases the same welder or welding operator does not weld both sides of a butt joint. If two welders or welding operators weld opposite sides of a butt joint it is permissible to examine their work with one spot radiograph. If the radiograph is rejected, additional spot radiographs shall be taken (?) to determine whether one or both of the welders or welding operators are at fault.

Page 44: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

8.1.2.6 An equal number of spot radiographs shall be taken from the work of each welder or welding operator in proportion to the length of joints welded.

8.1.2.7 As welding progresses, radiographs shall be taken as soon as it is practicable. The locations where spot radiographs are to be taken may be determined by the Purchaser’s inspector.

8.1.2.8 Each radiograph shall clearly show a minimum of 150 mm (6 in.) of weld length. The film shall be centered on the weld and shall be of sufficient width to permit adequate space for the location of identification marks and an image quality indicator (IQI) penetrometer

minimum diagnostic length of 6 in.

Actual length shall ≧ 6 in. to include sufficient overlapped

Page 45: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

8.1.2.9 When bottom annular plates are required by 5.5.1, or by M.4.1, the radial joints shall be radiographed as follows:

(a)For double-welded butt joints, one spot radiograph shall be taken on 10 % of the radial joints; (?)

(b)For single-welded butt joints with permanent or removable back-up bar, one spot radiograph shall be taken on 50 % of the radial joints. (?)

Extra care must be exercised in the interpretation of radiographs of single-welded joints that have a permanent back-up bar. In some cases, additional exposures taken at an angle may determine whether questionable indications are acceptable. The minimum radiographic length of each radial joint shall be 150 mm (6 in.). Locations of radiographs shall preferably be at the outer edge of the joint where the shell plate and annular plate join.

Page 46: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

8.1.3 Technique8.1.3.1 Except as modified in this section, the radiographic examinationmethod employed shall be in accordance with Section V, Article 2, of the ASME Code.

8.1.3.2 Personnel who perform and evaluate radiographic examinations according to this section shall be qualified and certified by the Manufacturer as meeting the requirements of certification as generally outlined in Level II or Level III of ASNT SNT-TC-1A (including applicable supplements). Level-I personnel may be used if they are given written acceptance/rejection procedures prepared by Level-II or Level-III personnel. These written procedures shall contain the applicable requirements of Section V, Article 2, of the ASME Code. In addition, all Level-I personnel shall be under the direct supervision of Level-II or Level-III personnel.

Page 47: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

8.1.3.3 The requirements of T-285 in Section V, Article 2, of the ASME Code are to be used only as a guide. Final acceptance of radiographs shall be based on whether the prescribed penetrameter image and the specified hole can be seen.

8.1.3.4 The finished surface of the weld reinforcement at the location of the radiograph shall either be flush with the plate or have a reasonably uniform crown not to exceed the following values:

Page 48: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

8.1.4 Submission of RadiographsBefore any welds are repaired, the radiographs shall be submitted to the inspector with any information requested by the inspector regarding the radiographic technique used.

8.1.5 Radiographic StandardsWelds examined by radiography shall be judged as acceptable or unacceptable by the standards of Paragraph UW-51(b) in Section VIII of the ASME Code.

Page 49: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

8.1.6 Determination of Limits of Defective WeldingWhen a section of weld is shown by a radiograph to be unacceptable under the provisions of 8.1.5 or the limits of the deficient welding are not defined by the radiograph, two spots adjacent to the section shall be examined by radiography; however, if the original radiograph shows at least 75 mm (3 in.) of acceptable weld between the defect and any one edge of the film, an additional radiograph need not be taken of the weld on that side of the defect.

If the weld at either of the adjacent sections fails to comply with the requirements of 8.1.5, additional spots shall be examined until the limits of unacceptable welding are determined, or the erector may replace all of the welding performed by the welder or welding operator on that joint. If the welding is replaced, the inspector shall have the option of requiring that one radiograph be taken at any selected location on any other joint on which the same welder or welding operator has welded. If any of these additional spots fail to comply with the requirements of 8.1.5, the limits of unacceptable welding shall be determined as specified for the initial section.

Page 50: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

if the original radiograph shows at least 75 mm (3 in.) of acceptable weld between the defect and any one edge of the film, an additional radiograph need not be taken of the weld on that side of the defect.

http://www.sentinelltd.co.nz/Sentinel

3 in.?

Page 51: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

8.1.7 Repair of Defective Welds8.1.7.1 Defects in welds shall be repaired by chipping or melting out the defects from one side or both sides of the joint, as required, and rewelding. Only the cutting out of defective joints that is necessary to correct the defects is required.

8.1.7.2 All repaired welds in joints shall be checked by repeating the original examination procedure and by repeating one of the testing methods of 7.3, subject to the approval of the Purchaser.

Page 52: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

8.1.8 Record of Radiographic Examination8.1.8.1 The Manufacturer shall prepare a radiograph map showing the final location of all radiographs taken along with the film identification marks.

8.1.8.2 After the structure is completed, the films shall be the property of the Purchaser unless otherwise agreed upon by the Purchaser and the Manufacturer.

Page 53: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Page 54: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Page 55: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

4. WELD SIZES FOR SHELL & ROOF OPENINGS The inspector should be familiar with determining the sizes and spacing of welds for shell openings to the extent of being able to use the information in the following Figures and Tables: a) API-650, Figures 5-7a, 5-7b, 5-8, 5-9, 5-12, 5-14, 5-16, 5-17, 5-19, 5-20, 5-

21b) API-650, Tables 5-6, 5-7, 5-9 c) API-653, Figures 9-1, 9-2, 9-4, 9-5

Page 56: Understanding apiicp653 reading 2 650 selected reading

Figure 5.7a—Shell Manhole

500 mm (20 in.) manhole: 645 mm (253/8 in.) OD 508 mm (20 in.) ID 3 mm (1/8 in.) thickness600 mm (24 in.) manhole: 746 mm (293/8 in.) OD 610 mm (24 in.) ID 3 mm (1/8 in.) thickness750 mm (30 in.) manhole: 899 mm (353/8 in.) OD 762 mm (30 in.) ID 3 mm (1/8 in.) thickness900 mm (36 in.) manhole: 1051 mm (413/8 in.) OD 914 mm (36 in.) ID 3 mm (1/8 in.) thickness

Gasket (see Note 1):

Reinforcing padshall be shapedto suit tankcurvature

Rounded corners(150 mm [6 in.] minimum radius)

Arc dimension = W/2 500 mm (20 in.) and 600 mm (24 in.) manhole: 750 mm (30 in.)750 mm (30 in.) manhole: 900 mm (36 in.)

900 mm (36 in.) manhole: 1050 mm (42 in.)(Increase as necessary for weld clearance)

t

T

Seedetails

125 mm (5") minimum32 mm (11/4 in.)

500 mm (20 in.) and 600 mm (24 in.) shell manholes: twenty-eight 20 mm-diameter (3/4 in.) bolts in 23 mm (7/8 in.) holes750 mm (30 in.) and 900 mm (36 in.) shell manholes: forty-two 20 mm-diameter (3/4 in.) bolts in 23 mm (7/8 in.) holes(Bolt holes shall straddle the flange vertical centerline.)

(See Figure 5-7b)

Alternativecircular shape

(see Note 8)

1

1

230 mm(9 in.)

10 mm-diameter(3/8 in.) rod

75 mm(3")

150 mm(6 in.)

OD

DR

DO/2 (see

Note 8)

CL CL

Db DP

Dc

6 mm (1/4 in.)

C L

One 6 mm (1/4 in.) telltalehole in reinforcing plate,

on horizontalcenterline

L

Sym

met

rical

abo

ut

DR/2 (see

Note 8)L

SeeFigure5-7b

(SeeNote 7)

See Note 2

(seeNote 4)

Roundedcorner Manhole OD

Uniform, smooth surface

tn 6 mm(1/4 in.)

Detail a

See Note 2

tn (seeNote 4)

t f (see Note 3)

Manhole ODRounded

corners

SeeNote 5

Detail bt f (see Note 3)

tc

t f

tn

(seeNote 8)

NOTES1. Gasket material shall be specified by the Purchaser. See 5.7.5.4. 2. The gasketed face shall be machine-finished to provide a minimum

gasket-bearing width of 19 mm (3/4 in.).3. See Table 5.3a and Table 5.3b.4. See Table 5.4a and Table 5.4b.5. The size of the weld shall equal the thickness of the thinner member

joined.6. The shell nozzles shown in Figure 5.8 may be substituted for

manholes.

7. The minimum centerline elevations allowed by Table 5.6a, Table 5.6b, and Figure 5.6 may be used when approved by the Pur-chaser.

8. For dimensions for OD, DR, Do, L, and W, see Table 5.6a and Table 5.6b, Columns 2, 4, 5, and 6. For Dimension DP see Table 5.7a and Table 5.7b, Column 3.

9. At the option of the Manufacturer, the manhole ID may be set to the OD dimension listed in Table 5.6a and Table 5.6b, Column 2. Reinforcement area and weld spacing must meet 5.7.2 and 5.7.3 requirements respectively.

