UK/Netherlands SNS Hackathon · | UK / Netherland SNS Hackathon Output Report Gallery Share the...

11
UK/Netherlands SNS Hackathon Output Report Gallery April 2019

Transcript of UK/Netherlands SNS Hackathon · | UK / Netherland SNS Hackathon Output Report Gallery Share the...

Page 1: UK/Netherlands SNS Hackathon · | UK / Netherland SNS Hackathon Output Report Gallery Share the love The four ‘Rs’ – Rules, reviews, reuse and recycle • Shared learnings review

UK/Netherlands SNS HackathonOutput Report Gallery

April 2019

Page 2: UK/Netherlands SNS Hackathon · | UK / Netherland SNS Hackathon Output Report Gallery Share the love The four ‘Rs’ – Rules, reviews, reuse and recycle • Shared learnings review

2

| UK / Netherland SNS Hackathon Output Report Gallery

Share the love

The four ‘Rs’ – Rules, reviews, reuse and recycle

• Shared learnings review made mandatory as part of a Decommissioning programme

• Contracts should be focussed on special decom activity as opposed to traditional contracts

• Early engagement between operators and suppliers required to provide clarity of upcoming demand in the market place

• More clarity of project requirements passed down to all tiers of the supply chain ( not just Tier 1 contractors).

• Shared learnings review made mandatory as part of a Decommissioning programme

• Contracts should be focussed on special decom activity as opposed to traditional contracts

• Early engagement between operators and suppliers required to provide clarity of upcoming demand in the market place

• More clarity of project requirements passed down to all tiers of the supply chain ( not just Tier 1 contractors).

• Shared learnings review made mandatory as part of a Decommissioning programme

• Contracts should be focussed on special decom activity as opposed to traditional contracts

• Early engagement between operators and suppliers required to provide clarity of upcoming demand in the market place

• More clarity of project requirements passed down to all tiers of the supply chain ( not just Tier 1 contractors)

• Common regulation between the UK and Netherlands

Early involvement with the supply chain with reuse a priority

• External engagement with all regularity bodies to join the dots including authority’s and technology bodies e.g. OGTC

• The next step considering alternative uses e.g. CO2 storage or hydrogen production

• Early review of reuse/recycle alternatives

Share the love

The Four ‘Rs’ – Rules, reviews, reuse and recycle

RRRR

• Shared learnings review made mandatory as part of a Decommissioning programme

• Contracts should be focussed on special decom activity as opposed to traditional contracts

• Early engagement between operators and suppliers required to provide clarity of upcoming demand in the market place

• More clarity of project requirements passed down to all tiers of the supply chain ( not just Tier 1 contractors)

• Common regulation between the UK and Netherlands

Early involvement with the supply chain with reuse a priority

• External engagement with all regularity bodies to join the dots including authority’s and technology bodies e.g. OGTC

• The next step considering alternative uses e.g. CO2 storage or hydrogen production

• Early review of reuse/recycle alternatives

Share the love

The Four ‘Rs’ – Rules, reviews, reuse and recycle

RRRR

Page 3: UK/Netherlands SNS Hackathon · | UK / Netherland SNS Hackathon Output Report Gallery Share the love The four ‘Rs’ – Rules, reviews, reuse and recycle • Shared learnings review

3

| UK / Netherland SNS Hackathon Output Report Gallery

The web of success

Probe the melon

• Early engagement with a range of non-traditional supply companies

• An industry programme of activity managed by specialist Decom integrators

• Industry wide forums sharing learning across all operators

• Learning from the most recent successful projects

• Early pre-tender work by the operators to examine new approaches and cost saving alternatives.

• Using existing well data to understand all issues within the well before starting the work

• Evolve contracting strategies to partnering agreements as opposed to lowest cost models

• Establish trusting relationship with all suppliers – let supply companies get on with the job

• Open book contracting -cost price plus overheads and profits

• Performance incentives for outstanding delivery.

