Ukujima Photovoltaic Park 400...
Transcript of Ukujima Photovoltaic Park 400...
PHOTOVOLTDEVELOPMENT PARTNERS
29 Juli 2014 Page 1
Ukujima Photovoltaic Park 400 MWStable Integration of a 400MW Photovoltaic Farm int o the Japanese Power
System – Challenges and Chances
PHOTOVOLTDEVELOPMENT PARTNERS
29 Juli 2014 Page 2
Characteristics of the Project
2
Parameter Detail
Generation Site Ukujima Island
Source of Energy Photovoltaic
Installed Power ≈ 430 MW
Voltage at Generation Site 0.4 / 33 kV
Point of Common Coupling Ainoura Substation
Network Operator at PCC Kyushu Power & El.
Length to PCC 65.5 km
Voltage at PCC 220 kV
約500m
漁業権境界
Ukujima S/S
400 MW
Ainoura S/S220 kV
65.5 km
PHOTOVOLTDEVELOPMENT PARTNERS
29 Juli 2014 Page 3
3
The installed capacity of 400MW is identically to kinds of conventional Power Plants
The project‘s Character of a Power Plant and therefore the meaning for the existing
Japanese Transmission System requires the consideration of appropriate
technical solutions concerning
• The use of applications according to the State of the Art
• The fulfillement of the criteria for the reliability of power supply
• The knowledge of specifics for the Japanese Transmission system (e. g. JEAC)
• The application of international experiences for the grid connection of Renewables
• The electrical phenomena caused by the long submarine cable connection
Two Issues are the main Challenge concerning the Planning Process:
- A technical-economical Green-Field Structure for the Network at Ukujima
- The Identification of the optimal HV power transmission technology!
Challenges: Project Internal DesignGeneral Considerations
PHOTOVOLTDEVELOPMENT PARTNERS
29 Juli 2014 Page 4
4
Baseline Design PV Farm 400MW
• Internal PV-DC network 10Tkm
• Invertertstations 217 pcs.
434 Inverter 1000kVA each
• Network 33kV 150km
- Radial MV network structure
- max 18 Stations per MV-String
- max 630 A per String
- only Load-break switches
• Substation 220kV 2 x 250 MVA
• Submarine Cable 220kV 65km
cross section 1.600 mm² Al
General Structure of the internal MV Network
Challenges: Project Internal DesignGreen-Field Network Planning
AB C
33 kV
D
PHOTOVOLTDEVELOPMENT PARTNERS
29 Juli 2014 Page 5
Challenges: Project Internal DesignPower Transmission Technology to Ainoura
HVDC
LCC- / CSC-Technology *1
- Use Since early 1950
- Requires connection of two active power networks at both sides of the link
VSC-Technology *2
- Use since 1999
- Contrary to LCC, can be applied for linking isolate networks, like remote islands
HVAC
- Use of AC technology for long distances on- and offshore is well approved and experienced
Not applicablefor Ukujiima!
Applicablefor Ukujiima!
Applicablefor Ukujiima!
*1 Line Commutated Current-Sorced Converter*2 Voltage Source Commutated
For both technologies practical
experiences are available
vs.
PHOTOVOLTDEVELOPMENT PARTNERS
29 Juli 2014 Page 6
Challenges: Project Internal DesignInt’l HV Power Transmission Experiences
Other worlwide appli-
cations – besides
Germany / Europe –
are available for both
technologies as well!
VSC -HVDC HVAC
The power to be
transmitted
The length of
connection
Conclusion
for the
UMSP project
400 MW
65 km
Both Technologies
- HVAC and HVDC –
are applicable!
