The project presentation of the Capital city
Cooperation offer
1, JUNE 2014
![Page 2: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/2.jpg)
POPULATION1.3 million
(46% of Mongolia)
TERRITORY4700 km2 (0.3% of
Mongolia)
GDP ₮ 8 784 666 mil.
(63% of Mongolia)
LOANS84% of Mongolia
AUTOMOBILE59% of Mongolia
SAVINGS83% of
Mongolia
UB CITY STATISTICS
![Page 3: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/3.jpg)
INVESTMENT PROJECT ARRANGEMENT /CITY BUDGET/
/million tugrug/
95 837,8 45%
48 393,923%
39 680,019%
10 577,05%
9 924,1 5% 6 502,6
3%
URBANIZATION, INFRACTRUCTURE BRANCH SOCIAL BRANCH AUTO ROAD BRANCH TRANSPORTATION BRANCH STATE SERVICE
LANDSCAPING, GREEN AREA
![Page 4: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/4.jpg)
2020 2030
It is projected that population of the capital city will be 50.3% of total population of the country in order to ensure national security, water resource and keep balance of nature and ecology.
Population of Mongolia - 2020
3,162
UB region
1,534 /48,5%/
Other 4 region
1,628 /51,5%/
Population of Mongolia - 2030
3,501
UB region
1,763 /50,3%/
Other 4 region
1738 /49,7%/
UB REGIONAL POPULATION PROSPECT /thousands/
№ Name of the city, town
2010
/statistics/Planned population
Population Households 2020 % 2030 %
1Ulaanbaatar /Metropolitan/
1058,129 264,311 1235,5 80,5 1400.0 79.4
2 Suburbs 103,656 30,106 298,5 19,4 363.0 20.6
Total population of capital city
1161,785 294,416 1534,0 1763.0
UB REGIONAL POPULATION PROSPECT
4
![Page 5: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/5.jpg)
Needs About 16 bilion USD for Implementation
of the Master Plan of Ulaanbaatar
ULAANBAATAR MASTER PLAN 2020
![Page 6: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/6.jpg)
Capital city budget MCUD /State budget/ MEDS /State budget/
Projects started in 2013 Projects to be done in 2014
Capital city budget
ULAANBAATAR MASTER PLAN 2020
![Page 7: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/7.jpg)
GER DISTRICT
Apartment area 5,857 Ha (21%)
61% 736.
0 people
39% 470.
6 people
Apartment buildings
Ger area
Ger area 21,823 Ha (79%)
7
![Page 8: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/8.jpg)
Яармаг
Шинэ төв
Сонсголон
Гурвалжин
Bayankhoshuu Selbe
Хотын хуучин төв
Амгалан
Financed by ADB with a 1.5$ million technical assistance, investment program project for developing subcenters Bayankhoshuu, Selbe is ready.
The mission of the program is to build a network in sub-centers that has economic opportunity, housing and urban infrastructure services with healthy, safe, comfortable and favorable condition
“ULAANBAATAR URBAN SERVICES AND GER AREAS DEVELOPMENT INVESTMENT PROGRAM”
![Page 9: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/9.jpg)
Baganuur district
(1,5 khoroo)
17 khoro
o
Sukhbaatar district
15 khoro
o
9,10,11,12 khoroo
13,14 khorо
о8,16 khoro
o12 khoro
о
2 khoro
o2,4 khorо
о
Bayanzu
rkh d
istr
ict
Khan-Uul district
(4 khoroo)7district
34khoroo Population:69072
10,11 khoroo
11 khoroo
Bayangol district 7,8
khoroo
7 khoro
o
9,10,11 khoroo
13, 15 khoro
o
Chingeltei district
5,6,7 khoro
o
10 khoro
o
Songin
o k
hair
khan
dis
tric
t
1,2,20
khoroo
30 khoro
o
28 khoro
o
RE-PLANNING THE GER AREAS
![Page 10: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/10.jpg)
RAILBUS Will be open on June
6th 2014300 million tugrug decided from the Municipality.
NUMBER OF SITS: 136 PEOPLE
TOTAL NUMBER OF PASSENGERS: 350-400 PEOPLE
NUMBER OF TRAVELS:AMONG 1 ROAD PER DAY 3 TIMESAMONG DUAL ROAD PER DAY 6 TIMES
SPEED: 100KM/HOUR
TIME:TOLGOIT-AMGALAN 47 MINAMGALAN-TOLGOIT 45 MIN
SERVICE WORK TEAM: 4 PEOPLE
![Page 11: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/11.jpg)
BUS RAPID TRANSIT /BRT/
1ST line of 22 km, 28 stops, 18 t/a
2nd line of 30 km, 32 stops, 16 t/a
• INTEGRATED PLANNING
![Page 12: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/12.jpg)
6.6 km: Underground
6.2 km: Soaring
4.9 km: Soaring
Tootal length 17.7 km
• Establish a legal framework in relation to the construction of a subway in the city of Ulaanbaatar
• In 2014, in preparation for construction of a subway in the city of Ulaanbaatar, will conduct the work such as drafting a plan, detailed engineering studies, assessment of environmental impact and determining the cost of the project.