Page 57: Understanding apiicp653 reading 2 650 selected reading

DO (m

in)

L and W or D

O(see Tables 5-6a and 5-6b)

Shell joint or outer periphery

of insert plate

(See

Note 2)

CL

J JNeck bevel should be about 10 degrees

Round and grind corner

(See Tables 5-7a and 5-7b)

(See Tables 5-6a, 5-6b, 5-7a, and 5-7b)

CL

T + t(min)

Shell

(See

Note 2)

DO (m

in) (See Note 3)A

t (min)

45º

1/3 (T + t) min

(See

Note 2)

1/3 (t +T) min

(See Tables 5-7a and 5-7b)

T + t(min)

A

Bottom

45º

[10 mm (3/8 in.) maximum][10 mm (3/8 in.) maximum]

Radiograph(see 8.1.2.2,

Item d)

T + t(min)

1:4bevel

Alternativebevel

Radiograph(see 8.1.2.2,

Item d)

45º

CL

CL

A

Radiograph(see 8.1.2.2,Item d and e)

t t

1.5 mm (1/16 in.)1.5 mm (1/16 in.)

t1:4 bevel

1:4 bevel

(See Tables 5-6a,

5-6b, 5-7a, and 5-7b)

(See N

ote 1)

Manufacturer’s standard

(15 degrees minim

um,

35 degrees maxim

um)

T t

A

Round corner if weld <T(See Tables 5-7a and 5-7b) (See Tables 5-7a and 5-7b)

A[10 mm (3/8 in.) maximum]

JJ

(See N

ote 1)

Manufacturer’s standard

(15 degrees minim

um,

35 degrees maxim

um)

L and W (Tables 5-6a and 5-6b) or D

O

T t

T or t[40 mm (11/2 in.) maximum]

A

1.5 mm (1/16 in.)

T or t[40 mm (11/2 in.) maximum]

1.5 mm(1/16 in.)

Round corner if weld <T

(See Tables5-6a, 5-6b, 5-7a, and 5-7b)

Round and grind

Neck bevel should beabout 10 degrees

(See Tables 5-7a and 5-7b)

Manhole or Nozzle Nozzle

Insert-type Reinforcement for Manholes and Nozzles

Alternativeneck detail

tn

tn

tn

1.5 mm (1/16 in.)

Nozzle

Nozzle

Notes:1. See Table 5.7a and Table 5.7b, Column 3, for the shell cutout, which shall

not be less than the outside diameter of the neck plus 13 mm (1/2) in.2. See 5.7.3 for minimum spacing of welds at opening connections.3. The weld size shall be either A (from Table 5.7a and Table 5.7b, based on t)

or tn (minimum neck thickness from Table 5.4a, Table 5.4b, Table 5.6a, Table 5.6b, Table 5.7a and Table 5.7b), whichever is greater.

4. Other permissible insert details are shown in Figure 5.8 of API Standard 620. The reinforcement area shall conform to 5.7.2.

5. Dimensions and weld sizes that are not shown are the same as those given in Figure 5.7a and Table 5.4a through Table 5.8b.

6. Details of welding bevels may vary from those shown if agreed to by the Purchaser.

Figure 5.7b—Details of Shell Manholes and Nozzles

Page 58: Understanding apiicp653 reading 2 650 selected reading

Figure 5.8—Shell Nozzles (see Tables 5.6a, 5.6b, 5.7a, 5.7b, 5.8a, and 5.8b)

Reinforcing Plate

Regular-type Flanged Nozzles, NPS 3 or Larger(Bolt holes shall straddle flange centerlines)

Diamond Circular

Single Flange Special Flange

Detail B

One 6 mm (1/4 in.) telltale holein reinforcing plate,

on horizontal centerline

Bend reinforcing plate toradius of tank shell

Alternative shapefor low-type nozzles

See Detail A or B forbottom edge

(See Figure 5-7b) (See Figure 5-7b)(See Figure 5-7b)

(See Figure 5-7b)

Arc distance

11

Tank bottom

Victaulic grooveor threads

(See Note 1) (See Note 1)

(See Note 1)

(See Note 5)60º

t /2 [6 mm (1/4 in.) minimum]

C

Chip

DO

DP

DRD

P

W

L

D

R

DR/2

DR/2

J Jt

TQ

OD

BB

HN

OD

J Jt

TQ Q

J t

TQ

OD

B

Nozzle CL

Double Flange

T Tt t

L

Detail ALow-type Flanged Nozzles, NPS 3 or Larger

(Bolt holes shall straddle flange centerlines)

NOTES1. See 5.1.5.7 for information on the size of welds.2. See 5.8.9 for information on the couplings used in shell nozzles.3. Nozzles NPS 3 or larger require reinforcement.

4. Details of welding bevels may vary from those shown if agreed to by the Purchaser.

5. Shop weld not attached to bottom plate.6. See 5.7.6.2 for information on supplying nozzles flush or with an

internal projection.

Page 59: Understanding apiicp653 reading 2 650 selected reading

Figure 5.8—Shell Nozzles (continued)

Dimension A = size of fillet weld A(see Note 1)

Shell Shell Shell ShellHN C

Bottom Bottom Bottom Bottom

t

Type A Type B Type C Type D

45º

CL

A

t

J

0

t t10 mm (3/8 in.) maximum

10 mm (3/8 in.) maximum

11/4 tmin(see Note 8) 11/4 tmin

(see Note 8)

(see Note 7)

A(see Note 7) 1.5 mm (1/16 in.)

Couplings and Flanged Fittings, NPS 3/4 Through NPS 2 (see Note 3)

A

Low

type

Reg

ular

NOTES (continued)7. See Table 5.7a and Table 5. 7b, Column 6.8. tmin shall be 19 mm (3/4 in.) or the thickness of either part joined by the fillet weld, whichever is less.9. The construction details apply to unreinforced threaded, non-threaded, and flanged nozzles.

14

Page 60: Understanding apiicp653 reading 2 650 selected reading

Figure 5.9—Minimum Spacing of Welds and Extent of Related Radiographic Examination

Toe of weld

Toe of weld

Reinforcing plateReinforcing plate

Penetration Without Reinforcing Plate

Penetration With Reinforcing Plate

Toe of weld

Minimum spacing shall be 8 times theshell thickness or 1/2 the radius of theopening, whichever is less

of butt-weldedshell joint

CL

See 5.7.3E

xten

t of r

adio

grap

hy

1.5D

P1.

5DP

Ext

ent o

f rad

iogr

aphy

1.5D

P1.

5DP

Minimum spacing shall be 8 times theshell thickness

of butt-weldedshell joint

CLSee 5.7.3

Minimum spacing shall be 8 times theshell thickness or 1/2 the radius of the

opening, whichever is less

Ext

ent o

f rad

iogr

aphy1.5D

P1.

5DP

Detail a Detail b

Detail c Detail d Detail e

of butt-weldedshell joint

CL

Note: Dp = diameter of opening.

Page 61: Understanding apiicp653 reading 2 650 selected reading

Figure 5.12—Flush-Type Cleanout Fittings (see Tables 5.9a, 5.9b, 5.10a, 5.10b, 5.11a, and 5.11b)

Shell plate at cleanout fitting = td

See Detail b

Equal spaces

Nearest horizontal weld

125 mm(5 in.)

One telltale 6 mm (1/4 in.) hole in reinforcingplate at aboutmid-height

r2

Reinforcing plate = td

Shell plateof lowestshellcourse = t

(See Note 1)

6 mm(1/4 in.) 6 mm

(1/4 in.)

6 mm(1/4 in.)

6 mm (1/4")

6 mm(1/4 in.)

6 mm(1/4 in.)

6 mm(1/4 in.)

5 mm(3/16 in.)

5 mm(3/16 in.)

5 mm (3/16 in.)

gB

B

300 mm (12 in.) min

150 mm(6 in.) min

W/2 arc dimensions

Flange bolt-holediameter = boltdiameter (see Tables 5-9aand 5-9b) + 3 mm (1/8 in.)

b/2

f2

r1 L

A

A

f3e

eEqual spacesf3 6 mm (1/4 in.)

See Detail a

td

See Detail bfor top and sides

tc

tb

h

Bottomplate

e

Section A-A

Grind radius on cornerwhen weld is less than td

td[40 mm

(11/2 in.) max]

tdtd

tc

td[19 mm (3/4 in.) max]

td

Neck bevel shall beapproximately 10 degrees

f3

(SeeNote 1)

Cover plate

Versine

Detail aSection B-B

tdtd

tb

(See Note 1)

Full-filletweld

td + td + 250 mm (10 in.)(see Note 2)

32 mm(11/4 in.) min

DD 90 degrees ± 30 degrees

32 mm (11/4 in.) min125 mm (5 in.) min

Section C-C

Section D-D

32 mm(11/4

in.) min

75 mm (3 in.) radius

10 mm (3/8 in.) thick175 mm (5 in.)

38 mm (11/2")

38 mm (11/2")

38 mm(11/2")

50 mm(2 in.)

or

Full-penetrationweld

(See Note 3)

75 mm(3 in.)

CC

Roundand grind

Detail b

Lifting Lug

Notch as required to provide flush joint under shell ring (see Section D-D)

375 mm(15 in.) min

(See Note 5)

(See Note 5)

(See Note 5)

Notes:1. Thickness of thinner plate joined (13 mm [1/2 in.] maximum).2. When an annular plate is provided, the reinforcing plate shall be

regarded as a segment of the annular plate and shall be the same width as the annular plate.

3. When the difference between the thickness of the annular ring and that of the bottom reinforcing plate is less than 6 mm (1/4 in.), the radial joint between the annular ring and the bottom reinforcing plate

may be butt-welded with a weld joint suitable for complete penetration and fusion.