PHOTOVOLTDEVELOPMENT PARTNERS
29 Juli 2014 Page 7
Advantages Disadvantages
HVDC • Independent control of Active
and Reactive Power
• More expansive than HVAC
Cost Break-even >70km; lower losses will
not compensate higher investment costs
• Space problems for the placement
of the landside converter station
• Extreme long lead time
HVAC • Most economical solution
considering CAPEX + OPEX
• More References
• Expected influences to the existing
transmission system 220kV
Separate System Studies are necessary
Challenges: Project Internal DesignOptimal HV Power Transmission Technology
PHOTOVOLTDEVELOPMENT PARTNERS
29 Juli 2014 Page 8
The Main System Study Issues due to the influence of the existing transmission system by a long distance HVAC cable are:
I. Power Quality Analysis
•Impedance-Frequency-Curve and
Harmonics
II. Electromagn. Transient Analysis
•Voltage Drops, Surge Resonances and
Harmonics during switching processes
•Zero-miss currents during normal and
disturbed network conditions
•Effects of the Cable Discharge to the existing equipment (e. g. breakers)
•Lower Harmonic Resonances during a Fault Current
Challenges: Project Internal DesignNeed and Content of System Studies
0
50
100
150
200
0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800
Imp
ed
an
ce [
Oh
m]
Frequency [Hz]
Z=f(f) without UMSP
Z=f(f) with UMSP Displacement of the Resonancedue to the long HVAC cable
PHOTOVOLTDEVELOPMENT PARTNERS
29 Juli 2014 Page 9
Challenges: Project Internal DesignPowerful System Analysis Software
• Load Flow analysis and Short-Circuit Analysis ( IEC 60909, ANSI C37, IEC 61363, complete method, multiple faults, DC Short-Circuit calculation according to IEC 61660 and ANSI/IEEE 946)
• Optimal Power Flow (OPF): Reactive power optimization and economic dispatch
• Protection Functions: Time-Overcurrent Protection and Distance Protection; comprehensive relay library with relay models suitable for steady-state, RMS and EMT calculations
• Voltage stability analysis: PQ and QV curves; P-, Q-, I- and V-measurement models, consideration of load flow constraints, verification of system observability
• Cable Sizing: Automatic cable sizing and cable reinforcement optimization
• Basic MV/LV Network Analysis: Feeder Analysis Tool, Radial Feeder Tool, Backbone Calculation
• Power Quality and Harmonic Analysis– Harmonic Load Flow and Filter Analysis: Various harmonic distortion indices, Multiple harmonic injections
– Flicker Analysis: Flicker Assessment (IEC 61400-21), Flicker Meter (IEC 61000-4-15)
– Impedance-Frequency-Curve: Balanced and unbalanced network model
• Stability Analysis Functions (RMS): balanced/unbalanced, multi-phase AC networks, DC networks, simulation of any kind of faults or events
• +Electromagnetic Transients (EMT): FACTS, HVDC interconnections, power electronic devices
PowerFactory – DIgSILENT, Germany
PHOTOVOLTDEVELOPMENT PARTNERS
29 Juli 2014 Page 10
Output
The Main Outcome of the System Studies is:
• Definition of measures for a secure and stable operation under undisturbed conditions – Fulfilment of the Grid Code requirements acc. to JEAC 9701
• Definition of Countermeasures for the specific electrical phenomena due to long-distance submarine cables (e. g. harmonic filters, surge arresters)
• Definitions for the setting of the Protection Devices
Challenges: Project Internal DesignOutcome of the System Studies
System
Study
Contribution to a Stable Operation of the Transmission System
InputCons-trution
Challenges Chances
PHOTOVOLTDEVELOPMENT PARTNERS
29 Juli 2014 Page 11
The Operator of the Transmission System (TSO) is responsible for the keep of it’s Stability!
Chances: Stability of Transmission SystemsStability Criteria
Power System Stability
Frequency Stability Voltage Stability Rotor Angle Stability *
Stability of the ActicePower Balance
Stability of the ReacticePower Balance
Small SignalStability
Large Signal(Transient Stability)
Generation
SystemFrequency
Demand
TSO
Umin
Pmax
Balanced ReactivePower Area
Unbalanced ReactivePower Area
Safe Operation Area
CriticalOperationArea
ImpossibleOperation Area
U
P** * Not in Scope** Source: EirGrid
PHOTOVOLTDEVELOPMENT PARTNERS
29 Juli 2014 Page 12