• Early engagement with a range of non-traditional supply companies

• An industry programme of activity managed by specialist Decom integrators

• Industry wide forums sharing learnings across all operators

• Learning from the most recent successful projects

• Early pre-tender work by the operators to examine new approaches and cost saving alternatives

• Using existing well data to understand all issues within the well before starting the work

• Evolve contracting strategies to partnering agreements as opposed to lowest cost models

• Establish trusting relationship with all suppliers – let supply companies get on with the job

• Open book contracting -cost price plus overheads and profits

• Performance incentives for outstanding delivery

The web of success

Probe the Melon

• Early engagement with a range of non-traditional supply companies

• An industry programme of activity managed by specialist Decom integrators

• Industry wide forums sharing learnings across all operators

• Learning from the most recent successful projects

• Early pre-tender work by the operators to examine new approaches and cost saving alternatives

• Using existing well data to understand all issues within the well before starting the work

• Evolve contracting strategies to partnering agreements as opposed to lowest cost models

• Establish trusting relationship with all suppliers – let supply companies get on with the job

• Open book contracting -cost price plus overheads and profits

• Performance incentives for outstanding delivery

The web of success

Probe the Melon

Page 4: UK/Netherlands SNS Hackathon · | UK / Netherland SNS Hackathon Output Report Gallery Share the love The four ‘Rs’ – Rules, reviews, reuse and recycle • Shared learnings review

4

| UK / Netherland SNS Hackathon Output Report Gallery

Flexi decom

Speedy removal

Rigless

• Funded concept competitions

• Don’t be frightened to try new approaches- break away from how it was always done

• Operator to present overall project scope on website

• Regulator to take a firmer line on aligning activity

• Common UK/Netherlands regulations.

• Multi operator campaigns

• Use of innovative walk to work vessels as alternatives to helicopters

• Floatation as an alternative to lifting

• Consider use of explosives for cutting

• Start decom engineering during late life production phase.

• Self-propelled jack up rigs

• Multi use vessels with cranes and diving spread

• Selecting operator with past experience to lead the JV project.

• Funded concept competitions

• Don’t be frightened to try new approaches- break away from how it was always done

• Operator to present overall project scope on website

• Regulator to take a firmer line on aligning activity

• Common UK/Netherlands regulations

• Self-propelled jack up rigs

• Multi use vessels with cranes and diving spread

• Selecting operator with past experience to lead the JV project

Flexi Decom

Rigless

Speedy removal

• Multi operator campaigns • Use of innovative walk to work vessels as alternatives to helicopters

• Floatation as an alternative to lifting

• Consider use of explosives for cutting

• Start decom engineering during late life production phase

• Funded concept competitions

• Don’t be frightened to try new approaches- break away from how it was always done

• Operator to present overall project scope on website

• Regulator to take a firmer line on aligning activity

• Common UK/Netherlands regulations

• Self-propelled jack up rigs

• Multi use vessels with cranes and diving spread

• Selecting operator with past experience to lead the JV project

Flexi Decom

Rigless

Speedy removal

• Multi operator campaigns • Use of innovative walk to work vessels as alternatives to helicopters

• Floatation as an alternative to lifting

• Consider use of explosives for cutting

• Start decom engineering during late life production phase

• Funded concept competitions

• Don’t be frightened to try new approaches- break away from how it was always done

• Operator to present overall project scope on website

• Regulator to take a firmer line on aligning activity

• Common UK/Netherlands regulations

• Self-propelled jack up rigs

• Multi use vessels with cranes and diving spread

• Selecting operator with past experience to lead the JV project

Flexi Decom

Rigless

Speedy removal

• Multi operator campaigns • Use of innovative walk to work vessels as alternatives to helicopters

• Floatation as an alternative to lifting

• Consider use of explosives for cutting

• Start decom engineering during late life production phase

Page 5: UK/Netherlands SNS Hackathon · | UK / Netherland SNS Hackathon Output Report Gallery Share the love The four ‘Rs’ – Rules, reviews, reuse and recycle • Shared learnings review

5

| UK / Netherland SNS Hackathon Output Report Gallery

Remove risk

• Starting point should be what does ‘endpoint’ look like

• Can supply chain take the ‘keys’ of the platform and complete all works (but who takes the risk??)

• How do we quantify all financial risks in a decom project – can insurance products be viable.

• Starting point should be what does ‘end point’ look like

• Can supply chain take the ‘keys’ of the platform and complete all works (but who takes the risk??)

• How do we quantify all financial risks in a decom project – can insurance products be viable

• Contracting strategies designed specifically for decom projects

• Collaboration period for contractors to understand project complexity

• Define what can be fixed price

• Guaranteed maximum price with incentives for contractors to achieve lower

• Fit for purpose specifications no need for gold standards

• Look to nuclear decom for alternative models

Remove Risk

Contracting strategies

Contracting strategies

• Contracting strategies designed specifically for decom projects

• Collaboration period for contractors to understand project complexity

• Define what can be fixed price

• Guaranteed maximum price with incentives for contractors to achieve lower

• Fit for purpose specifications no need for gold standards

• Look to nuclear decom for alternative models.`

• Starting point should be what does ‘end point’ look like

• Can supply chain take the ‘keys’ of the platform and complete all works (but who takes the risk??)