4. Gasket material shall be specified by the Purchaser. The gasket mate-rial shall meet service requirements based on product stored, design metal temperature, maximum design temperature and fire resistance.

5. The thickness (td) of the shell plate at the cleanout opening, the reinforcing plate, and the neck plate, shall be equal to or greater than the thickness (t) of the shell plate of the lowest shell course.

Page 62: Understanding apiicp653 reading 2 650 selected reading

Figure 5.14—Flush-type Shell Connection

tn = 16 mm (5/8 in.) min

One 6 mm (1/4") telltalehole in reinforcing plateat about mid-height

Section B-B

Section A-A

B

h

50 mm (2 in.) min

150 mm(6 in.) min

W/2 arc dimensions

150 mm (6 in.) min

L

375 mm (15 in.) min

C

C

Shell or insert plate inflush connection = td

Reinforcing plate = td

B

75 mm(3 in.)

Bottom reinforcing plate

Shell plate oflowest shellcourse = t

See Section C-C(Figure 5-11 —continued)

Centerline of connection

tb

tdtd

32 mm (11/4 in.) min

Bottom reinforcing plate

A

A

Butt-weldNozzle transition to

circular flange

Butt-weld

75 mm(3 in.) radius

125 mm (5 in.) min

Full-fillet weld

All joints approximately90 degrees

Bottom plate

Bottom transition plate for minimumarc dimension of W + 1500 mm (60 in.)

2td + 250 mm (10 in.)

(See Note 2)

Centerlineof connection

600 mm(24 in.) min

32 mm (11/4 in.) min

Notch as required to provideflush joint

Full-penetrationweld

5 mm(3/16 in.)

6 mm(1/4 in.)

r2

r1

b/2

300 mm(12 in.) min

Page 63: Understanding apiicp653 reading 2 650 selected reading

Figure 5.16—Roof Manholes (see Table 5.13a and Table 5.13b)

150 mm (6 in.)

150 mm (6 in.)

A

16-mm (5/8-in.) diameter bolts in 20-mm (3/4 in.)diameter holes (see Table 5-13a and Table 5-13bfor number of bolts; bolt holes shall straddle centerlines)

A

6 mm (1/4 in.) cover plate

DB 16 mm (5/8 in.)diameter rod

DC

DP

DR

ID

6 mm (1/4 in.)

6 mm (1/4 in.)

6 mm (1/4 in.)

Axis alwaysvertical

or 150 mm (6 in.) min

6 mm (1/4 in.)cover plate

IDDP

Roof plate

Section A-A—Roof Manhole With Reinforcing Plate

Base For Roof Manhole Without Reinforcing Plate

Alternative Neck-to-Roof-Plate Joint

Roof plate

6 mm (1/4 in.)

6 mm (1/4 in.)

6 mm (1/4 in.)

6 mm(1/4 in.)

6 mm (1/4 in.)

5 mm (3/16 in.)

5 mm (3/16 in.)

150 mm(6 in.)

75 mm (3 in.)

Reinforcing plate

1.5 mm (1/16 in.)thick gasket

Alternative Flange Detail

Page 64: Understanding apiicp653 reading 2 650 selected reading

Figure 5.17—Rectangular Roof Openings with Flanged Covers

Typical

75 mm (3 in.) typical

45º

Grind flush

Section A-A, Typical

AA

125 mm (5 in.)typical

Neck 6 mm (1/4 in.) thick min.

16 mm (5/8 in.) diameter rod,4 places

Except for handles, coverplate not shown.

1800 mm(6 ft) max

900 mm (3 ft) max

B B

Typical

1.5 mm (1/16 in.) thick gasket

Cover 5 mm (3/16 in.) thick minimum

5 mm (3/16 in.) galv. wirerope lanyard

250 mm(10 in.) max

Note 1

6 mm (1/4 in.) reinforcing plate, when required. See Note 4.

38 mm (1.5 in.) x 38 mm (1.5 in.) x 6 mm (1/4 in.) tab

Section B-B

Note 3

75 mm(3 in.)

150 mm(6 in.)

5 mm (3/16 in.) typical 100 mm (4 in.) minimum75 mm (3 in.) x 10 mm (3/8 in.)bar flange

Roof plate

Notes:1. Weld size shall be the smaller of the plate thicknesses being joined.2. Cover may be either parallel to roof or horizontal. Opening may be oriented as desired.3. Bolts shall be 16-mm (5/8-in.) diameter in 20-mm (3/4-in.) holes, which shall be equally spaced and shall not exceed 125-mm (5 in.) on center.4. When required, provide 6-mm (1/4-in.) reinforcing plate. Width at least 1/2 smallest opening dimension. Round outside corners with 75 mm (3 in.) radius, minimum. Seams shall be square groove butt-welded.

Page 65: Understanding apiicp653 reading 2 650 selected reading

Figure 5.19—Flanged Roof Nozzles (see Table 5.14a and Table 5.14b)

Figure 5.20—Threaded Roof Nozzles (see Table 5.15a and Table 5.15b)

Figure 5.21—Drawoff Sump (see Table 5.16a and Table 5.16b)

DR

Axis alwaysvertical

AlternativeNeck-to-Roof-Plate

Joint

Roof plate

Base for Nozzle without Reinforcing Plate

Axis alwaysvertical

Roof plate6 mm(1/4 in.)

6 mm (1/4 in.)6 mm

(1/4 in.)5 mm

(3/16 in.)

DP

DP

Plain or raised-faceslip-on welding, welding-neck,or plate ring flange

(See note)

Standard-weight line pipe

HR

Nozzle with Reinforcing Plate

Note: When the roof nozzle is used for venting, the neck shall be trimmed flush with the roofline.

6 mm (1/4 in.) 6 mm (1/4 in.)

6 mm (1/4 in.)5 mm (3/16 in.)

Roof plate

Nozzle without Reinforcing Plate

Axis alwaysvertical

Roof plate

DP

(See note)

Nozzle with Reinforcing Plate

DRDP

Axis always vertical

Pipe coupling

Note: See 5.8.9 for requirements for threaded connections. When the roof nozzle is used for venting, the neck shall be trimmed flush with the roofline.

Full fillet

Full fillet

Full filletDetail a1 Detail a2

Detail b Detail c

Detail a4

Detail a3

C

B 1 pipediameter (min)

100 mm (4 in.)Sand cushion A

t

t

t

Tank bottom

See Detailb, c, or d

Tank shell

Nozzle neck

Tack-weldbackup barto flange60

6 mm (1/4 in.)6 mm (1/4 in.)

6 mm(1/4 in.)

6 mm(1/4 in.)

6 mm(1/4 in.)

6 mm(1/4 in.)

8 mm (5/16 in.)

8 mm (5/16 in.)

8 mm(5/16 in.)

Internal pipe

Detail d

Full fillet weld

NOTE The erection procedure shall be performed by one of the following methods or by an alternate design approved by a Storage Tank Engineer:

a) For sumps being placed in the foundation before bottom placement, the sump shall be placed in position with at least 100 mm (4 in.) of thoroughly compacted sand, or other suitable fill material, around the sump. The sump then shall be welded to the bottom.

b) For sumps being placed in the foundation after bottom placement, sufficient bottom plate shall be removed to allow for the sump to be placed in position with at least 100 mm (4 in.) of thoroughly compacted sand, or other suitable fill material, around the sump. The sump shall then be welded to the bottom.

Page 66: Understanding apiicp653 reading 2 650 selected reading

Table 5.6a—Dimensions for Shell Nozzles (SI)Dimensions in millimeters

Column 1 Column 2 Column 3 Column 4 Column 5 Column 6 Column 7 Column 8 Column 9c

NPS(Size of Nozzle)

Outside Diameter of

PipeOD

Nominal Thickness of Flanged Nozzle Pipe

Walla

tn

Diameter of Hole in

Reinforcing Plate

DR

Length of Side of

Reinforcing Plateb or Diameter

L = Do

Width of Reinforcing

PlateW

Minimum Distance

from Shell-to-Flange

FaceJ

Minimum Distance from Bottom of Tank to Center

of Nozzle

Regular Typed

HN

Low TypeC

Flanged Fittings

60 1524.0 e 1528 3068 3703 400 1641 1534

54 1371.6 e 1375 2763 3341 400 1488 1382

52 1320.8 e 1324 2661 3214 400 1437 1331

50 1270.0 e 1274 2560 3093 400 1387 1280

48 1219.2 e 1222 2455 2970 400 1334 1230

46 1168.4 e 1172 2355 2845 400 1284 1180

44 1117.6 e 1121 2255 2725 375 1234 1125

42 1066.8 e 1070 2155 2605 375 1184 1075

40 1016.0 e 1019 2050 2485 375 1131 1025

38 965.2 e 968 1950 2355 350 1081 975

36 914.4 e 918 1850 2235 350 1031 925

34 863.6 e 867 1745 2115 325 979 875

32 812.8 e 816 1645 1995 325 929 820

30 762.0 e 765 1545 1865 300 879 770

Page 67: Understanding apiicp653 reading 2 650 selected reading

28 711.2 e 714 1440 1745 300 826 720

26 660.4 e 664 1340 1625 300 776 670

24 609.6 12.7 613 1255 1525 300 734 630

22 558.8 12.7 562 1155 1405 275 684 580

20 508.0 12.7 511 1055 1285 275 634 525

18 457.2 12.7 460 950 1160 250 581 475

16 406.4 12.7 410 850 1035 250 531 425

14 355.6 12.7 359 750 915 250 481 375

12 323.8 12.7 327 685 840 225 449 345

10 273.0 12.7 276 585 720 225 399 290

8 219.1 12.7 222 485 590 200 349 240

6 168.3 10.97 171 400 495 200 306 200

4 114.3 8.56 117 305 385 175 259 150

3 88.9 7.62 92 265 345 175 239 135

2f 60.3 5.54 63 — — 150 175 h

11/2f 48.3 5.08 51 — — 150 150 h

1f 33.4 6.35 — — — 150 150 h

3/4f 26.7 5.54 — — — 150 150 h

Threaded and Socket-Welded Couplings

3g 108.0 Coupling 111.1 285 360 — 245 145

2f 76.2 Coupling 79.4 — — — 175 h

11/2f 63.5 Coupling 66.7 — — — 150 h

1f 44.5 Coupling 47.6 — — — 150 h

3/4f 35.0 Coupling 38.1 — — — 150 h

a For extra-strong pipe, see ASTM A53M or A106M for other wall thicknesses; however, piping material must conform to 4.5.b The width of the shell plate shall be sufficient to contain the reinforcing plate and to provide clearance from the girth joint of the shell course.c Low type reinforced nozzles shall not be located lower than the minimum distance shown in Column 9. The minimum distance from the bottom