The Main International Requirements to Generating Units – including Renewables – are:
Chances: Stability of Transmission SystemsStability Requirements to Generating Units
Criterion Description of the Requirement Stability Type
JEAC 9701
Frequency range Normal operation 47.5 Hz ≤ fr50Hz ≤ 51.5 Hz or 57.0 Hz ≤ fr60Hz ≤ 61.8 Hz (Europe 48.5 Hz ≤ fr50Hz ≤ 50.5 Hz)
Frequency�
Voltage range Normal operation between 80% ≤ Ur ≤ 120 % (Europe 80% ≤ Ur ≤ 120 %)
Voltage�
Active Power Control
Active Power Control within a given Frequency Range Frequency ---Reactive Power Control
Possibility to meet a given P-Q-diagram independently to voltage changes (P-Q-diagram in a voltage band)
Voltage�
Fault Ride-Through
Stable connection during network faults within a give time-frame; (not in JEAC: injection of a reactive current)
Voltage�
Information exchange
Online transfer for the value of active power and possibility for its reduction by the grid operator
Frequency�
Control system Voltage, reactive power or power factor control Voltage�
PHOTOVOLTDEVELOPMENT PARTNERS
29 Juli 2014 Page 13
Detailed Requirements to Renewables according to JEAC 9701-2012:
Chances: Stability of Transmission SystemsStability Requirements to Generating Units
• No specific requirements regarding the control of the active power due to frequency deviations
• Power Factor between0.9 lag and 0.95 lead (systems point of view)
• No specific requirements regarding theinfeed of a reactive current during
• Not disconnection during a voltage drop down to 20% Ur over 0.3 sec
• Reversion to 80% of Ur within 0.1 s afterclearence of the external network failure
• Achievement of the origin voltage after 1.5 sec
-200
-150
-100
-50
0
50
100
150
200
-400 -350 -300 -250 -200 -150 -100 -50 0 50 100
Q [M
var]
P [MW]
PMax
Lagging 0.85
0.9 lag
0.95 lead
+Q
-Q
+P-P
Active PowerControl
Reactive PowerControl
Fault-Ride-Through
0
10
20
30
40
50
60
70
80
90
100
110
-0.10 0.00 0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00 1.10 1.20 1.30 1.40 1.50
Vo
lta
ge
Le
ve
l [p
. u
.]
Time [s]
After March 2017
Before March 2017
PHOTOVOLTDEVELOPMENT PARTNERS
29 Juli 2014 Page 14
Ability for Stability Support by the INVERTERS of the UMSP in Comparison to JEAC 9701
Chances: Stability of Transmission SystemsStability Requirements to Generating Units
Criterion According to JEAC 9701-2012 Additional Abil ity
• Full Compliance to JEAC Normal Operation in the range 57.0 Hz ≤ fr60Hz ≤ 61.8 Hz
• AP Reduction starting froma Setpoint (e. g. 50.2Hz);• The Gradient of the Power Reduction in MW/Hz must beDefined by the TSO
• Full Compliance to JEAC
• Full Compliance to JEAC • Injection of a Reactive Current during the external network fault
• Additional support for theVoltage at the PCC
Active Power(AP) Control
Reactive Power Control
Fault-Ride-Through
nf
f∆
refP
P∆
n
i
f
f∆−
Active Power Setpoint
Droop
-150
-100
-50
0
50
100
150
200
-400 -350 -300 -250 -200 -150 -100 -50 0 50 100
Q [
Mva
r]
P [MW]
0.9 lag
PMax
0.95 lead
0.85 lag
Reverse Power FlowNon-Reverse Power Flow
PHOTOVOLTDEVELOPMENT PARTNERS
29 Juli 2014 Page 15
Summarize: How UMSP is able to meet stability requirements of JEAC?
Chances: Stability of Transmission SystemsCapabilities of the Renewables Assets
Criterion Description Inverter - Cability according toJEAC 9701 Add. Ability
Active Power ControlNormal operation 57.0 Hz ≤ fr60Hz ≤ 61.8 Hz
AP Variation during Frequency deviations
Reactive Power ControlNormal operation between 80% ≤ Ur ≤ 120 %
0.9 lag ≤ cos φ ≤ 0.9 lead
Fault-Ride-ThroughNot Disconnection; Voltage Recovery
Reactive Current injection during FRT
UMSP is able to meet the Stability requirements by JEAC AND
to provide additional services for the keep of the stability!
PHOTOVOLTDEVELOPMENT PARTNERS
29 Juli 2014 Page 16
Please don’t hesitate to ask any questions at any time
Contact:
Photovolt Development Partners GmbHKurfuerstendamm 136, D-10711 Berlin
Joerg Zillmer Peter GerstmannPrincipal Consultant Managing DirectorPhone: +49 173 6095034 Phone: +49 30 375926711email: [email protected] email: [email protected]
PHOTOVOLTDEVELOPMENT PARTNERS
29 Juli 2014 Page 17
Chances: Stability of Transmission SystemsCapabilities of Renewables Assets
1
23
f / Hz
P / kVA