• How do we quantify all financial risks in a decom project – can insurance products be viable

• Contracting strategies designed specifically for decom projects

• Collaboration period for contractors to understand project complexity

• Define what can be fixed price

• Guaranteed maximum price with incentives for contractors to achieve lower

• Fit for purpose specifications no need for gold standards

• Look to nuclear decom for alternative models

Remove Risk

Contracting strategies

Page 6: UK/Netherlands SNS Hackathon · | UK / Netherland SNS Hackathon Output Report Gallery Share the love The four ‘Rs’ – Rules, reviews, reuse and recycle • Shared learnings review

6

| UK / Netherland SNS Hackathon Output Report Gallery

Partnership

• Sharing expertise with offshore wind

• Sharing logistics e.g. walk to work vessels

• Introducing lower cost solutions from offshore wind e.g. contracting strategies

• Could hydrogen manufacturing utilise existing infrastructure in conjunction with offshore wind

• Put wind turbines on old jackets.

• Sharing expertise with offshore wind

• Sharing logistics e.g. walk to work vessels

• Introducing lower cost solutions from offshore wind e.g. contracting strategies

• Could hydrogen manufacturing utilise existing infrastructure in conjunction with offshore wind

• Put wind turbines on old jackets

Partnership

Reuse

• How to create a market for reuse equipment– e-bay model

• The legal requirement and cost of re-certifications needs to be reduced to make this viable

• Use old platforms onshore for training

• Should regulator/government require reuse as part of decommissioning programme

• Learn from the Netherlands reuse examples on regulatory drivers

• Ethical versus cost – Could third world countries benefit.

• How to create a market for reuse equipment – e-bay model

• The legal requirement and cost of re-certifications needs to be reduced to make this viable

• Use old platforms onshore for training

• Should regulator/government require reuse as part of decommissioning programme

• Learn from the Netherlands reuse examples on regulatory drivers

• Ethical versus cost – Could third world countries benefit

Reuse

• Could the polythene ropes be dissolved and concrete blocks left behind

• Operators study on the benefits and disadvantages of leaving mattresses behind

• Could mattresses be used in coastal protections projects

• Seabed ’JCB’ to load mattresses into seabed skips

• Seabed burial

Mattresses

Page 7: UK/Netherlands SNS Hackathon · | UK / Netherland SNS Hackathon Output Report Gallery Share the love The four ‘Rs’ – Rules, reviews, reuse and recycle • Shared learnings review

7

| UK / Netherland SNS Hackathon Output Report Gallery

Mattresses

• Could the polythene ropes be dissolved and concrete blocks left behind

• Operators study on the benefits and disadvantages of leaving mattresses behind

• Could mattresses be used in coastal protections projects

• Seabed ’JCB’ to load mattresses into seabed skips

• Seabed burial.

• How to create a market for reuse equipment – e-bay model

• The legal requirement and cost of re-certifications needs to be reduced to make this viable

• Use old platforms onshore for training

• Should regulator/government require reuse as part of decommissioning programme

• Learn from the Netherlands reuse examples on regulatory drivers

• Ethical versus cost – Could third world countries benefit

Reuse

• Could the polythene ropes be dissolved and concrete blocks left behind

• Operators study on the benefits and disadvantages of leaving mattresses behind

• Could mattresses be used in coastal protections projects

• Seabed ’JCB’ to load mattresses into seabed skips

• Seabed burial

Mattresses

Reward for all

• Common guidelines between the UK and Netherlands to encourage cross border projects

• Flexible and multiskilled workforce

• More focus on data gathering prior to starting project.

• Common guidelines between the UK and Netherlands to encourage cross border projects

• Flexible and multiskilled workforce

• More focus on data gathering prior to starting project

• Step by step planning prior to commence of work

• Multiple assets decommissioned under a single project

• Multi operator and regional campaigns

Reward for all

Strictly Decom

Time Bandit

• Don’t let time schedules drive up costs – need flexible scheduling • Where appropriate delay work until new technology developed

• Adopt cost models to mitigate lost weather time and allow all year working

• Operators to be transparent and share project information at an early stage

Page 8: UK/Netherlands SNS Hackathon · | UK / Netherland SNS Hackathon Output Report Gallery Share the love The four ‘Rs’ – Rules, reviews, reuse and recycle • Shared learnings review

8

| UK / Netherland SNS Hackathon Output Report Gallery

Strictly decom

• Step by step planning prior to commence of work

• Multiple assets decommissioned under a single project

• Multi operator and regional campaigns.