ULAANBAATAR – METRO PROJECT
![Page 13: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/13.jpg)
WORK NOTE
1 “Ulaanbaatar New City Hall” project is implemented to build in 6th khoroo of the Songinokhairkhan district, which general plan is approved by City Council of Ulaanbaatar.
City council 7/29 decree, 2013
2 On June 7th, 2013, the tender for companies and enterprise that will complete the construction was announced.
Batch Number Redevelopment of ger area project-2013/8
3 The Mayor of Ulaanbaatar city ratified that “Halla Gonsol” company is selected for the project from 5 companies.
Mayor’s A/761 th charge, 12/Aug/2013
4 The task force is established by Mayor’s 783th charge on August 19th, 2013.
Held 15 meetings
5 The task force worked and acquainted with the re-planning project in Korea, agreed mutually about the type of financing, type of agreement, energy efficient, environmental friendly and containing national patterns.
12/Sep/2013
6 The Mayor requested to Prime Minister Mr. N.Altankhuyag for supporting of implementation the new administrative center of the city’s construction project.
By 01/788 official letter and by himself, 18/March/2014
7 Presented at a meeting of government and recognized by Government. 28/March/2014
THE PROJECT OF ULAANBAATAR NEW CITY HALL
![Page 14: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/14.jpg)
![Page 15: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/15.jpg)
“New complex of the cities administration:
Building of the City Consul of Ulaanbaatar /6 floor/;Building of the Center acceptance for the citizen /2 floor/;Governor office of the UB city, Subsidiary agencies /20 floor/;Sport hall /1 floor/ consists of these 4 basic buildings. For implementing this project from 9,2 hectare square planed building 13%, 57% landscaping square, 30% road, parking place. Total building square is 50,000м2 potentially 1429 officers can work here.
Building of the Center acceptance for the citizen potentially consists of 100 kindergarten, at once can accept 200 people, 100 people can served by library.
Regarding the technology should contain energy saving (eco-friendly), advanced smart technology (intelligent building), veracious for the public (openness, transparency), national features style.
ABOUT THE BUILDING
![Page 16: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/16.jpg)
Working title Halla Gonsol /dollars/
Construction 38,917,465
Land 6,827,625
Equipment 10,241,438
Electricity 10,525,922
Public tied house operation
9,956,956
Sum 76,469,406
Drawing 2,294,082
Total 78,763,488
Construction value, cost statement
![Page 17: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/17.jpg)
FINANCING STRUCTURE OF PROJECT
MUB Customer bank
Contractor bankHalla Gonsol
Financing (Credit / Bond)
Collateral, Sponsion
Financing (non-project company)
Direct contractsMonthly bill
(Monthly payment claims/IPC approvals)
Letters of credit or bonds (due within 3 years from the date of commissioning)
![Page 18: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/18.jpg)
Hui Doloon Hudag is a beautiful green valley where Mongolians used to celebrate its great Summer Festival and located 32 km westward on the main road to the Western province from UB central Chingis Khan square.
“Mongol Naadam Complex” situated in Hui Doloon Hudag
![Page 19: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/19.jpg)
The “Mongol Naadam Complex” plans to construct the following buildings in its 13600 square m land.
![Page 20: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/20.jpg)
Construction works planned from 2014 to 2020
1. Arena for horse racing2. Stadium3. Open stadium for archery 4. Ankle bone shooting tent
5. Road along with horse race route6. Ski and Snowboard camps7. Complex for horse racing8. Sport center for the capital city dwellers
9. Horse symbol10. Archery symbol11. Wrestler symbol12. Car park
12
34
5
6
7
89
1011
12
![Page 21: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/21.jpg)
STADIUM
40.000 capacity stadium designed for football and other mass sport events shall take place. In future during national Great Holiday Naadam it will be major arena for wrestling and other sport and mass events.
![Page 22: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/22.jpg)
Arena for Horse Racing
VERSION 1 /DESIGN/ 200Х34Х24М SIZE 40.000 CAPACITY HALF OPEN ARENA, WITH METAL AND CONCRETE COVER, ON THE LOWER FLOOR SERVICE CENTER, EXHIBITION HALL, CONFERENCE HALL AND VIP ROOM.