shown in Column 9 complies with spacing rules of 5.7.3 and Figure 5.6.d Regular type reinforced nozzles shall not be located lower than the minimum distance HN shown in Column 8 when shell thickness is equal to

or less than 12.5 mm. Greater distances may be required for shells thicker than 12.5 mm to meet the minimum weld spacing of 5.7.3 and Figure 5.6.

e See Table 5.7a, Column 2.f Flanged nozzles and couplings in pipe sizes NPS 2 or smaller do not require reinforcing plates. DR will be the diameter of the hole in the shell

plate, and Weld A will be as specified in Table 5.7a, Column 6. Reinforcing plates may be used if the construction details comply with reinforced nozzle details.

g A coupling in an NPS 3 requires reinforcement.h See 5.7.3 and Figure 5.6.

NOTE See Figure 5.8.

Table 5.6a—Dimensions for Shell Nozzles (SI) (Continued)Dimensions in millimeters

Column 1 Column 2 Column 3 Column 4 Column 5 Column 6 Column 7 Column 8 Column 9c

NPS(Size of Nozzle)

Outside Diameter of

PipeOD

Nominal Thickness of Flanged Nozzle Pipe

Walla

tn

Diameter of Hole in

Reinforcing Plate

DR

Length of Side of

Reinforcing Plateb or Diameter

L = Do

Width of Reinforcing

PlateW

Minimum Distance

from Shell-to-Flange

FaceJ

Minimum Distance from Bottom of Tank to Center

of Nozzle

Regular Typed

HN

Low TypeC

Page 68: Understanding apiicp653 reading 2 650 selected reading

Table 5.7a—Dimensions for Shell Nozzles: Pipe, Plate, and Welding Schedules (SI)

Dimensions in millimeters

Column 1 Column 2 Column 3 Column 4 Column 5 Column 6

Thickness of Shell and Reinforcing

Platea

t and T

Minimum Pipe Wall Thickness of Flanged Nozzlesb

tn

Maximum Diameter of Hole

in Shell Plate(Dp) Equals

Outside Diameter of Pipe Plus

Size of FilletWeld B

Size of Fillet Weld A

Nozzles Larger Than NPS 2

NPS 3/4 to 2 Nozzles

5 12.7 16 5 6 6

6 12.7 16 6 6 6

8 12.7 16 8 6 6

10 12.7 16 10 6 6

11 12.7 16 11 6 6

13 12.7 16 13 6 8

14 12.7 20 14 6 8

Page 69: Understanding apiicp653 reading 2 650 selected reading

b) The portion lying within the shell-plate thickness.

c) The portion extending inward from the inside surface of the tank shell plate to the distance specified in Item a.

Column 1 Column 2 Column 3 Column 4 Column 5 Column 6

Thickness of Shell and Reinforcing

Platea

t and T

Minimum Pipe Wall Thickness of Flanged Nozzlesb

tn

Maximum Diameter of Hole

in Shell Plate(Dp) Equals

Outside Diameter of Pipe Plus

Size of FilletWeld B

Size of Fillet Weld A

Nozzles Larger Than NPS 2

NPS 3/4 to 2 Nozzles

16 12.7 20 16 8 8

17 12.7 20 18 8 8

20 12.7 20 20 8 8

21 12.7 20 21 10 8

22 12.7 20 22 10 8

24 12.7 20 24 10 8

25 12.7 20 25 11 8

27 14 20 27 11 8

28 14 20 28 11 8

30 16 20 30 13 8

32 16 20 32 13 8

33 18 20 33 13 8

35 18 20 35 14 8

36 20 20 36 14 8

38 20 20 38 14 8

40 21 20 40 14 8

41 21 20 40 16 8

43 22 20 40 16 8

45 22 20 40 16 8

a If a shell plate thicker than required is used for the product and hydrostatic loading (see 5.6), the excess shell-plate thickness, within a vertical distance both above and below the centerline of the hole in the tank shell plate equal to the vertical dimension of the hole in the tank shell plate, may be considered as reinforcement, and the thickness T of the nozzle reinforcing plate may be decreased accordingly. In such cases, the reinforcement and the attachment welding shall conform to the design limits for reinforcement of shell openings specified in 5.7.2.

b This column applies to flanged nozzles NPS 26 and larger. See 4.5 for piping materials.

NOTE See Figure 5.8.

Table 5.7a—Dimensions for Shell Nozzles: Pipe, Plate, and Welding Schedules (SI) (Continued)

Dimensions in millimeters

Page 70: Understanding apiicp653 reading 2 650 selected reading

Table 5.9a—Dimensions for Flush-Type Cleanout Fittings (SI)Dimensions in millimeters

Column 1

Column 2

Column 3

Column 4

Column 5

Column 6

Column 7

Column 8

Column 9

Column 10

Column 11

Height of Opening

h

Width of Opening

b

Arc Width of Shell

Reinforcing Plate

W

Upper Corner Radius

of Opening

r1

Upper Corner

Radius of Shell

Reinforcing Plate

r2

Edge Distanceof Bolts

e

Flange Widtha (Except

at Bottom)

f3

Bottom Flange Width

f2

Special Bolt

Spacingb

g

Numberof

Bolts

Diameterof

Bolts

203 406 1170 100 360 32 102 89 83 22 20

610 610 1830 300 740 38 102 95 89 36 20

914 1219 2700 610 1040 38 114 121 108 46 24

1219c 1219 3200 610 1310 38 114 127 114 52 24

a For neck thicknesses greater than 40 mm, increase f3 as necessary to provide a 1.5 mm clearance between the required neck-to-flange weld and the head of the bolt.

b Refers to spacing at the lower corners of the cleanout-fitting flange.

c Only for Group I, II, III, or IIIA shell materials (see 5.7.7.2).

NOTE See Figure 5.12.

Table 5.9b—Dimensions for Flush-Type Cleanout Fittings (USC)Dimensions in inches

Column 1

Column 2

Column 3

Column 4

Column 5

Column 6

Column 7

Column 8

Column 9

Column 10

Column 11

Height of

Openingh

Width of Opening

b

Arc Width of Shell

Reinforcing Plate

W

Upper Corner Radius

of Opening

r1

Upper Corner

Radius of Shell

Reinforcing Plate

r2

Edge Distanceof Bolts

e

Flange Widtha (Except

at Bottom)

f3

Bottom Flange Width

f2

Special Bolt

Spacingb

g

Numberof

Bolts

Diameterof

Bolts

8 16 46 4 14 11/4 4 31/2 31/4 22 3/4

24 24 72 12 29 11/2 4 33/4 31/2 36 3/4

36 48 106 24 41 11/2 41/2 43/4 41/4 46 1

48c 48 125 24 511/2 11/2 41/2 5 41/2 52 1

a For neck thicknesses greater than 19/16 in., increase f3 as necessary to provide a 1/16 in. clearance between the required neck-to-flange weld and the head of the bolt.

b Refers to spacing at the lower corners of the cleanout-fitting flange.

c Only for Group I, II, III, or IIIA shell materials (see 5.7.7.2).

NOTE See Figure 5.12.

Page 71: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

8. IMPACT TESTING The inspector should understand the importance of tank materials having

adequate toughness. The inspector should be able to determine: a) Tank design metal temperature (API-650, 4.2.9.3 & Figure 4-2) b) Material Group Number for a plate (API-650, Tables 4-3a and 4-3b) c) If impact testing is required (API-650, Figure 4-1a and 4-1b) d) If impact test values are acceptable (API-650, Table 4-4a and 4-4b)

Page 72: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

4.2.9 Impact Testing of Plates4.2.9.1 When required by the Purchaser or by 4.2.10, a set of Charpy V-notch impact specimens shall be taken from plates after heat treatment (if the plates have been heat treated), and the specimens shall fulfill the stated energy requirements. Test coupons shall be obtained adjacent to a tension-test coupon. Each full-size impact specimen shall have its central axis as close to the plane of one-quarter plate thickness as the plate thickness will permit.

4.2.9.2 When it is necessary to prepare test specimens from separate coupons or when plates are furnished by the plate producer in a hot-rolled condition with subsequent heat treatment by the fabricator, the procedure shall conform to ASTM A20.