• Common guidelines between the UK and Netherlands to encourage cross border projects

• Flexible and multiskilled workforce

• More focus on data gathering prior to starting project

• Step by step planning prior to commence of work

• Multiple assets decommissioned under a single project

• Multi operator and regional campaigns

Reward for all

Strictly Decom

Time Bandit

• Don’t let time schedules drive up costs – need flexible scheduling • Where appropriate delay work until new technology developed

• Adopt cost models to mitigate lost weather time and allow all year working

• Operators to be transparent and share project information at an early stage

Time bandit

• Don’t let time schedules drive up costs – need flexible scheduling

• Where appropriate delay work until new technology developed

• Adopt cost models to mitigate lost weather time and allow all year working

• Operators to be transparent and share project information at an early stage.

• Common guidelines between the UK and Netherlands to encourage cross border projects

• Flexible and multiskilled workforce

• More focus on data gathering prior to starting project

• Step by step planning prior to commence of work

• Multiple assets decommissioned under a single project

• Multi operator and regional campaigns

Reward for all

Strictly Decom

Time Bandit

• Don’t let time schedules drive up costs – need flexible scheduling • Where appropriate delay work until new technology developed

• Adopt cost models to mitigate lost weather time and allow all year working

• Operators to be transparent and share project information at an early stage

Page 9: UK/Netherlands SNS Hackathon · | UK / Netherland SNS Hackathon Output Report Gallery Share the love The four ‘Rs’ – Rules, reviews, reuse and recycle • Shared learnings review

9

| UK / Netherland SNS Hackathon Output Report Gallery

Getting the right partner/culture

• Partnerships with supply chain

• Collaboration with others

• Trusted trader

• We need to find the right culture for decom.

• Partnerships with supply chain

• Collaboration with others

• Trusted trader

• We need to find the right culture for decom

Getting the right partner / culture

One stop shop

• Is there a one stop shop in the supply chain to allow scope to be outsourced?

• Is there potential to farm out/offload this work

• Could this one stop shop become a model approach for others?

• Are there any off-the-shelf solutions available.

• Is there a one stop shop in the supply chain to allow scope to be outsourced?

• Is there potential to farm out / offload this work

• Could this one stop shop become a model approach for others?

• Are there any off-the-shelf solutions available

One Stop Shop

ONE STOP SHOP

Page 10: UK/Netherlands SNS Hackathon · | UK / Netherland SNS Hackathon Output Report Gallery Share the love The four ‘Rs’ – Rules, reviews, reuse and recycle • Shared learnings review

10

| UK / Netherland SNS Hackathon Output Report Gallery

Combining with others

• Synergies with Brownfield projects to combine scope?

• Could subsea and topsides scopes be integrated?

• Is there value in UK work being integrated into Netherlands scopes?

• Not worth building in-house capability as scope small.

• Could the work piggy backed onto another operators workload?

• Can we share vessels/equipment?

• Synergies with Brownfield projects to combine scope?

• Could subsea and topsides scopes be integrated? • Is there value in UK work being integrated into Netherlands scopes?

• Not worth building in-house capability as scope small.

• Could the work piggy backed onto another operators workload?

• Can we share vessels / equipment?

Combining with others

Simplified decom

• Simplification is best for decommissioning

• Is there a need for a reverse tender simplified contract?

• What would simplification look like?

• How would this address risk?

• Lean decom.

• Simplification is best for decommissioning

• Is there a need for a reverse tender simplified contract? • What would simplification look like?

• How would this address risk?

• Lean decom

Simplified decom

Page 11: UK/Netherlands SNS Hackathon · | UK / Netherland SNS Hackathon Output Report Gallery Share the love The four ‘Rs’ – Rules, reviews, reuse and recycle • Shared learnings review

www.ogauthority.co.uk

Copyright © Oil and Gas Authority 2019

Oil and Gas Authority is a limited company registered in England and Wales with registered number 09666504 and VAT registered number 249433979. Our registered office is at 21 Bloomsbury Street, London, United Kingdom, WC1B 3HF