![Page 23: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/23.jpg)
Complex for horse racing:
There will be built 40.000 seats stadium with capacity to allow betting through the internet. In this stadium:House for horse breeding Service center Shop for horse racing sport Restaurant
![Page 24: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/24.jpg)
Open Stadium for Archery competitions:
On 3 square km land, will be built arena with capacity for 3000 viewers and 600 archery sportsmen. There also will be mounted large tent with seats for 1000 spectators and where simultaneously can compete 64 teams in ankle bone shooting.
![Page 25: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/25.jpg)
Ankle bone shooting tent
There also will be mounted large tent for ankle bone shooting competition for 1000 spectators and where simultaneously can compete 64 teams in ankle bone shooting.
![Page 26: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/26.jpg)
Ski and Snowboard Camps
There is plan to construct skiing center for international competitions on 100 square m land. It shall have capacity to serve in one day for 3000 people. There will be arena also for snowboarding and other types of winter sports.
![Page 27: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/27.jpg)
МММмМ
Sport center for the capital city dwellers:
1. Office 2. Warehouse3. Security
office4. Hotel5. Ger camp6. Water slide7. Conference
hall8. Spa sauna9. Play grounds10. Green house
for flowers
warehouse Ger camp Play grounds
Water slide
Hotel
Massage
Spa
Sauna
![Page 28: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/28.jpg)
10th khoroo of Khan-Uul district Model project of Morindavaa area
Project
Action Plan of Governor and Mayor of Ulaanbaatar city, 2013-2016
City goals for economic and social 2014,
The Ulaanbaatar city urban planning policy “ Master Plan “ up to 2020 ,
Action plan documents of the development trend up to 2030,
City land management plan 2014, On 30th May, 2013, the City Council
based on the №10/39th resolution “Domestic demand for defining the location of land to citizens".
![Page 29: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/29.jpg)
New municipal land
“CITY TOWN”
Propoesd land
Center of Ulaanbaatar
![Page 30: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/30.jpg)
“BAYANGOL DOWNHILL” 1st khoroo of Songinokhairkhan district
6800 apartments
Propoesd land
Military town area Center of city
![Page 31: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/31.jpg)
HOUSING SUPPLY /2030/Total of 215000
household People who can afford direct payment
People who can afford mortgage with advanced paymentPeople who live abroad
People without savings -with permanent income -rural residences
From total of 215 000 housing required household current statistic shows that 70% /140 000/ household will be involved in HOCK program.
![Page 32: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/32.jpg)
Авто худалдааны төв орчим
FIRST INTENDING LOCATIONS
![Page 33: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/33.jpg)
NORTH SIDE OF THE YARMAG SPORT COMPLEX KHAN-UUL district, 16th khoroo /959 family, 3836
people/
![Page 34: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/34.jpg)
According the partial overall
planning nearly Buyant-Uhaa scheduled consists of 9 buildings, 15 floors, one-two entrances
Regarding the buildings all the first floors and the buildings grounded along the mean road from first to third floors should be used for service.
For the outside parking space planned openly 300, inside 400 cars, totally provide 70% of the family.
NORTH SIDE OF THE YARMAG SPORT COMPLEX KHAN-UUL district, 16th khoroo /959 family, 3836 people/
![Page 35: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/35.jpg)
NORTH SIDE OF THE YARMAG SPORT COMPLEX KHAN-UUL district, 16th khoroo /959 family, 3836
people/
![Page 36: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/36.jpg)
“BAYANGOL DOWNHILL” 1st khoroo of Songinokhairkhan district
6800 apartments
![Page 37: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/37.jpg)
“BIO-SONGINO” KHAN-UUL DISTRICT 12 khoroo
/household:2837, population:11348/
![Page 38: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/38.jpg)
“BIO-SONGINO” KHAN-UUL DISTRICT 12 khoroo /household:2837, population:11348/
![Page 39: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/39.jpg)
Finance diagram
China exim bank
Shanghai group
Apartment
Ulaanbaatar
NOSK
House holder
Housing fund
Mongolia China
Apartm
ent
Infrastr
ucture
Saving
Pay back
construct
Ulaanbaatar• Land • Infrastructure • School • Kindergarten• HospitalChinese side• Investment • Construct a building• Commercial center NOSK • Acquisition• Order /From citizen/
![Page 40: ULAANBAATAR MONGOLIA PROJECT AND COOPERATION DEPARTMENT 91003310](https://reader038.fdocuments.net/reader038/viewer/2022103000/55544fc8b4c905b7428b4ed0/html5/thumbnails/40.jpg)
THANK YOU