Page 73: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

4.2.9.3 An impact test shall be performed on three specimens taken from a single test coupon or test location. The average value of the specimens (with no more than one specimen value being less than the specified minimum value) shall comply with the specified minimum value. If more than one value is less than the specified minimum value, or if one value is less than two-thirds the specified minimum value, three additional specimens shall be tested, and each of these must have a value greater than or equal to the specified minimum value.

Page 74: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Figure 4.1a—Minimum Permissible Design Metal Temperature for Materials Used in Tank Shells without Impact Testing (SI)

Page 75: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

NOTE 1The Group II and Group V lines coincide at thicknesses less than 13 mm.NOTE 2The Group III and Group IIIA lines coincide at thicknesses less than 13 mm.NOTE 3The materials in each group are listed in Table 4.4a and Table 4.4b.NOTE 4Deleted.NOTE 5Use the Group IIA and Group VIA curves for pipe and flanges (see 4.5.4.2 and 4.5.4.3).NOTE 6Linear equations provided in Table 4.3a can be used to calculate Design Metal Temperature (DMT) for each API material group and the thickness range.

Page 76: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Figure 4.2—Isothermal Lines of Lowest One-Day Mean Temperatures (°F)

Page 77: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Table 4.3a—Linear Equations for Figure 4.1a (SI)

Page 78: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Page 79: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Page 80: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Page 81: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Page 82: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

10. RECONSTRUCTED TANK SHELL - MINIMUM THICKNESS The inspector should be able to determine the minimum thickness of the shell of a reconstructed tank. The inspector should be able to: a) Determine “Sd”, allowable stress for design condition (API-650, table 5-2,

API-653, 8.4.2) b) Determine “St”, allowable stress for hydrostatic test condition (API-650,

Table 5-2, API-653, 8.4.3) c) Calculate “td”, design shell thickness (API-650, 5.6.3.2, for tanks of 200

foot diameter and smaller) d) Calculate “tt”, hydrostatic test shell thickness (API-650, 5.6.3.2)

Page 83: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Page 84: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

5.6.3.2 The required minimum thickness of shell plates shall be the greater of the values computed by the following formulas:

Page 85: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

td is the design shell thickness, in inches;tt is the hydrostatic test shell thickness, in inches;D is the nominal tank diameter, in ft (see 5.6.1.1, Note 1);H is the design liquid level, in ft:

is the height from the bottom of the course under consideration to the top of the shell including the top angle, if any; to the bottom of any overflow that limits the tank filling height; or to any other level specified by the Purchaser, restricted by an internal floating roof, or controlled to allow for seismic wave action,

G is the design specific gravity of the liquid to be stored, as specified by the Purchaser;

CA is the corrosion allowance, in inches, as specified by the Purchaser (see 5.3.2);

Sd is the allowable stress for the design condition, in lbf/in.2 (see 5.6.2.1);St is the allowable stress for the hydrostatic test condition, in lbf/in.2

(see 5.6.2.2).

Page 86: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

A. The inspector should have the knowledge and skills required to review a Procedure Qualification Record and a Welding Procedure Specification or to answer questions requiring the same level of knowledge and skill. Questions covering the specific rules of Section IX will be limited in complexity and scope to the SMAW and SAW welding processes.

1. Questions will be based on: a) No more than one process b) Filler metals limited to one c) Essential, non-essential, variables only will be covered d) Number, type, and results of mechanical tests e) Base metals limited to P1 f) Additional essential variables required by API-650 or API-653

Page 87: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

9.2 Qualification of Welding Procedures9.2.1 General Requirements9.2.1.1 The erection Manufacturer and the fabrication Manufacturer if other than the erection Manufacturer, shall prepare welding procedure specifications and shall perform tests documented by procedure qualification records to support the specifications, as required by Section IX of the ASME Code and any additional provisions of this standard. If the Manufacturer is part of an organization that has, to the Purchaser’s satisfaction, established effective operational control of the qualification of welding procedures and of welder performance for two or more companies of different names, then separate welding procedure qualifications are not required, provided all other requirements of 9.2, 9.3, and Section IX of the ASME Code are met. Welding procedures for ladder and platform assemblies, handrails, stairways, and other miscellaneous assemblies, but not their attachments to the tank, shall comply with either AWS D1.1, AWS D1.6, or Section IX of the ASME Code, including the use of standard WPSs.

Page 88: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

9.2.1.2 The welding procedures used shall produce weldments with the mechanical properties required by the design.

9.2.1.3 Material specifications listed in Section 4 of this standard but not included in Table QW-422 of Section IX of the ASME Code shall be considered as P-No. 1 material with group numbers assigned as follows according to the minimum tensile strength specified:

a) less than 485 MPa (70 ksi)- Group 1; b) equal to or greater than 485 MPa (70 ksi) but less than 550 MPa (80 ksi)-

Group 2; c) equal to or greater than 550 MPa (80 ksi)—Group 3.

Separate welding procedures and performance qualifications shall be conducted for A841M/A841 material.

Page 89: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

9.2.1.4 Welding variables (including supplementary essential variables when impact tests are required by 9.2.2), as defined by QW-250 of Section IX of the ASME Code, shall be used to determine the welding procedure specifications and the procedure qualification records to be instituted. In addition, when impact tests of the heat-affected zone are required, the heat-treated condition of the base material shall be a supplementary essential variable. Plates produced by the controlled-rolled process are not to be considered as having received any heat treatment. If a protective coating has been applied to weld edge preparations, the coating shall be included as an essential variable of the welding procedure specification, as required by 7.2.1.9.

Page 90: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

9.2.2 Impact Tests9.2.2.1 Impact tests for the qualification of welding procedures shall comply with the applicable provisions of 4.2.9 and shall be made at or below the design metal temperature.

Page 91: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

9.2.2.2 When impact testing of a material is required by 4.2.9, 4.2.10, or 4.5.4 impact tests of the heat-affected zone shall be made for all machine, automatic, and semiautomatic welding procedures.

9.2.2.3 For all materials to be used at a design metal temperature below 10°C (50°F), the qualification of the welding procedure for vertical joints shall include impact tests of the weld metal. If vertical joints are to be made by a machine, automatic, or semiautomatic process, impact tests of the heat-affected zone shall also be made.

9.2.2.4 When the design metal temperature is below -7°C (20°F), impact tests of the weld metal shall be made for all procedures used for welding the components listed in 4.2.10.1, for welding attachments to these components, and for fabricating shell nozzles and manholes from pipe and forgings listed in 4.5.

Page 92: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

9.2.2.5 Impact tests shall show minimum values for acceptance inaccordance with 4.2.9.3 and the following:

a) for P-No. 1, Group 1, materials- 0 J (15 ft-lbf), average of three specimens;b) for P-No. 1, Group 2, materials- 27 J (20 ft-lbf), average of three specimens; c) for P-No. 1, Group 3, materials- 34 J (25 ft-lbf), average of three specimens.

For shell plates thicker than 40 mm (1½ in.), these values shall be increased by 7J (5 ft-lbf) for each 13 mm ( ½ in.) over 40 mm (1½ in.)

Page 93: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

9.2.2.6 Weld-metal impact specimens shall be taken across the weld with one face substantially parallel to and within 1.5 mm (1/16 in.) of the surface of the material. The notch shall be cut normal to the original material surface and with the weld metal entirely within the fracture zone.

9.2.2.7 Heat-affected-zone impact specimens shall be taken across the weld and as near the surface of the material as is practicable. Each specimen shall be etched to locate the heat-affected zone, and the notch shall be cut approximately normal to the original material surface and with as much heat-affected-zone material as possible included in the fracture zone.

9.2.2.8 Production welding shall conform to the qualified welding procedure, but production-weld test plates need not be made.

Page 94: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

C. API-650 and API-653: General welding requirements: 1. API Standard 650, Welded Steel Tanks for Oil Storage: The inspector

should be familiar with and understand the general rules for welding in API-650, Section 9 and other rules for welding in API-650 such as those for:

a) typical joints and definitions b) weld sizes c) restrictions on joints d) maximum allowable reinforcement e) inspection requirements

Page 95: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

III. NONDESTRUCTIVE EXAMINATION ASME Section V, Nondestructive Examination NOTE: The examination will cover only the main body of each referenced Article, except as noted:

F. API-650 and API-653: General nondestructive examination requirements: 1. API Standard 650, Welded Steel Tanks for Oil Storage: The inspector

should be familiar with and understand the general rules for NDE in API-650, Section 8.

2. API Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction: The inspector should be familiar with and understand the general rules for NDE in API-653, Section 12

Page 96: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

API Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction and the related portions of API Standard 650, Welded Steel Tanks for Oil Storage (NOTE: all of API-653 is applicable to the examination unless specifically excluded.)

3. The inspector should have an understanding of the requirements for performing repairs and alterations such as:

a) definitions of repairs and alterations b) repairs to foundations, shell plates, welds, tank bottoms, nozzles & penetrations, roofs, seals c) knowledge of the repair/alteration material and toughness requirements d) use of unidentified materials for repairs/alterations e) hot tap requirements and procedures f) inspection and NDE requirements for repairs and alterations g) hydrostatic and leak testing requirements h) lap welded patch plates (API-653, 9-3) i) new bottoms supported by grillage API-650, Annex I, excluding calculations)

Page 97: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

API-653 ABOVEGROUND STORAGE TANK INSPECTOR-BOK

Page 98: Understanding apiicp653 reading 2 650 selected reading

05/15

Page 1 of 12

653_BOK_2015

BODY OF KNOWLEDGE

API-653 ABOVEGROUND STORAGE TANK INSPECTOR CERTIFICATION EXAMINATION

November 2015, March 2016 and July 2016 (Replaces October 2013)

API Authorized Aboveground Storage Tank Inspectors must have a broad knowledge base relating to tank

inspection and repair of aboveground storage tanks. The API Aboveground Storage Tank Inspector Certification

Examination is designed to identify individuals who have satisfied the minimum qualifications specified in API

Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction.

Questions may be taken from anywhere within each document in this Body of Knowledge (BOK), unless

specifically excluded herein.

In the event that specific sections of a document are listed as excluded– all other sections within that document are

included.

In some cases specific paragraphs or sections, such as the example shown below, are included as an aid to the

candidate. This is not intended to exclude other paragraphs.

For example: In the “Corrosion Rate and Inspection Intervals” section of this BOK (Section A, sub-section 1), it

states:

The Inspector must be able to calculate:

a) Metal Loss (including corrosion averaging - API-653, Section 4)

This means that the metal loss calculation will be found in Section 4. It does not mean that other sections in that

document are excluded.

The examination consists of two parts. The closed-book part tests the candidate on knowledge and tasks requiring

everyday working knowledge of API Standard 653 and the applicable reference documents. The open-book portion

of the examination requires the use of more detailed information that the inspector is expected to be able to find in

the documents, but would not normally be committed to memory.

REFERENCE PUBLICATIONS:

A. API Publications

API Recommended Practice 571, Damage Mechanisms Affecting Equipment in Refining Industry

API Recommended Practice 575, Inspection of Atmospheric and Low-Pressure Storage Tanks

API Recommended Practice 577, Welding Inspection and Metallurgy

API Standard 650, Welded Steel Tanks for Oil Storage

API Recommended Practice 651, Cathodic Protection of Aboveground Petroleum Storage Tanks

API Recommended Practice 652, Lining of Aboveground Petroleum Storage Tank Bottoms

API Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction

B. ASME Publications

American Society of Mechanical Engineers (ASME) Boiler & Pressure Vessel Code:

Section V, Nondestructive Examination

Section IX, Welding and Brazing Qualifications

Note: Refer to the Publications Effectivity Sheet in the application package for a list of which editions, addenda, and

supplements of the reference publications are effective for your exam.

Page 99: Understanding apiicp653 reading 2 650 selected reading

05/15

Page 2 of 12

653_BOK_2015

CALCULATIONS & TABULAR EVALUATIONS FOR EVALUATING THICKNESS MEASUREMENTS,

WELD SIZES, AND TANK INTEGRITY

(NOTE: Paragraph references for all formulas and calculations listed here should be checked for accuracy to the

edition, addenda, or supplement for the examination you plan to take per the Publication Effectivity Sheet in the API

Examination Application.)

NOTE: Candidates are expected to be able to understand SI units (metric system) and the US customary units (inches,

feet, PSI, etc.) and to use both system formulas.

A. Calculation questions will be oriented toward existing tanks, not new tanks. API Authorized AST Inspectors

should be able to check and perform calculations included in the following categories:

1. CORROSION RATES AND INSPECTION INTERVALS (API-575, Paragraph 7.2)

The Inspector should be able to take inspection data and determine the internal and external inspection intervals.

These calculations could be in either the “open book” or “closed book” portion of the exam. The Inspector must be

able to calculate:

a) Metal Loss (including corrosion averaging – (API-653, Section 4)

b) Corrosion Rates

c) Remaining Life

d) Remaining Corrosion Allowance

e) Inspection Interval (API-653, Section 6)

Remaining life (years) = t actual - t minimum

corrosion rate [inches (millimeters) per year]

Where:

t actual = the thickness, in inches (millimeters), recorded at the time of

inspection for a given location or component.

t minimum = minimum allowable thickness, in inches (millimeters), for a

given location or component.

Corrosion rate = t previous - t actual

years between t actual and t previous

t previous = the thickness, in inches (millimeters), recorded at the same

location as t actual measured during a previous inspection.

The formulas for performing the above calculations and rules for setting the inspection intervals may be "closed-

book" during the exam. The inspector should also be able to compensate for the corrosion allowance. (Add or

subtract based on requirements from the exam problem.)

2. JOINT EFFICIENCIES

The inspector must be able to determine the joint efficiency, "E", of a tank weld. Inspector should be able to

determine:

a) Joint Types (API-653 Section 4, Table 4-2)

b) Type and extent of radiography performed (API 653, Table 4-2, Section 12; API 650, Section 8.1, Figure 8-

1)

c) Joint efficiency by reading API-653, Table 4-2

Page 100: Understanding apiicp653 reading 2 650 selected reading

05/15

Page 3 of 12

653_BOK_2015

Determining joint efficiency may be part of a minimum thickness or maximum fill height problem since joint

efficiency, "E", is used in the formulas for determining required thickness. (API-653, 4.3.3.1)

3. MAXIMUM FILL HEIGHT (HYDROSTATIC TESTING)

The inspector should be able to determine the maximum liquid height for a tank. To determine the height, the “t min”

formula in API-653 is rearranged as follows. This formula will be provided in the exam. The inspector is NOT

expected to derive this formula by using transposition.

a) Calculate the minimum allowable thickness per Section 4 of API 653 or the maximum fill height in the

localized corroded area per:

HS E t

D G

min

.2 6

b) Calculate the minimum allowable thickness per Section 4 of API 653 or the maximum fill height for an

entire shell course per:

HS E t

D G

min

.2 6+ 1

4. WELD SIZES FOR SHELL & ROOF OPENINGS

The inspector should be familiar with determining the sizes and spacing of welds for shell openings to the extent of

being able to use the information in the following Figures and Tables:

a) API-650, Figures 5-7a, 5-7b, 5-8, 5-9, 5-12, 5-14, 5-16, 5-17, 5-19, 5-20, 5-21

b) API-650, Tables 5-6, 5-7, 5-9

c) API-653, Figures 9-1, 9-2, 9-4, 9-5

5. HOT TAPPING

a) The Inspector should be familiar with the Hot Tapping requirements. (API-653, Paragraph 9.14)

b) The inspector should be able to calculate the minimum spacing between an existing nozzle and a new hot tap

nozzle. (API-653 Paragraph 9.14.3)

6. SETTLEMENT EVALUATION

The Inspector should be able to calculate the maximum allowed settlement for the following:

a) Edge Settlement (API-653 Annex B.2.3, fig. B-5)

b) Bottom Settlement Near the Tank Shell (API-653, Annex B.2.4, Figures B-6, B-7, B-9 B-10, B-11, B-12, B-

13)

c) Localized Bottom Settlement Remote from the Tank Shell (API-653, Annex B.2.5, Fig. B-8)

7. NUMBER OF SETTLEMENT POINTS

a) The inspector should be able to calculate the number of survey points for determining tank settlement. (API-

653 12.5.2, Annex B, Figure B-1, Figure B-2)

Page 101: Understanding apiicp653 reading 2 650 selected reading

05/15

Page 4 of 12

653_BOK_2015

8. IMPACT TESTING

The inspector should understand the importance of tank materials having adequate toughness. The inspector should

be able to determine:

a) Tank design metal temperature (API-650, 4.2.9.3 & Figure 4-2)

b) Material Group Number for a plate (API-650, Tables 4-3a and 4-3b)

c) If impact testing is required (API-650, Figure 4-1a and 4-1b)

d) If impact test values are acceptable (API-650, Table 4-4a and 4-4b)

9. EXISTING TANK SHELL - MINIMUM THICKNESS

a) Calculate “S”, allowable stress (API-653, 4.3.3.1 & 4.3.4.1)

b) Determine “E”, Joint efficiency (API-653, 4.3.3.1, 4.3.4.1 & Tables 4-2 & 4-3)

c) Determine “H”, liquid height (API-653, 4.3.3.1 & 4.3.4.1)

d) Calculate- minimum acceptable thickness (API-653, 4.3.3.1 & 4.3.4.1)

e) Calculate the thickness required for continued service (API-653, 4.3.3.1 & 4.3.4.1)

10. RECONSTRUCTED TANK SHELL - MINIMUM THICKNESS

The inspector should be able to determine the minimum thickness of the shell of a reconstructed tank. The inspector

should be able to:

a) Determine “Sd”, allowable stress for design condition (API-650, table 5-2, API-653, 8.4.2)

b) Determine “St”, allowable stress for hydrostatic test condition (API-650, Table 5-2, API-653, 8.4.3)

c) Calculate “td”, design shell thickness (API-650, 5.6.3.2, for tanks of 200 foot diameter and smaller)

d) Calculate “tt”, hydrostatic test shell thickness (API-650, 5.6.3.2)

11. TANK SHELL - CORRODED AREA

The inspector should be able to determine if a tank shell corroded area is acceptable for continued service. The

inspector should be able to:

a) Select “t2”, minimum thickness exclusive of pits for a corroded area (API-653, 4.3.2.1.a & Figure 4-1)

b) Calculate “L”, critical length for a corroded area (API-653, 4.3.2.1.b & Figure 4-1)

c) Determine “t1”, average thickness for a corroded area (API-653, 4.3.2.1.c, 4.3.2.1.d, Figure 4-1)

d) Determine “t min” for the corroded area “H”, height and “E”, joint efficiency will be based on corroded area

(API-653, 4.3.3.1)

e) Determine if tmin is acceptable (API-653, 4.3.3.1.a & .b)

12. TANK SHELL - PITTING

The inspector should be able to evaluate a pitted area. The inspector should be able to:

a) Calculate maximum acceptable pit depth (API-653, 4.3.2.2.a)

b) Determine the maximum length of pits in any 8” vertical length (API-653, 4.3.2.2.b & Figure 4-2)

13. BOTTOM PLATE MINIMUM THICKNESS

The inspector should be able to determine if the bottom thickness is acceptable for continued service. The inspector

should be able to:

Page 102: Understanding apiicp653 reading 2 650 selected reading

05/15

Page 5 of 12

653_BOK_2015

Calculate “MRT”, minimum remaining thickness at the next inspection. (API-653, 4.4.5.1)

Calculate “O”, maximum period of operation. These formulas will be provided in the exam.

14. REPLACEMENT PLATES

a) The inspector should be able to determine the minimum dimensions for a replacement plate. (API-653,

Figure 9-1)

15. LAP WELDED PATCH PLATES

Per API-653, Paragraph 9.3 the inspector should be able to determine:

a) The minimum thickness

b) The minimum weld size

c) The allowable size of the patch plate

B. Typical code calculations and requirements that candidates will NOT be expected to know for purposes of the

certification examination.

1. Required thickness calculations for wind, earthquake, and small internal pressures;

2. Nozzle calculations for external loads;

3. Flange calculations;

4. Brazing requirements;

5. Calculating venting requirements;

6. Ladder, stairway, and other structural type calculations;

7. Calculations for bottoms supported by grillage;

8. Variable point method calculations

Page 103: Understanding apiicp653 reading 2 650 selected reading

05/15

Page 6 of 12

653_BOK_2015

II. WELDING ON ATMOSPHERIC ABOVEGROUND STORAGE TANKS

ASME Section IX, Welding and Brazing Qualifications

(NOTE: Candidates should be familiar with the basic requirements for welding qualifications for procedures and

welding personnel contained in ASME Section IX. Brazing is NOT covered on the examination. )

A. The inspector should have the knowledge and skills required to review a Procedure Qualification Record and a

Welding Procedure Specification or to answer questions requiring the same level of knowledge and skill.

Questions covering the specific rules of Section IX will be limited in complexity and scope to the SMAW and

SAW welding processes.

1. Questions will be based on:

a) No more than one process

b) Filler metals limited to one

c) Essential, non-essential, variables only will be covered

d) Number, type, and results of mechanical tests

e) Base metals limited to P1

f) Additional essential variables required by API-650 or API-653

2. The following are specifically excluded:

a) Dissimilar base metal joints

b) Supplemental powdered filler metals and consumable inserts

c) Special weld processes such as corrosion-resistant weld metal overlay, hard-facing overlay, and dissimilar

metal welds with buttering

d) Charpy impact requirements and supplementary essential variables

e) Any PQR and WPS included on the examination will not include heat treatment requirements.

B. The inspector should know that the WPS must reference the applicable PQR and that the PQR must be signed and

dated.

C. API-650 and API-653: General welding requirements:

1. API Standard 650, Welded Steel Tanks for Oil Storage: The inspector should be familiar with and

understand the general rules for welding in API-650, Section 9 and other rules for welding in API-650 such

as those for:

a) typical joints and definitions

b) weld sizes

c) restrictions on joints

d) maximum allowable reinforcement

e) inspection requirements

2. API Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction: The inspector should be

familiar with and understand the general rules for welding in API-653, Section 11.

Page 104: Understanding apiicp653 reading 2 650 selected reading

05/15

Page 7 of 12

653_BOK_2015

III. NONDESTRUCTIVE EXAMINATION

ASME Section V, Nondestructive Examination

NOTE: The examination will cover only the main body of each referenced Article, except as noted:

A. Article 1, General Requirements:

The inspector should be familiar with and understand:

1. The Scope of Section V,

2. Rules for use of Section V as a referenced Code,

3. Responsibilities of the Owner / User, and of subcontractors,

4. Calibration,

5. Definitions of “inspection” and “examination”,

6. Record keeping requirements.

B. Article 2, Radiographic Examination:

The inspector should be familiar with and understand:

1. The Scope of Article 2 and general requirements,

2. The rules for radiography as typically applied on butt welded AST horizontal and vertical seams such as, but

not limited to:

· required marking

· type, selection, number, and placement of IQIs,

· allowable density

· control of backscatter radiation

· location markers

3. Records

C. Article 6, Liquid Penetrant Examination, Including Mandatory Appendix II:

The inspector should be familiar with and understand:

1) The Scope of Article 6,

2) The general rules for applying and using the liquid penetrant method such as but not limited to:

a) procedures

b) contaminants

c) techniques

d) examination

e) interpretation

f) documentation

g) record keeping

D. Article 7, Magnetic Particle Examination (Yoke and Prod techniques only, excluding paragraphs T-765 and T-766):

The inspector should be familiar with and understand the general rules for applying and using the magnetic particle

method such as but not limited to:

1. The Scope of Article 7,

2. General requirements such as but not limited to requirements for:

a) procedures

b) techniques (Yoke and Prod only)

Page 105: Understanding apiicp653 reading 2 650 selected reading

05/15

Page 8 of 12

653_BOK_2015

c) calibration

d) examination

e) interpretation

3. Documentation and record keeping

E. Article 23, Ultrasonic Standards, Section SE–797 only – Standard practice for measuring thickness by manual

ultrasonic pulse-echo contact method:

The inspector should be familiar with and understand;

1. The Scope of Article 23, Section SE-797,

2. The general rules for applying and using the Ultrasonic method

3. The specific procedures for Ultrasonic thickness measurement as contained in paragraph 7.

F. API-650 and API-653: General nondestructive examination requirements:

1. API Standard 650, Welded Steel Tanks for Oil Storage: The inspector should be familiar with and understand

the general rules for NDE in API-650, Section 8.

2. API Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction: The inspector should be familiar

with and understand the general rules for NDE in API-653, Section 12

IV. PRACTICAL KNOWLEDGE - GENERAL

A. The following topics may be covered:

1. Organization and Certification Requirements.

2. Types and Definitions of Inspections.

3. Types Corrosion and Deterioration.

4. Materials and Fabrication Problems.

5. Welding.

6. Nondestructive Examination (NDE) Methods

7. Corrosion and Minimum Thickness Evaluation.

8. Estimated Remaining Life.

9. Inspection Interval Determination and Issues Affecting Intervals.

10. Inspecting Relief Devices.

11. Inspection Safety Practices.

12. Inspection Records and Reports.

13. Repairs / Alterations.

14. Disassembly and Reconstruction.

15. Hydro Testing,

16. Pneumatic Testing

More information relevant to each of these categories is contained in section “V. PRACTICAL KNOWLEDGE -

SPECIFIC” where each reference publication applicable for study for the examination has been listed with the relevant

topics that may be covered on the examination.

B. Typical code requirements that candidates will NOT be expected to know for purposes of this certification examination.

1. Required thickness calculations for wind, earthquake, and small internal pressures

2. Nozzle calculations for external loads;

3. Flange calculations;

4. Brazing requirements;

5. Calculating venting requirements (API 650 5.8.5);

6. Ladder, stairway, and other structural type calculations;

Page 106: Understanding apiicp653 reading 2 650 selected reading

05/15

Page 9 of 12

653_BOK_2015

7. NDE requirements for eddy current, and motion radiography per ASME Section V, Article 9

8. Technical interpretations of API & ASME Codes and Standards

9. Welding process requirements other than shielded metal arc welding (SMAW) and submerged arc welding

(SAW)

10. API 650, Annex D

11. API 650, Annex E

12. API 650, Annex F

13. API 650, Annex G Except for G1.

14. API 650 Annex I Except for 1.1 and 1.2

15. API 650, Annex J

16. API 650, Annex K

17. API 650, Annex L

18. API 650, Annex M Except for M1.

19. API 650 Annex O Except for O1 & O2

20. API 650, Annex P.

21. API 650, Annex R

22. API 650, Annex S Except for S1

23. API 650, Annex SC

24. API 650, Annex T.

25. API 650, Annex V.

26. API 650, Annex W.

27. API 650, Annex X

28. API 650, Annex Y

V. PRACTICAL KNOWLEDGE - SPECIFIC

A. Each reference publication relative to study for the examination is listed below. A list of topics, which may be

covered, is listed for each publication. Some topics may be listed under more than one publication. For example;

ASME Section IX is the basic document for welding requirements as referenced by API-650 and API-653. The

referencing API documents contain additional welding requirements and exceptions or additions to those contained

in ASME Section IX. Therefore, welding requirements may be listed under all three documents and all three

documents may be listed under the general heading of “Welding on Tanks”.

API RP 571, Damage Mechanisms Affecting Fixed equipment in the Refining Industry

ATTN: Inspectors are not required to memorize the definitions of terms included in Section 3 (Definitions of Terms

and Abbreviations), but are expected to be familiar with the common terms and abbreviations and be able to find

definitions, if needed in the solution of a test question.

Test questions will be based on the following mechanisms only:

4.2.7 - Brittle Fracture

4.2.16 - Mechanical Fatigue

4.3.2 - Atmospheric Corrosion

4.3.3 - Corrosion Under Insulation (CUI)

4.3.8 - Microbiologically Induced Corrosion (MIC)

4.3.9 - Soil Corrosion

4.3.10 – Caustic Corrosion

4.5.1 - Chloride Stress Corrosion Cracking (Cl-SCC)

4.5.3 - Caustic Stress Corrosion Cracking (Caustic Embrittlement)

5.1.1.10- Sour Water Corrosion (Acidic)

5.1.11 - Sulfuric Acid Corrosion

Page 107: Understanding apiicp653 reading 2 650 selected reading

05/15

Page 10 of 12

653_BOK_2015

API Recommended Practice 575, Inspection of Atmospheric and Low-Pressure Storage Tanks

NOTE: API RP-575 is a Recommended Practice and contains many general statements that are not strict requirements.

Some questions on the examination related to RP-575 may contain phrases such as “it is best to” or “an inspector would

normally” when information or statements from RP-575 are covered. In these cases it is important to be familiar with

the content of RP-575 and to be able to pick the best answer of those given. All of RP-575 is applicable to the

examination unless specifically excluded.

A. The inspector should have a practical understanding and be familiar with the information contained in RP-575

(excluding Annex C) as related to:

1. types of tanks covered

2. procedures to perform internal and external inspection

3. the types of external and internal inspections

4. procedures to determine suitability for continued service

5. evaluation change-of-service effects on suitability for continued service

6. evaluation and general condition of:

a) distortions, flaws, windgirders, stiffeners, welds, and nozzles

b) tank bottoms

c) tank foundations

d) causes of corrosion, leaks, cracks, and mechanical deterioration

e) auxiliary equipment.

f) anchor bolts, pipe connections, ground connections

g) insulation.

h) shells and roofs

API RP 577, Welding Inspection and Metallurgy

1. Definitions

2. Welding inspection

3. Welding processes

4. Welding procedure

5. Welding materials

6. Welder qualifications

7. Non-destructive examination

8. Metallurgy

9. Refinery and Petrochemical Plant Welding Issues

10. Terminology and symbols

11. Actions to address improperly made production welds

12. Welding procedure review

13. Guide to common filler metal selection

14. Example report of RT results

API Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction and the related portions of API

Standard 650, Welded Steel Tanks for Oil Storage

(NOTE: all of API-653 is applicable to the examination unless specifically excluded.)

A. Tank Inspection, NDE, and Testing

1. The inspector should have a practical understanding and be familiar with the information contained in API-

653 related to general inspection practices such as:

Page 108: Understanding apiicp653 reading 2 650 selected reading

05/15

Page 11 of 12

653_BOK_2015

a) types of tanks covered

b) applicable inspection tasks for internal and external inspection (e.g., API Standard 653, Annex C,

Checklists for Tank Inspection).

c) safe working practices

d) thickness and dimensional measurements and tolerances

e) requirements of external and internal inspections

f) frequencies and intervals for external and internal inspection

g) alternatives to the required internal inspection intervals

h) NDE procedures and NDE personnel qualification requirements

i) types of roofs and seals and types of deterioration

j) reasons for inspection and causes of deterioration of storage tanks

k) procedures to check or test storage tanks for leaks

l) tools and equipment for tank inspection

m) failure assessment and deterioration of auxiliary equipment

n) suitability for continued service.

o) change-of-service effects on suitability for continued service

p) evaluation of tank bottom conditions

q) evaluate tank foundation conditions

r) risk of failure due to brittle fracture

s) evaluate the causes of corrosion, leaks, cracks, and mechanical deterioration.

t) evaluate the condition of anchor bolts, pipe connections, ground connections, and insulation

2. The inspector should have an understanding and be able to perform calculations related to: (See also

previous section on “CALCULATIONS FOR EVALUATING THICKNESS MEASUREMENTS AND

TANK INTEGRITY”)

a) actual and minimum required thickness for shell plates

b) maximum allowable fill height

c) required thickness for hydrotesting and for elevated temperatures

d) evaluation of corroded areas and pits on shell plates

e) t min, corrosion rate, inspection interval and remaining corrosion allowance

f) distortions, flaws, welds, and nozzles.

g) minimum thickness for tank bottoms and annular plate rings and shell rings

h) evaluate the effects of tank bottom settlement and acceptable limits

i) evaluate the condition of tank shells and roofs.

j) weld size at roof-to-shell and bottom-to-shell junctions per design requirements

3. The inspector should have an understanding of the requirements for performing repairs and alterations such

as:

a) definitions of repairs and alterations

b) repairs to foundations, shell plates, welds, tank bottoms, nozzles & penetrations, roofs, seals

c) knowledge of the repair/alteration material and toughness requirements

d) use of unidentified materials for repairs/alterations

e) hot tap requirements and procedures

f) inspection and NDE requirements for repairs and alterations

g) hydrostatic and leak testing requirements

h) lap welded patch plates (API-653, 9-3)

i) new bottoms supported by grillage API-650, Annex I, excluding calculations)

Page 109: Understanding apiicp653 reading 2 650 selected reading

05/15

Page 12 of 12

653_BOK_2015

4. The inspector should have an understanding of the requirements for recording the inspection data and

records related to inspection, repairs, and alterations such as:

a) nameplate requirements

b) record-keeping requirements

c) reports for inspection, repair and alterations

API Recommended Practice 651, Cathodic Protection of Aboveground Petroleum Storage Tanks

NOTE: Only Sections 1, 2, 3, 4, 5, 6, 8, and 11 will be covered on the examination.

A. The inspector should have a practical understanding and be familiar with the information contained in RP-651

related to:

1. Corrosion of Aboveground Steel Storage Tanks

2. Determination of Need for Cathodic Protection

3. Methods of Cathodic Protection for Corrosion Control

4. Operation and Maintenance of Cathodic Protection Systems

B. Information contained in RP-651 which the inspector will not be examined on:

1. design of cathodic protection systems

2. sources, detection, and control of interference currents

API Recommended Practice 652, Lining of Aboveground Petroleum Storage Tank Bottoms

A. The inspector should have a practical understanding and be familiar with the information contained in RP-652

related to:

1. types of tank bottom linings and advantage and disadvantages of each

2. considerations for recommending tank bottom linings

3. causes of tank bottom lining failures

4. types of tank bottom lining materials

5. surface preparation requirements for the installation of tank bottom linings

6. issues affecting the application of a tank bottom lining

Page 110: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

API-653 ABOVEGROUND STORAGE TANK Publications Effectivity Sheet

Page 111: Understanding apiicp653 reading 2 650 selected reading

653_2015_53014

API 653 Exam Administration -- Publications Effectivity Sheet

FOR: November 2015, March 2016 and July 2016

Listed below are the effective editions of the publications required for this exam for the date(s) shown above.

Please be advised that API and ASME documents and publications are copyrighted materials. Reproducing

these documents without API permission is illegal.

API Recommended Practice 571, Damage Mechanisms Affecting Fixed Equipment in the Refining Industry,

Second Edition, April 2011

ATTENTION: Only the following sections / mechanisms from RP 571 are included on the exam:

Section 3, Definitions

Par. 4.2.7 Brittle Fracture

4.2.16 Mechanical Fatigue

4.3.2 Atmospheric Corrosion

4.3.3 Corrosion Under insulation (CUI)

4.3.8 Microbiologically Induced Corrosion (MIC)

4.3.9 Soil Corrosion

4.3.10 Caustic Corrosion

4.5.1 Chloride Stress Corrosion Cracking (Cl-SCC)

4.5.3 Caustic Stress Corrosion Cracking (Caustic Embrittlement)

5.1.1.10 Sour Water Corrosion (Acidic)

5.1.1.11 Sulfuric Acid Corrosion

API Recommended Practice 575, Inspection of Atmospheric and Low-Pressure Storage Tanks, Third

Edition, April 2014

API Recommended Practice 577 – Welding Inspection and Metallurgy, Second Edition, December 2013

API Standard 650, Welded Tanks for Oil Storage, Twelfth Edition, March 2013 with Addendum 1

(September 2014), Errata 1 (July 2013), and Errata 2 (December 2014).

API Recommended Practice 651, Cathodic Protection of Aboveground Petroleum Storage Tanks, Fourth

Edition, September 2014.

API Recommended Practice 652, Lining of Aboveground Petroleum Storage Tank Bottoms, Fourth

Edition, September 2014

API Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction, Fifth Edition, November 2014.

American Society of Mechanical Engineers (ASME), Boiler and Pressure Vessel Code, 2013 Edition

i. ASME Section V, Nondestructive Examination, Articles 1, 2, 6, 7 and 23 (section SE-797 only)

ii. Section IX, Welding and Brazing Qualifications (Welding Only)

___________________________________________________________________________

Please ensure you obtain authorized documents from one of API’s redistributors:

Techstreet: www.techstreet.com; Phone: 1-800-699-9277

IHS Documents: www.global.ihs.com; Phone: 1-800-854-7179

Page 112: Understanding apiicp653 reading 2 650 selected reading

http://independent.academia.edu/CharlieChong1http://www.yumpu.com/zh/browse/user/charliechonghttp://issuu.com/charlieccchong

Charlie Chong/ Fion Zhang

Page 113: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Page 114: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Page 115: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Good Luck!

Page 116: Understanding apiicp653 reading 2 650 selected reading

Charlie Chong/ Fion Zhang

Good Luck!